Sunteți pe pagina 1din 55

VOLUME A: BACKGROUND AND NEED

A4 Project Description: Runway Layout

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-123
FOR PUBLIC COMMENT
VOLUME A: BACKGROUND AND NEED

A4 Project Description: Runway Layout

CONTENTS 4.8 Subsurface and


Geotechnical Conditions 141
Part 1 Permanent Works 126 4.8.1 Geotechnical Investigations 141
4.1 Existing Development 128 4.8.2 Ground Conditions 141
4.1.1 Existing Infrastructure on Airport 128 4.8.3 Subsurface Channels 142
4.8.4 Engineering Design Considerations142
4.2 Description of the
New Parallel Runway 128 4.8.5 Construction Timing 143
4.3 Site Planning 128 4.8.6 Adopted Geotechnical Design 143
4.3.1 Introduction 128 4.9 Airport Drainage 144
4.3.2 New Parallel Runway 4.9.1 Major Tidal Channels 144
Design Standards 131 4.9.2 Secondary Channels 147
4.4 Preliminary Design Process 131 4.9.3 Local Non-Tidal Channels 149
4.5 Existing Airport Conditions 132 4.9.4 Detention Storage and
Vegetated Buffer 149
4.5.1 Site History 132
4.9.5 Hydraulic Structures 150
4.5.2 Environmental Condition 132
4.9.6 Water Quality During Operations 150
4.6 Design Requirements 133
4.10 Dryandra Road Tunnel 151
4.6.1 Runway Location 133
4.10.1 Existing Dryandra Road 151
4.6.2 Design Aircraft and Trafc 133
4.10.2 Dryandra Road Alignment 151
4.6.3 Geometric Design 133
4.10.3 Future Land Use and Demand 151
4.6.4 Runway Length 133
4.10.4 Engineering Design 152
4.6.5 Runway Width 134
4.6.6 Taxiways 134 4.11 Perimeter Roads 153
4.6.7 Rapid Exit Taxiways 136 4.12 Security Fencing 153
4.6.8 Link Taxiway 136 4.13 Airport Lighting 154
4.6.9 Existing 14/32 Runway 136 4.13.1 Approach Lighting 154
4.6.10 Converting 14/32 Runway into 4.13.2 Approach Lighting Structure 154
a Taxiway 136
4.13.3 Ground Lighting System 154
4.6.11 Construction Staging 137
4.13.4 Construction Staging 155
4.6.12 Aviation Operations 137
4.14 Seawall 155
4.6.13 Staged Development of Runway
and Taxiway System 137 4.14.1 Existing Conditions 155
4.14.2 Proposed Seawall Alignment and
4.7 Aireld Pavements 138
Construction 155
4.7.1 Existing Runway and
Taxiway Pavements 138 4.15 Rescue and Fire Fighting Services 155
4.7.2 Design Considerations 138 4.16 Services 156
4.7.3 Aircraft and Operational 4.16.1 Introduction 156
Considerations 138 4.16.2 Existing Services 156
4.7.4 Geotechnical Considerations 139 4.16.3 New Services 157
4.7.5 Pavement Types 139
4.17 Landscaping 157
4.7.6 Adopted Pavement Thicknesses 139
4.17.1 Existing landscape features 157

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-124 FOR PUBLIC COMMENT
VOLUME A: BACKGROUND AND NEED

A4 Project Description: Runway Layout

Part 2 Temporary Works 158 FIGURES AND TABLES


4.18 Temporary Works Introduction 158
Figures
4.19 Dredge Selection 158
Figure 4.1: Existing Airport Development
4.19.1 Introduction 158
Figure 4.3: Proposed New Parallel Runway
4.19.2 Previous Dredging/Reclamation at Infrastructure
Brisbane Airport 159
Figure 4.6: General Layout Plan
4.19.3 Types of Dredging Work Methods 159
4.19.4 Design Dredge 160 Figure 4.7: Runway and Taxiway Pavement
Layout
4.20 Dredging Location and Dredge
Figure 4.9a: Drainage Layout Plan
Footprint Selection 161
4.20.1 Background 161 Figure 4.9b: Typical Drainage Channel Details

4.20.2 Project Requirements Figure 4.20a: Middle Banks Investigation Area


and Investigations 161 Figure 4.20b: Location of Dredge Footprint at
4.20.3 Proposed Dredge Footprint 162 Middle Banks (Source: Arup)

4.21 Mooring Locations and Pipeline Figure 4.21: Dredge Mooring Location and
Route Options 164 Pipeline Routes
4.21.1 General 164 Figure 4.22: Dredge Mooring Site Plan
4.21.2 Investigation into Mooring Sites 164 Figure 4.23: Luggage Point Wastewater Treatment
4.21.3 Mooring Site Assessment 166 Plant Outfall Channel Crossing

4.21.4 Preferred Option 169 Figure 4.24: Sediment Pond Location

4.22. Dredge Mooring Design 169


4.22.1 Dredge Operations 169 Tables
4.22.2 Mooring Layout and Operation 171 Table 4.19: Physical Characteristics of the
4.23 Pipeline Design and Dredge Fleet
Temporary Structures 172
4.23.1 Introduction 172
4.23.2 Pipeline through Luggage Point
Wastewater Treatment Plant 172
4.23.3 Airport Drain Crossing 173
4.23.4 Airport Runway and
Taxiway Crossing 173
4.24 Sediment Ponds 175

NEW PARALLEL RUNWAY DRAFT EIS/MDP


FOR PUBLIC COMMENT A4-125
VOLUME A: BACKGROUND AND NEED

A4 Project Description: Runway Layout

Part 1 Permanent Works

The following table provides a summary of the permanent works associated with the New Parallel Runway (NPR)
project and identies those aspects of the project that are relevant to the assessment of the Master Development
Plan (MDP) under section 91 (1) of the Airports Act.

Design Element Details Further Information Relevant


on Impact to the MDP
Assessment/ Yes/No
Mitigation
Clearing of approximately 361 ha Vegetation including plantation Volume B: Airport Yes
of vegetation. casuarina and mangroves will be and Surrounds
removed for the NPR project. (Refer Chapter B5 of
Draft EIS/MDP)
Reclaiming 15 Mm3 of sand from Sand, proposed to be sourced from Volume C: Yes
Middle Banks in Moreton Bay for Middle Banks in Moreton Bay, will be Middle Banks, relevant to
site surcharging and lling. used to surcharge and ll the NPR site. Moreton Bay consideration
of section
91(1) (h)
Reconstructing the existing A seawall will replace an existing Volume B: Yes
seawall along the Moreton Bay/ poorly constructed seawall on the Airport and Surrounds
Airport boundary. foreshore of Moreton Bay. The seawall
will provide protection to the NPR from
storm tide events.
Constructing the NPR and The runway will facilitate the arrival Volume A: Background Yes
associated taxiways. and departure of aircraft. Taxiways and Need (Refer
will be used to enable aircraft to Chapter A5 of
manoeuvre between the runway and Draft EIS/MDP)
terminal facilities.
Widening and strengthening of The existing 14/32 runway will be Volume A: Background Yes
the 14/32 runway pavement, and converted into a taxiway that links the and Need (Refer
enhancements to the existing northern end of the NPR system to Chapter A5 of
runway system. the northern end of the existing major Draft EIS/MDP)
runway. Ahead of the opening of the
NPR, the upgraded 14/32 will be used
as a runway.
Constructing a new dual parallel The full-length dual parallel taxiway Volume A: Background Yes
taxiway (adjacent to the NPR). system has been designed to service and Need (Refer
the expected Airport demand. Chapter A5 of
Construction of this taxiway system Draft EIS/MDP)
will be staged as the full system is
not required in the short to medium
term. Its future construction will be
dependent upon Airport demand and
future developments within the aireld.
Constructing a link taxiway A link taxiway will provide an efcient Volume A: Background Yes
from the NPR to the main connection between the NPR and and Need (Refer
existing runway. existing runway. It will be a dual Chapter A5 of
link taxiway to allow for future Draft EIS/MDP)
connections into an expanded
domestic terminal apron. Construction
of the parallel link taxiway system will
be staged as the full system is not
required in the short to medium term.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-126 FOR PUBLIC COMMENT
Design Element Details Further Information Relevant
on Impact to the MDP
Assessment/ Yes/No
Mitigation
Establishing new aireld lighting Approach lighting is provided at Volume A: Background Yes
including approach lighting. each end of the runway centreline and Need (Refer
to enable use during periods of Chapter A5 of
low visibility. Because the NPR is Draft EIS/MDP)
close to the Moreton Bay boundary,
approach lighting for planes landing
over Moreton Bay is proposed to
extend approximately 660 m from
the Moreton Bay shoreline. It will be
supported by piles.
Constructing a new re station. A re station within three minutes Volume A: Yes
response time of the NPR is required Background and Need
under CASA regulations. (Refer Chapter A5 of
Draft EIS/MDP)
Constructing a road tunnel The construction of the NPR involves Volume A: Background Yes
along Dryandra Road under the the construction of a major link taxiway and Need (Refer
link taxiway. between the existing runway and the Chapter A5 of
new runway. As an area of the NPR site Draft EIS/MDP)
is allocated for future aviation facilities
including the General Aviation Terminal
and Royal Flying Doctor Service, there
is a need to provide a vehicular link via a
tunnel under the link taxiway.
Constructing new perimeter To enable regular maintenance of Volume A: Background Yes
roads around the aireld. the aireld, security inspections and and Need (Refer
response to emergencies. Chapter A5 of
Draft EIS/MDP)
Constructing new permanent The Kedron Book Drain and Volume A: Background Yes
drainage channels. Serpentine Inlet Drain are major tidal and Need (Refer
channels that will be constructed to Chapter A5 of
provide ood immunity and to maintain Draft EIS/MDP)
existing ood immunity to existing
infrastructure.
Constructing new Substantial drainage infrastructure Volume A: Background Yes
aireld drainage. will be constructed to provide and Need (Refer
ooding immunity to new and existing Chapter A5 of
infrastructure. Draft EIS/MDP)
Installing new security fencing. To maintain safe, reliable Airport Volume A: Background Yes
operations and dening a boundary and Need (Refer
between airside and publicly Chapter A5 of
accessible landside areas. Draft EIS/MDP)
Relocating power and Relocation and installation of water, Volume A: Background Yes
utility services. electrical and telecommunication and Need (Refer
services will be required for the NPR. Chapter A5 of
Draft EIS/MDP)
Rehabilitating the site including The Kedron Brook Drain and Volume B: Airport Yes
the use of mangroves at Serpentine Inlet Drain include and Surrounds
selected locations along 10 m wide benches suitable for (Refer Chapter B5 of
drainage channels. the establishment of mangrove Draft EIS/MDP)
communities. The mangrove
benches assist in stabilisation of
the tidal channels and enhance
environmental amenity.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


