Sunteți pe pagina 1din 46

Construction Industry Payment

and Adjudication Act 2012


(Act 746) CIPAA

A Short Briefing for Sunway Group


(05 August 2014)

Acknowledgements:
Chow Kok Fong, Chartered Arbitrator and Chartered Quantity Surveyor
Kuala Lumpur Regional Centre for Arbitration
Construction Industry Development Board, Malaysia
1
THIS BRIEFING

OBJECTIVES PROGRAMME

 Background
 Provide an overview of
CIPAA, and an awareness of  Overview of CIPAA
the responsibilities and
possible liabilities under the
Act.  Impact on Construction
Industry

 Some CIPAA Details


 A quick look at some of the
lessons learnt from other
jurisdictions  Lessons learnt

 Rules, Procedures & Forms

 Q&A
2
Background

3
BACKGROUND
Statutory Adjudication
An alternative dispute resolution
c.f. arbitration, litigation.

Not ad hoc or contractual


Mandated by law (e.g. CIPAA 2012)
Applicable Act and Regulations stipulate
Scope and nature of disputes covered
Procedural issues
Effects of decision / determination
Miscellaneous matters

Generally meant to prevail over any ad hoc and/or contractual


adjudication arrangement between the parties.

4
Historical BACKGROUND
1994 Latham Report
Review of procurement and contractual arrangements in the UK construction industry cascade system making
insolvency a particular serious problem recommendations for outlawing unfair payment practices such as pay-
when-paid clauses; proposed adjudication.
Housing Grants, Construction And Regeneration Act 1996 (UK) in force 1998
Various statutory adjudication legislation relating to construction industry follows, e.g.
NSW (1999), NZ (2002), Queensland (2004), Singapore (2004), Victoria (2006), Malaysia (2012)

Malaysia
2004 Working Group on Payment (WG10) led by ISM was formed to look into chronic problem of
delayed and non-payment in the Malaysian Construction Industry
2005 international forum held in Kuala Lumpur
2006 consultative forum was held in Putra World Trade Center
Various industry consultative forums & road shows
2009 Cabinet agreed for CIPAA to be enacted
November 2011 Final draft
01 December 2011 CIPA Bill first reading in Parliament
02 April 2012 Second Reading
07 May 2012 Third Reading
18 June 2012 Royal Assent
22 June 2012 Publication in the Gazette

CIPAA 2012 came into force in on 12 APRIL 2014


5
IMPACT OF CIPAA
CIPAA Be prepared for the impact on
Construction industry
Employers
Contractors
Sub-contractors
Construction professionals
Claims consultants / lawyers
Adjudicators
Courts
Contract documentation
Contract administration
Miscellaneous issues

6
The Overview
(CIDB)

7
8
9
10
11
12
13
14
15
16
17
18
19

Adjudication
Decision
Adjudication
Notice
20
Potential Impact on
Construction Industry

21
POTENTIAL IMPACT ON CONSTRUCTION INDUSTRY & CONTRACTNG PARTIES

CONSTRUCTION SUB-CONTRACTORS,
EMPLOYERS CONTRACTORS
INDUSTRY ETC.

 Change the payment culture  Change attitude towards payment  Ameliorate the harsh and  Generally as for contractors
issues pervasive risk allocation imposed
 Permit a more even allocation of on them by employers  Allow enforcement of payment in
payment risk  Compel a more fairer allocation of the absence of express
risk despite dominant position  Allow receipt of regular and timely provisions in the sub-contract
 Curb unfair and pervasive payment
practice of constructing cash flow  Compel mandatory payment of  Develop a healthy and
in the supply line the amount due to the contractor  Improve their cash-flow professional body / corpus of
with effective sanctions downstream suppliers / sub-
 Improve quality of work and  Enable speedy resolution of contractors effectively supporting
professionalism  Improve professional and good payment disputes cheaply the upstream players / parties.
governance in administering through adjudication
 Minimise payment disputes from payments
proceeding to arbitration, litigation  Allow statutory mandated
etc.  Weed out the delinquent and recovery of payment after
recalcitrant employers adjudication

