Documente Academic
Documente Profesional
Documente Cultură
a r t i c l e i n f o a b s t r a c t
Article history: Due to the increasing deployment of intermittent renewables, the residual load prole, as seen by the dis-
Received 24 January 2014 patchable generation units, becomes lower and more volatile. This paper introduces a new system plan-
Received in revised form 21 January 2015 ning model on a power plant resolution, taking into account technical operational constraints. The
Accepted 20 February 2015
objective of this model is to determine the optimal set of generation units, able to serve a given demand.
Available online 12 March 2015
Two initial solutions are obtained; one from a classical screening curve model, and another from a model
using mixed integer linear programming (MILP). These initial solutions are perturbed and combined with
Keywords:
an operational model to validate and further improve the solution. The developed model complements
Power system planning
Renewables
other models available from the literature, in its level of detail (power plant level and full year hourly
Screening curve time resolution) combined with a fast computation time (<1 h). The evolution of the optimal amount of
Unit commitment generation capacity as a function of the installed wind capacity is examined in a case study. As the share
Wind power of wind power increases in the portfolio, a shift takes place from base load generation towards mid and
peak load. This shift is triggered both by the lower demand and the increasing volatility. This demon-
strates that operational constraints of power plants (individual basis) have an important impact on the
conguration of the optimal generator set, and need being considered, especially at increasing rates of
intermittent renewables.
2015 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.ijepes.2015.02.033
0142-0615/ 2015 Elsevier Ltd. All rights reserved.
34 A. Belderbos, E. Delarue / Electrical Power and Energy Systems 71 (2015) 3341
Nomenclature
Parameters Variables
Ai fuel cost at minimum output [/h] d(i, j, l) generated electric power in each segment [MW]
ai constant coefcient of quadratic cost function [/h] cap(t) installed capacity [MW]
bi rst order coefcient of quadratic cost function fc xed cost []
[/MW/h] fu(i, j) fuel cost [/h]
ci second order coefcient of quadratic cost function gt; j hourly generation [MW]
[/MW2/h] om(i, j) variable operation and maintenance cost [/h]
Dj demand [MW] sc(i, j) startup cost []
F i;l slope of linearized cost function [/MW h] tc total cost []
fcrt relative xed cost [/MW/y] ui investment status []
MDT i minimum down time [h] vc variable cost []
MUT i minimum up time [h] zi; j commitment status []
OMi variable operation and maintenance cost [/MW h]
evaluating classic system planning approaches, which are also Other models start from an operational model and include the
often used as such in this context. investment decision as a variable, taking into account a limited
Several power system planning models have been developed number of time periods [25]. A recent formulation/analysis, com-
over time [4]. While some focus on the expansion of the transmis- bining full year representation and power plant resolution has
sion and/or distribution system [5,6], the scope of this work is on been presented by Palmintier [26,27]. A clustered UC formulation
expansion of the electricity generation system. The textbook exam- is proposed, embedded in a planning model formulation.
ple of generation system planning optimization is the so-called Compared to the existing literature, this paper presents a novel
load duration based or screening curve approach (see, e.g., approach for system planning optimization. It takes a full year
Stoft [7]). Several specic features have been added to such plan- horizon (with hourly time steps) into account and works on a pow-
ning models. Santos and Legey incorporate environmental costs er plant resolution (rather than on a technology basis), taking into
in an expansion planning model [8]. Delgado et al. use a planning account technical operational constraints (with binary variables).
model in a stochastic setting to focus on the impact of nuclear The developed modeling methodology can be solved in relatively
(they for instance consider different scenarios for fuel and allow- limited calculation time (<1 h). It can therefore easily be used for
ance prices) [9]. Unsihuay-Vila et al. consider both generation broader system studies and sensitivity analyses. This model is then
and transmission expansion planning, in a load duration based used to quantify the impact of taking into account technical con-
model setting with multiple objectives (i.e., cost, life-cycle emis- straints of power plants, and as such, addresses the impact of inter-
sions and diversication) [10]. mittent RES on electricity generation planning. This way, the
RES integration (e.g., wind) is often studied from an operational present research adds to the available literature, by the develop-
viewpoint (see, e.g., [11,12]). However, also from a planning per- ment of the model and the quantitative insights stressing the rele-
spective, the exibility requirement in modeling is being acknowl- vance of operational characteristics.