FOR PUBLIC COMMENT A4-127
4.1 Existing Development Reconstructing the existing seawall along the
Moreton Bay/Airport boundary;
Constructing the NPR and associated taxiways;
4.1.1 Existing Infrastructure on Airport
Widening and strengthening of the 14/32 runway
The existing development on the Airport site pavement for its conversion to a taxiway for
includes both aviation related development and Code F aircraft (large wide-body);
commercial development which benets from close
proximity to Airport operations. Constructing a new dual parallel taxiway
(adjacent to the NPR);
The existing aviation-related development at Brisbane
Airport is shown on Figure 4.1. The signicant Constructing a link taxiway from the NPR to the
infrastructure includes: main existing runway;

01/19 runway (main runway); Constructing rapid exit taxiways from the NPR to
the parallel taxiway;
14/32 runway (cross runway);
Establishing new aireld lighting including
International Terminal building and apron; approach lighting;
Domestic Terminal building and apron; Constructing a new re station;
General Aviation area and apron; Constructing a road tunnel along Dryandra Road
Control tower and related facilities; under the link taxiway;

Catering facilities; Constructing new perimeter roads around


the aireld;
Cargo handling facilities;
Constructing new permanent drainage channel
Aircraft maintenance facilities;
upstream of the runway;
Services and utilities
Augmenting the existing permanent
Car parking facilities; drainage channel at Serpentine Inlet with
Local road network; and an additional drain;

Airtrain link (Rail link from the Airport to the Constructing new aireld drainage;
Queensland Rail network). Installing new security fencing;
The NPR is part of Brisbane Airport Corporations Clearing and lling for the Future Aviation
(BAC) $1.5B investment in infrastructure that includes Facilities Area (FAFA); and
additional roads, aprons and terminal expansions.
Relocating power and utility services.
These projects will interact with the runway project
either through design or construction. Chapter A1 The construction methodology for each of these
described the other signicant projects that are elements is further described in Chapter A5
occurring at Brisbane Airport. Runway Construction.

4.2 Description of the 4.3 Site Planning


New Parallel Runway
The proposed NPR consists of the following major 4.3.1 Introduction
elements:
The location of the NPR is shown in the Brisbane
Dredging 15 million cubic metres (Mm3) of sand Airport Master Plan (2003) and the current proposed
from Middle Banks in Moreton Bay; location is consistent with the Master Plan (2003)
Surcharging the NPR site with the dredged sand; in that it will be offset 2,000 m to the west and
staggered 1,350 m to the north from the existing

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-128
FOR PUBLIC COMMENT
Figure 4.1: Existing Airport Development.

N
0 200 400 600 800 1000m

NEW PARALLEL RUNWAY DRAFT EIS/MDP NEW PARALLEL RUNWAY DRAFT EIS/MDP A4-129
FOR PUBLIC COMMENT FOR PUBLIC COMMENT
Figure 4.3: Proposed New Parallel Runway Infrastructure.

N
0 200 400 600 800 1000m

A4-130 NEW PARALLEL RUNWAY DRAFT EIS/MDP NEW PARALLEL RUNWAY DRAFT EIS/MDP
FOR PUBLIC COMMENT FOR PUBLIC COMMENT
01/19 runway (refer Figure 4.3). The proposed The design was undertaken in four distinct phases:
conguration of the rapid exit taxiways was
Scoping;
rationalised during the design process in recognition
of the anticipated operating modes. Investigations and modelling;

4.3.2 New Parallel Runway Option assessment; and


Design Standards
Preliminary design.
The International Standards and recommended
The scoping phase focused on reviewing
practices are formalised in Annex 14 of the
all relevant documentation regarding Airport
Convention on International Civil Aviation, adopted
infrastructure and environmental characteristics of
by the International Civil Aviation Organisation
the Airport site. This information was held by BAC
(ICAO). The national standards and advisory
at the time of preliminary design (before detailed
publications are administered in Australia by the
ecological and other environmental studies were
Civil Aviation Safety Authority (CASA) under the Civil
undertaken for the Draft EIS/MDP phase of work).
Aviation Act 1988, the Civil Aviation Regulation 1988
The preliminary design built on existing work carried
(CAR 1988) and the Civil Aviation Safety Regulations
out in support of the BAC Master Plan (2003) and
1998 (CASR 1998).
project denition phase.
The CASR 1998 is divided into a number of
The eld investigations included commissioning
sections. This is known as the Manual of Standards
geotechnical, acid sulfate soil and eld survey
(MOS) and species the requirements for safe air
investigations to support the development of the
navigation. The key sections of the MOS are:
design. Flood modelling of Kedron Brook and the
MOS Part 139 The requirements for existing drainage on Airport was performed, and
aerodromes used in air transport operations are analysis of the geotechnical eld data was undertaken.
prescribed in the CASA policy manual;
Design options were investigated to understand
MOS Part 172 The requirements and standards and where possible, quantify the impacts of some
for compliance by an air trafc service (ATS) design elements on the environment, Airport
provider, including the facilities and equipment security, aviation operations and constructability.
required; and Existing information on the environmental condition
of the Airport site was fundamental in informing
Advisory Circulars (ACs) - intended to provide the preliminary design of the NPR. A number of
recommendations and guidance to illustrate a design iterations were assessed to understand the
means of complying with the Regulations. relative impact of some key components of the
The planning and design considerations for the preliminary design and develop a preferred design
geometry of the new runway are predominantly the to optimise whole-of-project outcomes, balancing
requirements and recommendations of ICAO and aviation operations, constructability, security and
Part 139 CASA MOS. environmental performance.

Preliminary design and documentation of the project


4.4 Preliminary Design Process along with preparation of a construction cost estimate
followed the adoption of preferred design options.

