RATES for 2071/72
Rate With 15%
S.N. Items Unit Remarks
Overhead
1. EARTHWORK
1.1 EarthWork in exc. in soft soil Cu.M. 385.56
1.2 EarthWork in exc. in- BMS Cu.M. 440.63
1.3 E/W for foun. trench (soft soil) Cu.M. 550.79
1.4 E/W for foun. trench - BMS Cu.M. 875.76
1.5 Earth fill. With water compact Cu.M. #REF!
1.6 Mud filling with transportation of mud up to 2.00
Cu.M. #REF!
Km. distance.
1.7 Stone filling at foundation Cu.M. 3,286.13
1.8 Sand fill. With compaction Cu.M. 3,738.08
1.9 Stone Dust Filling. Cu.M. #REF!

2. BRICK WORK
2.1 Brick soling in sand - flat Sq.M. #REF!
2.2 Brick soling in sand - vert Sq.M. #REF!
2.4 For ground floor
2.4a Brick mas.in c.m. - 1:3 Cu.M. #REF!
2.4b Brick mas.in c.m. - 1:4 Cu.M. #REF!
2.4c Brick mas.in c.m. - 1:6 Cu.M. #REF!
2.4d Brick mas.in mud mortar Cu.M. #REF!
2.5 Above ground floor
2.5a Brick mas.in c.m. - 1:3 Cu.M. #REF!
2.5b Brick mas.in c.m. - 1:4 Cu.M. #REF!
2.5c Brick mas.in c.m. - 1:6 Cu.M. #REF!
2.5d Brick mas.in mud mortar Cu.M. #REF!

3. STONE WORK
3.1 Dry Stone soling in sand Cu.M. #REF!
3.2 Stone mas.in c.m. - 1:4 Cu.M. #REF!
3.3 Stone mas.in c.m. - 1:6 Cu.M. 9,956.01
3.4 Stone mas.in c.m. - mud Cu.M. #REF!
3.5 Stone work for dry wall Cu.M. #REF!

4. CONCRETE WORK
4.1 PCC 1:5:10 general work (gravel) Cu.M. 9,374.05
4.2 PCC 1:4:8 general work (gravel) Cu.M. 10,282.55
4.3 PCC 1:3:6 general work (gravel) Cu.M. 11,400.93
4.4 PCC 1:2:4 general work (gravel) Cu.M. 13,457.30
4.5 For RCC -PCC 1:2:4 crush. Agg.-M15 Cu.M. #REF!
4.6 For RCC -PCC 1:1.5:3 cru. Agg. -M20 Cu.M. 16,694.15
4.7 For RCC -PCC 1:1:2 cru. Agg. -M25 Cu.M. #REF!

5. WOODEN WORK
5.1 Sal wood- Chaukhat Cu.M. #REF!
5.2 Sal wood- Beam Cu.M. #REF!

Prepared by:- Checked by:- Approved by:-


2/15

NEPAL DOORSANCHAR COMPANY LIMITED


EASTERN REGIONAL DIRECTORATE
CIVIL SECTION
BIRATNAGAR, MORANG
DISTRICT:- ILAM
RATES for 2071/72
Rate With 15%
S.N. Items Unit Remarks
Overhead
5.3 38mm thick Sal. Panelled shutters Sq.M. #REF!
5.4 " " - with 4mm glass Sq.M. #REF!
5.5 " " - 4mm plywood Sq.M. #REF!
5.6 " " - GI plain sheet 24 # Sq.M. #REF!
5.10 4mm glass + listy on frame Sq.M. #REF!
5.11 24 Gauge GI sheet fixing with listy Sq.M. #REF!
5.12 Wooden form work for R.C.C.+P.C.C. Sq.M. 1,061.56
5.13 12mm Th. Plywood partition with salwood frame Sq.M. #REF!
5.14 25mmth saal wooden planking works Sq.M. #REF!

6. PLASTERING WORK
6.1 12.5mm cement plaster - 1:3 ceil. Sq.M. #REF!
6.2 - 1:4 ceil. Sq.M. #REF!
6.3 - 1:4 On Walls Sq.M. 336.52
6.4 - 1:6 On Walls Sq.M. #REF!
6.5 20mm " " " - 1:4 Sq.M. 448.63
6.6 Flush cem.pointing1:2- brick wall Sq.M. #REF!
6.7 Flush cem.pointing1:2- stone wall Sq.M. #REF!
6.8 3 mm cement punning Sq.M. 243.48
6.9 Plain Plaster of Paris Sq.M. #REF!

