Documente Academic
Documente Profesional
Documente Cultură
Dozers
DOZERS
GENERAL INTRODUCTION
General Introduction
How it is made up?
Where it is used ?
Typical applications
Productivity Calculation
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 2
1
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 4
2
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 5
3
19 April 2017
Ripper
This is an
Undercarriage
attachment tools This is the feet of the machine
that use to dig that use to move / turn machine
hard surfaces
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 7
DOZER USES
Typical Applications are:
Dozing / Pushing materials
Land clearing
Ripping
Towing other piece of construction
equipment
Assisting scraper in loading
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 8
4
19 April 2017
DOZING/
LEVELING
PUSHING
MATERIALS
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 9
LAND CLEARING
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 10
5
19 April 2017
ASSITING SCAPERS
RIPPING ROCKS
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 11
DOZERS TYPES
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 12
6
19 April 2017
TYPES OF DOZERS
1. Crawler / Track Type 2. Wheel Type
Wheel Dozer
Track Dozer
- Can work on variety of soil surface - Good on firm soil and concrete surface
- Can work over almost all terrain - Best for level and downhill work
- Can work on soft ground and mud-stick - Can not work on soft ground and mud-
surfaces. stick surfaces.
- Exert low ground pressure - Exert high ground pressure
- Good for short working distance - Good for long working distance
- Slow return speed - Fast return speed
- Can push large blade load - Can only push moderate blade load
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 13
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 14
7
19 April 2017
2. Wheel Dozers
The front frame and rear frame is
connected by the vertical central
pivot.
Wheels are mounted on front and
rear axles.
Power from final drive exert rimpull
force that turns the wheels and
moves machine in forward or
reverse direction. Have all powered four
Traction force can be improved by Wheel Drive.
proper tyre selection. Wider tyres Breaking action on wheels
as in Vehicle.
provide greater contact area and
increase flotation. Steering achieved by
Articulation between Front
Larger sized tyre will reduce and Rear portion of the
developed rimpull, increase Equipment
torque.
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 15
Performance Characteristics
Track type dozer is suitable for jobs that
require high tractive efforts and Wheel
type is for high speed operation.
The usable force available to perform work
is often limited by traction.
This limitation is dependent on the coefficient
of traction of surface being traversed; and
The weight carried by the drive wheels.
Coefficient Weight
Tractive Effort = of x on drive
Traction Wheel
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 16
8
19 April 2017
Performance Characteristics
Operating weight is important for usable drawbar
pull/ rimpull. Required traction pull can be improved
using ballast load.
Coefficient of Traction depend on ground surface.
Rubber tyre is better on dry hard surfaces and
Track type is better on soft and wet clay surface.
Direct drive system is better efficient for constant
load/ speed operation
Power shift transmission works better on variable
load / speed condition. They allow automatic
selection of speed best suited for the load.
The performance chart for rimpull/ drawbar pull are
based on standard equipment including tire.
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 17
Performance Characteristics
Coefficient of Traction for Various Surfaces
Surface Rubber tire Crawler / Track
Dry, rough concrete 0.80 - 1.00 0.45
Dry, clay 0.50 - 0.70 0.90
Wet, clay 0.40 - 0.50 0.70
Wet sand and gravel 0.30 - 0.40 0.35
Loose, dry sand 0.20 - 0.30 0.30
Dry snow 0.20 0.15 - 0.35
Ice 0.10 0.10 - 0.25
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 18
9
19 April 2017
Dozer Specifications
Machine (Make/ Model/ Sr. No., overall dimension)
Operating Weight (kN) (with operator, cabin and all
standard items accessories)
Engine (Make/ Model/ Sr. No./Type, Cly. No./stroke,
CI/SI, Torque/ RPM/ Cooling type
Flywheel Power (kW)
Undercarriage (Track shoe size type, roller no., track length,
ground pressure etc.)
OR
Wheel (Tire size: dia. Width, type)
Transmission (make/model/ type)
Hydraulic System
Bucket (Type, Length, height, SAE capacity)
Cabin (ROPS, FOPS)
Performance Data / Chart (Gear/ Speed/Rimpull)
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 19
10
19 April 2017
(Performance
Chart for a
(CAT- D7G),
150 kW, 203
kN Track type
dozer with a
Power-shift.)
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 2
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 22
11
19 April 2017
(Performance Chart
for a CAT, 161 kW,
202 kN, Wheel type
dozer with Power-
shift.)
Performance Comparison
Usable drawbar pull/ rimpull depend on the weight
and traction of fully equipped dozer
Even though, the engine can develop a certain
drawbar pull or rimpull force all the pull may not be
available to do the work.