The preliminary design of the runway was The works for the Draft EIS/MDP commission
undertaken (initially pre-EIS/MDP works) to commenced during the development of the
provide the basis for assessment of impacts in the preliminary design, allowing information from the
Draft EIS/MDP and to establish the estimated cost Draft EIS/MDP investigations to be used to inform
for project construction. and improve the preliminary design of the project.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-131
FOR PUBLIC COMMENT
4.5 Existing Airport Conditions 4.5.2 Environmental Condition

The site of the NPR is characterised by topography


4.5.1 Site History with little surface relief and generally low ground
elevation. There are a number of remnant creeks
Construction of the runway and domestic terminal, and constructed earth channels on the site that are
in its current location, commenced in May 1980 tidally inuenced. Constructed tidal channels on the
and was completed in March 1988. A program site maintain connectivity of remnant tidal channels
of dredging and reclamation was undertaken as and provide local drainage connections for existing
part of the initial construction works to provide a Airport infrastructure.
foundation upon which the new Airport could be
constructed. Approximately 16 Mm3 of sand was Much of the NPR site maintains existing vegetation.
dredged from Middle Banks, in Moreton Bay to Existing vegetation communities located within the
complete the project. In 1990, a second dredging NPR site include:
and reclamation project of approximately 4 Mm3 of
Casuarina plantation;
sand, again from Middle Banks, was undertaken for
construction of the International Terminal building Freshwater wetland and sedge;
and apron.
Open grasslands;
Both of these projects required signicant
modication to the natural environment including Mangroves;
tidal creek diversions, mangrove clearing and broad Salt marsh/mudats; and
lling of the generally low lying site. As described
in Chapter B5 Terrestrial and Marine Ecology, large Amenity landscaping.
numbers of casuarina were planted to stabilise
Casuarina plantation is the dominant vegetation
the cleared surfaces and discourage colonisation
community located within the NPR site, and the
by birds and other fauna. While most vegetation
plantation has low conservation value. The open
introduced onto the site are native species, some
grassland and associated freshwater wetland and
exotic species were used for landscaping purposes.
sedge communities located adjacent Kedron Brook
Floodway provide habitat for the Lewins Rail, listed
rare under the Nature Conservation (Wildlife)
Regulation 1994.

The Airport Environment Strategy (2004)


identies three remnant mangrove areas that are
environmentally signicant, located at:

The mouth and banks of Jacksons Creek;

The mouth of old Serpentine Creek Inlet; and

The abutment with the Pinkenba residential


community.

The existing environmental condition of the NPR


site was fundamental in informing the design of
the runway and associated infrastructure, and
guided the selection and design of a number of key
infrastructure components.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-132
FOR PUBLIC COMMENT
4.6 Design Requirements The trafc forecasts considered in the design of
the aireld are consistent with those used in the
assessment of noise and other impacts. The trafc
4.6.1 Runway Location forecasts take into consideration the expected
changes in the aircraft arrival and departure frequency
The location of the proposed parallel runway at
and the changes in the aircraft eet expected
Brisbane Airport is to the west of the existing
during the life of the project (refer Chapter A2). The
01/19 runway (refer Figure 4.3). The new and
preliminary design used the aircraft eet and forecasts
existing runways will be separated by a distance of
in a simulation model to identify the capacity of the
2,000 m, placing the proposed runway as close as
runway and taxiway system and verify the location of
practicable to the western boundary of the Airport
taxiways and connections.
and the Kedron Brook Floodway. The design of
the new runway optimises the separation distance 4.6.3 Geometric Design
available between the new and existing runways,
providing maximum exibility in the design of future The geometric design of the proposed aireld facilities
Airport developments between the runways, is in accordance with the prescribed requirements
such as additional terminal development of the CASA MOS. These standards govern the
(refer Chapter A3). aireld characteristics such as the dimensions and
shape of runway, taxiways and related facilities. The
The proposed parallel runway is to be located MOS refers to the aerodrome reference code (4F) in
1,350 m further north than the existing 01/19 runway, prescribing the aireld dimensions that are necessary
introducing a stagger between the new and existing to safely move the required category of aircraft
01/19 runway and placing the NPR as close as around the aireld. Below is a description of the main
practicable to the Moreton Bay shoreline. The location geometric design elements that contribute to the
of the NPR minimises residential aircraft noise and proposed aireld design.
provides increased safety by introducing vertical
separation for arriving and departing aircraft on each 4.6.4 Runway Length
runway.
The active length of the runway is determined by
4.6.2 Design Aircraft and Trafc reviewing the operational requirements of the aircraft
for which the runway is intended. The existing
ICAO has an international code system to specify 01/19 runway has an operational length of 3,560 m
the standards for individual Airport facilities, suitable and the proposed runway is to adopt the same
for use by aircraft with a range of performances length. The 3,600 m runway length is capable of
and sizes. The proposed runway and associated accommodating the requirements of all current
infrastructure has been designed based on an aircraft and provides exibility in accepting different
Aerodrome Reference Code 4F. This Code has aircraft in the future.
been chosen as it is suitable to accommodate the
next generation of large aircraft, as represented At each runway end, a safety zone is required.
by the Airbus A380 aircraft type, as well as all Known as the Runway End Safety Area (RESA), this
the current aircraft types. To ensure exibility of is an additional area over which aircraft could travel in
the proposed design, a theoretical aircraft, longer an emergency. It is not included in the assessment
than any currently proposed was developed as of runway length. This area must be provided at the
the design aircraft for the purposes of plotting end of the runway strip to protect the aircraft in the
the aircraft wheel tracks as it moves on the event of undershooting or overrunning the runway.
taxiway or runway system. The design aircraft Current CASA standards indicate that the RESA
could be described as a stretched A380, in must be 90 m in length and free of xed objects,
acknowledgement that historically all commercial other than visual or navigational aids which will be
aircraft have been extended or elongated to designed to be of low mass and frangibly mounted
improve efciency. so that they break upon aircraft impact.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-133
FOR PUBLIC COMMENT
4.6.5 Runway Width The proposed taxiway layout (refer Figure 4.6)
provides:
The required width of the proposed runway is
determined in accordance with CASA standards for A dual parallel taxiway, parallel to the new
Aerodrome Reference Code 4F where a 60 m wide runway;
runway is prescribed.
A dual link taxiway, connecting the new runway
In addition to the runway width, runway shoulders with the existing runway;
are required. For a Code 4F runway, 7.5 m wide
Conversion of runway 14/32 into a link taxiway
shoulders are designed to be ush with the runway
that connects the northern ends of the new and
surface and equal in width on both sides. The
existing runways; and
shoulders are designed to be resistant to aeroplane
engine blast erosion through the use of a dense A rapid exit taxiway system connecting the
graded asphalt surface and are adequate to support runway and parallel taxiways.
an aeroplane running off the runway, without causing
structural damage to the aircraft. The geometry of the taxiway pavements is a function
of the design aircrafts wheel track dimensions and
The nal element which determines the overall width pavement edge clearance requirements. Within
required to operate the runway is the runway strip. the standards, a straight section of taxiway suitable
The runway strip width is 150 m, with the runway for Code 4F aircraft needs to be a minimum width
being centrally located within the runway strip. The of 25 m. In addition, the width of any section
runway strip is required to provide a safety zone for the of taxiway must be sufciently wide to provide a
aircraft and is designed to be free from all xed objects minimum clearance between the outer aircraft
other than visual aids (lights) for aircraft guidance. wheels and edge of the taxiway, of 4.5 m. This
Visual aids, where required, are designed to be of low criterion has determined the overall taxiway shape,
mass and frangibly mounted to minimise structural particularly on parts of the taxiway where aircraft are
damage to the aircraft if impacted. turning (refer section 4.6.2).
The runway strip is grassed or vegetated with low On curved sections of taxiway, and at junctions and
slopes away from the runway shoulders towards intersections with the runway or other taxiways,
the natural surface. Drainage channels are provided the taxiway width is increased to enable aircraft to
to ensure stormwater does not pond within the manoeuvre on the taxiway pavement. The widening
runway strip. is called a llet. To determine the shape and size
of the llets, aircraft tracks for each aircraft in the
4.6.6 Taxiways current eet and the theoretical design aircraft were
To enable the aircraft to manoeuvre between modelled on the proposed taxiway layout to ensure
the runway and terminal a network of taxiways the 4.5 m clearance will be maintained.
is required. The taxiway conguration needs to In addition to the taxiway pavement, taxiway
provide efcient aircraft movement around the shoulders are required on each side of the taxiway
aireld, minimising taxi distance and maximising pavement. The taxiway shoulders measure
exibility. There are many elements to the taxiway 17.5 m and are required either side of the taxiway
system, including parallel taxiway, rapid exit taxiways to accommodate Aerodrome Reference Code 4F
and other link taxiways all of which perform a aircraft. The shoulders are designed to be resistant
specic function. to aircraft engine blast erosion. Similar to the
runway strip, a taxiway strip is provided around each
taxiway. The taxiway strip will be grassed and free
of xed obstacles or obstructions.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-134
FOR PUBLIC COMMENT
Figure 4.6: General Layout Plan.