7. FLOORING WORK
7.1 Brick vertical soling in (1:6) and Pointing Sq.M. #REF!
7.2 25mm thick Mozaic flooring Sq.M. #REF!
7.3-a Tile Porcelain -Glazed-Wall-NS-76 Sq.M. #REF!
7.3-b Tile Porcelain -Glazed-floor-NS-76 Sq.M. #REF!
7.4-a Marble slab flooring Sq.M. #REF!
7.4-b 38mm cement concrete flooring with punning Sq.M. #REF!
7.4-c 50mm cement concrete flooring with punning Sq.M. #REF!
7.4-d Granite flooring Sq.M. #REF!

8. ROOFING WORK
8.1 CGI sheet roof - 26 # plain Sq.M. #REF!
8.2 CGI sheet roof - 26 # coloured Sq.M. #REF!
8.3 GI sheet ridge-24 # (60 cm wide) R.Mt. #REF!
8.4 GI sheet ridge-26 # (60 cm wide) Colour R.Mt. #REF!
8.5 GI plain sheet fixing work - 24 # Sq.M. #REF!
8.7 False ceilling of 4mm ply.in sal wood frame Of 50
mm.*75 mm. size & Room 600 mm.*900 mm. Sq.M. #REF!

9. STEEL WORK
9.1 Barbed wire fencing 12 # R.Mt. #REF!
9.2 M.S. grill 3x20 (13.45Kg/sm) Sq.M. #REF!
9.3 M.S. grill 4.5x20 (20.17Kg/sm) Sq.M. #REF!
9.4 Collapsible Gate(37.66 Kg.) Sq.M. #REF!
9.5 Rolling Shutter(18 Gauge) Sq.M. #REF!
9.6 MS Angle Fixing work Kg #REF!

Prepared by:- Checked by:- Approved by:-


3/15

NEPAL DOORSANCHAR COMPANY LIMITED


EASTERN REGIONAL DIRECTORATE
CIVIL SECTION
BIRATNAGAR, MORANG
DISTRICT:- ILAM
RATES for 2071/72
Rate With 15%
S.N. Items Unit Remarks
Overhead
Making Gabin with 100*120 mm size mesh with Sq.M. #REF!
9.7 medium GI wire.
Making Gabin with 80*100 mm size mesh with
Sq.M. #REF!
9.8 medium GI wire.
9.9 Iron rod( TOR steel) for RCC dia. 8mm& below Kg #REF!

10. PAINTING WORK


10.1 2 Coat white wash in new surf. Sq.M. #REF!
10.2 2 coat snocem (cement paint) Sq.M. #REF!
10.3 Primer + 1 coat enamel painting Sq.M. #REF!
10.4 Primer + 2 coat enamel (new) Sq.M. #REF!
10.5 - aluminium Sq.M. #REF!
10.6 One coat of distemper paint Sq.M. #REF!
10.7 Two coats of distemper paint Sq.M. #REF!
10.8 One coat of Plastic Emulsion painting Sq.M. #REF!
10.9 Two coats of Plastic Emulsion painting Sq.M. #REF!
10.10 One coat of Apex painting with Primer Sq.M. #REF!
10.11 Two coats of Apex painting with Primer Sq.M. #REF!

12. WATER PROOFING WORK


12.1 38mm thick D.P.C. (1:2:4) with WPC. Sq.M. #REF!
12.2 Water proofing (P.C.C. -1:2:4, Safecrete ) Cu.M. #REF!
13. NETWORK RATE
13.1 Pitch cutting work Sq.M. #REF!
13.2 Site clearence of top soil Sq.M. 32.09
13.3 19mm plywood form work for RCC Sq.M. #REF!
13.4 PVC Duct pipe 110mm dia laying R.Mt. #REF!
13.5 Earth back filling with compaction Cu.M. 133.69
13.6 Disposal work at least 2.00 KM Cu.M. #REF!