 Improve quality of work / finished  As for the employers in regard to


product their obligations to their sub-
contractors

22
POTENTIAL IMPACT OF CIPAA ON THIRD PARTIES

CONSTRUCTION CLAIMS CONSULTANTS


ADJUDICATORS COURTS
PROFESSIONAL / LAWYERS

 Payment for consultancy work  New / increased opportunities  New opportunities for increase in  Need to be educated / updated
undertaken: volume of work available on the philosophy, aims /
1. For adjudication support objectives, implementation, etc.
1. Easier to receive; and work  Need to maintain competency, of adjudication
2. In time 2. To become adjudicator integrity and professionalism
3. Remedies for default available  Necessity to:
through CIPAA  For lawyers:  Statutory immunity against:
1. Recognize the differences
 For valuation and certification role 1. New / increased 1. Any action / suit between adjudication and
opportunities 2. Provided acting in good faith other ADR and TDR methods
1. Need to improve professionalism 2. For consequential litigation 2. Give effect to CIPAA whole
and good practice work e.g. application for heartedly
2. Default possible claims in: stays, enforcement, etc.
 Breach of contract  Must be prepared for an increase
 Tort of negligence  Liability for default possible in adjudication generated
claims for: litigation
 Necessity to get P.I. Insurance
1. Breach of contract
 Opportunity to: 2. Tort of negligence

1. Become adjudicators
2. Do adjudication support work

23
Some CIPAA Details

24
25
FASTFACTS
An Act to facilitate regular and timely payment, to provide a mechanism for speedy dispute resolution
through adjudication, to provide remedies for the recovery of payment in the construction industry and to
provide for connected and incidental matters.

Principal Act comprises


41 sections, divided into 7 parts

Enforcement:
Date of Royal Assent - 18 June 2012
Date of publication in the Gazette - 22 June 2012.
Came into force upon Ministers order (12 April 2014)
Not retrospective (according to KLRCAs circular)

Principal Act + Regulations to give full effect or the better carrying out of the provisions of [the] Act.

Applies to construction contract (including construction consultancy contract) made in writing, for
construction works carried out wholly or partly within the territory of Malaysia, including a construction
contract entered into by the Government.

Non-application (s3) natural person, building is less than 4-storey and for own occupation.

Exemptions by Minister (s40)


upon recommendation from KLRCA for person/class from all/any provision of the CIPAA subject to
terms/conditions as may be prescribed

No contracting out (implied).

Applies to payment disputes.


26
Part I
Preliminary
CIPAA Part II
(Sections 1 to 4)
Regulations Application of Payment
(Refer KLRCA Website) Disputes
(Sections 5 to 20)

Part VII CIPAA : CONTENTS Part III Adjudicator


Miscellaneous & FRAMEWORK (Sections 21 to 27)
(Sections 38 to 41)

Part IV Enforcement
Part VI Part V of Adjudication
General Adjudication Authority Decision
(Sections 34 to 37) (Sections 32 to 33) (Sections 28 to 31)

27
1. Preliminary stage
Making a claim
Response to a claim
Decision of unpaid party

2. Initiation of Adjudication stage


Decision to initiate adjudication
Initiation of adjudication process

28
3. Appointment of Adjudicator stage
Selection of adjudicator
Appointment of adjudicator

29
4. Conduct of adjudication
proceedings stage
Commencement of
adjudication proceedings
Submissions
Determination

5. Post decision
stage
Post publication of
decision
Enforcement of
decision
Enforcement of
other remedies

30
QS - Valuation and Certification
(PAM06)

31
NON-PAYMENT TRIGGERS CIPAA
 PAM06  Possible cause of Non-payment
Clause 30.1 Delay in issuing Interim Certificate

Within 21 Days from Contractors payment application, Delay by Employer to make payment
Architect is to issue Interim Certificate
QS / Architect under-certifies without reasonable
\Within Period of Honouring Certificate (default = 21 cause
Days), Employer to make payment according to the
Interim Certificate Employer does not pay in full without reasonable
cause

 Delay in certification is not a non-payment if


Employer pays within (21 Days + Period of
Honouring Certificate).

Payment Contractor
Payment Ar. issues Due Date may issue a
Application Payment Employer CIPAA
by Certificate must make 2012
Contactor payment Payment
Claim

PAM06 21 Days Period of Honouring Certificate If Employer does not make payment at the end of
period, it is considered Non-payment whether or
CIPAA default payment provision: not the Architect has issued a certificate
Monthly; Payment due date is 30 days from receipt of invoice

Contractor
Invoice may issue a
CIPAA 2012
Payment
CIPAA2012 Claim 32
PAYMENT RESPONSE
 CIPAA 2012  Failure to provide a Payment Response
Section 5 Payment Claim Non-paying party deemed to dispute the whole
amount
(1) An unpaid party may serve a payment claim on a non-paying party for
payment pursuant to a construction contract.
Respondent cannot later raise counter claim or
defense which was not specified in the
Payment Response section 27(1)
Section 6 Payment Response

