Documente Academic
Documente Profesional
Documente Cultură
1. INTRODUCTION
1.1 GENERAL
A bridge is a structure that crosses over a river, bay, or other obstruction, permitting the smooth
and safe passage of vehicles, trains, and pedestrians. An elevation view of a typical bridge is A
bridge structure is divided into an upper part (the superstructure), which consists of the slab, the
floor system, and the main truss or girders, and a lower part (the substructure), which are columns,
piers, towers, footings, piles, and abutments. The superstructure provides horizontal spans such as
deck and girders and carries traffic loads directly. The substructure supports the horizontal spans,
elevating above the ground surface.
Steel Bridges steel bridge may use a wide variety of structural steel components and systems:
girders, frames, trusses, arches, and suspension cables.
Concrete Bridges: There are two primary types of concrete bridges: reinforced and pre-stressed.
Timber Bridges: Wooden bridges are used when the span is relatively short.
Metal Alloy Bridges: Metal alloys such as aluminum alloy and stainless steel are also used in
bridge construction.
Composite Bridges: Bridges using both steel and concrete as structural materials.
2
Aqueduct Bridges: Bridges supporting pipes with channeled water flow. Bridges can
alternatively be classified into movable (for ships to pass the river) or fixed and permanent or
temporary categories.
Plate Girder Bridges: The main girders consist of a plate assemblage of upper and lower flanges
and a web. H or I-cross-sections effectively resist bending and shear.
Box Girder Bridges: The single (or multiple) main girder consists of a box beam fabricated from
steel plates or formed from concrete, which resists not only bending and shear but also torsion
effectively.
T-Beam Bridges: A number of reinforced concrete T-beams are placed side by side to support the
live load.
Composite Girder Bridges: The concrete deck slab works in conjunction with the steel girders to
support loads as a united beam. The steel girder takes mainly tension, while the concrete slab
takes the compression component of the bending moment.
Grillage Girder Bridges: The main girders are connected transversely by floor beams to form a
grid pattern which shares the loads with the main girders.
Truss Bridges: Truss bar members are theoretically considered to be connected with pins at their
ends to form triangles. Each member resists an axial force, either in compression or tension.
Arch Bridges: The arch is a structure that resists load mainly in axial compression. In ancient
times stone was the most common material used to construct magnificent arch bridges.
3
Cable-Stayed Bridges: The girders are supported by highly strengthened cables (often composed
of tightly bound steel strands) which stem directly from the tower. These are most suited to bridge
long distances.
Suspension Bridges: The girders are suspended by hangers tied to the main cables which hang
from the towers. The load is transmitted mainly by tension in cable
Permanent Bridges
Temporary Bridges
Beam and slab bridges are probably the most common form of concrete bridge today, the success
of standard precast prestressed concrete beams developed originally by the Prestressed Concrete
Development Group (Cement & Concrete Association) supplemented later by alternative designs
by others, culminating in the Y-beam introduced by the Prestressed Concrete Association in the
late 1980s.
They have the virtue of simplicity, economy, wide availability of the standard sections, and speed
of erection.
The precast beams are placed on the supporting piers or abutments, usually on rubber bearings
which are maintenance free. An in-situ reinforced concrete deck slab is then cast on permanent
shuttering which spans between the beams.
The precast beams can be joined together at the supports to form continuous beams which are
structurally more efficient. However, this is not normally done because the costs involved are not
justified by the increased efficiency. Simply supported concrete beams and slab bridges are now
giving way to integral bridges which offer the advantages of less cost and lower maintenance due
to the elimination of expansion joints and bearings.
This is most commonly adopted type of bridge for span range of 10 to 25m.
4
It is so name because the main longitudinal girder are designed as T-beam which is integral part of
deck slab cast monolithically with the deck slab.
Simply supported T-beam spans of over 25m are rare as the dead load then becomes too heavy.
However there is a bridge have single span of 35m named Advice Bridge in Goa.
In other words we can say T-beam Bridge is the combination of [deck slab with longitudinal
girders & cross girders] superstructure & [piers, abutment & foundations] substructure.
