Sunteți pe pagina 1din 54

2

COST CONCEPTS AND


DESIGN ECONOMICS

Muhammad Aljalali, Ph.D.


Cost Terminology
2

Do its benefits exceeds its costs


Important cost concepts

Economic perspective in engineering design

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost Terminology
3

Fixed, variable, and incremental costs.


Direct, indirect and standard costs.

Cash cost versus book cost.

Sunk cost.

Opportunity cost.

Life-cycle cost.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost Terminology
4

Fixed, Variable, and Incremental Costs

Fixed Costs:
Those unaffected by changes in activity level.
Variable Costs:
Those associated with production output.
Incremental Cost:
Additional cost from increasing the output by one unit.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost Terminology
5

Fixed, Variable, and Incremental Costs

Cost

Variable Costs

Fixed Costs

Production Volume (Quantity)


2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Cost Terminology
6

Example 2.1
In connection with surfacing a new highway, a
contractor has a choice of two sites on which to set
up the asphalt mixing plant equipment.
He estimates that it will cost $2.75 per cubic yard
per mile (yd3-mile) to haul the asphalt-paving
material from the mixing plant to the job location.
The table below shows the factors relating to each
site.
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Cost Terminology
7

Example 2.1

Site A
Site B

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost Terminology
8

Example 2.1
Site B Site A

Cost Factor Site A Site B


Average hauling distance 4 miles 3 miles
Monthly rental of site $2,000 $7,000
Cost to set up and remove equipment $15,000 $50,000
Hauling expense $2.75/yd3 -mile $2.75/yd3 -mile
Flagperson Not required $150/day

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost Terminology
9

Example 2.1
The job required 50,000 cubic yard of mixed asphalt
paving material. It is estimating that 4 months (17 weeks
of five days per week) will be required for the job.
Compare the two sites in terms of their fixed, variable
and total costs. Assume the cost of the return trip is
negligible:
Which is the better site?
For the selected site, how many cubic yards of paving
material does the contractor have to deliver before starting
to make a profit if paid $12 per cubic yard delivered to
the job location?
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Cost Terminology
10

Solution 2.1
Site B Site A

Fixed or
Cost Variable Site A Site B
Rent Fixed $8,000 $28,000
Setup Fixed $15,000 $50,000
Flagman Fixed 0 5(17)($150) = $12,750
Hauling Variable 4(50,000)($2.75) = 3(50,000)($2.75) =
$550,000 $412,500
$573,000 $503,250
Site B has the smaller total cost for the job.
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Cost Terminology
11

Solution 2.1
The contractor will make profit when:

Total cost = Total Revenue


Fixed costs + Variable costs = Total revenue
$90,750 + 3($2.75)x = $12 x
$90,750 + $8.25 x = $12 x

x = 24,200 yd3
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Cost Terminology
12

Solution 2.1
Cost or
revenue TR = p . q
TC = FC + VC
= FC+ cv . q

FC

q Production Volume

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost Terminology
13

Direct, Indirect, and Standard Cost


Direct costs:
Can measured and allocated to unit cost of production.
Labor and material costs.
Direct costs are variable costs.

Indirect (overhead, burden) costs:


Costs that difficult to allocate to a specific output or work
activity.
There are methods to allocate these costs to production units.
Allocation in proportion to (Direct labor hours, Direct labor costs,
Direct material costs, etc.).
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Cost Terminology
14

Direct, Indirect, and Standard Cost


Standard costs:
Representativecost per unit of output.
Developed from:
Direct labor hours, Materials, Overhead categories (certain level of
production).
Some typical uses of standard costs:
Estimating future manufacturing costs.
Measuring operation performance.
Preparing bids.
Establishing the value of work in process and finished inventories.
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Cost Terminology
15

Cash Cost versus Book Cost

Cash cost:
The actual cost in transaction.
Book cost:
Accounting or historical cost.
Recovery of past expenditure over a period of time
(depreciation).