(1) A non-paying party who admits to the payment claim served on him shall
Examples:
serve a payment response on the unpaid party together with the whole amount
claimed or any amount as admitted by him. No payment response, or payment response did
not mention deduction of Liquidated Damages
(2) A non-paying party who disputes the amount claimed in the payment claim, respondent cannot later raise this in defense
either wholly or partly, shall serve a payment response in writing on the unpaid
party stating the amount disputed and the reason for the dispute.
No payment response, or payment response did
not mention set-off for rectification of defective
(3) A payment response issued under subsection (1) or (2) shall be served on works carried out by others respondent cannot
the unpaid party within ten working days of the receipt of the payment claim. later counter claim in this adjudication.
(4) A non-paying party who fails to respond to a payment claim in the manner
provided under this section is deemed to have disputed the entire payment claim.  Whether a Payment Response was provided
or not, the unpaid party may proceed to issue
Section 27 Jurisdiction of Adjudicator the notice of adjudication at the end of the
stipulated period (10 working days)
(1) Subject to subsection (2), the adjudicators jurisdiction in relation to any
dispute is limited to the matter referred to adjudication by the parties pursuant to
sections 5 and 6.

(2) The parties to adjudication may at any time by agreement in writing extend
the jurisdiction of the adjudicator to decide on any other matter not referred to the
adjudicator pursuant to sections 5 and 6.

33
ADJUDICATION RESPONSE
CIPAA 2012  Failure to provide an
Adjudication Response, or
Section 9 Adjudication Claim providing an inadequate
response
(1) The claimant shall, within ten working days from the
receipt of the acceptance of appointment by the adjudicator Failure to answer the
under subsection 22(2) or 23(2), serve a written
adjudication claim containing the nature and description of Claimants adjudication
the dispute and the remedy sought together with any claim
supporting document on the respondent.
Could be fatal to
Section 10 Adjudication Response Respondent for
adjudication based on
(1) The respondent shall, within ten working days from the documents only since the
receipt of the adjudication claim under subsection 9(1), Adjudicator has very limited
serve a written adjudication response which shall answer time.
the adjudication claim together with any supporting
document on the claimant.

(2) The respondent shall provide the adjudicator with a


copy of the adjudication response together with any
supporting document within the time specified under
subsection (1).

(3) If the respondent fails to serve any adjudication


response, the claimant may proceed with the adjudication
after the expiry of the time specified under subsection (1).
34
Comparative :
Adjudication under PAM06 (With amendments) & CIPAA 2012
Clause 30.1 - Contractor submits
payment application

set off issue non-payment issue

Suggested amendments for cl. 30.4


notice / negotiation timeline is
reduced from 21 to 14 days

President of
PAM appoints
adjudicator

35
Lessons Learnt

36
Lessons Learnt

 Potential of AMBUSH - Employer has limited time to response, but


response he must
Walter Construction Group v CPL (Slurry Hills) Pty Ltd [2003] NSWSC 266
 A Christmas ambush launched when consultants were on holiday. Payment Claim
$13.9 million. Amount subsequently certified by Superintendent was $952,351.00.
Several of these claims amounted to no more than mere assertions.

 Payment Claim of $13.9 million was upheld because of failure to provide the
Payment Schedule (ie payment response under CIPAA) within the stipulated time of
10 business days.

All Consultants and Clients on Holiday!

37
Lessons Learnt
 Ambush is allowed! Beware of the short time frame allowed for dispute which is
complex or involves large volumes of material!

Bovis Lend Lease Ltd v. The Trustees of the London Clinic [2009] EWHC
64
 Short timetable does not mean that the process is unfair.
 Affirming CIB Properties Ltd v Brise Construction [2004] EWHC 2365,
TCC, and London & Amsterdam Properties Ltd v Waterman
Partnership Ltd (2003) that an "ambush" by the claiming party in an
adjudication does not in itself amount to procedural unfairness.

 Variation works must be paid if done!

Minister for Commerce v Contrax Plumbing & Ors [2004] NSWSC 823
 Clause stipulating elaborate contract administration process was held to be
invalid.

38
Lessons Learnt

 Volumes of Documents Do not mean procedural unfairness

The Dorchester Hotel Ltd v Vivid Interiors Ltd [2009] EWHC 70


 37 lever arch files, including 6 substantial witness statements and two experts'
reports

 Tight timetable = real risk of a breach of natural justice?