1.4 BACKGROUND
Nearly 590,000 roadway bridges span waterways, dry land depressions, other roads, and railroads
throughout the United States. The most dramatic bridges use complex systems like arches, cables,
Figure 1 Beam Bridge Timber Framed
5
or triangle-filled trusses to carry the roadway between majestic columns or towers. However, the
work-horse of the highway bridge system is the relatively simple and inexpensive concrete beam
bridge.
Also known as a girder bridge, a beam bridge consists of a horizontal slab supported at each end.
Because all of the weight of the slab (and any objects on the slab) is transferred vertically to the
support columns, the columns can be less massive than supports for arch or suspension bridges,
which transfer part of the weight horizontally.
A simple beam bridge is generally used to span a distance of 250 ft. (76.2 m) or less. Longer
distances can be spanned by connecting a series of simple beam bridges into what is known as a
continuous span. In fact, the worlds longest bridge, the Lake Pontchartrain Causeway in
Louisiana, is a pair of parallel, two-lane continuous span bridges almost 24 mi (38.4 km) long.
The first of the two bridges was completed in 1956 and consists of more than 2,000 individual
spans. The sister bridge (now carrying the north-bound traffic) was completed 13 years later;
although it is 228 ft. longer than the first bridge, it contains only 1,500 spans.
A bridge has three main elements. First, the substructure (foundation) transfers the loaded weight
of the bridge to the ground; it consists of components such as columns (also called piers) and
abutments. An abutment is the connection between the end of the bridge and the earth; it provides
support for the end sections of the bridge. Second, the superstructure of the bridge is the
horizontal platform that spans the space between columns. Finally, the deck of the bridge is the
traffic-carrying surface added to the superstructure.
1.5 HISTORY
Prehistoric man began building bridges by imitating nature. Finding it useful to walk on a tree that
had fallen across a stream, he started to place tree trunks or stone slabs where he wanted to cross
streams. When he wanted to bridge a wider stream, he figured out how to pile stones in the water
and lay beams of wood or stone between these columns and the bank.
The first bridge to be documented was described by Herodotus in 484 B.C. It consisted of timbers
supported by stone columns, and it had been built across the Euphrates River some 300 years
earlier.
Most famous for their arch bridges of stone and concrete, the Romans also built beam bridges. In
fact, the earliest known Roman Bridge, constructed across the Tiber River in 620 B.C., was called
the Pons Sublicius because it was made of wooden beams (sublicae). Roman bridge building
techniques included the use of cofferdams while constructing columns. They did this by driving a
circular arrangement of wooden poles into the ground around the intended column location. After
lining the wooden ring with clay to make it watertight, they pumped the water out of the
enclosure. This allowed them to pour the concrete for the column base.
Bridge building began the transition from art to science in 1717 when French engineer Hubert
Gautier wrote a treatise on bridge building. In 1847, an American named Squire Whipple wrote A
6
Work on Bridge Building, which contained the first analytical methods for calculating the stresses
and strains in a bridge. "Consulting bridge engineering" was established as a specialty within civil
engineering in the 1880s.
Further advances in beam bridge construction would come primarily from improvements in
building materials.
Concrete has good strength to withstand compression (pressing force), but is not as strong under
tension (pulling force). There were several attempts in Europe and the United States during the
nineteenth century to strengthen concrete by embedding tension-resisting iron in it. A superior
version was developed in France during the 1880s by Francois Hennebique, who used reinforcing
bars made of steel. The first significant use of reinforced concrete in a bridge in the United States
was in the Alvord Lake Bridge in San Francisco's Golden Gate Park; completed in 1889 and still
in use today, it was built with reinforcing bars of twisted steel devised by designer Ernest L.
Ransome.
The next significant advance in concrete construction was the development of prestressing. A
concrete beam is prestressed by pulling on steel rods running through the beam and then
anchoring the ends of the rods to the ends of the beam. This exerts a compressive force on the
concrete, offsetting tensile forces that are exerted on the beam when a load is placed on it. (A
weight pressing down on a horizontal beam tends to bend the beam downward in the middle,
creating compressive forces along the top of the beam and tensile forces along the bottom of the
beam.)