Example-1:
Consider a Track-type and a Wheel-type dozers with power-
shift transmission having same drawbar and rimpull of 200 kN
and 202 kN respectively. If the working surface is dry clay
loam, what are the usable pull for each Dozer.
Track Dozer:
Coefficient of Traction = 0.90 (From the table)
Usable Drawbar Pull = 200 x 0.9 = 180 kN
Wheel Dozer:
Coefficient of Traction = 0.60 (From the table)
Usable Drawbar Pull = 202 x 0.6 = 121.2 kN
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 24
12
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 25
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 26
13
19 April 2017
Dozers BLADE
BLADE is the main working
tools (Implements) mounted
BLADE C-Frame
on C frame in front of the
machine perpendicular to
direction of travel which
PUSH (cut/ shear/ rolls) earth
cutting in forward direction.
In the case of ANGLE
DOZER blade is mounted on
C frame at a set angle with
direction of travel and push
materials forward at one side.
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 27
BLADES: Types
The blade attached to the machine must be
matched to expected work. They are classified
base on geometrical shape.The most commonly
used STANDARD blades are:
Straight (S-blade)
(A-Blade)
Angle (A-blade) (S-Blade)
Universal (U-blade)
Cushioned (C-blade)
(U-Blade) (C-Blade)
14
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 29
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 30
15
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 31
Blade Performance
A Dozers pushing potential is measured by
two standards
Power per unit length of cutting edge (kW/m)
Power per unit volume (loose) of material
retained in front of Blade (kW/lcm)
kW/m provide the indication of the ability to
blade to penetrate and obtain load. The
higher the ratio, more aggressive the blade
kW/lcm measure the ability of blade to push
load. The higher the ratio can push material
at greater speed.
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 32
16
19 April 2017
Dozer Productivity
How dozer productivity estimated ?
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 33
17
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 35
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 36
18
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 37
Manufacturers rating
Equipment may provide blade rating
based on SAE recommendation (J1265):
Vs = 0.8*W*H2
Vu = Vs + Z*H*(W-Z)*tan()
Where:
Vs = Capacity of straight blade or angling blade (lcm)
Vu = Capacity of universal blade (lcm)
W = Blade width (m), exclusive of end bits
H = Effective blade height (m)
Z = Wing length measured parallel to the blade width (m)
= Wing angle
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 38
19
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 39
Field Measurement
Obtain a normal load:
The dozer pushes a normal blade load onto to
a level area.
Create a symmetrical pile shape as possible.
H H2
H 1
2
W W2
W 1
2
Blade Load (lcm) = 0.375 *(H*W*L)
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 40
20
19 April 2017
Example-2:
What is the blade capacity in loose cubic
meters for the tested materials ? If the
measurement taken from a blade-load test
were as follow:
H1= 1.5m; H2 = 1.6m; W1 = 2m; W2 = 2.1m
L = 3.8 m
H = (1.5+1.6)/2 =1.55m
W = (2+2.1)/2 = 2.05m
Blade Load (lcm) = 0.375 *(H*W*L)
= 0.375*1.55*2.05*3.8
= 4.53 (lcm)
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 41
21
19 April 2017
Cycle Time:
The formula to calculate Dozer production
in loose cubic meters per a 60-min hour is
given by:
60 * B.L.
P
P.T. R.T. M.T.
Where:
P = Production rate (lcm/hr.) Maneuver time (M.T.)
Power-shift = 0.05 min
B.L = Blade Load (lcm) Direct drive = 0.1 min
P.T. = Push time (minute)
R.T. = Return time (minute)
M.T. = Maneuver time (minute)
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 43
Example: 3
Considering that the blade load calculated in
above (example-2) was for a track-type dozer
equipped with a power shift transmission. The
dozer will be used to push a distance of 30m what
production can be expected in loose cubic meter.
Assume pushing speed is 3 kmph.
Blade load = 4.53 lcm (taken from above example)
Distance 30(m) 60
P.T . * 0.6 min
Push Velocity 3(km / hr) 1000
For return time the maximum speed that can attained is 6 km/h from the
performance chart (as it is only 30m distance gear can not go beyond
second speed).
Distance 30(m) 60
R.T . * 0.3 min
Return Velocity 6(km / hr) 1000
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 44
22
19 April 2017
Example: 3
M.T.= 0.05
(for power shift)
3 6
60 * 4.53
Production 286 (lcm/hr)
0.6 0.3 0.05
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 45
Example: 4
Assume a percent swell of 25% for the silty sand of the previous
example (Example-3) and that job efficiency will equal a 50-min
hour. What is the actual production that can be expected in bank
cubic meter? If the machine has owning and operating cost of
Rs.3000 per hour and operator cost Rs. 500 per hour. What is the
cost of pushing the silty sand?.
loose volume bank volume lcm
Swell(%) *100 bcm 1 swell
bank volume
50
Efficiency( E ) 0.833
60
lcm / hr 286(lcm / hr )
Pr oduction * E * 0.833 190(bcm / hr )
1 Swell 1.25
total cos t (3000 500)
Unit cos t ( Rs. / bcm) 18.4( Rs. / bcm)
bcm 190
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 46
23
19 April 2017
Production Formula
The following production formula is developed by
International Harvest (IH) and can be used as a Rule-of
Thumb formula for power shift transmission.