15. DEMOLISHING WORK


15.1 Demolishing - cem.plaster Sq.M. #REF!
15.2 - wall in mud Cu.M. #REF!
15.3 - wall in c.m. Cu.M. #REF!
15.4 - PCC Cu.M. #REF!
15.5 - RCC Cu.M. #REF!

This Rate Analysis is prepared on the basis of approved Norms-


2041 (2nd Rivision) excluding VAT.

Prepared by:- Checked by:- Approved by:-


RATE OF LABOURS & CONSTRUCTION MATERIALS
FOR 2072-73
DISTRICT:- BHOJPUR
Transportation
Description Unit Rate cost Final rate Remarks
LABOUR RATE
Skilled (carpenter, mason) M.D. 660.00 660.00
Plumber " 650.00 650.00
Helper " 495.00 495.00
Unskilled " 465.00 465.00
CONSTRUCTIONAL MATERIAL RATE
Cement Nepali 53 grade OPC M.Ton. 13400.00 5250.00 18650.00 dist. Rate
Gravel crushed (Crusher) - 10 mm Cu.M. 2115.00 2115.00
Gravel crushed (crusher) - 20 mm Cu.M. 2065.00 2065.00
Gravel crushed (crusher)- 40mm Cu.M. 2015.00 2015.00
Nails Kg. 85.00 7.35 92.35 dist. Rate
Sand Cu.M. 2650.00 2650.00
Sand-Gravel mixed Cu.M. 2295.00 2295.00
Stone Cu.M. 1800.00 1800.00
Wood Ku-Kath Cu.M. 95283.00 95283.00

Prepared by:- Checked by:- Approved by:-


1/15
NEPAL TELECOM
NEPAL DOORSANCHAR COMPANY LIMITED
EASTERN REGIONAL DIRECTORATE
(CIVIL SECTION)
BIRATNAGAR, MORANG

DISTRICT:- BHOJPUR RATE ANALYSIS for 2072/73


Items Descript. Unit Quantity U.Rate Amount
Excavation of soft clay & silty soils Unskilled m.d. 0.70 465.00 325.50
including disposal upto 10m lead Equipment
and 1.5m lift 3%of labour 9.77
Item No. per Sub-Total 335.27
1.1 1 cu.m. Contract Rate(1.15) 385.56
Norms - 2(1) page 5 Contract U.Rate cu.m. 385.56
Earthwork in excav. : soft soil per cu.m. 385.56

Excavation of hard clay and soils mixed Unskilled m.d. 0.80 465.00 372.00
with soft moorum stones (upto 30mm Equipment
size) including disposal upto 10m lead 3%of labour 11.16
and 1.5m lift
Item No. per Sub-Total 383.16
1.2 1 cu.m. Contract Rate(1.15) 440.63
Norms - 2(2) page 5 Contract U.Rate cu.m. 440.63
Earthwork in excav. : B.M.Soil per cu.m. 440.63

Filling by stones in the foundation and Unskilled m.d. 1.50 465.00 697.50
levelling including haulage distance Bloc stone cu.m. 1.00 1800.00 1800.00
upto 30m Bond stone cu.m. 0.20 1800.00 360.00
Item No. per Sub-Total 2857.50
1.7 1 cu.m. Contract Rate(1.15) 3286.13
Norms - 6(5) page 39 Contract U.Rate cu.m. 3286.13
Filling of dry stone at trench per cu.m. 3286.13

Rubble masonry work including supply skilled m.d. 1.50 660.00 990.00
of hard stone blocks preparing cement unskilled m.d. 5.00 465.00 2325.00
sand mortar and construction of the cement m.t. 0.106 18650.00 1976.90
wall upto 5m high haulage distance Sand cu.m 0.47 2650.00 1245.50
upto 10m bl.stone " 1.00 1800.00 1800.00
a) cement sand mortar 1:6 bond st. " 0.10 1800.00 180.00
Water Ltr. 70.00 2.00 140.00
Item No. per Sub-Total 8657.40
3.3 1 cu.m. Contract Rate(1.15) 9956.01
Norms - 6a(3) page 35 Contract U.Rate cu.m. 9956.01
Stone work in c.m. - 1:6 per cu.m. 9956.01

Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00


walls (cement concrete) including supply unskilled m.d. 4.00 465.00 1860.00
of materials and haulage distance upto cement m.t. 0.22 18650.00 4103.00
30 m a) P.C.C.(1:3:6) gravel_1 cu.m. 0.65 2015.00 1309.75
Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.24 2065.00 495.60
Gravel_2 =20 mm gravel from river sand cu.m. 0.47 2650.00 1245.50
Water Ltr. 120.00 2.00 240.00
Item No. per Sub-Total 9913.85
4.1 1 cu.m. Contract Rate(1.15) 11400.93
Norms-7(c) page 44 Contract U.Rate cu.m. 11400.93
P.C.C. - ( 1:3:6 ) - river gravel per cu.m. 11400.93

Prepared by:- Checked by:- Approved by:-


2/15
DISTRICT:- BHOJPUR RATE ANALYSIS for 2072/73
Items Descript. Unit Quantity U.Rate Amount
Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00
walls (cement concrete) including supply unskilled m.d. 4.00 465.00 1860.00
materials and haulage distance upto 30m cement m.t. 0.32 18650.00 5968.00
a) P.C.C.(1:2:4) gravel_1 cu.m. 0.52 2015.00 1047.80
Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.22 2065.00 454.30
Gravel_2 =20 mm gravel from river gravel_3 cu.m. 0.11 2115.00 232.65
Gravel_3 =10 mm gravel from river sand cu.m. 0.445 2650.00 1179.25
Water Ltr. 150.00 2.00 300.00
Item No. per Sub-Total 11702.00
4.2 1 cu.m. Contract Rate(1.15) 13457.30
Norms-7(d) page 44 Contract U.Rate cu.m. 13457.30
P.C.C. - 1:2:4 -General work (river gravel) per cu.m. 13457.30

Concreting works of super structure skilled m.d. 0.80 660.00 528.00


deck slabs, beams including supply unskilled m.d. 7.00 465.00 3255.00
of materials and haulage distance upto cement m.t. 0.40 18650.00 7460.00
30 m. a) P.C.C.(1:1.5:3) gravel_1 cu.m. 0.57 2015.00 1148.55
Gravel_1 =20 mm broken aggregate gravel_2 cu.m. 0.29 2065.00 598.85
Gravel_2 =10 mm broken aggregate sand cu.m. 0.425 2650.00 1126.25
Water Ltr. 200.00 2.00 400.00
Item No. per Sub-Total 14516.65
4.4 1 cu.m. Contract Rate(1.15) 16694.15
Norms-7(4)b page 46 Contract U.Rate cu.m. 16694.15
P.C.C. for RCC - (1:1.5:3) broken aggregate per cu.m. 16694.15

Making wooden form work including supply skilled m.d. 1.72 660.00 1135.20
and selection of materials fixing, nailing unskilled m.d. 2.57 465.00 1195.05
according to drawings, placing separa- wood cu.m. 0.07 95283.00 6669.81
tors, dismantling forms and hauling killa kg 2.50 92.35 230.88
upto 30 m distance (Use of wood 7 times)
Item No. per Sub-Total 9230.94
5.12 10 sq.m. Contract Rate(1.15) 10615.58
Norms-8(2a) page 55 Contract U.Rate sq.m. 1061.56
Wooden Form work for slab per sq.m. 1061.56

12.5 mm thick cement sand plastering skilled m.d. 12.00 660.00 7920.00
works on walls unskilled m.d. 16.00 465.00 7440.00
a) Cement sand ratio - 1:4 cement m.t. 0.538 18650.00 10033.70
sand cu.m 1.46 2650.00 3869.00
Item No. per Sub-Total 29262.70
6.3 100 sq.m. Contract Rate(1.15) 33652.11
Norms-12(1c) page 110 Contract U.Rate sq.m. 336.52
12.5mm cement sand (1:4) plaster work. per sq.m. 336.52

20 mm thick cement sand plastering skilled m.d. 14.00 660.00 9240.00


works unskilled m.d. 19.00 465.00 8835.00
a) Cement sand ratio - 1:4 cement m.t. 0.810 18650.00 15106.50
sand cu.m 2.20 2650.00 5830.00
Item No. per Sub-Total 39011.50
6.5 100 sq.m. Contract Rate(1.15) 44863.23
Norms-12(4 b) page 112 Contract U.Rate sq.m. 448.63
20mm cement sand (1:4) plaster work. per sq.m. 448.63