N
0 100 200 300 400 500m

NEW PARALLEL RUNWAY DRAFT EIS/MDP NEW PARALLEL RUNWAY DRAFT EIS/MDP A4-135
FOR PUBLIC COMMENT FOR PUBLIC COMMENT
4.6.7 Rapid Exit Taxiways currently service both international and domestic
aircraft movements:
Rapid Exit Taxiways (RET) increase overall runway
efciency by allowing arriving aircraft to exit the The main runway is 3,560 m long and 45 m wide
runway quickly. The geometry of the RET, typically and is sufcient for large, wide bodied aircraft
angled at 45 degrees to the runway, allows aircraft (01/19 runway); and
to exit the runway while travelling at greater speed,
The minor runway is 1,760 m long and 30 m
reducing the occupancy time on the runway.
wide and is suitable for a limited range of aircraft
Four RETs are included in the taxiway system of the (14/32 runway).
NPR project. Three are suitable for aircraft arriving
At present, aircraft operations on the minor runway
from the north (19R landing mode) and one suitable
(14/32) are restricted by its length and the strength
for aircraft arriving from the south (01L landing mode)
and condition of the existing runway pavement.
(refer Figure 4.6). These are located to take into
The operational restriction is dened in terms of
account the preferred operating mode of the new
an aircraft weight limit. The current aircraft weight
runway and different aircraft types in both wet and
restriction limits the 14/32 runway operation to small
dry conditions:
aircraft, with a maximum weight limit of 56 tonnes.
The rst RET (19R landing mode) is designed to
suit turboprops on a wet runway; 4.6.10 Converting 14/32 Runway into a
Taxiway
The second RET (19R landing mode) is designed
to suit domestic jets on a dry runway; Construction and operation of the new runway
requires the existing 14/32 runway to be converted
The third RET (19R landing mode) is designed into a Code F taxiway that links the northern end
to suit long haul wide body jets on a dry (19R) of the NPR system to the northern end
runway (which also coincides with wet runway (19L) of the existing major runway. Converting
requirements for domestic jet operations); and the existing 14/32 runway into a taxiway requires
pavement strengthening and changing the geometry
The fourth RET (01L landing mode) is designed
of the existing formation. The construction work
to suit long haul wide body jets on a dry runway
proposed includes:
and domestic jet operations on a wet runway.
Relocating services at the site;
4.6.8 Link Taxiway
Ground treatment at the northern end of the
To enable an efcient connection between the runway (including vacuum consolidation);
new runway and existing runway, a link taxiway
is proposed. The proposed link is a dual link Installation of drainage culverts beneath the
taxiway that will allow for future connections into an runway;
expanded domestic terminal apron. Incorporated
A protection structure for the dredge pipeline
into the design of the link taxiway is the allowance
beneath taxiway links Alpha and Bravo;
for a road tunnel which passes under the link
taxiway and provides access from the domestic Pavement construction and earthworks to the
terminal precinct and into the General Aviation area anks; and
and Future Aviation Facilities Area (FAFA). The
vertical alignment of the link taxiway accounts for Aerodrome ground lighting.
the tunnel beneath it with a slight vertical curve.
Constructing the required improvements requires
the closure of the 14/32 runway for up to
4.6.9 Existing 14/32 Runway
24 months, during which time all air trafc will be
The existing aireld comprises two runways and required to use the major runway (01/19).
connecting parallel taxiways. The two runways

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-136
FOR PUBLIC COMMENT
4.6.11 Construction Staging Additional runway length (3,600 m) is required
for long-haul international departures from the
Accepting that the 14/32 runway requires closure for NPR. Construction of the full 3,600 m runway to
a length of time to complete the construction works, accommodate long-haul international departures
the adopted construction staging is focused on is a long term development plan and may be
minimising the period of time that the 14/32 runway constructed following development of the future
is closed and ensuring that the closure is executed western apron and terminal facilities.
early in the project when trafc demand is lowest. In
addition, sufcient works will be undertaken to allow 4.6.13.2 Taxiways
the runway to be reopened and used as a runway
The nal design of the new runway system includes:
during the construction period for the NPR. Refer
Chapter A5 for details on the construction phasing. Full length, dual parallel taxiway system alongside
the runway to service the expected Airport
4.6.12 Aviation Operations demand; and
The aviation objective of the staged construction Dual link taxiway connecting the existing runway
is to provide opportunity for continued use of and new runway;
the 14/32 runway during the construction of the
parallel runway project and to minimise the length The full length dual parallel taxiway system is not
of time runway 14/32 is unavailable. Following the required in the short to medium term, and as such,
construction and reopening, the 14/32 runway will construction of it will be staged to provide the
be a Code 3C runway, allowing arrival and departure minimal taxiway infrastructure to service the runway.
of commercial jets up to Boeing 737-800 and Airbus Further stages of the taxiway construction will be
A-320-200 type aircraft. This will extend the current dependent on the increased Airport demand and
availability of the 14/32 runway for different aircraft future developments within the aireld.
and improve exibility for Airport operations.
The construction of a full dual link taxiway from
Following the commissioning and opening of the existing runway to the new runway will not be
the parallel runway, the 14/32 runway would be required in the short term and as such, it will not
decommissioned as a runway and opened as a be constructed as part of the initial construction.
Code F taxiway. The lighting system and navigational Further development of the domestic terminal
aids would be changed to reect the changing use. apron may provide the impetus for constructing
All arriving and departing aircraft would be directed to the duplication of the link taxiway. By providing
the existing or the NPR. only a single link taxiway initially, the design can
accommodate the existing Qantas Catering building
4.6.13 Staged Development of Runway and by constructing only the eastern taxiway link as
Taxiway System shown on Figure 4.6. The staged development will
delay relocating this facility until the dual link taxiway
4.6.13.1 Runway
is required.
The NPR is designed to have an ultimate length of
Air trafc control procedures specify standard taxiing
3,600 m, however initial development of the NPR
routes that avoid the use of common taxiway areas
involves construction of 3,000 m (refer Figure 4.6).
for opposite direction taxiing. These procedures
The preferred operating mode for the parallel have been allowed for within the staged taxiway
runway system will involve 01R departures (existing design. Each stage of taxiway construction has
main runway) and 19R arrivals (new parallel runway). been simulated to verify the operational performance
Under this operating mode, there will be no using a Total Airspace and Airport Modeller (TAAM)
operational restrictions for the current aircraft eet simulation model.
arriving on the NPR or for long haul departures from
the existing runway.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-137
FOR PUBLIC COMMENT
4.7 Aireld Pavements Based upon the successful operation of the existing
Airport with both exible and rigid pavements, the
new runway will incorporate similar pavements
Runways and taxiways require specically designed where appropriate. Based upon this experience,
pavements to cater for the loading from aircraft during a requirement for the design life for each pavement
landings, takeoff and taxiing. In general, aircraft was established:
are heaviest and require the most support from the
pavement during taxiing, immediately prior to takeoff. Flexible pavements 15 years between asphalt
Landing aircraft and aircraft taxiing to the terminal resurfacing; and
immediately after landing are considerably lighter than
Rigid pavements 40 years.
the corresponding departing aircraft, owing to the
reduced volume of fuel on board the aircraft.
4.7.2 Design Considerations
Each component of the taxiway infrastructure or the
A number of factors were taken into account in
runway must be designed with these operational
determining the preliminary design of the runway
considerations in mind including the type of aircraft,
and taxiway pavements including:
expected frequency of aircraft trafc and the
environmental considerations specic to the site. Aircraft eet, numbers and expected operations;
Typically, runway pavements at Australian airports and
are constructed using gravel pavements with
asphalt surfacing (exible pavements) while taxiways Geotechnical considerations.
are constructed using both concrete pavements
These factors have informed the design process
(rigid pavements) and exible pavements, depending
and inuenced the preliminary pavement selection.
upon the specic situation.
4.7.3 Aircraft and Operational
4.7.1 Existing Runway and Taxiway
Considerations
Pavements
The aircraft eet used in the preliminary design
The existing Brisbane Airport runway and taxiway
was estimated based upon the air trafc forecasts
pavements have performed to the satisfaction
developed for the project (refer Chapter A2). The
of BAC (both exible and rigid pavements).
critical aircraft within the forecast aircraft mix differ
The existing runway is constructed from exible
for each design element. The critical aircraft for the
pavement with asphalt surfacing while the majority
design of the runway and taxiway pavements is
of the existing parallel taxiway system is constructed
dependent upon the wheel loading of each aircraft,
from rigid pavements.
which is in turn dependent upon the number of wheels
After approximately 15 years of use, the existing (or bogeys) and the total weight of the aircraft.
runway pavement was resurfaced with asphalt,
The preliminary design of the NPR and taxiway
in line with the design intent. Resurfacing asphalt
pavements considered both the critical aircraft as
pavements is required from time to time to correct
well as the forecast aircraft eet mix and the forecast
irregularities in the pavement surface and replace
movements of each aircraft type within the eet
the existing asphalt that has weakened and
(refer Chapter A2 and section 4.6.2).
deteriorated due to exposure to the environment.
Since its resurfacing, the pavement has performed Aircraft undertake different manoeuvres on different
as expected. parts of the aireld and require different performance
from the pavement over which the aircraft is
The existing rigid pavements on the parallel taxiway
trafcking. Of specic interest in the preliminary
(servicing the existing main runway) are serviceable
design were the locations where aircraft are
and expected to last for a period of approximately
expected to stop and/or turn. Aircraft stopped or
40 years from the opening of the runway in 1988.
stopping and turning exert different loads on the