Prestressing can be applied to a concrete beam that is precast at a factory, brought to the
construction site, and lifted into place by a crane; or it can be applied to cast-in-place concrete that
is poured in the beam's final location. Tension can be applied to the steel wires or rods before the
concrete is poured (pretensioning), or the concrete can be poured around tubes containing
untensioned steel to which tension is applied after the concrete has hardened (posttensioning).
1.7 DESIGN
Each bridge must be designed individually before it is built. The designer must take into account a
number of factors, including the local topography, water currents, river ice formation possibilities,
wind patterns, earthquake potential, soil conditions, projected traffic volumes, aesthetics, and cost
limitations.
7
In addition, the bridge must be designed to be structurally sound. This involves analyzing the
forces that will act on each component of the completed bridge. Three types of loads contribute to
these forces.
Dead load refers to the weight of the bridge itself.
Live load refers to the weight of the traffic the bridge will carry.
Environmental load refers to other external forces such as wind, possible earthquake action, and
potential traffic collisions with bridge supports. The analysis is carried out for the static
(stationary) forces of the dead load and the dynamic (moving) forces of the live and
environmental loads.
Since the late 1960s, the value of redundancy in design has been widely accepted. This means that
a bridge is designed so the failure of any one member will not cause an immediate collapse of the
entire structure. This is accomplished by making other members strong enough to compensate for
a damaged member.
8
1.8.1 Substructure
A cofferdam is constructed around each column location in the riverbed, and the water is
pumped from inside the enclosure. One method of setting the foundation is to drill shafts through
the riverbed, down to bedrock. As an auger brings soil up from the shaft, a clay slurry is pumped
into the hole to replace the soil and keep the shaft from collapsing. When the proper depth is
reached (e.g., about 80 ft. or 24.4 m), a cylindrical cage of reinforcing steel (rebar) is lowered
into the slurry-filled shaft (e.g., 72 in or 2 m in diameter). Concrete is pumped to the bottom of
the shaft. As the shaft fills with concrete, the slurry is forced out of the top of the shaft, where it
is collected and cleaned so it can be reused. The aboveground portion of each column can either
be formed and cast in place, or be precast and lifted into place and attached to the foundation.
Bridge abutments are prepared on the riverbank where the bridge end will rest. A concrete
backwall is formed and poured between the top of the bank and the riverbed; this is a retaining
wall for the soil beyond the end of the bridge. A ledge (seat) for the bridge end to rest on is
formed in the top of the backwall. Wing walls may also be needed, extending outward from the
back-wall along the riverbank to retain fill dirt for the bridge approaches.
1.8.2 Superstructure
A crane is used to set steel or prestressed concrete girders between consecutive sets of columns
throughout the length of the bridge. The girders are bolted to the column caps. For the
Albuquerque freeway bridge, each girder is 6 ft. (1.8 m) tall and up to 130 ft. (40 m) long,
weighing as much as 54 tons.
Steel panels or precast concrete slabs are laid across the girders to form a solid platform,
completing the bridge superstructure. One manufacturer offers a 4.5 in (11.43 cm) deep
corrugated panel of heavy (7-or 9-gauge) steel, for example. Another alternative is a stay-in-
place steel form for the concrete deck that will be poured later.
9
1.8.3 Deck
A moisture barrier is placed atop the superstructure platform. Hot-applied polymer-modified
asphalt might be used, for example.
A grid of reinforcing steel bars is constructed atop the moisture barrier; this grid will
subsequently be encased in a concrete slab. The grid is three-dimensional, with a layer of rebar
near the bottom of the slab and another near the top.
