MATERIALS
fcu 35 N/mm m 1.5 concrete Min bar = 10
fy 500 N/mm m 1.15 steel Max bar = 16
h agg 20 mm steel class A
Cover 25 mm Density 23.6 kN/m Nominal top steel ? Y
(Normal weight concrete)
DIMENSIONS Sectional Elevation
LOADING
Imposed 4.00 kN/m 47.08 kN/m ult 37.81 kN/m ult
Flight finishes 1.60 kN/m (20.87 + 11.16) (16.91 + 8.84)
Landing finishes 1.30 kN/m
DESIGN
LANDING A, gk = 4.13 + 1.30 = 5.43 kN/m n = 1.4 x 5.43 + 1.6 x 4.0 = 14.00 kN/m
FLIGHT, gk = 7.78 + 1.60 = 9.38 kN/m n = 1.4 x 9.38 + 1.6 x 4.0 = 19.53 kN/m
LANDING C, gk = 4.72 + 1.30 = 6.02 kN/m n = 1.4 x 6.02 + 1.6 x 4.0 = 14.83 kN/m
MATERIALS
fcu 35 N/mm m 1.5 concrete Min bar = 10
fy 500 N/mm m 1.15 steel Max bar = 16
h agg 20 mm Density 23.6 kN/m
Cover 25 mm (Normal weight concrete) Nominal top steel ? Y
DIMENSIONS
a = 1200 mm epth, h = 175 mm
b = 1200 mm idth, w = 1200 mm
c = 250 mm
d = 175 mm L = 3000 mm
LOADING
LANDING mposed 4.00 kN/m 79.3 kN ult 74.0 kN ult
Finishes 1.50 kN/m 66.1 kN/m ult 61.6 kN/m ult
Slab 4.13 kN/m n = 1.4 x 5.63 + 1.6 x 4.0 = 14.28 kN/m
gk qk
Flight a reaction 20.87 11.16 kN/m n1 = (1.4 x 20.87 + 1.6 x 11.16)/1.20 = 39.23 kN/m
Flight b reaction 16.91 8.84 kN/m n2 = (1.4 x 16.91 + 1.6 x 8.84)/1.20 = 31.51 kN/m
DESIGN
Zero shear is at (66.11 - 2.50) /(14.28 + 39.23) + 0.175 = 1.364 m from left
M = 66.11 x 1.364 - 14.28 x 1.364/2 - 39.23 x 1.189/2 = 49.15 kNm/m
d = 175 - 25 - 8 = 142 mm K = 0.0696 As = 870 mm/m
### ###
Enhanced by 12.7 % for deflection H10 @ 325 T in span
L/d = ### Err:520
Project Spreadsheets to BS 8110
Location South Staircase
STAIR FLIGHTS AND LANDINGS to BS 8110:2005 Made by rmw Job No R68
Originated from RCC71.xls' v4.0 on CD 2006 TCC Date 31-May-17
FLIGHT LANDING
M 41.64 49.15 Lookup Tables
h 200 175 0 10 10
assume d = 169 144 8 10 10
K 0.0417 0.0677 10 10 10
z 160.55 132.20 12 12 12
As/m 596.56 855.20 16 16 16
=% 0.3530 0.5939 20 16 16
Clause b? N N 25 16 16
Smax 422.50 360.00 32 16 16
Dia 16 16
0 10 10
As nom 260 228 8 10 10
Dia 10 10 10 10 10
S 300 325 12 12 12
As' prov 262 242 16 16 16
=% 0.1568 0.1702 20 20 20
25 25 25
32 32 32
Disclaimer
All advice or information from MPA-The Concrete Centre is intended for those who will evaluate the significance and limitations of its
contents and take responsibility for its use and application. No liability (including that for negligence) for any loss resulting from such advice
or information is accepted by MPA-The Concrete Centre or its subcontractors, suppliers or advisors. Users should note that all MPA-The
Concrete Centre software and publications are subject to revision from time to time and they should therefore ensure that they are in
possession of the latest version.
This spreadsheet should be used in compliance with the accompanying publication 'User Guide RC Spreadsheets: v4' available from The
Concrete Centre www.concretecentre.com/rcdesign Tel +44 (0)1276 606800
Status of spreadsheet This spreadsheet is shareware but may not be used for commercial purposes until the user has
Public release version. registered with The Concrete Centre using the licence validation form available on The Concrete
Centre website www.concretecentre.com/rcdesign