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-138
FOR PUBLIC COMMENT
pavement and generally, where these manoeuvres 4.7.5 Pavement Types
are expected, rigid pavements are required. Rigid
pavements offer a greater resistance to scufng and Based upon the above considerations, rigid
shearing loads typical of slow moving and turning pavements were adopted for the:
aircraft. Typically, the parallel taxiway system is Parallel taxiway;
subject to high loads, where aircraft can be stopped
for extended periods and can undertake large Runway ends;
numbers of turning manoeuvres.
Sections of the link taxiway; and
By contrast, rapid exit taxiways are areas where the Taxiway links between existing 01/19 and the
aircraft is travelling at relatively high speed, exiting the upgraded 14/32 runway.
runway immediately after landing. As such, these
taxiways can only be trafcked by aircraft travelling Flexible pavements were adopted for the:
with lower fuel loads, moving relatively quickly and
New Parallel Runway pavement;
are suited to exible pavement construction.
Rapid exit taxiways;
4.7.4 Geotechnical Considerations
Sections of the link taxiway; and
The natural ground material over most of the runway
site is characterised by weak, soft clay material that Upgraded 14/32 runway.
does not provide adequate stability or support in The pavement type layout is presented in
its unaltered state. Typically, mangrove mud/clay, Figure 4.7 showing all pavement types.
similar to those found on the runway site, have a
very low strength. To enhance the strength and 4.7.6 Adopted Pavement Thicknesses
suitability of the site, the existing surface requires
signicant ground treatment or consolidation prior The runway pavement design adopted 550 mm
to pavement construction (refer section A4.8 and thick gravel pavement with a 60 mm thick asphalt
Chapter B3). surfacing. In addition to the gravel pavement,
2 m of sand is required over the existing surface
Flexible pavements rely on gravel or granular materials to support the pavement materials.
materials being placed in layers over the existing
surface with a surfacing over the top layer. To The concrete taxiway design adopted 400 mm thick
provide sufcient strength, each layer must be Portland cement concrete over a minimum of 2 m of
stronger than the previous layer, with the top sand material.
layer comprising the hardest and strongest gravel
materials. The surfacing material in this case is
asphalt. As the in situ soils at Brisbane Airport are
weak, a signicant depth of granular material is
required beneath the pavement, for the pavement
to have sufcient strength. As with the existing
Brisbane runway, an estimated 2 m of sand material
is required between the in situ soils and the base of
the pavement materials to provide sufcient strength
to support the pavement.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-139
FOR PUBLIC COMMENT
Figure 4.7: Runway and Taxiway Pavement Layout.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-140
FOR PUBLIC COMMENT
4.8 Subsurface and Geotechnical continuously. These tests ranged in depth from 9 m
Conditions to over 32 m but were generally executed until the
probe encountered a hard surface that could not
be penetrated.
The new runway site is located in a low lying estuarine
environment between Kedron Brook Floodway and The results of these tests enable the depth of soft
the existing Airport development. The majority of the surface soils to be measured. The depth of the
site is unlled with the exception of an area that was surface soils and their strength and engineering
used as a dump for dredge spoil, extracted from the properties are critical in the design of ground
Kedron Brook oodway in the 1980s. treatment measures.

Although the site is considered mostly at, it is 4.8.2 Ground Conditions


heavily modied with a large casuarina plantation
established across the new runway site during The testing found that ground conditions across
the construction of the existing runway and the site were broadly similar to other locations in
terminal development. the general vicinity of the new runway site. A broad
summary of the ground conditions is:
4.8.1 Geotechnical Investigations
Vegetation and topsoil; over
As part of the preliminary design, geotechnical
A crust of surface soils approximately 1.0 m
investigations were undertaken to determine the
deep; over
engineering and geological characteristics of the
in situ soils so that these characteristics could be Compressible materials (typically sandy clays and
incorporated into the design. Specic geotechnical clayey sands) to between 7 m and 12 m in depth;
investigations supplemented existing geotechnical
information held by BAC. Compressible silty clays to between 10 m and
32 m in depth; and
Existing geotechnical information included:
Stiff clay and dense sands below the
10 peizocone penetrometer tests from a compressible materials.
preliminary investigation in the NPR site;
The groundwater depth was estimated (based
7 peizocone penetrometer tests from various on soil pore pressure response during piezocone
investigations around the domestic terminal penetrometer testing) to be approximately 1.0 m
precinct; and to 2.5 m below ground surface level. Further
assessment of groundwater depth was undertaken
3 boreholes from previous investigations around
during acid sulfate soils investigation, and the results
the domestic terminal precinct.
of these investigations are presented in Chapter B3.
Geotechnical investigations undertaken during
The presence of the soft compressible materials is
preliminary design include:
understood to be the result of geological processes
Drilling and sampling 10 boreholes, generally where the soft silts and muds were deposited on the
along the centreline of the NPR; site when the site was underwater. The soft material
lled in numerous surface features including old
27 piezocone penetrometer tests; and creek channels and other depressions the shape,
location and extent of which was determined during
A further 9 piezocone penetrometer tests around
the investigation. The location and depth of these
the northern end of the 14/32 runway.
in lled, subsurface channels is important to the
The piezocone penetrometer tests enabled a probe engineering design of the runway.
to be pushed into the in situ materials and the
characteristics of the materials to be measured

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-141
FOR PUBLIC COMMENT
For a full description of the ground conditions, Primary settlement (during construction phase of
including testing for acid sulfate soils, refer to the project); and
Chapter B3.
Secondary settlement (during the operational
4.8.3 Subsurface Channels phase of the project).

A key characteristic from the geotechnical Generally, it is desirable for a construction technique
investigations that inuences the design is the level to be employed that maximises the primary
or depth of the compressible materials. As part settlement and minimises the secondary settlement.
of the investigation, the depth of the compressible Once the project is constructed, excessive
materials was mapped across the site (refer secondary settlement is difcult to manage and
Chapter B3). The investigations indicate that there can result in excessive maintenance. The total
is a deep relict channel lled with compressible settlement experienced on any site is a function
materials to the east of the proposed runway. of the subsurface conditions while the secondary
The channel can be traced to the north, adjacent settlement is a function of the ground treatment
the end of the existing 14/32 runway. employed during construction.

The depth of soft material in the inlled channel BAC requested that the design adopt a construction
is typically greater than 30 m. The conditions are technique with a target secondary settlement of
similar to those encountered on the International 100 mm. To address this requirement, a number of
Terminal building project where old deep, inlled construction techniques were investigated, including:
channels were managed through the design and
Preloading lling the site to a predetermined
construction of the terminal building and apron.
level and allowing the ground to settle to the
The ground conditions on the existing runway site
nominated design level over a period of time;
are slightly different to those encountered on the
new runway site. The existing runway site does Surcharging surcharging involves lling the site
have areas of soft inlled material but does not have to a greater level than the nal level and allowing
channels to such depth. the surcharge to remain for a predetermined
period, while allowing the site to settle; and
4.8.4 Engineering Design Considerations
Surcharging with wick drains as above with
Factors considered in the engineering design of the the addition of vertical wick drains that aim to
ground treatment and lling of the site include: accelerate the consolidation process by providing
improved subsurface drainage.
Consolidation of the subsurface lls;
In addition to these construction techniques, a
Filling program or construction method; and
more aggressive consolidation technique, vacuum
Final settlement (secondary settlement) while consolidation, was investigated for use in areas with
in use. particularly deep subsurface channels. Vacuum
consolidation involves the application of a vacuum
Consolidation of subsurface soils occurs when pressure to vertical wick drains to further accelerate
the ground water trapped in the subsurface soils the consolidation process. The use of vacuum
is squeezed out in response to increased surface consolidation is warranted where consolidation is
loading. This process is particularly relevant to the required quickly and the other measures investigated
new runway project site where the consolidation of cannot deliver the settlement in a timely manner.
the soft, wet materials contained within the deep
subsurface channels is required as part of the Once complete, each of these ground treatments
construction process. The evidence of consolidation aims to accelerate the primary settlement of the site.
occurring during construction is the lowering of the Further, it is possible for each of these options to be
ground surface level commonly called settlement. used on different parts of the site, dependent upon
Settlement generally occurs in two phases: the ground conditions. Each of the consolidation

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-142
FOR PUBLIC COMMENT
techniques is equally valid, depending upon Typically, settlements across the site range
the construction timeframe and ground surface between 500 mm and 1.5 m with those areas
conditions. The more aggressive techniques are near the deep subsurface channels expecting
effective at improving the drainage of groundwater settlements in the order of 2 m. This primary
from the soft, subsurface materials, resulting in settlement is combined with a secondary target
shorter timeframes for delivery of primary settlement. of 100 mm (measured after 50 years of runway
operation).
With the exception of preloading, all techniques
require the temporary placement of additional sand To achieve these settlements in a reasonable
ll material over the runway site. To increase the timeframe, a combination of all construction
applied load and further accelerate consolidation, techniques is proposed.
additional ll can be placed over wick drains in
combination with vacuum consolidation. An In summary:
important consideration in the development of the Some areas along the runway centreline can be
construction technique is the maximum amount of constructed using preloading only. The elevated
ll available from Moreton Bay. ground level in this area, due to the dredge spoil
from Kedron Brook Floodway dredging (refer
4.8.5 Construction Timing above) has been acting as a preload since the
In addition to the subsurface conditions, there early 1980s, thus reducing the need for further
are construction timing constraints on the project ground treatment in this area.
that need to be considered when developing the
The majority of the parallel taxiway requires
ground treatment design. Refer to Chapter A5
surcharging with wick drains to varying surcharge
for a detailed description of the construction
heights from 5.5 m to 6.5 m above existing
methodology and timing.
ground level. The deeper areas of soft material
In summary, BAC requires: require more aggressive treatment to drain
groundwater from the subsurface materials.
Construction of the 14/32 runway upgrading over
a short period so that the runway closure and The connection of the link taxiway to the existing
impact on Airport operations is minimised; and parallel taxiway will require surcharge to a
height of 5.5 m. This area was partially lled
Construction of the remainder of the project (to a low height) during the construction of the
in a reasonable timeframe, consistent with the existing runway and has since undergone some
cost effective delivery of the ground treatment consolidation.
components of the project.
An area suitable for vacuum consolidation is
These two requirements have inuenced the design identied at the northern end of the 14/32 runway.
of the ground treatment. The need to minimise closure of the 14/32 runway
results in a more aggressive ground treatment
4.8.6 Adopted Geotechnical Design technique being adopted in this area.
The ground treatment methods listed above were The proposed ground treatment plan will allow the
assessed for suitability on the runway site with a project to be delivered to the construction program
view to establishing the amount of settlement and provided in Chapter A5.
the timeframe required to achieve it.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-143
FOR PUBLIC COMMENT
4.9 Airport Drainage 4.9.1.1 General

Alternatives for the provision of the major tidal


The NPR project is located at the lower end of drainage channels were investigated during the
Kedron Brook catchment, bounded by Moreton preliminary design. The considerations that
Bay to the north and adjacent waterways including informed the chosen locations included:
Kedron Brook Floodway and Landers Pocket Drain.
The existing development on the Airport and the
The site of the NPR is currently subject to inundation
locations of existing drainage outfalls from the
during large regional ood events and through regular
General Aviation area and the domestic terminal
tidal cycles. The ooding context of the NPR area
precinct;
and the interacting waterways is discussed further in
Chapter B7 Surface Water Hydrology and Hydraulics. Environmental considerations, including the
location of ora and fauna areas with high
Substantial drainage infrastructure will be
conservation value;
constructed as part of the new runway project
to provide suitable ooding immunity to new and Site geotechnical conditions and the areas of
existing infrastructure on the site (refer Figure 4.9a). the site where large settlements are expected,
The drainage infrastructure constructed will include: specically the area beneath the proposed
runway immediately adjacent to the existing
Major tidal channels (at the discharge locations
14/32 runway;
from the Airport);
The desire to use the major tidal channels during
Secondary channels (connecting non-tidal
both the construction and operational phase of
channels to major tidal channels);
the runway to limit the disturbance to existing
Local non-tidal channels; creeks and drains; and

Detention storage and vegetated buffer areas; and The size, location and geometry of the proposed
taxiway and runway.
Hydraulic structures.
The domestic terminal precinct and general aviation
The site of the NPR is currently extensively modied area generally drain towards the runway site through
from its original condition, although it remains a series of culvert outfalls. During construction
undeveloped. The site does not include an and during the operation of the NPR, drainage to
engineered drainage system, but includes a number existing facilities must be maintained at all times.
of remnant and modied tidal channels that drain The locations and size of drainage outfalls informed
the existing Airport development and the ood the locations of the major tidal drainage channels.
waters that inundate the site from the Kedron Brook
drainage system. The NPR will be located in areas of poor soil
conditions that will be subject to signicant post-
4.9.1 Major Tidal Channels construction settlement (refer Chapter B3 Geology
and Soils). Use of drainage structures beneath the
The Kedron Brook Floodway Drain and Serpentine
NPR, in areas where high settlements are expected,
Inlet Drains are major tidal channels that will be
is likely to cause unacceptable surface undulations
constructed in association with the NPR project.
along the runway as the soft, compressible natural
These major tidal channels provide ooding
material settles away from any rigid drainage
immunity to the NPR and maintain existing ooding
structures. In addition to geotechnical constraints,
immunity to existing infrastructure, reduce the
the provision of the 150 m wide runway strip (refer
impact of the NPR on regional ooding on- and
section 4.6.5) requires the installation of very long
off-Airport, and enhance the environmental amenity
cross runway culverts which would prove difcult
of the new runway project.
to maintain and may prove difcult to secure.
Accordingly, cross-runway drainage is not proposed.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-144
FOR PUBLIC COMMENT
The at topography of the site places a limitation on reclamation process (refer section 4.24) and the
the change in channel bed elevation from the top of discharge of construction stormwater, removing
each drain to the point of discharge, which ultimately the need to construct additional drainage for
limits the length of drains. Accordingly, major tidal construction purposes.
drainage channels are required at each end of the
NPR to reduce the total length of drainage branches. The Kedron Brook Floodway Drain is designed
The site is effectively broken by the link taxiway into to provide a low energy environment that limits
two similar sized catchments, each draining to one of opportunity for scouring and erosion on its bed and
the major tidal drains. banks during ood events. The entry into Kedron
Brook is designed to provide an environment where
Consideration of these factors and the likely the velocity of ows in the drain is similar to the
discharge locations leads to the provision of major velocity of the water in the Kedron Brook Floodway,
tidal channels around the southern end of the NPR in order to minimise turbulence and the associated
and beneath the 14/32 taxiway to Serpentine Inlet. scouring and erosion.

4.9.1.2 Kedron Brook Floodway Drain 4.9.1.3 Serpentine Inlet Drain

The Kedron Brook Floodway Drain (refer The location of Serpentine Inlet Drain was
Figure 4.9a) is located at the southern end of the selected following investigation into the likely
NPR. The alignment of the drain is from west of outfall of operational stormwater, construction
the existing domestic terminal building, around the stormwater and supernatant from the new runway
southern end of the NPR, joining Kedron Brook site combined with the constraints placed upon
Floodway opposite Nudgee Golf Course. Kedron drainage by the runway geometry and geotechnical
Brook Floodway Drain is needed to: constraints (refer section 5.9.1.1). The Serpentine
Inlet Drain (refer Figure 4.9a) is located alongside
Divert the existing Landers Pocket Drain from
the existing remnant channel entering Serpentine
entering the NPR site; Inlet at the northern end of the Airport. Based upon
Intercept regional overland ow that travels surveys of the Airport site prior to development,
through the area between Airport Drive and the Serpentine Inlet Drain is proposed in a similar
Kedron Brook Floodway during large regional location to the original Serpentine Inlet Creek
ood events (refer Chapter B7); and mouth, which was severed by the construction
of the existing runway. On the southern side of
Provide a discharge location for existing Airport Serpentine Inlet and at the outlet to the existing
drainage that currently discharges into the airside drain, is a deeper channel from Serpentine
Landers Pocket Drain, Serpentine Creek and Inlet out into Bramble Bay. Apart from this deeper
Jacksons Creek system, and for drainage from channel, the remainder of the Inlet is relatively at
the southern end of the NPR. and shallow and with large areas exposed at low
tide. Immediately adjacent to the proposed drain
The alignment of Kedron Brook Floodway Drain
outlet is a series of sand bars that provide habitat
places the channel as far north as practicable to
to mangroves and other marine plants. Parts of
minimise the total footprint of the NPR project,
these sand bars are elevated above normal tidal
while allowing for the full 3,600 m NPR length and
range. A small stormwater channel discharges from
associated Runway End Safety Areas (RESA).
the existing re ghting training area to Serpentine
The lower end of Kedron Brook Floodway Drain
Inlet, parallel to the proposed Serpentine Inlet
skirts the new runway end to its conuence with
Drain. This small, existing channel is well vegetated
Kedron Brook Floodway to avoid encroaching on
with mangroves and will be maintained throughout
Lewins Rail habitat located to the south of the NPR
construction of the Serpentine Inlet drain. The
(refer Chapter B5 Terrestrial and Marine Ecology).
proposed Serpentine Inlet Drain will terminate
By locating the Kedron Brook Floodway Drain
at the existing shoreline and outlet at about the
adjacent the runway end, the drain can be used
same invert level as the intertidal ats that make
as a discharge for the supernatant water from the

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-145
FOR PUBLIC COMMENT
Figure 4.9a: Drainage Layout Plan.

N
0 100 200 300 400 500m

NEW PARALLEL RUNWAY DRAFT EIS/MDP NEW PARALLEL RUNWAY DRAFT EIS/MDP A4-146
FOR PUBLIC COMMENT FOR PUBLIC COMMENT
up the Inlet. Further excavation of the Serpentine from the channel invert level to top of bank. The
Inlet Drain into the intertidal ats at its outlet will bank slopes of the channels have rock protection to
not improve the efciency of the drainage and will reduce scour of bank materials and promote bank
further disturb the Inlet and modify existing habitats. stabilisation. The rock protection has a 1 m toe
On this basis, additional excavation at the outlet is extended into the channel bed to provide a dened
avoided in the proposed design. channel prole.

The channel alignment is from the east of the existing The bed of the major tidal channels includes
14/32 runway to Serpentine Inlet and is needed to structural lining (rock protection) around the outlet
provide a discharge location for existing drainage and downstream of the outlet from the sediment
catchments of the general aviation areas at the ponds used during construction (refer section 4.24).
northern part of the site that currently discharge to The lining of major tidal channels will minimise the
the Serpentine and Jacksons Creek systems and to scour of bed material in the tidal channels that
provide a discharge point for drainage of the northern may potentially result from extended release of
end of the NPR (refer Figure 4.9a). The Serpentine supernatant water from the sediment ponds. Tidal
Inlet Drain is sized to account for future development ow and stormwater ow will not cause appreciable
within the FAFA and is sufcient to cater for large scour in the major tidal channels, and the channels
storm event runoff from this area. The Serpentine Inlet will remain unlined upstream of the outlet from the
Drain is designed to be a low energy environment with sediment ponds.
low ow velocities to minimise bed and bank scour.
The drain outlet, if required, will also be provided with The Kedron Brook Floodway Drain and Serpentine
a diffuser structure to reduce ow velocities entering Inlet major tidal channels include 10 m wide
Serpentine Inlet to ensure that impacts on ora and benches above the channel invert level for
fauna living in Serpentine Inlet are minimised (refer to establishment of mangrove communities. The
Chapter B5 Terrestrial and Marine Ecology). mangrove benches assist in stabilisation of the
tidal channels and incorporate environmental
4.9.1.4 Major Tidal Drain Geometry amenity. Mangrove benches are designed between
elevations of 1.5 m and 2.0 m (Airport Datum),
The low elevation and at topography of the NPR
known to be suitable for Grey Mangrove and River
site and the tidal characteristics of the drainage
Mangrove colonisation. The rock protection applied
receiving waters place a constraint on the invert level
to the channel banks will assist in controlling the
of Kedron Brook Floodway Drain and Serpentine
colonisation of mangroves on the channel banks
Inlet Drain. In addition, the invert levels of existing
and in the invert, required for the hydraulic capacity
drainage from the Airport development places
of the channel.
a constraint on the inverts of any new drainage
channels. As a result, the invert level of each drain 4.9.2 Secondary Channels
needs to be below mean sea level, and will therefore
be tidally inuenced during the normal tidal cycle. A number of secondary channels are used to
The invert levels of the two major tidal channels connect local drainage from existing Airport
have been designed at approximately Mean Low developments and the NPR project to either of
Water Neap (MLWN) level (0.545 m Airport Datum) the two major tidal channels. The secondary tidal
to promote tidal ows within the waterways that channels (refer Figure 4.9a) are required to provide
can support ecosystem function. Localised a number of functions in the drainage system,
channel deepening occurs upstream of the outlet including:
of each channel to provide hydraulic stability at
Connecting local non-tidal drainage branches to
the conuence of the drains and the receiving
major tidal channels; and
environments.
Providing stormwater treatment function through
The geometry of the major tidal channels is shown in
the ltration action provided by the vegetated
Figure 4.9b. The channels have a 30 m wide base
channel lining.
width, with approximately 15 degree bank slopes

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-147
FOR PUBLIC COMMENT
A4-148
MANGROVE BENCH CHANNEL WIDTH VARIES MANGROVE BENCH
HYDROMULCH HYDROMULCH

H.A.T H.A.T
RL 2.425 RL 2.425
RL 2.000 RIPRAP PROTECTION RIPRAP PROTECTION RL 2.000

1 1
4 RL 1.500 RL 1.500 4

1 1
4 4

TIDAL CHANNELS
Figure 4.9b: Typical Drainage Channel Details.

DRAIN WIDTH VARIES


DRAIN WIDTH VARIES
HYDROMULCH TURF TO TOP OF DRAIN HYDROMULCH
TURF TO TOP OF DRAIN
HYDROMULCH HYDROMULCH
BENCH 2000 BENCH
BASE WIDTH
2000
BASE WIDTH

1 5.0% 5.0% 1
4 4

1 1 TURF TO CHANNEL INVERT


4 4

FOR PUBLIC COMMENT


TYPE B - MAJOR CHANNELS TYPE A - MINOR CHANNELS

NEW PARALLEL RUNWAY DRAFT EIS/MDP


NON-TIDAL CHANNELS

0 1 2m
The secondary channels are typically short Providing drainage for future Airport
sections of tidally inuenced channel connecting developments; and
the local non-tidal drainage branches to major tidal
channels. The secondary channels commence Providing stormwater treatment function
at the downstream side of the tidal control gates through the ltration action provided by the
(refer section 4.9.5), and have a bed level between grass channel lining.
approximately 1 m at the upstream end and The geometry of local non-tidal channels is based
0.545 m (Airport Datum) at the downstream end on hydraulic requirements of local catchments and
(connecting to the major tidal channels). The non- varies according to the local catchment discharge.
tidal local channels join the secondary channels at Trapezoidal geometry is used throughout the minor
the upstream end. drainage system, and the base width is varied
The geometry of secondary channels forms a to accommodate ow. Toward the lower end of
transition between the local non-tidal upstream minor drainage channels, small low ow inverts
channels and the major tidal channels downstream are designed within larger trapezoidal channels to
and is based on providing the hydraulic capacity maintain ow velocities above siltation velocity but
for drainage of existing Airport infrastructure, the below scour velocity.
new runway and future Airport development. The Local non-tidal channels are grass lined to provide
secondary channels include mangrove benches treatment of stormwater through ltration of
similar to those featured in the major tidal channels, solid particles and particle-bound contaminants.
although the bench width is reduced (typically 5 m). Signicant ow length through the grass lined
These benches extend upstream in the secondary drains provides signicant treatment potential for
channels until the channel bank level exceeds stormwater pollution.
approximately 2 m (AD).
4.9.4 Detention Storage and Vegetated
4.9.3 Local Non-Tidal Channels Buffer
Development of the new runway requires The drainage system around the NPR, includes
construction of an engineered drainage system to detention storage between the runway and taxiway
provide rapid and effective drainage of runway and pavements and within the footprint of the NPR
taxiway infrastructure. Local non-tidal drainage and taxiway system (refer Figure 4.9a). These
channels are used for drainage of the runway and areas form large basins that are used for temporary
taxiway area and for drainage of existing facilities that storage of stormwater runoff during rainfall events.
currently drain through the site of the new runway. Discharge of runoff from the storage basins is
Local non-tidal drainage channels are used controlled by culvert structures that pass beneath
throughout the NPR project as collector drains the taxiway pavements to the local non-tidal
for secondary channels and ultimately major drainage channels.
tidal channels. Local non-tidal channels (refer Detention of stormwater reduces the peak discharge
Figure 4.9b) have a number of functions that from the runway and taxiway area which reduces
include: hydraulic impact on downstream waterways, including
Providing direct drainage of local catchments the receiving waters at Kedron Brook Floodway and
associated with the NPR project; Serpentine Inlet. Use of runoff storage between
runway and taxiway pavements is consistent with the
Providing drainage of existing drainage drainage scheme of the existing 01/19 runway.
catchments that drain to the Landers Pocket
Drain, Serpentine Creek and Jacksons Creek
systems;