edged [13]. Recent developed models for system planning made The structure of this paper is as follows. The next section presents
efforts to take explicitly into account the exibility limitations of the problem formulation, rst for the power system planning model
thermal generators, focusing on wind power integration, preserv- (on technology basis), second for an operational optimization (UC)
ing the chronological order of time segments (hourly or aggregat- and third for an integrated approach. Section Integrated system
ed) [14,15]. Delarue et al. also added uncertainty on cost planning model with operational constraints presents the newly
parameters as risk in such framework [16]. Also in existing bot- developed methodology. In Section Model simulations the
tom-up modeling frameworks, such as ReEDS [17] and TIMES simulation results of the case study are presented and discussed.
[18,19], the impact of RES are being studied. These models are Section Conclusion concludes this paper.
typically set-up as linear models, working on technology rather
than individual power plant basis, and considering a limited set
of so-called time-slices, to represent the variations in demand Problem formulation
and RES generation. Within such frameworks, efforts have recently
been made to expand the temporal resolution, to cover the full Many models exist to optimize the electricity system. The mod-
8760 h [20]. Such improved representation can have signicant els relevant in the context of this paper can be traditionally divided
impact on the actual amount of RES generation achieved in a sys- in several groups (see discussion in previous section), i.e., the sys-
tem or on CO2 emissions [21,22]. Several approaches also have tem planning models, the operational scheduling models or a com-
used planning models as TIMES, soft-linked to an operational mod- bined approach. A problem formulation of each model type will be
el to validate results in technical terms [23,24]. elaborated below.
A. Belderbos, E. Delarue / Electrical Power and Energy Systems 71 (2015) 3341 35
System planning variable O&M cost om, over all power plants i and all time periods
j (in this case hourly time steps):
The objective of this model type is to determine the optimal mix X X X
minimize v c fui; j TP sci; j omi; j TP 6
of generation technologies able to meet a given load. The mix of
i;j i;j i;j
generation technologies has to be optimal in a cost effective way,
based on xed and variable costs. The technology specic xed The fuel cost of a power plant is typically a quadratic function of
cost is an annualized cost [/MW/y], covering investment as well its output g and commitment status z (with a; b and c the cost coef-
as xed operation and maintenance costs. The technology specic cients) [29]:
variable cost [/MW h] encompasses fuel and variable operational 2
and maintenance costs. fui; j ai zi; j bi g i; j ci g i; j ; 8i 2 I; 8j 2 J 7
A system planning model can be formulated as linear program This (convex) quadratic cost function can be linearized by a
(LP) which uses only continuous variables. The solution of the number of stepwise linear segments (index l. Let Pmax and
model is expressed as an amount of generation capacity for each Pmin be the maximum and minimum power output (if online)
generation technology. The lack of discrete variables implies that respectively, A the fuel cost at minimum output, F l the slope of
no discrete number of generation units can be calculated. the cost function of segment l, and T l the upper bound power lim-
Furthermore no inter-hourly constraints are taken into account it of each segment (note that in this case for the last segment nl:
(as there is no resolution on power plant level). The time horizon T nl = Pmax). With d the actual power generation in each segment l,
of a system planning method is at least one year. the fuel cost and generation limits are set by the following
The objective of a basic system planning model is to minimize equations:
the overall cost tc [] (for a one year period). This cost is equal to X
the sum of the xed cost fc [] and variable cost vc []: fui; j Ai zi; j F i;l di; j; l; 8i 2 I; 8j 2 J 8
l
Minimize tc fc v c 1 X
gi; j Pmini zi; j di; j; l; 8i 2 I; 8j 2 J 9
The xed cost is the sum of the xed costs of the different l
installed technologies t (set T, with fcr the relative xed cost for
each technology [/MW/y] and cap the installed capacity [MW]: g i; j 6 Pmaxi zi; j; 8i 2 I; 8j 2 J 10
X
fc fcr t capt 2 di; j; l 6 T i;l T i;l1 ; 8i 2 I; 8j 2 J; 8l 2 . . . nl 11
t
The variable cost is the sum of the variable cost over all tech- di; j; l 6 T i;l Pmini ; 8i 2 I; 8j 2 J; l 1 12
nologies t and all time periods j (every hour of the year), with vcr
the relative variable cost [/MW h], and g the hourly generation di; j; l P 0; 8i 2 I; 8j 2 J; 8l 2 L 13
[MW] (TP is the operational time period length, equal to 1 [h]):
Parameter Ai is the cost [/h] at minimum output, and deter-
X
vc v crt gt; j TP 3 mined as
t;j 2
Ai ai bi Pmini ci Pmini ; 8i 2 I; 8j 2 J 14
For every hour j, the total generation needs to meet the demand
