PLUMBING AND FIRE-FIGHTING

Shapooji Pallonji E&C Page 1 of 1


PLUMBING AND FIRE-FIGHTING

TABLE OF CONTENTS

S.NO DESCRIPTION

A CHECKLIST

1 Brick Masonry Inspection Chember

2 G.I./CPVC pipe/Copper Pipe

3 Fire-fighting and sprinkler

4 Valves

5 M.S.Sleeve

6 Drain Piping (Internal and External)

8 Bracket & Support

9 Bracket support and piping in tunnel/trench

B TESTING REPORT

1 GI/CPVC pipe/UPVC/Copper pipe

2 Drain piping

3 Fire-fighting and sprinkler

C Handing Over

1 Handing Over Checklist

2 Handing Over Delivarable Note


Shapoorji Pallonji E&C Page 1 of 1
Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

CHECKLIST FOR BRICK MASONRY INSPECTION CHEMBER

Size

Location

Date:

Drawing No:

S.No Description Remarks

Refer to the approved WMS and Shop drawing

Check for availibility of material at the installation


1
site
Check for readiness of the site for Erection, i.e.
2
competion of the preceding activities.
Check for provision and working condition of
3
Installation aids.
Check whether installation is carried out as per
4
sequence
Check for alignment,levels,locations,orientation
5
etc.
Mention the thickness of PCC (150mm) Is it as
6
per Specifications
Check for Brick Masonry-(230 mm thick) Is it as
7
per Specifications
Check for Plastering (Internal & External) above
8 brick masonry (12 mm thick) Is it as per
Specifications
Check whether Fixing of Chember Cover with
9
Frame as per Specification

10 Check for Testing.Is it as per Specifications

Check for incasing/backfilling (Other similar


11
processes) as per Specifications

Inspected By:

Sub-Contractor Rep. MEP Engineer

Shapoorji Pallonji E&C Page 1 of 1


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

CHECKLIST FOR G.I/CPVC/COPPER PIPE

Location
Date:
Ref.Drawing No:
Size:
S.No Description Remarks
Refer to the approved shop drawings and WMS
1 Check for availibility of material at the installation site
Check for readiness of the site for Erection, i.e. competion of the
2
preceding activities.
3 Check for provision and working condition of Installation aids.
4 Check whether installation is carried out as per sequence
5 Check for alignment,levels,locations,orientation etc.
Check for Wrapping Coating / Painting / Epocxy Painting.Is it as per
6
Specifications
7 Check for Support / Braket / PCC as per Specifications
8 Check for Testing as per Specifications
Check for incasing/backfilling (Other similar processes) as per
9
Specifications

Checked By

Sub-Contractor Rep. MEP Engineer

Shapoorji Pallonji E&C Page 1 of 1


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fi

Site Work Activity

CHECKLIST FOR FIRE-FIGHTING & SPRINKLERS

Location
Date:
Ref.Drawing No:
S.no Description Remarks

A FIREFIGHTING

1 Extinguisher No.

2 Extinguisher Type

3 Size of Extinguisher

4 Date of Refilled

5 Date of Expiry

6 Manufactured By

B SPRINKLERS

1 Grid Location

2 Temperature of the sprinkler

3 Sprinkler Make
No. of the sprinklers used between the
4
above grid
5 Check the alignment/orientation/level

Inspected By:

Sub-Contractor Rep. MEP Engineer


Shapoorji Pallonji E&C Page 1 of 1
Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity
CHECKLIST FOR VALVES

Location

Date:

Ref.Drawing No:

S.No DESCRIPTION REMARK

1 TYPE & MATERIAL OF VALVE

2 SIZE OF VALVE

3 CONNECTION FOR

4 CONNECTION PIPE & FITTINGS

5 ALIGNMENT AND ORIENTATION

6 SUPPORT, BRACKET, PCC

7 PAINTING AND COATING

8 MEASUREMENT

Inspected By:

Sub-Contractor Rep. MEP Engineer


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

CHECKLIST FOR GI/PVC PIPE SLEEVE/GI PIPE INSERT/M.S.SLEEVE

BLOCK :
AREA / GRID
REF. DRAWING NO.

S.No. DESCRIPTION REMARK


1 SIZE OF SLEEVE
2 REFERENCE LEVEL
3 ALIGNMENT AND ORIENTATION
4 SUPPORT, BRACKET, PCC
5 Check for Availibility of Material at the Installation site
Check for readiness of the site for Erection,i.e.
6
completion of preceding activities
Check for provision & working condition of installation
7
AIDS
Check whether installation is carried out as per
8
installation sequence.
9 Check for alignment,level,location,orientation etc.
Check for Painting / Epocxy Painting as per
10
Specifications

Inspected By:

Sub-Contractor Rep. QA/QC Manager

Shapoorji Pallonji E&C Page 1 of 1


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

CHECKLIST FOR DRAIN PIPING(Internal & External)

LOCATION :

REF. DRWG. NO.

Date:-

Size of Pipe :

S.No Description Remarks


Refer to the approved shop drawings and WMS

1 Check for availibility of material at the installation site

Check for readiness of the site for Erection, i.e. competion of the
2
preceding activities.