3 mm thick fine cement rubbing works skilled m.d. 1.00 660.00 660.00
unskilled m.d. 1.00 465.00 465.00
cement kg 53.20 18.65 992.18
Item No. per Sub-Total 2117.18
6.8 10 sq.m. Contract Rate(1.15) 2434.76

Prepared by:- Checked by:- Approved by:-


3/15
DISTRICT:- BHOJPUR RATE ANALYSIS for 2072/73
Items Descript. Unit Quantity U.Rate Amount
Norms-11(20) page 109 Contract U.Rate sq.m. 243.48
3mm cement punning per sq.m. 243.48

Filling with ordinary soil in 15 cm thick layer Unskilled m.d. 0.25 465.00 116.25
with hand compaction (haulage distance 10M)

Item No. per Sub-Total 116.25


13.5 1 cu.m. Contract Rate(1.15) 133.69
Norms - 2(25b) page 15 Contract U.Rate cu.m. 133.69
Earth back filling and compaction work per cu.m. 133.69

Prepared by:- Checked by:- Approved by:-


ESTIMATED QUANTITIES OF MATERIALS REQUIRED PER CUBIC METRE OF COMPACTED MORTAR OR CONCRETE

NOMINAL MIX WATER CEMENT


WATERRATIO CEMENT SAND CRUSHE
CEMEN F.A. C.A. PER BY BY (CUM) D
T 50KG WEIGHT NUMBE STONES
BAG OF (KG) R OF (CUM)
CEMEN BAGS
1 1 - 0.25 12.5 1015 20.3 0.71 -
1 1.5 0.28 14 815 16.3 0.855 -
1 2 - 0.3 15 687 13.74 0.963 -
1 2.5 - 0.35 17.5 585 11.7 1.023
1 3 - 0.4 20 505 10.1 1.06 -
1 4 - 0.53 26.5 395 7.9 1.106 -
1 6 - 0.7 35 285 5.7 1.197 -
1 8 - 0.9 45 220 4.4 1.232 -
1 1 2 0.3 15 560 11.2 0.392 0.784
1 2 2 0.42 21 430 8.6 0.602 0.602
1 1.5 3 0.42 21 395 7.9 0.414 0.828
1 1.66 3.33 0.48 24 363 7.26 0.419 0.838
1 2 3 0.5 25 385 7.7 0.539 0.808
1 2 3.5 0.53 26.5 330 6.6 0.462 0.808
1 2 4 0.55 27.5 310 6.2 0.434 0.868
1 2.5 3.5 0.57 28.5 305 6.1 0.534 0.748
1 2.5 4 0.6 30 285 5.7 0.499 0.798
1 3 4 0.65 32.5 265 5.3 0.556 0.742
1 2.5 5 0.65 32.5 255 5.1 0.446 0.892
1 3 5 0.69 34.5 240 4.8 0.504 0.84
1 3 6 0.75 37.5 215 4.3 0.452 0.904
1 4 8 0.95 47.5 165 3.3 0.462 0.924

Notes:

1. F.A.= Fine Aggregates, C.A.= Coarse Aggregates

2. The table is based on assumption that the voids in sand and crushed stone are 40 and 45 percent respectively.

3. Air content of 1 percent has been assumed.

4. For gravel aggregates decrease cement by 5 percent, increase sand by 2 percent and coarse aggregate in proportion to fine aggregate in mix

4. No allowance has been made in the table for bulking of sand and wastage./>
0.3
3.333333

ortion to fine aggregate in mix.


BASIC RATES OF BHOJPUR DISTRICT (CIVIL WORKS) (FY 2072/7

Rate at
S. Particulars Bazar/Sourse Quantity per
Unit Wt/m3 (kg)
Truck (m3)
No. (Km) (NRs.)