D, while the hourly generation per technology is restricted by the The commitment status z is a binary variable:
installed capacity: zi; j 2 f0; 1g; 8i 2 I; 8j 2 J 15
X
g t; j Dj ; 8j 2 J 4 The startup cost is a function of the time p the plant has been off
t line, previous to the startup. This is implemented as follows, with
parameter SC p presenting the startup cost if previously shut down
g t; j 6 capt; 8t 2 T; 8j 2 J 5 for p hours (set P:
" #
The optimization of this basic model corresponds to obtaining a X
p
Finally, the minimum up and down times (MUT and MDT, System planning models
Inial validaon
Integrated model
The above discussed models can now be combined, to include System planning models
investment decisions (system planning) on the one hand, as well
as a resolution on generation unit level and high technical detail, In a rst stage two different system planning approaches are
on the other hand. Towards this end, the system planning model developed and used, to obtain a power plant portfolio on gen-
is adjusted to run on power plant level (discrete generation units eration unit level. This solution will then be validated in opera-
index i instead of technology level (index t. An additional bina- tional terms and can be assessed as such. Furthermore, this
ry variable u is introduced to represent the investment decision in solution will also serve as a starting solution for further iterative
certain unit i. The initial set I of power plants should be sufciently improvement by the perturbation algorithm.
expanded, to include enough (possible) units of each technology, to
make an actual optimization possible, also in planning.
X Screening curve model
fc fcr i Pmaxi ui 24 The rst model is based on a basic screening curve model as
i presented before in Section System planning (solved by linear
The following constraints further need to be set on u: programming). The demand considered in the model formulation
is the original demand increased with the required reserves. The
ui P zi; j; 8i 2 I; 8j 2 J 25 temporal resolution is one hour, and the horizon of this model is
one year. The initial output of this screening curve model is a con-
ui 2 f0; 1g; 8i 2 I 26 tinuous amount of generation capacity. In order to use this result, it
is converted to a discrete number of generation units. This is done
The variable cost of the system planning model (Eq. (3)) is
replaced by the more detailed variable cost of the operational mod- by rounding-up the installed capacity per generation technology to
the nearest multiple of the capacity of a single unit.
el, as dened in Eq. (6). Hence, the integrated model has objective
function Eq. (1), and constraints (6), (8)(26).
Such integrated model could in theory determine the optimal MILP system planning model
set of generation units [30]. However, since the computational A second system planning model is an MILP model with the
requirements increase exponentially with the time horizon, it is investment decision as an extra variable. This model is essentially
extremely difcult to solve the optimization problem for an entire a direct implementation of the integrated model as described ear-
year due to computational limitations. A typical solution for this lier (objective Eq. (1), and constraints (6), (8)(26)), as MILP.
problem is provided in Section System planning models. As this problem formulation is too complex to solve for a
time horizon of an entire year, a typical approach is to use a set
Integrated system planning model with operational constraints of representative days/weeks (see, e.g., [25]). These different
representative periods (days up to weeks) can each be modeled
In this section, a new modeling approach is described, allowing in a cyclic way, and thus are decoupled in operational terms. The
to optimize the integrated system planning model (as described in investment variables, however, are set over all representative
Section Integrated model), incorporating technical constraints periods as a whole. In the model simulations, a set of three repre-
with an hourly and power plant level resolution, in an acceptable sentative days will be used. A methodological illustration is pre-
computation time. sented in Fig. 2.
It is important to capture the uctuations in demand during the
Overall methodology year. Hence, the three time periods are selected as the day that
contains the minimum demand level of the year, the day that con-
The overall model consists of different sub-models. First an ini- tains the maximum demand level and the day that contains the
tial set of power plants is determined. Second, this initial set is largest demand spread in 24 h. The importance of each time period
used in combination with an operational model to rst validate is weighted in such way that the weighted sum of the hourly
the solution in operational terms, and second to iteratively adjust demand of the three selected days equals the overall original
the portfolio of power plants to move towards an optimal solution demand of the entire year.
