Sunteți pe pagina 1din 4

Management Part 1 of this two-part article, which

focused on project plans, can be

Preliminary
found in the November issue of CEP
on pages 66–72.

and Final Engineering


Scopes
of Work

Glen Rosentrater,
Project Management
Professional
Use this project template to address
large capital projects in the CPI.

I n the chemical process industries (CPI), the vast majori-


ty of engineering involved in capital projects is out-
sourced. Few companies have the internal staff to design
for projects of any magnitude. Unfortunately, a design
firm is usually brought on board when the scope is still unde-
fined, and several expensive gyrations are made before the
curacy of the cost estimate increases greatly. There is always the
potential for the project to be killed at the end of preliminary or
final engineering. It’s also important to make the detailed-de-
sign/build firm responsible for solving the installation problems
at the site because on a large project, this is a full time job that
cannot be juggled effectively by the project manager.
scope is confirmed. Then, when the scope is finalized, the de- In order to bid on the preliminary-engineering contract,
sign firm, who is usually working on a time-and-materials the project manager must form a project team and generate a
(T&M) basis, and works without deadlines, makes many rough project scope. This is lifted out of the project plan and
mistakes that the company must pay for. used to bid on the preliminary engineering. The preliminary
Construction eventually starts with the design firm sub- engineering, which is a formalization of the rough project
mitting drawings, piecemeal, to the contractors. Unfortunate- scope, is then used to bid on the final engineering. The pro-
ly, the order of the completed drawings is usually not given ject team’s rough scope simply isn’t detailed enough to ob-
much thought. Often, no attempt is made to see all of the tain good quotes for final engineering. If you try to do so, de-
drawings as a package. Consequently, construction extras are sign firms will either bid high to cover the gray areas or bid
generally significant. It’s almost a given that construction low and try to use the gray to obtain extras. In the detailed-
contracts on large projects will have 30% or more in extras. design/build scope of work, it’s important to insist that all
Clearly, this is unsatisfactory, and it’s also unnecessary. It’s work be distributed across a handful of general contracts and
just a symptom of a lack of planning. that you list the title of those contracts. Unless this is done,
When it’s time to engineer, a scope of work must be writ- the design firm will have a never-ending supply of minor
ten that will allow your company to obtain fair prices and that contracts to issue that will delay completion. If it’s firmly
also clearly states what work must be done. The scope of stated that all contracts must be included in a set of general
work must be comprehensive enough to cover the entire job contracts, and dates are given, the design firm will have to
and detailed enough to allow the design firm to understand complete the design on your schedule. There will be no wig-
what it must do. The scope of work must go even further than gle room for playing with semantics.
this though. A plant buy-in must be obtained for what you’re
asking the design firm to do (CEP, Nov. 2001, pp. 66–72). Project template
I recommend issuing two design contracts (hopefully to To understand the importance of the scope of work, sev-
the same design firm)— one for preliminary engineering and eral key areas must be identified. These are: general infor-
the other for detailed design/build. During the preliminary- mation, the project schedule, the preliminary-design scope
engineering phase, equipment should be specified and or- of work details, and the detailed-design/build scope of
dered. This will expedite the overall schedule. work bid package details. An example of a drying project
Part of both contracts should be a cost estimate for project follows. This can be used with minor modifications to ad-
completion. As each stage of engineering is completed, the ac- dress any large capital project in the CPI.

