Documente Academic
Documente Profesional
Documente Cultură
Acknowledgements:
Chow Kok Fong, Chartered Arbitrator and Chartered Quantity Surveyor
Kuala Lumpur Regional Centre for Arbitration
Construction Industry Development Board, Malaysia
1
THIS BRIEFING
OBJECTIVES PROGRAMME
Background
Provide an overview of
CIPAA, and an awareness of Overview of CIPAA
the responsibilities and
possible liabilities under the
Act. Impact on Construction
Industry
Q&A
2
Background
3
BACKGROUND
Statutory Adjudication
An alternative dispute resolution
c.f. arbitration, litigation.
4
Historical BACKGROUND
1994 Latham Report
Review of procurement and contractual arrangements in the UK construction industry cascade system making
insolvency a particular serious problem recommendations for outlawing unfair payment practices such as pay-
when-paid clauses; proposed adjudication.
Housing Grants, Construction And Regeneration Act 1996 (UK) in force 1998
Various statutory adjudication legislation relating to construction industry follows, e.g.
NSW (1999), NZ (2002), Queensland (2004), Singapore (2004), Victoria (2006), Malaysia (2012)
Malaysia
2004 Working Group on Payment (WG10) led by ISM was formed to look into chronic problem of
delayed and non-payment in the Malaysian Construction Industry
2005 international forum held in Kuala Lumpur
2006 consultative forum was held in Putra World Trade Center
Various industry consultative forums & road shows
2009 Cabinet agreed for CIPAA to be enacted
November 2011 Final draft
01 December 2011 CIPA Bill first reading in Parliament
02 April 2012 Second Reading
07 May 2012 Third Reading
18 June 2012 Royal Assent
22 June 2012 Publication in the Gazette
6
The Overview
(CIDB)
7
8
9
10
11
12
13
14
15
16
17
18
19
Adjudication
Decision
Adjudication
Notice
20
Potential Impact on
Construction Industry
21
POTENTIAL IMPACT ON CONSTRUCTION INDUSTRY & CONTRACTNG PARTIES
CONSTRUCTION SUB-CONTRACTORS,
EMPLOYERS CONTRACTORS
INDUSTRY ETC.
Change the payment culture Change attitude towards payment Ameliorate the harsh and Generally as for contractors
issues pervasive risk allocation imposed
Permit a more even allocation of on them by employers Allow enforcement of payment in
payment risk Compel a more fairer allocation of the absence of express
risk despite dominant position Allow receipt of regular and timely provisions in the sub-contract
Curb unfair and pervasive payment
practice of constructing cash flow Compel mandatory payment of Develop a healthy and
in the supply line the amount due to the contractor Improve their cash-flow professional body / corpus of
with effective sanctions downstream suppliers / sub-
Improve quality of work and Enable speedy resolution of contractors effectively supporting
professionalism Improve professional and good payment disputes cheaply the upstream players / parties.
governance in administering through adjudication
Minimise payment disputes from payments
proceeding to arbitration, litigation Allow statutory mandated
etc. Weed out the delinquent and recovery of payment after
recalcitrant employers adjudication
22
POTENTIAL IMPACT OF CIPAA ON THIRD PARTIES
Payment for consultancy work New / increased opportunities New opportunities for increase in Need to be educated / updated
undertaken: volume of work available on the philosophy, aims /
1. For adjudication support objectives, implementation, etc.
1. Easier to receive; and work Need to maintain competency, of adjudication
2. In time 2. To become adjudicator integrity and professionalism
3. Remedies for default available Necessity to:
through CIPAA For lawyers: Statutory immunity against:
1. Recognize the differences
For valuation and certification role 1. New / increased 1. Any action / suit between adjudication and
opportunities 2. Provided acting in good faith other ADR and TDR methods
1. Need to improve professionalism 2. For consequential litigation 2. Give effect to CIPAA whole
and good practice work e.g. application for heartedly
2. Default possible claims in: stays, enforcement, etc.
Breach of contract Must be prepared for an increase
Tort of negligence Liability for default possible in adjudication generated
claims for: litigation
Necessity to get P.I. Insurance
1. Breach of contract
Opportunity to: 2. Tort of negligence
1. Become adjudicators
2. Do adjudication support work
23
Some CIPAA Details
24
25
FASTFACTS
An Act to facilitate regular and timely payment, to provide a mechanism for speedy dispute resolution
through adjudication, to provide remedies for the recovery of payment in the construction industry and to
provide for connected and incidental matters.
Enforcement:
Date of Royal Assent - 18 June 2012
Date of publication in the Gazette - 22 June 2012.
Came into force upon Ministers order (12 April 2014)
Not retrospective (according to KLRCAs circular)
Principal Act + Regulations to give full effect or the better carrying out of the provisions of [the] Act.
Applies to construction contract (including construction consultancy contract) made in writing, for
construction works carried out wholly or partly within the territory of Malaysia, including a construction
contract entered into by the Government.
Non-application (s3) natural person, building is less than 4-storey and for own occupation.
