The Zone Classis WBS Layout 18-May-17 10:48

Activity ID Activity Name Original Duration Start Finish

The Zone 183 10-Apr-17 08-Nov-17


Mobilization 40 10-Apr-17 25-May-17
Shop Drawings 60 10-Apr-17 18-Jun-17
Procurement 0
Site & Structural Works 183 10-Apr-17 08-Nov-17
Excavation 28 10-Apr-17 11-May-17
Building A1 12 10-Apr-17 23-Apr-17
Building A2 12 16-Apr-17 29-Apr-17
W.F.tank 3 19-Apr-17 22-Apr-17
Building B1 12 16-Apr-17 29-Apr-17
Building B1` 6 16-Apr-17 22-Apr-17
Building B2 18 10-Apr-17 30-Apr-17
Building B2` 18 10-Apr-17 30-Apr-17
Building C1 17 10-Apr-17 29-Apr-17
Building C1` 17 10-Apr-17 29-Apr-17
Building C2 16 10-Apr-17 27-Apr-17
Building C2` 16 10-Apr-17 27-Apr-17
Building D1 16 10-Apr-17 27-Apr-17
Building D1` 16 10-Apr-17 27-Apr-17
Building D2 14 10-Apr-17 25-Apr-17
Building D2` 14 10-Apr-17 25-Apr-17
Building E 22 10-Apr-17 04-May-17
Parking 1 28 10-Apr-17 11-May-17
Parking 2 28 10-Apr-17 11-May-17
Concrete 183 10-Apr-17 08-Nov-17
Building A1 137 24-Apr-17 30-Sep-17
PC Footing 4 24-Apr-17 27-Apr-17
RC Footing 7 29-Apr-17 06-May-17
Neck Column 7 07-May-17 14-May-17
Damp Proofing 2 15-May-17 16-May-17
Back Filling 4 17-May-17 21-May-17
Ground Beam 11 22-May-17 03-Jun-17
GB Damp Proofing 1 04-Jun-17 04-Jun-17
GB Back Filling 3 05-Jun-17 07-Jun-17

Page 1 of 4 TASK filter: All Activities


Oracle Corporation
The Zone Classis WBS Layout 18-May-17 10:48
Activity ID Activity Name Original Duration Start Finish

Slab on Grade 3 08-Jun-17 11-Jun-17


Ground Column 9 12-Jun-17 21-Jun-17
First Slab 27 22-Jun-17 23-Jul-17
First Column 9 24-Jul-17 02-Aug-17
Roof Slab 24 03-Aug-17 30-Aug-17
Roof Column and Parapet
P 7 31-Aug-17 07-Sep-17
Upper Roof Slab 6 09-Sep-17 14-Sep-17
Block Work Ground
Groun Floor 7 16-Sep-17 23-Sep-17
Block Work First Floor
F 5 24-Sep-17 28-Sep-17
Block Work Roof Floor
F 1 30-Sep-17 30-Sep-17
Building A2 137 30-Apr-17 05-Oct-17
PC Footing 4 30-Apr-17 03-May-17
RC Footing 7 04-May-17 11-May-17
Neck Column 7 13-May-17 20-May-17
Damp Proofing 2 21-May-17 22-May-17
Back Filling 4 23-May-17 27-May-17
Ground Beam 11 28-May-17 08-Jun-17
GB Damp Proofing 1 10-Jun-17 10-Jun-17
GB Back Filling 3 11-Jun-17 13-Jun-17
Slab on Grade 3 14-Jun-17 17-Jun-17
Ground Column 9 18-Jun-17 27-Jun-17
First Slab 27 28-Jun-17 29-Jul-17
First Column 9 30-Jul-17 08-Aug-17
Roof Slab 24 09-Aug-17 05-Sep-17
Roof Column and Parapet
P 7 06-Sep-17 13-Sep-17
Upper Roof Slab 6 14-Sep-17 20-Sep-17
Block Work Ground
Groun Floor 7 21-Sep-17 28-Sep-17
Block Work First Floor
F 5 30-Sep-17 04-Oct-17
Block Work Roof Floor
F 1 05-Oct-17 05-Oct-17
Building B1 166 30-Apr-17 08-Nov-17
PC Footing 4 30-Apr-17 03-May-17
Water Proofing 3 04-May-17 07-May-17