Materials

1 Cement. 670.00 bag.


3 Block Stone. 650.00 m 4.87 2,600.00
4 Bond Stone. 650.00 m 4.87 2,600.00
5 Sand. 500.00 m 5.38 1,500.00
6 Agregate 40 mm down. 800.00 m 4.87 2,250.00
7 Agregate 20 mm down. 850.00 m 4.87 2,250.00
8 Agregate 10 mm down. 900.00 m 4.87 2,250.00
9 River Pabbles 800.00 m 4.87 1,800.00
10 Reinforcement Steel. 81,950.00 MT
11 Binding Wire. 92.00 Kg.
12 Machine Made 1st Class Brick ? '000
13 Chimney Made 1st Class Brick 12,000.00 '000

dhankuta
L WORKS) (FY 2072/73)

Transportation Total Unit Rate at


Cost for 20+10 Transportation Site
km Cost (NRs.) (NRs.)

- 670.00
1,078.03 1,078.03 1,728.03 102.67
1,078.03 1,078.03 1,728.03 102.67
975.84 975.84 1,475.84 63.20
1,078.03 1,078.03 1,878.03 102.67
1,078.03 1,078.03 1,928.03 102.67
1,078.03 1,078.03 1,978.03 102.67
1,078.03 1,078.03 1,878.03 69.82
110.00 82,060.00
- 92.00
- #VALUE!
- 12,000.00
1/15
NEPAL TELECOM
NEPAL DOORSANCHAR COMPANY LIMITED
EASTERN REGIONAL DIRECTORATE
(CIVIL SECTION)
BIRATNAGAR, MORANG

DISTRICT:- BHOJPUR RATE ANALYSIS for 2072/73


Items Descript. Unit Quantity U.Rate Amount
Excavation of soft clay & silty soils Unskilled m.d. 0.70 465.00 325.50
including disposal upto 10m lead Equipment
and 1.5m lift 3%of labour 9.77
Item No. per Sub-Total 335.27
1.1 1 cu.m. Contract Rate(1.15) 385.56
Norms - 2(1) page 5 Contract U.Rate cu.m. 385.56
Earthwork in excav. : soft soil per cu.m. 385.56

Excavation of hard clay and soils mixed Unskilled m.d. 0.80 465.00 372.00
with soft moorum stones (upto 30mm Equipment
size) including disposal upto 10m lead 3%of labour 11.16
and 1.5m lift
Item No. per Sub-Total 383.16
1.2 1 cu.m. Contract Rate(1.15) 440.63
Norms - 2(2) page 5 Contract U.Rate cu.m. 440.63
Earthwork in excav. : B.M.Soil per cu.m. 440.63

Excavation of soft soil, disposal upto Unskilled m.d. 1.00 465.00 465.00
10m lead and 1.5m lift Equipment
3%of labour 13.95
Item No. per Sub-Total 478.95
1.3 1 cu.m. Contract Rate(1.15) 550.79
Norms - 2(9) page 8 Contract U.Rate cu.m. 550.79
E/W excav. for found. Trench - soft soil per cu.m. 550.79

Excavation for foundation drain, pipe Unskilled m.d. 1.59 465.00 739.35
line etc.in boulder mixed soil, disposal Equipment
(upto 10m lead and 1.5m lift) 3%of labour 22.18
Item No. per Sub-Total 761.53
1.4 1 cu.m. Contract Rate(1.15) 875.76
Norms - 2(14) page 9 Contract U.Rate cu.m. 875.76
E/w in excav. for found. trench B.M.Soil per cu.m. 875.76

Filling by stones in the foundation and Unskilled m.d. 1.50 465.00 697.50
levelling including haulage distance Bloc stone cu.m. 1.00 1800.00 1800.00
upto 30m Bond stone cu.m. 0.20 1800.00 360.00
Item No. per Sub-Total 2857.50
1.7 1 cu.m. Contract Rate(1.15) 3286.13
Norms - 6(5) page 39 Contract U.Rate cu.m. 3286.13
Filling of dry stone at trench per cu.m. 3286.13

Filling by sand and hand compaction Unskilled m.d. 0.70 465.00 325.50
(haulage distance 10m) with sprinkling Sand cu.m. 1.10 2650.00 2915.00
water Water Ltr. 5.00 2.00 10.00
Item No. per Sub-Total 3250.50
1.8 1 cu.m. Contract Rate(1.15) 3738.08
Norms - 2(42) page 21 Contract U.Rate cu.m. 3738.08
Filling of sand with water compaction per cu.m. 3738.08