 Affirmed CIB Properties v Birse a dispute which is complex or involves large


volumes of material does not necessarily mean that an adjudication is procedurally
unfair

39
Lessons Learnt

 Most Expensive adjudication case

CIB Properties Ltd v Brise Construction [2004] EWHC 2365, TCC


 The claim was contained in 53 files and the referral notice was accompanied by 49 files
containing 24 reports from experts

 The adjudicator was Professor John Uff, QC. One of the parties was represented by Sir
Vivian Ramsey, now the Head of the Technology Court.

 The referral was made on 14 November 2003. The decision was extended several time,
and given on 24 February 2004.

 The adjudicators decision runs 139 pages. Total costs came to 4 million.

40
Lessons Learnt

 Contracting out of CIPAA?

John Mowlem plc v Hydra-Tight Ltd [2000] 17ConstLJ 358


When contract provisions have the effect of modifying, restricting or prejudicing the
operation of the Act
New Engineering Contract 2nd Edition Sub-Contract published by ICE Option Y a
dispute require a Notice of Dissatisfaction to be given, and matter not resolved within 4
weeks
The Court held that the contract did not comply with the Act.

Minister for Commerce v Contrax Plumbing & Ors [2004] NSWSC 823
Clause stipulating elaborate contract administration process was held to be invalid
offended section 34 of NSW SOP Act / section 36 Sgp SOPA no equivalent in
CIPAA?

41
Rules, Procedures & Forms

42
Payment
Claim
Notice of
Adjudication

Rules

43
KUALA LUMPUR REGIONAL CENTRE FOR ARBITRATION
ADJUDICATION RULES & PROCEDURE

PART A - RULES SCHEDULE I FORMS


RULE 1: GENERAL FORM 1 - Payment Claim
RULE 2: COMMENCEMENT & REGISTRATION OF
ADJUDICATION FORM 2 - Payment Response
RULE 3: APPOINTMENT OF ADJUDICATOR FORM 3 - Notice of Adjudication
RULE 4: NOTIFICATION OF ADJUDICATION CLAIM FORM 3A - Notice to the Director of KLRCA to register the
RULE 5: NOTIFICATION OF ADJUDICATION adjudication
RESPONSE
FORM 4 - Request to the chosen adjudicator to act
RULE 6: NOTIFICATION OF ADJUDICATION
REPLY, IF ANY FORM 5 - Request to the Director of KLRCA to appoint an
RULE 7: THE PURPOSE OF THE ADJUDICATION adjudicator
AND THE ROLE OF THE FORM 6 - Notice of acceptance of the appointment to act as
ADJUDICATOR adjudicator
RULE 8: CONDUCT OF THE ADJUDICATION
FORM 7 - Adjudication Claim
RULE 9: FEES AND EXPENSES
RULE 10: ADJUDICATION DECISION
FORM 8 - Adjudication Response
FORM 9 - Adjudication Reply
FORM 10 - Agreement to extend the adjudicators jurisdiction
PART B - PROCEDURE
FORM 11 - Notice of withdrawal of adjudication claim/proceedings
FORM 12 - Notice of consolidation of adjudication proceedings
SCHEDULES FORM 13 - Adjudicators request for extension of time to deliver the
adjudication decision
SCHEDULE I - FORMS
FORM 14 - Notice for withholding the release of the decision until
SCHEDULE II - KLRCA STANDARD TERMS OF
payment of fees and expenses in full
APPOINTMENT
SCHEDULE III - ADMINISTRATIVE FEE SCHEDULE FORM 15 - Sample Format of an adjudication decision
SCHEDULE IV - ADJUDICATOR CODE OF FORM 16 - Delivery of Adjudication Decision
CONDUCT
44
SUMMARY
Both Employers and Consultants need to be aware and
be prepared for CIPAA Supporting the
Adjudication
Proceedings

Contract Responding to Answer the Claim


Documentation Payment Claim 1 do not just deny

Ensure Contract Internal process to Get the team to


1 complies with the 1 accommodate 2 cooperate on
Act statutory timeline timeline
Formulation of Data bank of
Sort out Contract
2 Formation Issues
2 response strategy 3 response
phraseology
Prescribe standard Adjudication Claim
Develop payment
3 claim format 3 response format 4 and Payment
Claim

45
The End

46

S-ar putea să vă placă și