74 www.cepmagazine.org December 2001 CEP


General 10.Equipment list 12:00 PM Wed. Mar. 21
The company intends to construct a new facility for sodi- 11. Line list 12:00 PM Wed. Mar. 21
um lauryl sulfate (SLS) drying, installing six new dryers with 12. Tie-in list 12:00 PM Wed. Mar. 21
all the necessary support equipment. A new process building 13. Valve list 12:00 PM Wed. Mar. 21
of approximately 20,000 ft2 must be installed with easy fu- 14. Material-and-energy 12:00 PM Wed. Mar. 21
ture expansion in mind. The company will accept bids and balance
award two contracts: 15. Utility requirements 12:00 PM Wed. Mar. 21
Preliminary engineering contract — The basic scope put 16. Process description 12:00 PM Wed. Mar. 21
together by the project team will be finalized under this 17. Operating instructions 12:00 PM Wed. Mar. 21
lump-sum contract. This contract will establish enough de- 18. Single-line diagram 12:00 PM Wed. Mar. 21
tail to allow effective bidding of the detailed-design/build 19. Motor listing 12:00 PM Wed. Mar. 21
contract through the preparation of a detailed-design/build 20. Work breakdown 12:00 PM Wed. Mar. 21
bid package. All new items shown on the process-and-in- structure
strumentation diagram (P&ID), except for manual valves, 21. Schedule 12:00 PM Wed. Mar. 21
will be purchased under the preliminary engineering con- 22. Detailed risk 12:00 PM Wed. Mar. 21
tract. Distributed-control-system (DCS) and motor-control- assessment & response development
center (MCC) equipment will also be purchased. The de- 23. Permitting report 12:00 PM Wed. Mar. 28
sign firm will be reimbursed after the equipment arrives at 24. Detailed-design/build 12:00 PM Wed. Mar. 28
the plant site. scope of work
Detailed-design/build contract — This contract will be 25. Total project-cost 12:00 PM Wed. Mar. 28
bid on using the results of the work obtained from the pre- estimate
liminary-engineering contract. Under the detailed-
design/build contract, the design firm will perform the de- The company will return all “for approval” documents
tailed design, write trade scopes of work, schedule pre-bid with comments eight working days after receiving them.
meetings, bid the work, let contracts, and supervise the The design firm will submit “final documents” on the fol-
work in the field. Any equipment items not purchased lowing dates.
under the preliminary-engineering contract will be pur- 26. P&ID 12:00 PM Wed. Apr. 4
chased here. All contractual obligations will be between 27. Hazop (to be held at the company) Fri. Apr. 6
the design/build firm and the contractors and vendors. 28. Hazop results incorporated in design Fri. Apr. 18
However, the design firm will be reimbursed for contractor 29. IO list 12:00 PM Wed. Apr. 18
and vendor materials that arrive at the plant site and for 30. Building & equipment 12:00 PM Wed. Apr. 18
completed construction. layout and elevation
The design/build firm will evaluate and award change or- 31. Building report 12:00 PM Wed. Apr. 18
ders that do not represent scope changes to solve installation 32. Equipment list 12:00 PM Wed. Apr. 18
problems at the plant site. These change orders must be antic- 33. Line list 12:00 PM Wed. Apr. 18
ipated, evaluated and awarded so as not to delay the schedule. 34. Tie-in list 12:00 PM Wed. Apr. 18
Actual design work will be lump sum. Field coordination, 35. Valve list 12:00 PM Wed. Apr. 18
however, will be T&M. 36. Material-and-energy 12:00 PM Wed. Apr. 18
balance
Schedule 37. Utility requirements 12:00 PM Wed. Apr. 18
1. Pre-bid meeting 9:30 AM Mon. Jan. 8 38. Process description 12:00 PM Wed. Apr. 18
2. Quote due 12:00 PM Mon. Jan. 29 39. Operating instructions 12:00 PM Wed. Apr. 18
3. Critical-path schedule 12:00 PM Mon. Jan. 29 40. Single-line diagram 12:00 PM Wed. Apr. 18
of at least 40 items 41. Motor listing 12:00 PM Wed. Apr. 18
4. Purchase order awarded Mon. Feb. 19 42. Work breakdown 12:00 PM Wed. Apr. 18
5. Kick-off meeting at the companyWed. Feb. 21 structure
43. Schedule 12:00 PM Wed. Apr. 18
The design firm will submit the following preliminary en- 44. Detailed risk 12:00 PM Wed. Apr. 18
gineering “for approval” documents. assessment & response development
6. P&ID 12:00 PM Wed. Mar. 14 45. Permitting report 12:00 PM Wed. Apr. 25
7. Instrumentation electrical 12:00 PM Wed. Mar. 14 46. Detailed-design/build 12:00 PM Wed. Apr. 25
inputs and outputs (IO) list scope of work
8. Equipment & building 12:00 PM Wed. Mar. 21 47. Total project-cost 12:00 PM Wed. Apr. 25
layout and elevation estimate
9. Building report 12:00 PM Wed. Mar. 21 48. All equipment purchased Wed. June 6