Rubble masonry work including supply skilled m.d. 1.50 660.00 990.00

Prepared by:- Checked by:- Approved by:-


2/15
DISTRICT:- BHOJPUR RATE ANALYSIS for 2072/73
Items Descript. Unit Quantity U.Rate Amount
of hard stone blocks preparing cement unskilled m.d. 5.00 465.00 2325.00
sand mortar and construction of the cement m.t. 0.106 18650.00 1976.90
wall upto 5m high haulage distance Sand cu.m 0.47 2650.00 1245.50
upto 10m bl.stone " 1.00 1800.00 1800.00
a) cement sand mortar 1:6 bond st. " 0.10 1800.00 180.00
Water Ltr. 70.00 2.00 140.00
Item No. per Sub-Total 8657.40
3.3 1 cu.m. Contract Rate(1.15) 9956.01
Norms - 6a(3) page 35 Contract U.Rate cu.m. 9956.01
Stone work in c.m. - 1:6 per cu.m. 9956.01

Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00


walls (cement concrete) including supply unskilled m.d. 4.00 465.00 1860.00
of materials and haulage distance upto cement m.t. 0.13 18650.00 2424.50
30 m a) P.C.C.(1:5:10) gravel_1 cu.m. 0.65 2015.00 1309.75

Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.24 2065.00 495.60

Gravel_2 =20 mm gravel from river sand cu.m. 0.47 2650.00 1245.50

Water Ltr. 78.00 2.00 156.00


Item No. per Sub-Total 8151.35
4.1 1 cu.m. Contract Rate(1.15) 9374.05
Norms-7-2(a) page 44 Contract U.Rate cu.m. 9374.05
P.C.C. - ( 1:5:10 ) - river gravel per cu.m. 9374.05

Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00


walls (cement concrete) including supply unskilled m.d. 4.00 465.00 1860.00
of materials and haulage distance upto cement m.t. 0.17 18650.00 3170.50
30 m a) P.C.C.(1:4:8) gravel_1 cu.m. 0.65 2015.00 1309.75
Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.24 2065.00 495.60
Gravel_2 =20 mm gravel from river sand cu.m. 0.47 2650.00 1245.50
Water Ltr. 100.00 2.00 200.00
Item No. per Sub-Total 8941.35
4.1 1 cu.m. Contract Rate(1.15) 10282.55
Norms-7-2(b) page 44 Contract U.Rate cu.m. 10282.55
P.C.C. - ( 1:4:8 ) - river gravel per cu.m. 10282.55

Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00


walls (cement concrete) including supply unskilled m.d. 4.00 465.00 1860.00
of materials and haulage distance upto cement m.t. 0.22 18650.00 4103.00
30 m a) P.C.C.(1:3:6) gravel_1 cu.m. 0.65 2015.00 1309.75
Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.24 2065.00 495.60
Gravel_2 =20 mm gravel from river sand cu.m. 0.47 2650.00 1245.50
Water Ltr. 120.00 2.00 240.00
Item No. per Sub-Total 9913.85
4.1 1 cu.m. Contract Rate(1.15) 11400.93
Norms-7(c) page 44 Contract U.Rate cu.m. 11400.93
P.C.C. - ( 1:3:6 ) - river gravel per cu.m. 11400.93

Prepared by:- Checked by:- Approved by:-


3/15
DISTRICT:- BHOJPUR RATE ANALYSIS for 2072/73
Items Descript. Unit Quantity U.Rate Amount
Concreting of foundation, vertical faces skilled m.d. 1.00 660.00 660.00
walls (cement concrete) including supply unskilled m.d. 4.00 465.00 1860.00
materials and haulage distance upto 30m cement m.t. 0.32 18650.00 5968.00
a) P.C.C.(1:2:4) gravel_1 cu.m. 0.52 2015.00 1047.80
Gravel_1 =40 mm gravel from river gravel_2 cu.m. 0.22 2065.00 454.30
Gravel_2 =20 mm gravel from river gravel_3 cu.m. 0.11 2115.00 232.65
Gravel_3 =10 mm gravel from river sand cu.m. 0.445 2650.00 1179.25
Water Ltr. 150.00 2.00 300.00
Item No. per Sub-Total 11702.00
4.2 1 cu.m. Contract Rate(1.15) 13457.30
Norms-7(d) page 44 Contract U.Rate cu.m. 13457.30
P.C.C. - 1:2:4 -General work (river gravel) per cu.m. 13457.30