(perturbation algorithm together with operational UC model). An
overview of this methodology is presented in Fig. 1.
As shown in Fig. 1, different system planning models are used to
determine the initial set of power plants. The performance of each
system planning model is discussed together with the simulation
results in Section Model simulations.
The different sub-models (system planning models, perturba-
tion algorithm and operational UC model) are now discussed. Fig. 2. Cyclic linkage of three representative periods.
A. Belderbos, E. Delarue / Electrical Power and Energy Systems 71 (2015) 3341 37
The operational model formulation corresponds to Eqs. (6) and Start set Start cost
(8)(23), as presented earlier. The model used in the overall algo- Subtract generator
of 1st type Total cost 1st set
rithm is based on an enhanced priority list approach, as developed
by Delarue et al. [31]. As demonstrated by these authors, this UC Selected set Subtract generator
Total cost 2nd set
model is well suited to solve relatively large instances (one year becomes start set of 2nd type
period, hourly time steps) with good accuracy in short computa-
tion times. Furthermore, this model is well suited to deal with Subtract generator
Total cost nth set
low residual demand problems (which is a relevant feature in of nth type
Table 2
Simulation results for the different wind scenarios (AE). SC denotes the set of power plants obtained with the screening curve methodology, MILP denotes the MILP system planning model (representative days), while Optimal denotes
Reference set of generation technology: technical data.
Optimal
1762.35
1096.21
666.14
0.00
Technology Pmin [MW] Pmax [MW] MUT [h] MDT [h] tcold [h] LT [y]
36
4
2
3
3
Oil 10 50 1 1 0 30
Peak gas 30 150 1 2 1 30
1917.61
1303.59
CCGT 147 420 2 4 2 30
614.03
MILP
NOC
Coal 300 750 5 8 4 30
8.10
12
Nuclear 600 1000 8 24 8 40
1
2
9
0
1835.74
880.64
955.1
4.00
NC
28
SC
4
3
2
5
E
Table 3
Reference set of generation technology: cost data.
Optimal
1827.04
1098.01
729.03
0.00
Technology INV a b c hc cc OM
30
[/kW] [/h] [/MW/h] [/MW2/h] []
3
2
2
4
[] [/MW h]
Oil 461 450 104 0.034 30 60 18
1130.87
1909.16
Peak gas 720 950 65.48 0.0043 1898 3796 5.38
778.29
MILP
NOC
CCGT 1069 1320 49.65 0.001 3765 7530 4.06
4.30
16
Coal 2539 2100 22.8 0.0002 5632 11,264 8.73
3
5
3
0
Nuclear 5383 3500 12.33 0.0001 7500 15,000 7.2
1881.22
1017.09
864.13
2.88
26
SC
D
4
2
2
5
6
IEA/NEA Projected Costs of Generating Electricity study (2010 edi-
tion) [34]. The technical characteristics are based on data obtained
1118.32
1913.31
Optimal
from Kazarlis et al. [35] and Grigg et al. [36]. Note that these char-
0.00
795
28
acteristics are purely methodological and intended to represent
2
2
1
5
different types of generation technology (i.e., base, mid and peak
1979.58
load) and thus, are to be regarded as such.
1147.7
831.88
MILP
The technical data is shown Table 2. tcold represents the
NOC
3.35
8
1
2
4
4
amount of hours after the minimum downtime from when it is
assumed that the unit will make a cold start. A last characteristic
1058.46
2054.87
given is LT, the assumed lifetime of each generator type.
996.4
6.89
Table 3 displays all cost-related characteristics. The investment
23
SC
C
4
2
2
6
5
cost is denoted by INV, and needs to be converted to an annual cost
fcr by using the lifetime LT. A two-step startup cost function is con-
Optimal
1217.07
2013.36
796.29
sidered for SC i;p , with hc and cc representing the hot and cold star-
0.00
tup cost, respectively (set P.
25
3
2
1
5
2084.77
1250.06
834.71
Simulation results
MILP
NOC
3.43
7
2
2
4
4
2064.16
927.02
3
2
1
6
All optimizations with the MILP system planning model are run
Optimal
1265.19
2128.74
0.00
2173.51
NOC
2.06
2
3
5
0
cost of serving the residual demand is calculated for each set. The
sum of investment and operational cost is shown as the total
1227.34
2149.75
922.41
cost. The relative gap denotes the difference between the total
the set obtained after perturbation.