Part IV Enforcement
Part VI Part V of Adjudication
General Adjudication Authority Decision
(Sections 34 to 37) (Sections 32 to 33) (Sections 28 to 31)
27
1. Preliminary stage
Making a claim
Response to a claim
Decision of unpaid party
28
3. Appointment of Adjudicator stage
Selection of adjudicator
Appointment of adjudicator
29
4. Conduct of adjudication
proceedings stage
Commencement of
adjudication proceedings
Submissions
Determination
5. Post decision
stage
Post publication of
decision
Enforcement of
decision
Enforcement of
other remedies
30
QS - Valuation and Certification
(PAM06)
31
NON-PAYMENT TRIGGERS CIPAA
PAM06 Possible cause of Non-payment
Clause 30.1 Delay in issuing Interim Certificate
Within 21 Days from Contractors payment application, Delay by Employer to make payment
Architect is to issue Interim Certificate
QS / Architect under-certifies without reasonable
\Within Period of Honouring Certificate (default = 21 cause
Days), Employer to make payment according to the
Interim Certificate Employer does not pay in full without reasonable
cause
Payment Contractor
Payment Ar. issues Due Date may issue a
Application Payment Employer CIPAA
by Certificate must make 2012
Contactor payment Payment
Claim
PAM06 21 Days Period of Honouring Certificate If Employer does not make payment at the end of
period, it is considered Non-payment whether or
CIPAA default payment provision: not the Architect has issued a certificate
Monthly; Payment due date is 30 days from receipt of invoice
Contractor
Invoice may issue a
CIPAA 2012
Payment
CIPAA2012 Claim 32
PAYMENT RESPONSE
CIPAA 2012 Failure to provide a Payment Response
Section 5 Payment Claim Non-paying party deemed to dispute the whole
amount
(1) An unpaid party may serve a payment claim on a non-paying party for
payment pursuant to a construction contract.
Respondent cannot later raise counter claim or
defense which was not specified in the
Payment Response section 27(1)
Section 6 Payment Response
(1) A non-paying party who admits to the payment claim served on him shall
Examples:
serve a payment response on the unpaid party together with the whole amount
claimed or any amount as admitted by him. No payment response, or payment response did
not mention deduction of Liquidated Damages
(2) A non-paying party who disputes the amount claimed in the payment claim, respondent cannot later raise this in defense
either wholly or partly, shall serve a payment response in writing on the unpaid
party stating the amount disputed and the reason for the dispute.
No payment response, or payment response did
not mention set-off for rectification of defective
(3) A payment response issued under subsection (1) or (2) shall be served on works carried out by others respondent cannot
the unpaid party within ten working days of the receipt of the payment claim. later counter claim in this adjudication.
(4) A non-paying party who fails to respond to a payment claim in the manner
provided under this section is deemed to have disputed the entire payment claim. Whether a Payment Response was provided
or not, the unpaid party may proceed to issue
Section 27 Jurisdiction of Adjudicator the notice of adjudication at the end of the
stipulated period (10 working days)
(1) Subject to subsection (2), the adjudicators jurisdiction in relation to any
dispute is limited to the matter referred to adjudication by the parties pursuant to
sections 5 and 6.
(2) The parties to adjudication may at any time by agreement in writing extend
the jurisdiction of the adjudicator to decide on any other matter not referred to the
adjudicator pursuant to sections 5 and 6.
33
ADJUDICATION RESPONSE
CIPAA 2012 Failure to provide an
Adjudication Response, or
Section 9 Adjudication Claim providing an inadequate
response
(1) The claimant shall, within ten working days from the
receipt of the acceptance of appointment by the adjudicator Failure to answer the
under subsection 22(2) or 23(2), serve a written
adjudication claim containing the nature and description of Claimants adjudication
the dispute and the remedy sought together with any claim
supporting document on the respondent.
Could be fatal to
Section 10 Adjudication Response Respondent for
adjudication based on
(1) The respondent shall, within ten working days from the documents only since the
receipt of the adjudication claim under subsection 9(1), Adjudicator has very limited
serve a written adjudication response which shall answer time.
the adjudication claim together with any supporting
document on the claimant.
President of
PAM appoints
adjudicator
35
Lessons Learnt
36
Lessons Learnt
Payment Claim of $13.9 million was upheld because of failure to provide the
Payment Schedule (ie payment response under CIPAA) within the stipulated time of
10 business days.
37
Lessons Learnt
Ambush is allowed! Beware of the short time frame allowed for dispute which is
complex or involves large volumes of material!
Bovis Lend Lease Ltd v. The Trustees of the London Clinic [2009] EWHC
64
Short timetable does not mean that the process is unfair.
Affirming CIB Properties Ltd v Brise Construction [2004] EWHC 2365,
TCC, and London & Amsterdam Properties Ltd v Waterman
Partnership Ltd (2003) that an "ambush" by the claiming party in an
adjudication does not in itself amount to procedural unfairness.
Minister for Commerce v Contrax Plumbing & Ors [2004] NSWSC 823
Clause stipulating elaborate contract administration process was held to be
invalid.
38
Lessons Learnt
39
Lessons Learnt
The adjudicator was Professor John Uff, QC. One of the parties was represented by Sir
Vivian Ramsey, now the Head of the Technology Court.
The referral was made on 14 November 2003. The decision was extended several time,
and given on 24 February 2004.
The adjudicators decision runs 139 pages. Total costs came to 4 million.
40
Lessons Learnt
Minister for Commerce v Contrax Plumbing & Ors [2004] NSWSC 823
Clause stipulating elaborate contract administration process was held to be invalid
offended section 34 of NSW SOP Act / section 36 Sgp SOPA no equivalent in
CIPAA?
41
Rules, Procedures & Forms
42
Payment
Claim
Notice of
Adjudication
Rules
43
KUALA LUMPUR REGIONAL CENTRE FOR ARBITRATION
ADJUDICATION RULES & PROCEDURE
45
The End
46