Concreting works of super structure skilled m.d. 0.80 660.00 528.00


deck slabs, beams including supply unskilled m.d. 7.00 465.00 3255.00
of materials and haulage distance upto cement m.t. 0.40 18650.00 7460.00
30 m. a) P.C.C.(1:1.5:3) gravel_1 cu.m. 0.57 2015.00 1148.55
Gravel_1 =20 mm broken aggregate gravel_2 cu.m. 0.29 2065.00 598.85
Gravel_2 =10 mm broken aggregate sand cu.m. 0.425 2650.00 1126.25
Water Ltr. 200.00 2.00 400.00
Item No. per Sub-Total 14516.65
4.4 1 cu.m. Contract Rate(1.15) 16694.15
Norms-7(4)b page 46 Contract U.Rate cu.m. 16694.15
P.C.C. for RCC - (1:1.5:3) broken aggregate per cu.m. 16694.15

Making wooden form work including supply skilled m.d. 1.72 660.00 1135.20
and selection of materials fixing, nailing unskilled m.d. 2.57 465.00 1195.05
according to drawings, placing separa- wood cu.m. 0.07 95283.00 6669.81
tors, dismantling forms and hauling killa kg 2.50 92.35 230.88
upto 30 m distance (Use of wood 7 times)
Item No. per Sub-Total 9230.94
5.12 10 sq.m. Contract Rate(1.15) 10615.58
Norms-8(2a) page 55 Contract U.Rate sq.m. 1061.56
Wooden Form work for slab per sq.m. 1061.56

12.5 mm thick cement sand plastering skilled m.d. 12.00 660.00 7920.00
works on walls unskilled m.d. 16.00 465.00 7440.00
a) Cement sand ratio - 1:4 cement m.t. 0.538 18650.00 10033.70
sand cu.m 1.46 2650.00 3869.00
Item No. per Sub-Total 29262.70
6.3 100 sq.m. Contract Rate(1.15) 33652.11
Norms-12(1c) page 110 Contract U.Rate sq.m. 336.52
12.5mm cement sand (1:4) plaster work. per sq.m. 336.52

20 mm thick cement sand plastering skilled m.d. 14.00 660.00 9240.00


works unskilled m.d. 19.00 465.00 8835.00
a) Cement sand ratio - 1:4 cement m.t. 0.810 18650.00 15106.50
sand cu.m 2.20 2650.00 5830.00
Item No. per Sub-Total 39011.50
6.5 100 sq.m. Contract Rate(1.15) 44863.23
Norms-12(4 b) page 112 Contract U.Rate sq.m. 448.63
20mm cement sand (1:4) plaster work. per sq.m. 448.63

3 mm thick fine cement rubbing works skilled m.d. 1.00 660.00 660.00
unskilled m.d. 1.00 465.00 465.00
cement kg 53.20 18.65 992.18
Item No. per Sub-Total 2117.18
6.8 10 sq.m. Contract Rate(1.15) 2434.76

Prepared by:- Checked by:- Approved by:-


4/15
DISTRICT:- BHOJPUR RATE ANALYSIS for 2072/73
Items Descript. Unit Quantity U.Rate Amount
Norms-11(20) page 109 Contract U.Rate sq.m. 243.48
3mm cement punning per sq.m. 243.48

Site clearence work Cutting of Top soil, Unskilled m.d. 0.06 465.00 27.90
levelling,and Leading of disposal.

Item No. per Sub-Total 27.90


13.2 1 sq.m. Contract Rate(1.15) 32.09
Norms - 1(8) page 4 Contract U.Rate sq.m. 32.09
Site clearence work of top surface. per sq.m. 32.09

Filling with ordinary soil in 15 cm thick layer Unskilled m.d. 0.25 465.00 116.25
with hand compaction (haulage distance 10M)

Item No. per Sub-Total 116.25


13.5 1 cu.m. Contract Rate(1.15) 133.69
Norms - 2(25b) page 15 Contract U.Rate cu.m. 133.69
Earth back filling and compaction work per cu.m. 133.69