Page 2 of 4 TASK filter: All Activities


Oracle Corporation
The Zone Classis WBS Layout 18-May-17 10:48
Activity ID Activity Name Original Duration Start Finish

RC Footing 7 08-May-17 15-May-17


Basement Column 8 16-May-17 24-May-17
Retaining Wall 10 25-May-17 05-Jun-17
Damp Proofing 2 06-Jun-17 07-Jun-17
Back Filling 2 08-Jun-17 10-Jun-17
Slab On Grade 5 11-Jun-17 15-Jun-17
Ground Floor Slab 23 17-Jun-17 12-Jul-17
Ground Floor Column
Colu 9 13-Jul-17 23-Jul-17
First Floor Slab 27 24-Jul-17 23-Aug-17
First Floor Column 9 24-Aug-17 03-Sep-17
Roof Floor Slab 24 04-Sep-17 01-Oct-17
Roof Floor Column and Parapet 7 02-Oct-17 09-Oct-17
Upper Roof Slab 13 10-Oct-17 24-Oct-17
Block Work Ground
Groun Floor 7 25-Oct-17 01-Nov-17
Block Work First Floor
F 5 02-Nov-17 07-Nov-17
Block Work Basement
Basem 1 08-Nov-17 08-Nov-17
Water Tank 37 23-Apr-17 04-Jun-17
PC Footing 2 23-Apr-17 24-Apr-17
Water Proofing 3 25-Apr-17 27-Apr-17
RC Footing 5 29-Apr-17 03-May-17
Water Tank Walls 13 04-May-17 18-May-17
Water Tank Slab 10 20-May-17 30-May-17
Water Proofing Walls
Wa 4 31-May-17 04-Jun-17
Building B1` 160 10-Apr-17 12-Oct-17
PC Footing 14 10-Apr-17 25-Apr-17
RC Footing 7 26-Apr-17 03-May-17
Neck Column 7 04-May-17 11-May-17
Damp Proofing 2 13-May-17 14-May-17
Back Filling 4 15-May-17 18-May-17
Ground Beam 11 20-May-17 31-May-17
GB Damp Proofing 1 01-Jun-17 01-Jun-17
GB Back Filling 3 03-Jun-17 05-Jun-17

Page 3 of 4 TASK filter: All Activities


Oracle Corporation
The Zone Classis WBS Layout 18-May-17 10:48
Activity ID Activity Name Original Duration Start Finish

Slab on Grade 12 11-Jun-17 24-Jun-17


Ground Column 9 25-Jun-17 04-Jul-17
First Slab 27 05-Jul-17 05-Aug-17
First Column 9 06-Aug-17 15-Aug-17
Roof Slab 24 16-Aug-17 12-Sep-17
Roof Column and Parapet
P 7 13-Sep-17 20-Sep-17
Upper Roof Slab 6 21-Sep-17 27-Sep-17
Block Work Ground
Groun Floor 7 28-Sep-17 05-Oct-17
Block Work First Floor
F 5 07-Oct-17 11-Oct-17
Block Work Roof Floor
F 1 12-Oct-17 12-Oct-17
Building B2 0
Building B2` 0
Building C1 5 10-Apr-17 15-Apr-17
Building C1` 5 10-Apr-17 15-Apr-17
Building C2 5 10-Apr-17 15-Apr-17
Building C2` 5 10-Apr-17 15-Apr-17
Building D1 5 10-Apr-17 15-Apr-17
Building D1` 5 10-Apr-17 15-Apr-17
Building D2 5 10-Apr-17 15-Apr-17
Building D2` 5 10-Apr-17 15-Apr-17
Building E 5 10-Apr-17 15-Apr-17
Parking 1 0
Parking 2 0
Mechanical Works 5 10-Apr-17 15-Apr-17
Electrical Works 5 10-Apr-17 15-Apr-17
SCECO 0
PROJECT HAND OVERING 0