8 Concrete pavement is poured. A thickness of 8-12 in (20.32-30.5 cm) of concrete pavement is
appropriate for a highway. If stay-in-place forms were used as the superstructure platform,
concrete is poured into them. If forms were not used, the concrete can be applied with a slip
form paving machine that spreads, consolidates, and smooths the concrete in one continuous
operation. In either case, a skid-resistant texture is placed on the fresh concrete slab by manually
or mechanically scoring the surface with a brush or rough material like burlap. Lateral joints are
provided approximately every 15 ft. (5 m) to discourage cracking of the pavement; these are
either added to the forms before pouring concrete or cut after a slip formed slab has hardened.
A flexible sealant is used to seal the joint.
Aggregate weight of complete structure elements such as deck, wearing coat, parapets,
stiffeners and utilities.
It does not changes its direction and magnitude with respect to the passage of time.
2. Live Load
Includes vehicle live load that are moving on the bridge.
IRC has categorized standards of vehicle live load as under three following category which
is-
(a) IRC CLASS AA LOADING
Treated as heavy loading and all NH & SH and industrial areas bridge are designed for
only IRC class AA loading.
If a bridge designed for IRC class AA loading then it will automatically satisfied IRC class
A & class B loading.
It has two pattern of loading
(I) tracked type (ii) wheeled type
(b) IRC CLASS A LOADING
Generally treated as standard loading for permanent bridges.
Having eight axles with a total length of 25m.
IRC CLASS B LOADING
12
3. Impact load
It is account for the dynamic effects of sudden loading of a vehicle on bridge structure.
It is calculated by multiplying the live load with an impact factor.
The impact factor is calculated as the IRC-6 suggested which are discussed below.
Figure 5 Impact Percentage for Highway Bridges for Class A and Class B Loading (clause 208.2)
4. Centrifugal force
Consider for bridge constructed on horizontal curve.
Considered to act at a height of 1.2m above the level of carriage way.
2
= 127
2.3 DESIGN
It is designed by either effective width method or by Pigeauds curve method as bending
moment calculation.
After calculation of bending moment we provide reinforcement and then do check for shear as
accordance by WSM method of RCC design.
Normal depth of deck slab is very from 350mm to 500mm.
In the same manner as effective width of dispersion there is also an effective length of dispersion
measured along the direction of movement of vehicle.
Calculated as- for both simply supported case as well as cantilever case
Dispersion length = length of tyre contact + 2(overall thickness of deck including wearing
coat)
Leff. = B + 2(D+2h)
Where
Leff. =effective length of dispersion
d=overall thickness of bridge deck
h=thickness of wearing coat
Pigeauds method
Short span (B) & long span (L) bending moment coefficients are read from curves
developed by M. Pigeaud.
Used for only 2-way slab design or slabs supported along four edges with restrained
corners and subjected to symmetrically placed loads distributed over some well-defined
area.
Curves developed for thin plates using the elastic flexural theory. However their use has
been extended to concrete slab too.
The short span (B) & long span (L) bending moment is calculated by following
expressions.
Short span B.M. =W (m1 +0.15m2) along the width (B) of slab.
Long span B.M. =W (0.15m1 +m2) along the length (L) of slab.
2.5 LIVE LOAD BENDING MOMENT DUE TO IRC CLASS A WHEELED VEHICLE
Size of one panel of deck slab = 2.5 m 3.9 m
For most severe moments, the rear axle of the vehicle having load of 114 KN is placed
symmetrically on the slab as shown
Tyre contact dimensions are 500 mm 250 mm
Figure 7 LIVE LOAD BENDING MOMENT DUE TO IRC CLASS A WHEELED VEHICLE
Since, the loading is unsymmetrical w.r.t X axis and Y axis, we assume the loading to consist of a
strip with UDL and subtracting the area not covered.