0.98
3
2
1
6
Nuclear [#]
Optimal Convergence).
CCGT [#]
Coal [#]
Oil [#]
Model
MI C
MI C
MI C
MI C
l
l
ima
ima
ima
ima
ima
Opt LP
Opt LP
Opt LP
Opt LP
Opt LP
S
Conclusion
Fig. 4. Installed capacity obtained as estimated set (screening curve SC and MILP)
and after perturbation (optimal) for each scenario.
This paper presents a new comprehensive method for optimal
electricity generation system planning, specically accounting for
exibility required at high penetration levels of renewables.
9 Compared to existing planning models and methods available in
the literature, the model developed in this paper combines ele-
Installed capacity per technology [GW]
9
As is clear from the perturbation algorithm, taking into account
8 operational constraints through an actual operational UC model
7 affects the optimal solution. Hence, the basic system planning
models can be used as such (providing feasible solutions), but need
6 Nuclear
Coal
further adaptation to improve their performance (in achieving bet-
5 CCGT ter solutions). Using the screening curve method to determine the
Peak Gas initial set, in combination with the perturbation algorithm and
4 Oil
operational UC model nally make up the preferred methodology
3 (i.e., providing the best solutions in computation times remaining
below 1 h).
2
The second conclusion relates to the evolution of the optimal
1 set in function of the amount of installed wind capacity. It is
0 observed that the total amount of installed capacity (excluding
wind) is approximately equal for all scenarios. When more wind
SC
SC
SC
SC
SC
l
l
ima
ima
ima
ima
ima
Opt
Opt
Opt
demand to decrease. A decrease in total residual demand leads to a [14] De Jonghe C, Delarue E, Belmans R, Dhaeseleer W. Determining optimal
electricity technology mix with high level of wind power penetration. Appl
decrease of the average generation output per generation unit. The
Energy 2011;88:22318.
decrease of generation output is unfavorable for base-load gen- [15] Nweke CI, Leanez F, Drayton GR, Kolhe M. Benets of chronological
eration units as they are only economically preferable when their optimization in capacity planning for electricity markets. In: Power system
generation output is high. The second effect is the operational technology (POWERCON), 2012 IEEE international conference on. IEEE; 2012.
p. 16.
effect. An increasing amount of installed wind capacity causes an [16] Delarue E, De Jonghe C, Belmans R, Dhaeseleer W. Applying portfolio
increase in the volatility of the residual demand. This leads to an theory to the electricity sector: energy versus power. Energy Econ 2011;33:
increasing need for exible generation units. This is again unfavor- 1223.
[17] Short W, Sullivan P, Mai T, Mowers M, Uriarte C, Blair N, Heimiller D, Martinez
able for the base-load generation units, since their operation ex- A. Regional energy deployment system (ReEDS). Technical report NREL/TP-
ibility is limited compared to the exibility of a peak-load 6A20-46534; 2011.
generation unit. An examination of the simulation results lead to [18] Loulou R, Remne U, Kanudia A, Lehtila A, Goldstein G. Documentation for the
TIMES model: Part I. Energy technology systems analysis programme (ETSAP);
the conclusion that both effects have a signicant impact on the 2005.
composition of the optimal generator set. [19] Loulou R, Lehtila A, Kanudia A, Remne U, Goldstein G. Documentation for
the TIMES model: Part II. Energy technology systems analysis programme
(ETSAP); 2005.
Acknowledgments [20] Kannan R, Turton H. A long-term electricity dispatch model with the TIMES
framework. Environ Model Assess 2013;18:32543.
Financial support for this research is provided by the Research [21] Haydt G, Leal V, Pina A, Silva C. The relevance of the energy resource
dynamics in the mid/long-term energy planning models. Renew Energy
Foundation Flanders (FWO).
2011;36:306874.
[22] Pina A, Silva C, Ferro P. Modeling hourly electricity dynamics for policy
References making in long-term scenarios. Energy Policy 2011;39:4692702.
[23] Pina A, Silva C, Ferro P. High-resolution modeling framework for planning
[1] Ortega-Vazquez MA, Kirschen DS. Assessing the impact of wind power electricity systems with high penetration of renewables. Appl Energy
generation on operating costs. IEEE Trans Smart Grid 2010;1:295301. 2013;112:21523.