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost Terminology
16

Sunk Cost

The sunk cost is one that occurred in the past


and has no relevance of future costs or
revenues relative to an alternative course of
action.
Replacement of assets example.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost Terminology
17

Opportunity Cost

An opportunity cost is incurred because of the


use of limited resources.
The cost of the best rejected (foregone)

opportunity.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost Terminology
18

Engineering Life-Cycle Cost


Economy
Studies
Potential for life- Cumulative life-
cycle cost savings cycle cost
Cost

Cumulative
committed life-
cycle cost

Time
0
Needs Conceptual Detailed Production or Operation or Retirement and
assessment; (preliminary) design construction customer use; disposal
definition of design maintenance
requirements and support
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
ACQUISITION PHASE OPERATION PHASE
Cost Terminology
19

Life-Cycle Cost

Investment cost.
Operating and maintenance cost (O&M).

Disposal cost.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
20

Consumer and producer goods and services.


Measure of economic worth.

Necessities, Luxuries, and Price Demand.

Market types.

Cost Volume Relationships.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
21

Consumer and Producer Goods and Services


Consumer Goods and Services:
Products or services that are directly used by people to
satisfy their wants.
Examples: (food, clothing, mobiles, TV sets, opera, etc.)

Producer Goods and Services:


Products or services that are used to produce consumer
goods and services.
Examples: (machines, buildings, equipment, buses, etc.)

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
22

Measures of Economic Worth

Goods and services are produced and


desired because they have utility.
Utility is the power to satisfy human wants

and needs.
Utility is measured in terms of value.

The price is the medium of exchange of value.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
23

Necessities, Luxuries, and Price Demand

Necessities.
Luxuries.

Price demand.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
24

Price Demand
p
D

Price p=abD

Units of Demand D

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
25

Competition

Perfect competition.
Monopolistic competition.

Oligopoly.

Monopoly.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
26

Total Revenue Function

TR = price demand = p D
TR = (a bD) D = aD bD2
for 0 D a/b and a > 0, b > 0
dTR / dD = a 2bD = 0
= a / 2b

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
27

Total Revenue Function

Max TR = a b2

Total
Revenue

Demand
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
The General Economic Environment
28

Cost, Volume, and Breakeven Point Relationships

TR = a D b D2
Cost And CT = CF + CV
Revenue Max.
Profit CV = cv . D

CF

D1 D* D2 Volume (Demand)
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
The General Economic Environment
29

Cost, Volume, and Breakeven Point Relationships

Profit = TR - CT
Profit = (a D b D2) (cv D + CF)
Profit = b D2 + (a - cv) D CF
d(Profit)/dD = 2b D* + (a - cv) = 0
D* = (a - cv) / 2 b

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
30

Cost, Volume, and Breakeven Point Relationships


Conditions must exist:
1st: (a cv) > 0
2nd: TR > CT for the period involved

Break Even Points (zero profit):


Profit = b D2 + (a - cv) D CF = 0


, =

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
31

Example 2.2
A company produce an electronic timing switch.
CF = $73,000 per month,
cv = $83 per unit,
Price = p = $180 0.02 (D)
a) Determine the optimal volume for this product and
confirm that profit occurs,
b) Find the volumes at which breakeven occurs.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
32

Solution 2.2 (a)


D* = (a cv)/(2b) = ($180 83)/(2(0.02))
= 2,425 units per month
The Conditions:
1: a cv = $180 83 = $97 > 0 o.k.
2: (TR CT) > 0 for D* = 2,425 units per month
($180(2,425) 0.02(2,425)2) ($73,000 + 83(2,425))
= $44,612 > 0 o.k.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
33

Solution 2.2 (b)


Total revenue = Total cost (breakeven point)
- bD2 + (a cv)D CF = 0
- 0.02D2 + ($180 - $83)D - $73,000 = 0
- 0.02 D2 + 97 D 73,000 = 0
.
. ,
, =
.
+ .
= =
.
.
= = ,
.
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
The General Economic Environment
34

Price is Independent of Demand

TR = p . D Profit
Cost and
Revenue CT = cv . D + CF
Loss
CF

D Volume (Demand)

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
35

Price is Independent of Demand

= +

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
36

Example 2.3
An engineering consulting firm measures its output in a
standard service hour unit, which is a function of the
personal grade levels in the professional staff. The
variable cost (cv) is $62 per standard service hour. The
charge-out rate [i.e., selling price (p)] is 1.38cv =
$85.56 per hour. The maximum output of the firm is
160,000 hours per year, and its fixed cost (CF) is
$2,024,000 per year.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
37

Example 2.3
For this firm:
a) What is the breakeven point in standard service
hours and in percentage to total capacity?
b) What is the percentage reduction in the breakeven
point (sensitivity) if fixed costs are reduced 10%; if
variable cost per hour is reduced 10%; if both costs
are reduced 10%; and if the selling price per unit is
increased by 10%?