3 Check for provision and working condition of Installation aids.

4 Check whether installation is carried out as per sequence

5 Check for alignment,levels,locations,orientation etc.

6 Check for Joints between Pipes

7 Check for Support / Bracket / PCC.Is it as per Specifications

8 Check for Testing.Is it as per Specifications

Check for incasing/backfilling (Other similar processes) as per


9
Specifications

CHECKED BY

Sub-Contractor Rep. MEP Engineer

Shapoorji Pallonji E&C Page 1 of 1


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

CHECKLIST FOR BRACKETS AND SUPPORTS

Location:
Ref.Drawing No:
Date:

S.No. DESCRIPTION REMARKS


1 Size of Bracket / Support
2 Area grid / Location
3 Support marking as per drawing
4 Support fixing as per Sequence
Welding / Cutting / threading / Gas Cutting as per given
5 specification
6 Checked for Alignment / Orientation
7 Checked for reference level
8 Painting and coating

Inspected By:

Sub-Contractor Rep. MEP Engineer

Shapoorji Pallonji E&C Page 1 of 1


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

CHECKLIST FOR BRACKETS AND PIPING IN TUNNEL/TRENCH

S.No. Description Remarks


1 Block
2 Ref.Drwg. No.
3 Size of Bracket / Support
4 Area grid / Location
5 Support marking as per drawing
6 Support fixing as per Sequence
Welding / threading / Gas Cutting as per given
7 specification
8 Checked for Alignment / Orientation
9 Checked for referance level
10 Painting and coating
11 Pipe Material
12 Size of pipe
13 Marking the position of pipe at site.
14 "V" groove making as per specification
15 Pipe cleaning before Installation or Painting
Welding / Cutting / threading / GasCutting / Solevant /
16
Cement joint as per given specification
17 Pipe checked for Alignment / Orientation
18 Pipe checked for reference level
19 Painting and coating
20 Pressure Testing
21 Final Painting
22 Result
23 Measurements

Inspected By:

Sub-Contractor Rep. MEP Engineer

Shapoorji Pallonji E&C Page 1 of 1


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

TESTING REPORT FOR GI/CI/SW/LA CLASS/UPVC/RCC/COPPER PIPE

S.No. DESCRIPTION REMARKS


1 Date
2 Blocks
3 Ref. Drawing No:
4 Size of Pipe
5 Area/Location
6 Marking the position at site
Laying pipes with Threading / Welding / Dripseal /
7
Solvent / Cement / Solder
8 Alignment and orientation
9 Support, Bracket,PCC
10 Painting and Coating
11 Testing

Result

Inspected By:

Sub-contractor MEP Engineer

Shapoorji Pallonji E&C Page 1 of 1


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighti
Site Work Activity

TESTING REPORT FOR DRAIN PIPING

S.No. Description Remarks


1 Date
2 Block
3 Ref.Drwg. No.
4 Size of pipe
5 Area grid / Location
6 Bracket marking
7 Bracket fixing as per specification
8 Marking the position of pipe at site.
Laying pipes with Threading / Welding / Dripseal /
9
Solvent / Cement / Solder
10 Pipe checked for Alingment / Orientation
11 Pipe checked for referance level
12 Testing

Result

Measurements

Inspected By:

Sub-Contractor Rep. MEP Engineer

Shapoorji Pallonji E&C Page 1 of 1


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

TESTING REPORT FOR FIRE FIGHTING & SPRINKLER PIPING

Description Remarks
Block

Ref. Drg. No.

Size of Pipe

Support Size

Area grid / Location

Sopport Marking as per Drawing

Support fixing as per specification

Marking the position at site

"V" groove making as per specification

Pipe cleaning before Installatino or Painting

Welding / Cutting / Threading / Gas Cutting


as per Specification

Pipe checked for Alignment / Orientation

Pipe Checked for Referance Level

Painting And Coating

Pressure Testing

Testing Period

Final Painting

Result

Measurement

INSPECTED BY

Sub-Contractor Rep. MEP Engineer

Note / Remark:-
........
........
........
Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

HANDOVER LIST (sample)


Block Floor Date:

Sr.No. Description Unit Qty ok testing Remark


A GENTS TOILET
1 W/c Nos
2 Flush valve Nos
3 Rasing spray Nos
4 Paper Holder Nos
5 Coat Hook Nos
6 Ablution Tap Nos
7 Wash Basin Nos
8 Piller Cock Nos
9 Angle cock Nos
10 urinals Nos
11 Urinal sensor Nos
12 Floor trap jali Nos
13 Shower mixer With Showr head Nos
LADIES TOILET
1 W/c Nos
2 Flush valve Nos
3 Rasing spray Nos
4 Paper Holder Nos
5 Coat Hook Nos
6 Ablution Tap Nos
7 Wash Basin Nos
8 Piller Cock Nos
9 Angle cock Nos
10 Floor trap jali Nos
11 Shower mixer With Showr head Nos
B JANITOR ROOM
1 Janitor sink Nos
2 Piller Cock Nos
3 Angle cock Nos
4 Floor trap jali Nos
C PANTRY AREA
1 S.S.Sink Nos
2 Sink Mixer Nos

Inspected By

Sub-Contractor Rep. MEP Engineer

Shapoorji Pallonji E&C Page 1 of 1


Plumbing and Fire-fighting
A-2.2/10-20-01 - Checklist for Plumbing and Fire-fighting
Site Work Activity

HANDING OVER DELIVERABLE NOTES


Project :
Name of client :
Name of Work :
Name of Vendor :
BLOCK :

Sr no Description Remarks

1 As built Drawings - Hard Copy


2 As built Drawings - on CD
3 Snag lists if any
4 Lab test reports/ factory test reports
5 Precommissioning Test Reports-site
6 Commissioning Report
7 O & M manuals
8 Reconciliation Statement/ Attic Stock
9 Equipment warranty certificate of Manufacturer
10 Special Warranties (if any)
11 Training
12 Escalation Matrix
13 Keys & Key Schedule
All as built drawings and test certificates etc must be signed by consultants/architect.

Any other deliverables :

Signautres of Vendor's Authorized Rep. Signatures of SP E&C Representative

Date: Date: