Documente Academic
Documente Profesional
Documente Cultură
INTRODUCTION
1.1 GENERAL
1
better progress. Also application of appropriate optimized techniques, effort & time can
be saved with better work progress.
2
1.4 TIME COST OPTIMIZATION CONCEPT
The cost optimization is a process that should be carried out throughout the
construction period to ensure that the cost of the building is kept within the estimated cost
limits. In the construction field, time saving can also be transformed into some kind of
opportunity such as bonus of early completion or saving in overhead. Therefore, the
lowest tender price may not be the only criterion for project success and thus concurrent
optimization in both time and cost is highly encouraged and desirable.
The time overrun in construction projects has become one of the most common
problems in the industry that cause multitude of negative effects on the projects and its
stakeholders. Therefore, this aspect has been constantly investigated by the researchers
across the world with a great enthusiasm.
However, this technique (crashing) may affect profit margins and quality of their
projects.
3
subdivision by detail and by integration with other functions. In comparison with a cost
standard method, the standard set up by estimator is compared at the time of tender.
There are also other standards efficiency can be judged include set up by the work study
department of a company, previous outputs achieved within the company or within the
knowledge of the companys employees in the past, and standards that have been
published in books primarily for use of estimator, giving data on recommended outputs
for labour and plant. In the subdivision by detail method, it is usually practiced by small
scale of contractors compares the amount of money received with the amount of money
he has had to pay out to complete the contract at the end of the contract. It is not
expensive but a risky operation, involves little or no optimization of costs. It is also
inaccurate since estimator often omits some contentious items from a valuation, even
though payment will result from them. In integration with other functions method, the
cost optimization system will combine with some other necessary operation in the
administration of a contract and not as a separate entity. For example, it may be
combined with a labour utilization scheme, in which the optimization is kept on the
optimal utilization of the labour employed.
These are resource optimization techniques which are used to adjust the project
schedule due to the demand and supply issues of project resources. Resource
optimization is a method of gaining efficiency and consistency of resource utilizations
within the project. Efficiency and Consistency means resources should not be over
allocated at any given time period than their calendar availability.
4
1.8 OBJECTIVE
To optimize time over run due to improper resource allocation & management in
construction industry. To minimize resource wastage due to inadequate professional
training of labours in construction industry. To evaluate and analyse the current resource
management techniques of construction companies. To develop a comprehensive
framework for optimal resource management.
To identify the probable areas of wastages which are prone to occur in the
construction industries and to provide optimal solutions for minimizing wastage of the
resource. Ensure Efficient/Effective Utilization of resources in construction industry.
5
CHAPTER 2
LITERATURE REVIEW
Jesper Kranker Larsen, et al (2016) [1] analyzed the factors that project managers
experience as having the greatest effect on time, cost, and quality. Factors were ranked
using the relative importance index. From the findings it was determined that the most
influential factor for time is unsettled or lack of project funding; for cost, errors in
consultant material; and for quality, errors in construction work. The main conclusion of
this research is that project schedule, budget, and quality level are affected in
significantly different ways
P.M. Pethkar, et al (2015) [3] studied time and cost overruns as the most important
factors responsible for abandonment and contractors failure. Although the Indian
construction industry has gained far more importance in recent times because of opening
up of Indian markets and the arrival of megaprojects for infrastructure development.
Delay gives increase to disturbance of work and loss of productivity, late completion of
project increased time related costs, and third party claims and abandonment or
termination of contract. It is important that general management keep track of progress to
6
reduce the possibility of delay occurrence. Delays often results in time overrun, disputes,
litigation, and complete abandonment of projects.
Seyed Ali Mousavi Dehmourdi (2014) [4] the Objective of this paper are to apply
the principles of engineering economics, basic economic concepts, finance and
quantitative techniques to modelling and analysis of civil engineering projects. Also a
practical application of linear programming in a real life project problem with two
objectives as optimization of transporting cost of equipment and finding the best solution
for reducing the functional costs of the equipment. Mainly structured linear programming
model is used for optimizing the transporting cost of equipment. Applications of this
approach helps in determining the need for the replacement and the maintenance analysis
are based on the econometric approach to the realistic problems and the result shows that
optimization with advanced techniques really helps in minimization of cost of project.
Ali & Alrayes (2014) [5] explained the variables that might affect e procurement
adoption in Kingdom of Bahrain. Researcher has studied perceived organization e
readiness factors (POER) and perceived external e readiness factors (PEER). POER
factors comprise of awareness, commitment, governance, resources (human, business and
technology) effect the institutional adoption. Main PEER factors are market forces,
supporting industries and government. Licker model called perceived e readiness model
(PERM) which includes internal and external factors for IT adoption. Researcher also
define the status of adopters of e procurement- Non adopters (no connection to web, only
email), Initial adopters (web with interaction with email query etc.) and Institutional
adopters (transaction web online selling and purchasing, integration with suppliers,
customers and other back office).
Barbole A.N., Yuvraj D. Nalwade, Santosh D. Parakh ( June. 2013) [6] The
survival today for any company is how to manage its service Cost, quality, and
performance. Now a days the customers are continuously demanding high quality and
better performance of services and at the same time they want the prices to fall. For this
7
author focus on impact of cost control and cost reduction techniques in present scenario.
An objective of this paper is to understand the basic concept of Cost, Cost Control, and
Cost Reduction and to study various Tool and Techniques available for Cost Control and
Cost Reduction. The Cost Control and Cost Reduction techniques used in manufacturing
sector like Value Engineering, Quality Control, and Budgetary Control are specified by
the author also cost, cost reduction, cost control etc. Various terms are specified by the
author.
Desai Megha, et al (2013) [7] studied the delay factors and catego0rised it in nine
major groups as: Project, owner, contractor, Consultant, Design, Material, Equipment,
Labour and External related delay factors depending on their nature and occurrence on
practical situations on projects. The study was done through questionnaire survey of
many Residential Projects across India and found its ranking through Relative
Importance Index and Importance Index consisting of Frequency and Severity Index and
finally the recommendations for theses delay factors are covered.
Ibrahim Mahamid, et al (2012) [8] conducted the study to investigate the time
performance of road construction projects in the West Bank in Palestine to identify the
causes of delay and their severity according to contractors and consultants through a
questionnaire survey. A total of 52 causes of delay were identified during the research.
The survey concluded that the top five severe delay causes are political situation, award
project to lowest bid price, progress payment delay by owner, and shortage of equipment.
A.S. Ali, S.N. Kamaruzzaman (2010) [9] as per the author for management of
construction 4 parameters important are as follows: scope, cost, time, and quality. the
main aim of the author is to find out the problem or parameters which contribute for the
cost overrun. for this they carried out the quaternary survey on the live projects. for the
data analysis the method used is quantitative based i.e. descriptive statistics and ranking
analysis is used. from the investigation they found that factors which contributes to cost
overrun was inaccurate or poor estimation of original cost and factor which don't affect is
8
mistake in design for this to control the construction cost method suggested by the author
is proper costing and financing. Also they concluded that cost overrun is most serious
problem which may affect the construction project effectively.
Ming Sun a. (2008) [10] Examined the impact of frequent construction project
change on its quality, time delay, cost. The project change causes are Project related,
Client related, Design related, Contract related and External factors Whereas change
effect are Time related, Cost related, Productivity related, Risk related and other effects.
The researcher proposed. A change management process model: start up, identification
and evaluation, approval and implementation and review.
Magdalena Rogalska (2008) [11] This paper identifies the analysis of the time/cost
relationship, performed using time coupling method TCM III. A modified hybrid
evolutionary algorithm (HEA) developed by Boejko and Wodecki was used for
optimization. He suggest the method of The Critical Chain Scheduling Buffer
Management which to take into account randomness, The relationship between additional
construction project realization costs generated as a result of the difference between the
actual work commencement dates and the latest work commencement dates was
examined. The future research can be carried out by applying presented ideas to other
problems of construction practice and other criterion functions, for which optimal
algorithms are powerless.
Van Truong Luu a, (2007) [12] Identified nine key performance indicators to
measure the project management performance as a benchmarking.
The key performance indicators are Construction cost performance, Construction time
performance, Customer satisfaction on services, Customer satisfaction on products,
Quality management system, The project team performance, Change management and
Labour safety management. The conceptual framework application was limited to only
three contractors hence the benchmarking can be applied to other construction projects
and more contractors.
9
Assaf, S.A. and Al-Hejji, S. (2006) [13] Aimed at identifying the reasons for delay
and time performance of various construction projects. The study identified 76 reasons
for the delay in projects. Majority of the respondents revealed that 70 percent of the
projects experience time overrun of 10 percent to 30 percent of the original time. The
study was done in Saudi Arabia on overall construction projects, and the future study
can be done on a specific type of construction projects, such as utility projects, highways
construction project, dam construction projects, etc.
Nirmal Kumar Acharyat, et al (2006) [15] surveyed that the instrument was distributed
in construction fields to obtain construction professionals experience that how much the
instrumented delay causes have been affecting the timely completion of the projects. The
Four categories of Owner, Contractor, Project and Third Party related delays were
adopted for this study. The mean score values and ranking is done to different delay
factors.
10
usually requires the engagement of additional labour and plant or the adoption of
alternative construction techniques which add extra cost liabilities to the contractor. For
time-cost optimization several analytical models have been developed. From those the
Genetic Algorithms (GA) could be used to establish the fitness of solutions by evaluating
the objective function and its constraints. the objective of paper is to compare the
analytical power of the GA with other techniques proposed for TCO. The results come
out which indicate that the GA techniques could generate the most optimal outcome for
construction Time Cost Optimization it is more beneficial when the project is large
and/or complex.
11
CHAPTER 3
METHODOLOGY
3.1 METHODOLOGY
The process of our research has been illustrated in the flowchart given below.
delay.
13
CHAPTER 4
DATA COLLECTION
Delay analysis data has been collected from various construction industries such
as commercial, Industrial areas, Pharma & Industrial project on different kinds of project
done by them.
Table-4.1 Kinds Of Project
No Research Area Number of Cases Identified
1 Commercial 10
2 Pharma 10
3 Industrial 10
PROJECT DURATION
PROJECT DELAYS IN
CLIENT MANAGEMENT OF
NAME PROJECT
CONSULTANT PROJECT
Jones Lang
NetApp, LaSalle Property
NetApp 10 months Yes (3months)
Bangalore Consultants
(India) Pvt Ltd
14
Bangalore (India) Pvt Ltd
Jones Lang
KOTAK, LaSalle Property
KOTAK 13 months Yes (4months)
Bangalore Consultants
(India) Pvt Ltd
SKF,
SKF CBRE 15 months Yes (4months)
Bangalore
Toyota,
Toyota CBRE 15 months Yes (3months)
Bangalore
Tyco,
Tyco CBRE 13 months Yes (2months)
Bangalore
Honeywell,
Honeywell CBRE 14 months Yes (4months)
Bangalore
Amada,
Amada Renaissance 06 months Yes (1months)
Bangalore
Jones Lang
Goldman
Goldman LaSalle Property
Sachs, 15 months Yes (4months)
Sachs Consultants
Bangalore
(India) Pvt Ltd
MRF,
MRF Renaissance 13 months Yes (4months)
Bangalore
15
Table-4.3 Occurrence of maximum delay in commercial project
S.No Schedule Actual Max Resource Others Type of
complete complete Delay In Delay work
Date Date Days
1 13-Dec-15 10-May-16 149 Material Climatic HVAC
39days, Factors
Manpower 37days
31days,
Machinery
42days
2 04-Nov-15 26-Jan-16 83 Material Climatic Plant room
49days, Factors
Manpower, 14days
Machinery
20days
3 03-Jan-16 19-May-16 137 Material Climatic Service
73days, Factors works
Manpower
23days,
Machinery
41days
4 04-Feb-16 20-Jun-16 137 Material Climatic HVAC
62days, Factors
Manpower, 45days
Machinery
30days
5 04-Nov-15 06-Feb-16 94 Material, Climatic STP
Manpower Factors
43days, 28days
Machinery
23days
6 18-Sep-15 13-Nov-16 56 Material, Climatic Painting
Manpower Factors works
38days, 18days
Machinery
7 03-Jan-15 09-May-16 127 Material Climatic HVAC
59days, Factors
Manpower
37days,
Machinery
31days
8 20-Jan-16 30-May-16 131 Material Climatic Black Utility
16
76days, Factors Piping
Manpower 33days
22days,
Machinery
9 04-Feb-15 25-Jun-16 142 Material Climatic HVAC
25days, Factors
Manpower 58days
37days,
Machinery
22days
10 04-Feb-16 30-Jun-16 147 Material, Climatic Service
Manpower Factors works
57days, 26days
Machinery
64days
PROJECT DURATION
PROJECT DELAYS IN
CLIENT MANAGEMENT OF
NAME PROJECT
CONSULTANT PROJECT
Jones Lang
Mylan Ltd, LaSalle Property
Mylan 11 months Yes (4months)
Bangalore Consultants
(India) Pvt Ltd
Jones Lang
Biocon, Biocon LaSalle Property
13 months Yes (2months)
Bangalore Limited Consultants
(India) Pvt Ltd
Jones Lang
Syngen, LaSalle Property
Syngen 15 months Yes (3months)
Bangalore Consultants
(India) Pvt Ltd
17
Cipla,
Cipla Renaissance 10 months Yes (4months)
Bangalore
Micro Lab,
Micro Lab CBRE 08 months Yes (2months)
Bangalore
Orchid Ltd,
Orchid Ltd Renaissance 13 months Yes (4months)
Bangalore
Ordain health,
Ordain Renaissance 11 months Yes (3months)
Chennai
Lupin Ltd,
Lupin CBRE 13 months Yes (3months)
Bangalore
Jones Lang
Ipca Ltd, LaSalle Property
Ipca 13 months Yes (4months)
Bangalore Consultants
(India) Pvt Ltd
18
3 18-Apr- 08-Aug-16 112 Material Climatic Footing
15 26days, Factors concreting
Manpower 27days
59days,
Machinery
4 13-Dec- 10-May- 149 Material Climatic HVAC
15 16 73days, Factors
Manpower
76days,
Machinery
5 18-Sep-15 11-Nov-15 54 Material Climatic Painting
12days, Factors works
Manpower 26days
16days,
Machinery
6 15-Jan-16 26-May- 132 Material, Climatic Black
16 Manpower Factors Utility
36days 49days Piping
Machinery
47days
7 03-Jan-16 19-May- 137 Material, Climatic HVAC
16 Manpower Factors
34days,
Machinery
73days
8 10-May- 25-Oct-16 168 Material Climatic CIVIL
15 74days, Factors WORKS
Manpower
53days,
Machinery
41days
9 17-Mar- 19-May- 63 Material, Climatic Excavation
15 15 Manpower, Factors
Machinery 41days
22days
10 28-Oct-15 29-Mar-16 153 Material87days, Climatic Chiller
Manpower, Factors installation
Machinery
66days
19
The above table shows delay analysis of various projects and are categorized
according to various works. For analysis Purpose Maximum delays were considered
which are based on the data collected from various pharma Projects.
PROJECT DURATION
PROJECT DELAYS IN
CLIENT MANAGEMENT OF
NAME PROJECT
CONSULTANT PROJECT
CIFI Bank,
CIFI Ltd CBRE 11 months Yes (4months)
Bangalore
Dell
International
Dell Ltd AN Prakash Ltd 09 months Yes (2months)
Service,
Bangalore
SAP Global
Delivery, SAP Ltd Renaissance 8 months Yes (2months)
Bangalore
BNC,
BNC CBRE 9 months Yes (2months)
Bangalore
Pragathi
Packing, Pragathi Aarvee Associates 8 months Yes (2months)
Hyderabad
Expedia,
Expedia Renaissance 13 months Yes (5months)
Hyderabad
Shell, Focus
Shell 9 months Yes (2months)
Bangalore Infrastructure
Siemens,
Siemens CBRE 11 months Yes (1months)
Bangalore
20
Dmart,
Dmart Aarvee Associates 13 months Yes (5months)
Bangalore
Jones Lang
Royal Enfield, LaSalle Property
Royal Enfield 13 months Yes (4months)
Bangalore Consultants
(India) Pvt Ltd
The above table shows delay analysis of various projects and are categorized according to
various works. For analysis Purpose Maximum delays were considered which are based
on the data collected from various Industrial Projects.
The analysis of data between scheduled time & actual completion time. Initially
preliminary analysis scheduled time and actual completion time is done and the deviation
in the schedule is found. From the collected data the reasons for the delay is examined.
This graph is based on the various projects vs. durations. Each project is compared with
the scheduled completion time and actual completion time. Project 6 is the most effective
in completion.
22
Fig.2 Schedule Completion time Vs Actual Completion time for commercial project
1 2 3 4 5 6 7 8 9 10
PROJECT
1 2 3 4 5 6 7 8 9 10
PROJECT
The above graph is based on the various projects vs. durations. Each project is compared
with the scheduled completion time and actual completion time. Project 5 is the most
effective in completion
23
4.5.3 INDUSTRIAL PROJECT
Fig.4 Schedule Complete time Vs Actual Complete time for industrial project
1 2 3 4 5 6 7 8 9 10
PROJECT
This graph is based on the various projects vs. durations. Each project is compared with
the scheduled completion time and actual completion time. Project 6 is the most effective
in completion.
Micro analysis is done on data collected from various projects, this is in depth
analysis on the data collected, each & every parameters are analysed in all aspects taken
into consideration, such as type of materials used for construction, the distance of
materials transported, timely delivery of the material, kind of labours, engineers
employed company, all staff experience has been analysed, an experienced man in
respective field will be helpful in increasing efficiency of work, then location of site from
the material resource, proper timely delivery is important for the continuous work,
environmental condition prevailing in the site area are examined, an rainy season
24
basically affects all sort of work progress, climate condition should be considered as
important parameter while planning a project. Financial status, credit facility also
analysed. Equipment used for various kinds of work are analysed, different kind of work
requires different types of equipment, proper and selective equipment usage helps us to
concentrate on progress of work.
25
This table displays the projects that affected by late material delivery
TOTAL CONTRIBUTION
10%
MATERIAL
20%
MACHINERY
50%
MANPOWER
OTHER FACTORS
20%
Based on the findings in the commercial projects, it is observed that the contribution
percentage of each delay. The delay percentage are determined as follows, Materials-
50%, Machinery-20%, Manpower-20% and other factors-10%. Contribution
26
delay for project 1 is calculated by ((71/221) *100) = 32%. Likewise it is calculated for
the delays and the maximum is taken into account.
Factors Total
Materials 3
Machinery 1
Manpower 2
Other 4
27
Fig.6 Contribution % of delay due to resources in residential project
TOTAL CONTRIBUTION
30% MATERIAL
40%
MACHINERY
MANPOWER
OTHER FACTORS
10%
20%
28
Table-4.10 Delay occurrence due to manpower
Project Delay Material Machinery Manpower Other Max
Delay
Max Max Max Max Max Max Max Max
out out out out
of of of of
100 100 100 100
1 168 73 43 --- --- 41 24 54 32 Material
2 161 84 52 77 48 --- --- --- --- Material
3 135 --- --- 46 34 33 24 56 41 Other
4 142 81 57 --- --- 61 43 --- --- Material
5 119 --- --- 53 44 47 39 19 16 Machinery
6 168 87 52 --- --- 35 20 46 27 Material
7 161 91 56 --- --- 70 43 --- --- Material
8 90 --- --- 43 47 --- --- 47 52 Other
9 149 71 47 78 52 --- --- --- --- Machinery
10 140 73 52 --- --- --- --- 67 48 Material
Factors Total
Materials 6
Machinery 2
Manpower 0
Other 2
29
Fig .7 Contribution % of delay due to resources in industrial project
TOTAL CONTRIBUTION
20%
MATERIAL
0%
MACHINERY
MANPOWER
20% 60%
OTHER FACTORS
Based on the findings in the Industrial projects, it is observed that the contribution
percentage of each delay. The delay percentage are determined as follows, Materials-
60%, Machinery-20%, Manpower-0% and other factors-20%.
Based on the analysis, the major factor that affects the project is delay in supply of
materials.
30
CHAPTER 5
It is clear that the reasons for maximum delay in above projects are due to material
supply. Based on the comparison of those three projects material goes major. Minimizing
delay in construction due to material supply would support the whole construction
industry and the development process in. Adding to that the efforts, energy, human
resources consumed in extra time in terms of delay at these construction projects.
DELAY COMPARISION
COMMERCIAL PHARMA INDUSTRIAL
INDUSTRIAL
7
COMMERCIAL
PHARMA
5
PHARMA
4
COMMERCIAL
COMMERCIAL
INDUSTRIAL
INDUSTRIAL
PHARMA
3
COMMERCIAL
PHARMA
2
INDUSTRIAL
0
MATERIAL MACHINERY MANPOWER OTHER
31
contributes to efficiency of project. Following Technique named, Just-In-Time, will
help us to be aware of the availability of the resources for the project. Hence, this
technique could be well suited for completion of project in scheduled time.
E-Procurement technology helps of supplier to help the stock of material needed of the
project
32
conducted for different countries with respect to E- procurement in construction industry
base on country wise challenges but no comprehensive study has done.
5.2 E PROCUREMENT
Due to globalization and the emergence of the Internet, the accessible market has
grown, thus leading to unprecedented opportunities for sellers and buyers alike.
Managing the purchasing process by traditional means can be very inefficient and
interminable due to the excessive complexity. The use of electronic media in
procurement activities can be conducive and thus lead to a significant cost and time
reduction. In most common definitions, e-procurement is the streamlining of the
procurement process by eliminating paperbased documents and rather conducting parts
or all of the purchasing process via web-based communication systems. Nevertheless, the
exact definition of e-procurement is still being discussed. For some authors, e-mail
ordering is also part of e-procurement, others draw the line at ordering via online shops
and some only talk about e-procurement if ordering software either in combination with
e-mail or electronic data interchange (EDI) is used for the procurement process. Tatsis et
al. For example, define e-procurement as the integration, management, automation,
optimization and enablement of an organizations procurement process, using electronic
tools and technologies, and web-based applications.
The e-Procurement scenario focuses the envisioning efforts mainly on two of these
tasks:
1. Selection of suppliers.
34
5.5 RECOMMENDATION
These delays are badly affecting the large construction industry and it is needed to
find a solution for countering the delays. The solution to avoid and counter delays is to
avoid and lessen the causes related with delays, and in result there will be lesser effects of
delays on large construction industry.
It is suggested to deal with the causes and find a solution so that these causes not
happen or happen very less. The financial problems should be avoided, by making the
payments on time. The client should make timely payments to the contractor and
contractor should make the timely payments to the subcontractors, suppliers and labor. It
is suggested that the time and cost estimation of the project should be accurate. The
material should not face the shortage situation and the materials quality should be
checked properly so that less errors and problems happen.
The subcontractors should complete their work on time and the suppliers should
supply the materials on time. The site should be managed properly and there should be
proper equipment for the construction. The new technology and techniques should be
preferred and there should be skilled workers and labour working on the construction
project. All changes should be done before the start of construction, because change
orders and design changes during the construction should be avoided. The site conditions
should be studied in detail before the start of construction and there should be
consideration about the disaster, geographical and soil conditions. It is suggested that
during the construction stage, the organizational changes and regulatory changes should
be avoided or so they should not affect the progress of construction. The effects should be
lessened by dealing with causes leading to the effects.
Time overrun and Cost overrun are most common effects, which can be solved or
lessened by dealing with the causes leading to time overruns and cost overruns. If the
construction project is started, then it should be completed and the case of abandonment
should not be considered. The disputes, negotiations and court cases should be solved on
35
time and it is preferred that they should not happen and if they happen then the timely
solution should be done. By studying the relationship between effects and causes, we can
counter the delays by dealing with causes leading to effects.
The literature reviewed and discussed above, which is primarily focused on the
scope of Procurement in Construction Projects, scope of application of eProcurement in
various industrial sectors, identifies a number of potential factors that might affect the
adoption of e-procurement within the Construction Industry.
However, it has become apparent from this review, that there are a number of
significant gaps in the current literature in relation to the uptake and adoption of
eProcurement. More specifically, the following important gaps have been identified:
36
Against this backdrop, a study was initiated to investigate the factors affecting the
uptake and adoption of e-procurement among the Construction Material buyers and
Suppliers in Kuwait. Whilst this study explicitly builds upon the factors identified in prior
studies, it was envisaged that it would provide a far deeper and richer data set, upon
which to draw conclusions.
37
CHAPTER 6
CONCLUSION
6.1. GENERAL
The projects failures can be witnessed. As a rule, 12 to 15 percent projects are well
scheduled. However, about 20 to 25 percent projects are planned with the available
resources. These projects may complete in time but always there is an uncertainty to its
completion time and cost. About 50 to 60 percent projects lack proper planning. It might
take much more time than the scheduled time for completion. From the analysis made, it
is clear that more than 47 percent of the delay is shared by materials. A control over the
procurement and carrying of materials will definitely reduce the total project cost. From
the literature there is no such system so far developed. Hence a model has been proposed
to optimize the material purchase and storage, which would beget support in completion
of project in time.
38
6.2 FUTURE RESEARCH
39
REFERENCES
Jesper Kranker Larsen, (2016) "Identifying the key process factors affecting
project performance", Engineering, Construction and Architectural Management,
Vol. 23 Issue: 5, pp.657-673, doi: 10.1108/ECAM-08-2015-0123
Greeshma B Suresh and Dr. S. Kanchana (2015) A study on quantification of
delay factors in construction industry (Kerala region) International journal on
engineering technology and sciences, vol. 2, pp. 96-103.
P .M. Pethkar, B.V.Birajdar Literature Review On Causes Of Delay In Building
Construction Projects Journal of Information, Knowledge and Research in civil
Engineering, 2015, ISSN:0975 - 6744 l Volume3
Seyed Ali Mousavi Dehmourdi (2014) Optimization Of Construction Cost
Applying Advanced Techniques International Journal Of Structural & Civil
Engineering Research.
Barbole A.N., Y. D. Nalwade, S. D. Parakh (June. 2013) Impact Of Cost Control
And Cost Reduction Techniques On Manufacturing Sector Indian Streams
Research Journal Volume 3.
Ibrahim Mahamid, AmundBruland, and Nabil Dmaidi (2012) Causes of Delay in
Road Construction Projects, Journal of Construction Engineering and
Management, Vol. 28.
A.S. Ali, S.N. Kamaruzzaman, 2010: Cost performance for building construction
projects in klang valley. Journal of Building Performance, vol 1, issue1.
Van Truong Luu a, (2007) Identified nine key performance indicators to measure
the project management performance as a benchmarking. International Journal of
Project Management, Vol. 27 Iss 1
Assaf, S.A., and Al-Hejji: Causes of delay in large construction projects,
International Journal of Project Management, Vol. 24 No.4, 2006;
40
Ala-Risku, T & Krkkinen, M 2006, 'Material delivery problems in construction
projects: A possible solution' International Journal of Production Economics, vol
104, no. 1, pp. 19-29.
Nirmal Kumar Acharya, Young Dai Lee, Soo Yong Kim and Jong Chool Lee,
Analysis of Construction Delay Factor: A Korean Perspective, Proceeding of the
7th Asia Pacific Industrial Engineering and management Systems conference, 17-
20 December (2006), Bangkok, Thailand
Daisy X. M., Zheng, S., Thomas N.g., & Mohan M. Kumaraswamy. (2005).
Applying Pareto Ranking and Niche Formation to Genetic Algorithm-Based
Multiobjective TimeCost. Optimization. Journal of Construction Engineering and
Management
C. Subramaniam and M.J. Shaw, Exploring the role of process and
organizational factors in B2B e-commerce impact: An economic perspective of
buyer-side B2B system, in: Proceedings of the 6th INFORMS Conference on
Information Systems
Aibinu, A.A. & Jagboro, G.O., 2002. The effects of construction delays on project
delivery in Nigerian construction industry. International Journal of Project
Management, Vol.20
Saleh Al Hadi Tumi, Abdelnaser Omran, Abdul Hamid Kadir Pakir( 2009):
Causes Of Delay In Construction Industry In Libya presented in The International
Conference on Economics and Administration, Faculty of Administration and
Business, University of Bucharest, Romania, ASCE
Murali Sambasivan, Yau Wen Soon. "Causes and effects of delays in Malaysian
construction industry." International Journal of Project Management, (2007)
Prakash Rao, B. and Joseph Camron Culas Causes of Delays in Construction
Projects- A Case Study International Journal of Current Research, 2014, Volume
-06
41
Abd El- Razek, M.E, Bassioni, H.A and Mobarak, A.M (2008) Causes of Delay
in Building Construction Projects in Egypt, Journal of Construction Engineering
and Management, Vol. 134
AjibadeAyodejiAibinu, and Henry AgboolaOdeyinka (2006) Construction
Delays and Their Causative Factors in Nigeria, Journal of Construction
Engineering and Management, Vol. 132
Samad M E Sepasgozar, Mohamad Ahmadzade Razkenari, Khalegh Barati. The
Importance of New Technology for Delay Mitigation in Construction
Projects. American Journal of Civil Engineering and Architecture. 2015
Enshassi, A., J.Al-Najjar and M.Kumaraswamy, 2009. Delays and cost overruns in
the construction projects in the Gaza Strip. J. Financial management. Property
Construction.
Kasimu, M.A, 2012: significant factors that causes cost overruns in building
construction projects in Nigeria. J. contemporary research in business vol 3, no.11.
P.A.Koushiki*, K. AL- Rashid and N.Kartam, Delays and cost increases in the
construction of private residential projects in Kuwait. Construction management
and economics (march 2005)
Critchlow Julian, Farr Alastair, Briggs Steve, Hammond John, Pickavance Keith,
Lavers Anthony: The Great Analysis Debate, Society of Construction Law in
association with the Centre of Construction Law&Management, Kings College
London, 2005
Abdullah, A. A., Mukmin, M. N. & Samad, Z. A. , 2011. Application of project
management methods in the construction of bungalow house project: A case study
in Kuala Terengganu, Malaysia. International Journal of Economics and
Management Sciences, Vol.1, no.2,
Sambasivan M., Soon Y. W. (2006), Causes and Effect of Delays in Malaysian
Construction Industry, International Journal of Project Management, 25, 517-526.
42
43