Work Done Till 13-5-17

1. Checklist prepared & Submitted.


2. 60 OMR received
3. Block Diagram prepared (Attached Below)
4. List of chemicals to be handled - prepared (Attached below)
5. Selection of MOC for the construction (Attached below)
6. Formulas to be used for Process Calculations & Process Design (Will be
submitted till 17/5/17, time will be conveyed on 16/5/17)
7. MSDS of the chemicals under consideration (Will be submitted by 14/5/17,
10:00 pm IST)
8. PFD of the process (Will be submitted by 14/5/17, 2:00 pm IST)
9. Process Calculations [HYSYS Process Data sheet] (Will be submitted by
20/5/17, time will be conveyed o 19/5/17) along with a demanding letter of
the next payment of 30 OMR
10.P&ID of the partial process (1 2 sheets; Just to check the quality of
work) (will be submitted by 21/5/17)
11.Description of the process along with the rough report* (including a
watermark) (Will be submitted by 22/5/17) along with a demanding letter
of the last payment, i.e., 27 OMR
12.The final report (Without watermark) will be mailed as soon as the
payment is received.

* Some data will be kept hidden. The only aim of the rough report will be to
check for any errors.
Note 1 : The word submitted above means a confirmation message
that the mentioned work has been completed and included in the
report. All the data (except some) will be sent to you in the rough
report.
Note 2: As mentioned 2sections of P&ID will be mailed for confirmation
of work progress.
Block Diagram
List of Chemicals to be Handled (i.e. the chemicals for which the system
is to be designed)
1. Hydrogen
2. Hydrogen Sulfide
3. Ammonia
4. Methane
5. Ethane
6. Propane
7. Butane
8. Pentane
9. Ethyl Mercaptan
10.Thiophene
11.Pyridine
12.Pyrrole
13.Dimethyl Disulfide
Material of Construction
1. Alloy 31
2. Stainless Steel