CEP December 2001 www.cepmagazine.org 75


Management

Preliminary design scope-of-work details sonnel from maintenance, automation, electrical and instru-
1. The following documents will be used as the basis for mentation (AE&I), and production departments. Approved
the preliminary design: requisitions will be issued as purchase orders (POs) by the de-
• Scope statement (contains maintenance needs, production sign firm. Three copies of approved POs and all supporting
needs, utility requirements, existing utility status, safety, envi- documents must be supplied to the company.
ronmental, standards, startup, and other strategic information) 5. The design firm will issue the POs and pay the invoices.
• Work breakdown structure The company will reimburse the design firm after the equip-
• P&ID (rough) ment has arrived onsite. The requisition must state the perti-
• Process description (rough) nent equipment numbers and that five sets of equipment man-
• Layout (rough) uals, spare part lists, and certified drawings be sent to the de-
• Existing underground sign firm for collation in five duplicate equipment manual
• Site information notebooks. These notebooks will be indexed according to
• Schedule equipment number with an index and tabs.
• Detailed risk assessment 6. The design firm, in the building report, will explore sev-
• Solicitation plan eral types of structure from a cost, integrity, and aesthetic
• Quality control plan perspective. At the least, brick and cinder block, steel skele-
• Risk response development ton with panel skin, steel skeleton with precast skin, and self
• Open issues and pending decisions supporting precast construction will be considered, with a
The design firm will use this information and their own recommendation for one. This report will recommend surface
expertise to create the required professional documents. Re- types for floors, ceilings, walls, platforms, and roofs. It will
sponsibility for obtaining any other necessary information is discuss floor and roof drainage, and doors, and windows,
left to the design firm. If more information is requested from lighting, and heat, ventilation and air-conditioning (HVAC)
the company and can be found within the its internal docu- plan, etc. to give a complete picture of building construction.
ments, the company’s project manager will direct the design 7. The design firm in the permitting report will discuss all
firm as to where to find it. If the additional information can- permits required and how they are obtained.
not be found internally, then it is the design firm’s responsi- 8. One person from the design firm, typically its project
bility to obtain the information from other sources. manager, will be the company’s main contact, who will an-
Part of the preliminary design duties is to create a scope of swer questions in a timely fashion and give updates on status.
work for the detailed-design/build contract. The firm that is 9. The design house will contract all testing that needs to
awarded the preliminary-design contract will be asked to bid be done for preliminary and final engineering.
on the detailed-design/build contract assuming their perfor- 10. Any additional requests must be brought to the atten-
mance has been acceptable. The company will handle the tion of the company’s project manager before the work is
bidding process for the detailed-design/ build contract. started. A lump-sum quote will be given, and when written
2. Once a week, the company’s project manager will visit approval is received, the work will proceed.
the design firm to review the work progress. These will not 11. All of the design firm’s employees working onsite
be document reviews and will only take place when “for ap- must attend the company’s safety seminar.
proval” documents are received. Instead, these will be 12. List all exceptions to this scope on a separate sheet of
progress reviews where the status of each document is looked paper in your quote.
at to gauge work output.
3. It is understood that the company will not be vigorously Detailed-design/build scope-of-work bid
checking the documents for inaccuracies. When “for ap- package details
proval” documents are received, they are expected to be free 1. The forementioned “final documents” along with any
from simple errors. If common errors exist on the documents, testing results will constitute the detailed-design/build bid
such as lines disappearing from one drawing to the next, package. Detailed-design and construction due dates are list-
equipment numbers for the same equipment changing from ed in the schedule.
drawing to drawing, equipment numbers from drawings not 2. All trade work and equipment with single item or quan-
matching those on the process description, the work will be tity value of more than $15,000 will be bid. Once a particular
considered inferior. type of contract is awarded, pertinent additional work or
4. When purchasing equipment, three quotes will be ob- items will simply be added to that contract after fair pricing
tained (where possible) for each piece of equipment using the has been established.
company’s solicitation plan to obtain applicable vendor names. 3. The company will reimburse the design/build firm for
The quotes will be tabulated on a bid form, and attached to a materials stored on the plant site and for installation.
requisition for review by the company. This review will take 4. The following separate contracts will be let, or in other
place at a regularly scheduled, weekly meeting at the company, words, all the work must be distributed across all of these
attended by the project manager, the process engineer, and per- contracts. In its quote, the final design/build firm must list all