P (kW) *103
Pr oduction (lcm)
Where: D 15
P= Net flywheel power (kW) (Power-shift track Dozer)
D = One way distance (m)
Example-5:
A power-shift track-type Dozer with 150 kW will be used to push
materials 27m. Use the IH formula to calculate the lcm production
which can be expected for this operation.
150 *103
Pr oduction (lcm) 367.8
Note:
27 15
The actual production will be less than 367.8 lcm because there are some other factors
that can effect the production such as: efficiency, material factor, weather condition etc.)
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 47
Production Curve
Production curves for estimating the amount of
material that can push are usually provided by
manufacturer. Example of such curve can be seen
on Caterpillar Performance Handbook.
These curves are produced based on a set of ideal
conditions as follows:
100% Efficiency (60-min hour)
Power-shift machine with 0.05 min fixed time
Soil density 1370 kg/lcm
Coefficient of Traction
Track machine 0.5 or better
Wheel machine 0.4 or better
Hydraulic-control blades (Pitching/Tilting/Angling)
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 48
24
19 April 2017
Production Curve
130
NOTE: This chart is based on numerous field studies made under varying job conditions.
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 49
Production Curve
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 50
25
19 April 2017
Correction Factors
OSCF
MTCF
OTCF
VCF
ECF
MTCF
GCF
For angling and cushion blade take 50% - 75% of straight blade BAF
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 51
1.24
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 52
26
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 53
Example-6 /contd.
A D7G track dozer with straight blade is to be used in
a slot-dozing operation. The material is dry non-
cohesive silty sand and is to be moved a distance of
90m from the beginning of the cut. Dozing is downhill
on 10% grade. The operator has average skill, dozer
has power-shift transmission, and both visibility and
traction are satisfactory. The material weight 1730
kg/m3 in bank state and is estimated swell 12% in the
loose state. Job efficiency is estimated to be 50-min.
hour.
Calculate the direct cost of the proposed earth-
moving operation in Rs. / bcm. Assume that the
owning and operating cost Rs. 3000/hr. and
operators wage Rs. 500/hr.
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 54
27
19 April 2017
Solution: Example-6
P(max.)/hr = 130 (lcm) from the chart for (90m dozing distance, D7G model)
MWCF = 1730(kg/bcm)/1.12 = 1545 (kg/lcm) (For 12% Swell)
= 1370/1545 = 0.88 (As standard condition 1370 kg/lcm)
OSCF = 0.75 (from the table for average skill)
MTCF = 0.80 (from the table for dry, non cohesive material)
OTCF = 1.20 (from the table for slot dozing operation)
VCF = 1 (Satisfactory visibility, as being standard condition)
ECF = 0.83 (from the table for 50-min hour)
MTF = 1 (for power-shift transmission, as being standard condition)
BAF = 1 (as STRAIGHT type blade being used)
GCF = 1.24 (from the grade correction chart for (-10% ) grade)
Where:
q aH L 2 a = Blade Factor
H = Blade height (m)
L = Blade width (m)
Where:
D D D = Hauling Distance (m)
Cm Z F= Forward speed (m/min)
F R
R = Reverse speed (m/min)
Z = Maneuver time (min)
Forward speed = 3 5 km/ hr Z = 0.1 min for direct drive
Reverse speed = 5 7 km/hr = 0.05 min for power-shift
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 56
28
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 57
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 58
29
19 April 2017
Example-7 ../contd.
Estimate the approximate output of a bulldozer for
the following conditions:
Materials: completely loosened soil
Swell = 25%
Haul distance : 30m, over level ground
Blade Size: Height = 0.9m, Width = 2.9 m
Operation factor: 50-min hr
Pushing speed @ 2.4 kmpr
Reverse @ 5.6 kmph
Loading and gear shifting time = 0.32 min
D D
Cycle time (Cm ) Z
F R
30 * 60 30 * 60
Cm 0.32 1.39 min
(2.4 *1000) (5.64 *1000)
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 59
Example-7
Production per cycle (q)
q a H 2 L 0.9 * 0.92 * 2.9 2.11(lcm)
Assuming Blade factor (a) = 0.9 from the table
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 60
30
19 April 2017
19 April 2017 Management of Construction Plant and Equipment: By Ashok K. Shrestha Slide No. 64
31