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
38

Solution 2.3

Cost TR = p . D
Revenue CT = cv . D + CF

CF

D Volume (Demand)

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
39

Solution 2.3

Cost or TR = p . D
Revenue
CT = cv . D + CF

CF

D Volume (Demand)

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


The General Economic Environment
40

Solution 2.3 (a)


Breakeven point

=

$, ,
= = ,
$, $
As a percentage
,
= = . = . %
,
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
The General Economic Environment
41

Solution 2.3 (b)


A 10% reduction in CF gives

=

. ($, , )
= = ,
$, $
As a percentage
, ,
= = %
,
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
The General Economic Environment
42

Solution 2.3 (b)


A 10% reduction in cv gives

=

$, ,
= = ,
$, (. )$
As a percentage
, ,
= = . %
,
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
The General Economic Environment
43

Solution 2.3 (b)


A 10% reduction in CF and cv gives

=

. ($, , )
= = ,
$, (. )$
As a percentage
, ,
= = . %
,
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
The General Economic Environment
44

Solution 2.3 (b)


A 10% increase in p gives

=

$, ,
= = ,
. ($, ) $
As a percentage
, ,
= = . %
,
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
The General Economic Environment
45

Solution 2.3 (b)


Change in Decrease in
Factor Value(s) Breakeven Point
10% reduction in CF 10.0%

10% reduction in cv 20.8%

10% reduction in CF and in cv 28.7%

10% increase in p 26.6%

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost-Driven Design Optimization
46

Life cycle of the design (cradle to grave),


Design for the Environment DFE (green
engineering),
Design for energy conservative,

Minimum life cycle costs.

Engineering Design is an economically driven art

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost-Driven Design Optimization
47

Minimum LCC is a goal achieved largely in the


early stages of design.
Engineers can accomplish a great deal toward
the goal of minimizing life cycle costs by simply
keeping in mind its importance!
Examples are plentiful in engineering.
The two main tasks:
1) Determine the optimal value for a certain alternatives
design variable,
2) Select the best alternative, each with its unique value for
the design variable.
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Cost-Driven Design Optimization
48

General Type of Cost Models


Fixed cost(s).
Cost(s) that vary directly with the design variable
Cost(s) that vary indirectly with the design Variable

= + +

= + + + +

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Cost-Driven Design Optimization
49

General Approach for optimizing a Design


1. Identify the design variable that is the primary cost
driver.
2. Write an expression for the cost model in terms of the
design variable.
3. Set the first derivative of the cost model with respect to
the continuous design variable equal to zero
4. Solve the equation found in step 3 for the optimum value
of the continuous design variable.
5. For continuous design variables use the second derivative
to determine whether the optimum value is maximum or
minimum.
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Cost-Driven Design Optimization
50

Examples

Examples 2-6 and 2-7 in the textbook.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Present Economy Studies
51

Evaluating past performance Evaluating and predicting future events

Accounting Engineering Economy

Past Future
Present

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.


Present Economy Studies
52

The Rules
RULE 1
When revenues and other economic benefits are present
and vary among alternatives, choose the alternative that
maximizes overall profitability based on the number of
defect-free units of product or service produced.

RULE 2
When revenues and other economic benefits are not
present or are constant among alternatives, consider only
the costs and select the alternative that minimizes total
cost per defect-free unit of product or service output.
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Present Economy Studies
53

Examples
Total cost in material selection (example 2-8
in the textbook).
Alternative machine speeds (example 2-9 in
the textbook).
Make versus purchase (outsourcing) studies
(example 2-10 in the textbook).
Trade-offs in energy efficiency studies
(example 2-11 in the textbook).
2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.
Homework
54

Self homework:
Problems 2-1, 2-29, 2-36, 2-

43.
Class homework:
Problems 2-4, 2-11, 2-12, 2-
15, 2-20.

2. Cost Concepts and Design Economics Muhammad Aljalali Ph.D.

S-ar putea să vă placă și