1141.1764
Loading intensity = =431.234 KN/m2
0.6850.454
Consider the loaded area of 2.2 0.46
K=0.21
1/K=4.781
For this area, m1 =0.027, m2 = 0.0025
Moment along shorter span = (0.027+ 0.15 0.0025) 2.2 0.46 431.25
19
= 11.95 KN-m
Moment along long span = (0.0025 + 0.15 .0027)2.2 0.46 431.23
= 2.86 KN-m
Consider the area between the loads- i.e. 1.10 0.46 m
K=0.418, 1/K = 0.35
m1 = 0.045 m2 = 0.005
Moment along shorter span = (0.045 +0.15 0.005) 1.1 0.46 461.234
= 3.47 KN-m
Moment along shorter span = (0.005 +.15 0.045) 1.1 0.46 431.234
= 2.564 KN-m
For all wheels 1, 2, 3 & 4;-
1
Net B.M. along the short span = 2 (11.95-3.47)
= 4.24 KN-m
1
Net B.M. along the longer span = 2 (2.86-2.564)
= 0.148 KN-m
Total B.M.
Total B.M. along short span = 4 4.24 =16.96 KN-m
Total B.M. along long span = 4 0.15 =0.6 KN-m
Since, the above calculation has assumed a simply supported slab. The deck slab, however is
continuous .so to allow for continuity, moments are multiplied by 0.8
Design B.M. along short span = 0.8 (46.96 +2.745)
= 15.764 KN-m
Design B.M. along short span = 0.8 (1.255+ 0.6)
= 1.484 KN-m
2.6 REINFORCEMENT
Using M25 grade concrete, cbc = 8.3 MPa
20
15.76410001000
Effective depth required = =120 mm
1.101000
The critical section for bending moment is the vertical section at the junction of the
cantilever portion and the end of longitudinal girder.
The design bending moment for cantilever slab portion is calculated as the sum of 0.2
times of dead load bending moment plus 0.3 times of live load bending moment.
Moment
S.No. Description Loading Lever arm
KN-m
1. Hand rails 1.74 1.40 2.44
2. Kerb (0.4750.27424) 3.13 1.34 4.19
3. Wearing course (1.10.07522) 1.81 0.55 1.00
4. Slab (1.5750.124) 3.78 0.79 2.99
0.50.251.57524 4.72 0.52 2.45
3.4 REINFORCEMENT
61.3310001000
Effective depth required = = 236 mm
1.11000
33.32719.519.5
Maximum B.M. = = 1584 KN-m
8
= 1.89W
4
RB = [1 + 0] = 1.33W
3
Rc = 4W (1.89+1.33) W
=0.78W
In the longitudinal directions the eight load of IRC Class A train can be accommodated as shown
.The C.G. of the loading system lies at 9558 mm from the first load. Maximum moment occurs
under the 5th load from the left.
From the condition shown in above fig. Maximum B.M. occurring under the fourth load is
1041.26 KN-m.
27
Use 6-22 mm diameter at bottom and 3-22 mm diameter rods at the top
Nominal shear provision: 4-legegd stirrups 10 mm diameter at 150 mm c/c shall suffice
6 BEARING
Bearing are mechanical arrangement provided in the superstructure to transmit the load to the
sub- structure. Thus it is a via media between superstructure and sub-structure which transmit
the load from superstructure in such a manner that bearing stresses induced in the subset are
within permissible limits.
7 SUBSTRUCTURE
A support of concrete or masonry for superstructure of bridge.
The base of a pier may rest directly over firm round or it may be supported on piles.
Center line of pier normally coincide with the center line of the superstructure. The dimensions of
the top of a pier depends on distances between girder (longitudinal girder) and distance required to
provide for the expansion of girder, size of bearing etc.
IRC 40 gives minimum top width of pier and abutment.
7.3 DESIGN
Cantilever Slab
Assumed slope is 3:1
So area of Cantilever Slab
0.675 0.1
W3 x 1.725
2
Weight W3 = 625.6575 KN
Cross Beam = [(1.275 0.675) x 0.250 x 24 x 2.2 ] x6 x 2
W4 = 127 KN (approximately)
T- Beam (longitudinal)
W5 = (0.8 x .3 x 24) x 3 x 19.5
= 336.96 KN
Other loads
Hand Rails = 1.74 KN
Kerb = 3.13 KN
W6 = 4.87 KN
Total dead load of one span
W = 1839.03 KN
Let take load for calculation = 2000KN
7.8 ABUTMENTS
An abutment is a structure that support one end of a bridge in other word we can say that it is a
structure located at the end & at the beginning of a bridge.