76 www.cepmagazine.org December 2001 CEP


work that will fall into each category: tor-coordination meeting will be held. A computer-generat-
• Demolition ed progress report will be given to the company’s project
• Concrete foundation, underground piping, and electrical manager on a weekly basis. Contractor performance and
• Structural steel contract compliance will be monitored. The field-coordina-
• Concrete floors and roof tion team will call the detailed-design/build firm directly
• General building architectural (walls, siding, doors, win- for answers to questions if necessary. They will also docu-
dows, roofing, fire protection, plumbing, etc) ment arriving equipment, keeping a computer-generated re-
• Mechanical (equipment setting, piping, HVAC and insu- port up to date, daily.
lation installation) 15. All contracts, equipment and trade work, will be bid
• Electrical and instrumentation on with clear specifications to make sure all are bidding on
• Programming the same or equivalent items. Unless unusual circum-
5. All bid documents must be reviewed by the company’s stances arise, contracts will be given to the low bidder.
project manager before being submitted to contractors. 16. A weekly meeting will be held with the detail/de-
6. All trade scopes of work will take into account the com- sign-build firm to establish contract compliance and project
pany’s shutdowns, and trade interactions, and will supply an status. Change orders will be explained and substantiated.
order of construction linked to drawings by drawing num- Issues that have arisen will be discussed. The first and third
bers, detail numbers and tie-in points. Each trade scope of weeks of every month, a variety of formal project status
work will request a computer-produced critical path schedule calculations (e.g., estimate at completion, cost variance and
of at least 40 items. Each schedule will use certain milestone schedule variance) will be submitted to the company. Esti-
tasks that will be stated in the scope of work, which will link mate-at-completion calculations will be computed for the
that trade’s work to the project’s master schedule. entire project and for each contract. Any contract anticipat-
7. A list of required drawings will be generated for all ing a 20% or more increase in cost must be analyzed by the
the trades (construction profession performed by union labor, design firm in a written report that will explain what hap-
such as brick laying and steel working). pened and what can be done to reduce costs. At the very
8. The original equipment list will be modified to include least, a drawing review is expected from the design firm.
equipment that has been specified as a result of detailed engi- The design firm must put in place an action plan to resolve
neering. The detailed-design/build firm will purchase this and any critical-path schedule delays.
update the five equipment manuals. 17. Equipment contracts will have clearly defined deliv-
9. At the end of construction, “as built” drawings will be ery dates, which will be expedited every week by the de-
returned to the design firm for updating. Three hardcopies sign firm.
of updated drawings will be provided, as will a CD-ROM, 18. All designs must correspond to OSHA and all feder-
and reproducibles. al and state regulations.
10. All drawings (civil, mechanical, electrical, structural, 19. The design firm must perform a detailed cost-esti-
etc.) will be done in a common, three dimensional (3-D) mate of the entire project within one week after the de-
mode to check for interferences. In addition, a 3-D walk- tailed design is complete using Richardson’s or some other
through of the project will be performed on a terminal for the well-known estimating method. The results must be sum-
project team. marized in an easy to read format. The results must be cat-
11. Tie-ins will be marked by the design firm in the field. egorized into material and labor. In addition, a single lump-
Note that this may entail the rental of a manlift. sum must be provided for the building, including all non-
12. For all the trades, the drawings supplied must be com- process utilities associated with it.
plete and professional, suitable for bidding. Piping, conduit, 20. All drawings must be stamped appropriately by pro-
structural steel and routing must be clear. The statement fessional engineers, electrical by an electrical engineer,
“field route” will not be allowed. structural by a structural engineer, etc.
13. Each project should have its own pertinent list of ex- 21. An isometric drawing must be supplied for any pip-
isting company drawings. These drawings must be updated to ing, electrical, etc. that must be rerouted to accommodate
reflect the new work completed. Computer-aided design for new structures. CEP

(CAD) drawings must be updated using CAD software. Pen-


cil drawings, however, do not need to be converted to CAD
drawings and can be updated with pencil.
14. The design firm will supply the construction man- GLEN ROSENTRATER is a senior project manager with over 14 years of
experience managing projects in the chemical processing and food
agement team, which will hold pre-bid meetings (bidding industries (E-mail: gutbar@aol.com). He obtained his BS and MS in
“solicitation plan” recommended contractors, or in other chemical engineering from the Univ. of Illinois at Chicago, and is a
words, receiving quotes from contractors the project team project management professional (PMP). Rosentrater is a member of
has approved), with onsite planning, management and co- AIChE and the Project Management Institute (PMI)
ordination of all construction activities. A weekly contrac-

CEP December 2001 www.cepmagazine.org 77

S-ar putea să vă placă și