[2] Restrepo JF, Galiana FD. Assessing the yearly impact of wind power through a [24] Deane JP, Chiodi A, Gargiulo M, Gallachir BP. Soft-linking of a power
new hybrid deterministic/stochastic unit commitment. IEEE Trans Power Syst systems model to an energy systems model. Energy 2012;42:30312.
2011;26:40110. [25] Ma J, Kirschen DS, Belhomme R, Silva V. Optimizing the exibility of a portfolio
[3] Ummels BC, Gibescu M, Pelgrum E, Kling WL, Brand AJ. Impacts of wind power of generating plants. In: Proceedings of the 17th power system computation
on thermal generation unit commitment and dispatch. IEEE Trans Energy conference (PSCC); 2011. p. 226.
Convers 2007;22:4451. [26] Palmintier B. Flexibility in generation planning: identifying key operating
[4] Kagiannas AG, Askounis DT, Psarras J. Power generation planning: a constraints. In: Proceedings of the 18th power system computation conference
survey from monopoly to competition. Int J Electr Power Energy Syst (PSCC); 2014. p. 17.
2004;26:41321. [27] Palmintier B. Incorporating operational exibility into electric generation
[5] Alizadeh B, Jadid S. A dynamic model for coordination of generation and planning impacts and methods for system design and policy analysis. PhD
transmission expansion planning in power systems. Int J Electr Power Energy thesis, Massachusetts Institute of Technology; February 2013.
Syst 2015;65:40818. [28] Carrin M, Arroyo JM. A computationally efcient mixed-integer linear
[6] Franco JF, Rider MJ, Romero R. A mixed-integer quadratically-constrained formulation for the thermal unit commitment problem. IEEE Trans Power
programming model for the distribution system expansion planning. Int J Syst 2006;21:13718.
Electr Power Energy Syst 2014;62:26572. [29] Wood AJ, Wollenberg BF. Power generation, operation, and control. John Wiley
[7] Stoft S. Power system economics. New York: Wiley; 2002. & Sons; 2012.
[8] Santos HL, Legey LF. A model for long-term electricity expansion planning [30] Nemhauser GL, Wolsey LA. Integer and combinatorial optimization. New
with endogenous environmental costs. Int J Electr Power Energy Syst York: Wiley; 1988.
2013;51:98105. [31] Delarue E, Cattrysse D, Dhaeseleer W. Enhanced priority list unit commitment
[9] Delgado F, Ortiz A, Renedo C, Prez S, Maana M, Zobaa AF. The inuence method for power systems with a high share of renewables. Electr Power Syst
of nuclear generation on CO2 emissions and on the cost of the Spanish Res 2013;105:11523.
system in long-term generation planning. Int J Electr Power Energy Syst [32] Elia. Grid data, demand; 2013. <http://www.elia.be/nl/grid-data/data-
2011;33:67383. download> [accessed July 2013].
[10] Unsihuay-Vila C, Marangon-Lima J, Zambroni de Souza A, Perez-Arriaga I. [33] Elia. Grid data, injected power from wind turbines; 2013. <http://www.elia.be/
Multistage expansion planning of generation and interconnections with nl/grid-data/productie/windproductie> [accessed July 2013].
sustainable energy development criteria: a multiobjective model. Int J Electr [34] IEA/NEA. Projected costs of generating electricity 2010 edition. International
Power Energy Syst 2011;33:25870. Energy Agency/Nuclear Energy Agency. Paris: OECD Publishing; 2010.
[11] DeCesaro J, Porter K, Milligan M. Wind energy and power system operations: a [35] Kazarlis SA, Bakirtzis A, Petridis V. A genetic algorithm solution to the unit
review of wind integration studies to date. Electr J 2009;22:3443. commitment problem. IEEE Trans Power Syst 1996;11:8392.
[12] Holttinen H. Wind integration: experience, issues, and challenges. Wiley [36] Grigg C, Wong P, Albrecht P, Allan R, Bhavaraju M, Billinton R, et al. The IEEE
Interdiscip Rev: Energy Environ 2012;1:24355. reliability test system-1996. A report prepared by the reliability test system
[13] Lannoye E, Flynn D, OMalley M. The role of power system exibility in task force of the application of probability methods subcommittee. IEEE Trans
generation planning. In: Proceedings of 2011 IEEE power and energy society Power Syst 1999;14:101020.
general meeting, Detroit, MI; July 2011.