Functions of abutment
Support the bridge deck at end.
Retain the embankment of approaching road.
Connected the approach road to the bridge deck.
8 DESIGN OF FOUNDATION
Design of foundations is an important part of overall design of a bridge. In order to design a
foundation for a bridge, we need to determine the following:
Maximum scour depth:
It is calculated using the formula:
D = 0.473(Q/f) 1/3
of sinking efforts and erection of shuttering, a single large diameter well is nowadays preferred to a
group of small sized wells.
A well foundation consists of the following components:
(a) Well curb
(b) Steining
(c) Bottom plug
(d) Sand filling
(e) Top plug
(f) Well cap.
The thickness of steining should not be less than 450 mm nor less than that given by equation
T= k (0.01H + 0.1D)
Where t= minimum thickness of concrete steining
H= full depth to which the well is designed to be sunk below the bed
D=external diameter of the well
K=a constant depending on the nature of subsoil, taken as 1.0 for sandy strata,
1.1 For soft clay, 1.25 for hard clay and 1.3 for hard soil with boulders.
The concrete well steining is reinforced with-longitudinal bond rods and hoop rods
on both faces of the well. The minimum reinforcement will be 9 kg/ms for bond
rods and 3.3 kg/m3 for hoops. The minimum cover to bond rods is 75 mm.
A bottom plug is essential to transfer the load from the well steining to the base
soil. It is usually provided for a thickness of about half the diameter of the dredge
hole .In practice the bottom plug is provided up to a height of 0. 3 m above the top
of well curb in case of small diameter wells .and 0.6 min case of large-diameter
42
wells. The concrete used is of M20 grade, the richness of the mix being
necessitated by the possibility of loss of part of the cement due to under-water
placing of the concrete.
8.3 DESIGN
Catchment area of chhoti gandak river = 3565 km2
Since River bed material is fine sand, silt factor K will be in the range of 0.5-0.68
Assuming K = 0.6
Given discharge Q = 375 cumec
According to IS 78:2014 Design discharge = 1.3 x 375
= 487.5 cumec
Theoretical linear waterway = 4.83
= 4.83 375
= 93.54 m
Effective linear waterway = 93.54 (3 x 2.7)
= 85.44 m
3 2
Mean depth of scour below HFL, dsm= 1.34 x
375
q = 85.44 = 4.39 m2/s
3 4.392
dsm =1.34 x 0.6
= 3.2m
Let us take 7 m
For abutments = 1.27 dsm
= 1.27 x 3.2 m
= 4.064 m
1
Minimum grip length for well foundation below design scour level = x dmax
3
1
For piers = x 6.4 = 2.2 m 2.5m
3
1
For abutment = x 4.064 = 1.355 1.5m
3
43
Well Steining
Thickness t = K x d
L = Depth of wells below LWL
K = Constant
For well in cement concrete K = 0.03
L = (7 + 2.5) (99.8- 93.8)
= 3.5 m
d = 10 m
t = 0.03 x 10 x 3.5
= 0.561m
Provide t = 1 m
9 CONCLUSIONS
9.5 PIER
Height = 9m
Cross section at bottom = 8.2 m x 2.7 m
9.6 FOUNDATION
External dia = 10 m
Internal dia = 8.2 m
Width of pier cap = 1.9 m
Thickness of well cap = 0.8 m
Thickness of well steining = 1 m
50
10 REFERENCES
1. IRC: 5 - 1998, "Standard Specifications and Code of Practice for Road Bridges, Section I
General Features of Design", The Indian Road Congress.
2. IRC: 6 - 2000, "Standard Specifications and Code of Practice for Road Bridges, Section II
- Loads and Stresses", The Indian Road Congress.
3. IRC: 78 2014, Standard Specifications and Code of Practice for Road Bridges, Section
VII Foundation and Substructure, The Indian Road Congress.
4. IS: 456 - 2000, "Plain and Reinforcement Concrete - Code of Practice", Bureau of Indian
Standards, New Delhi, 2000.