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-149
FOR PUBLIC COMMENT
4.9.5 Hydraulic Structures The proposed NPR will be constructed with the
following treatment train approach to optimise
Hydraulic structures used in the drainage system for water quality treatment function within the drainage
the NPR include: system design:
Culvert structures to control discharge from The runway is grooved with narrow grooves
detention storage areas to local non-tidal (approximately 5 mm 10 mm) at regular
channels; and intervals (approximately 50 mm) and the
Hydraulic gates at the interface of major and pavement is ush kerbed with the grass verge.
secondary tidal channels. These grooves drain stormwater in a disperse
manner to the grassed verges;
Culvert structures are used commonly throughout
the drainage system for the NPR to control Taxiway pavements are ush kerbed with the grass
discharge from the detention storage areas. The verge. This results in disperse ow shedding from
culvert outlet structures use predominantly pipe the pavement into the grassed verges;
culverts to maximise ow velocity through the The grassed verges act as lter strips to the
culverts to reduce siltation within the structures. disperse ow from the runway or taxiway drainage;
The interface between secondary channels and major The grassed verges drain into the detention
tidal channels is controlled by hydraulic gates (ood storage areas, where settling can occur as well
aps) that reduce salt water intrusion to the secondary as ltration and inltration; and
drainage system and the local non-tidal system.
A reduction in salt water intrusion is favourable to The detention storage areas drain into the local
maintain vegetative lining of open channels. Flood non-tidal channels, where ltration and inltration
aps at the interface between major drainage systems can occur.
and the secondary channels also addresses security
4.9.6.1 Grass Verges
requirements for the NPR, providing reduced access
to the aireld through drainage infrastructure. Grass verges act as lter strips which are effective
in the removal of coarse sediments. The lateral
It should be noted that hydraulic gates do at times
ow of water from the runway or taxiway pavement
allow tidal waters to enter the secondary channels
will lter across the grass verges. The width of the
drainage system. It is anticipated that this ingress
lateral ow from the edge of the pavement promotes
of tidal waters will not adversely impact upon the
shallow disperse ow which will have greater
function of the drainage system. It may result in
treatment effect as it ows across the grass verge.
edge effects with estuarine vegetation establishing
Hence, the grass verge will assist in the treatment of
within the limits of the tidal ingress.
water quality.
4.9.6 Water Quality During Operations 4.9.6.2 Detention Storage Areas
Chapter B8 Water Quality discusses the application The drainage system around the NPR includes
of different water quality objectives to the NPR detention storage in areas between runway and
project. The preliminary design approach towards taxiway pavements and within the footprint of the
water quality management focuses on optimising NPR and taxiway system (refers Figure 4.9a).
treatment within the drainage design without These areas form large basins that are used for
affecting the function of the NPR. The preliminary temporary storage of stormwater runoff during
design of stormwater infrastructure was informed rainfall events but maintain standing water between
by an assessment of potential stormwater rainfall events. They will be designed to discharge
contamination sources and the stormwater quality gradually after rain events to maximise sediment
from existing aviation infrastructure, and identied a settlement potential and inltration effects.
low potential for stormwater pollution from NPR and
taxiway stormwater runoff.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-150
FOR PUBLIC COMMENT
As these detention basins are designed with and the Qantas Catering and valet car parking area
relatively short detention periods, they will not to the south. Dryandra Road also provides access to
promote fauna attraction. The vegetation selected the existing security operations located at Gate 1 and
will be drought resistant, salt tolerant and will not is used by all vehicles prior to entering the protected
provide fauna habitat or feeding opportunity. airside area of the Airport. The general aviation area
houses a number of related aviation facilities including
The detention effect and the vegetated base of couriers and the Royal Flying Doctor Service. Access
the detention basins provide opportunities for the along Dryandra Road is unrestricted to the public and
treatment of stormwater pollutions. The detention at present its capacity is adequate for its use and the
effect will allow some settling of sediment. The road surface is in fair condition.
vegetative base and the wide shallow ow (some
50 m to 100 m wide) to the culvert outlet will 4.10.2 Dryandra Road Alignment
also provide some ltration treatment function for
stormwater pollution. The sand material that will be The current access to the Airport is via Airport Drive,
used for the reclamation lling will also allow inltration from the Gateway Motorway. BAC is currently
to occur during the period that the detention undertaking planning to provide an additional
basins are ponding water. This will also assist in access from the Gateway Motorway to the domestic
the treatment of water quality through the ltration terminal and have called the project the Northern
function of water passing through a sand media. Access Road (refer to Chapter A1).

4.9.6.3 Local Non-Tidal Channels In addition to the Northern Access Road, current
Airport planning includes an extension of the Domestic
Local non-tidal channels are grass lined to provide Terminal apron (to the north of the existing domestic
treatment of stormwater through ltration of solid terminal apron). Long term development of Brisbane
particles and particle-bound contaminants. The Airport includes a new apron and terminal located
sand material that will be used for the reclamation west of the existing domestic terminal building.
lling will also allow inltration to occur during the
period that the local non-tidal channels are owing To suit the apron layout and the car parking and road
with water. Flow length through these grass lined network necessary to support an additional western
drains provides adequate treatment potential for the terminal building and apron, the alignment of Dryandra
management of any stormwater pollution. Road must be moved further to the west. Refer to
Figure 4.3 for the alignment of Dryandra Road.
It should also be noted that the hydraulic gates
(ood aps) will control the discharge from the local 4.10.3 Future Land Use and Demand
non-tidal channels. This will potentially mean that
small events may not have sufcient ow to open The construction of the NPR involves the
the hydraulic gates (ood aps). This will result in construction of a major link taxiway between the
water ponding for short periods in the local non-tidal existing runway and the new runway. The link
channels and will maximise the inltration treatment of taxiway will enable taxiing aircraft to move from
these systems. the new runway to the existing domestic terminal
while providing for future growth of the domestic
terminal precinct. A large area of the runway site is
4.10 Dryandra Road Tunnel allocated for future aviation facilities. The FAFA area
is bordered by the link taxiway, general aviation area
and 14/32 runway and new runway, and may include
4.10.1 Existing Dryandra Road
long term aviation related developments including:
Dryandra Road is a two lane road that links the
Long term passenger terminal facilities;
existing general aviation area with the domestic
terminal precinct. It provides access to a number of Long term major aircraft maintenance facilities; and
commercial operations along its length, namely a large
area occupied by rental car companies to the north General aviation facilities.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-151
FOR PUBLIC COMMENT
The FAFA will have vehicle access via Dryandra Road. Construction in soft soils, below the level of
Accordingly, Dryandra Road may require widening to the water table requires a specic construction
four lanes to increase its capacity and will require a approach to prevent the construction area
connection into the FAFA, grade separated from the becoming inundated with ground water. Typically,
link taxiway. Dryandra Road and the tunnel into the construction below the water table requires the
FAFA have been designed to be four lanes to cater for installation of a barrier such as sheet piles to prevent
all future planned development. the inow of ground water and complex pumping
systems to ensure that any ground water that does
To provide access into the FAFA, a tunnel structure penetrate the sheet piles is managed.
is required on Dryandra Road that is capable of
providing for aircraft movements on the link taxiway Constructing the tunnel also requires the excavation
over the road. In setting the vertical alignment of of highly compressible, soft materials that are
the road and the vertical alignment of the taxiway, difcult to excavate and unstable when exposed.
it is necessary to consider surrounding land uses, The excavation for the tunnel is also in close
immediately adjacent to the road and taxiway. With proximity to the existing GA infrastructure and as
the current planning for extensions to the existing such, will need to be stable and safe in order to
terminal aprons on either side of Dryandra Road, the protect the adjacent infrastructure.
vertical alignments for both road and taxiway were
determined to maintain maximum exibility for future After considering these constraints, several structural
aviation development. options were considered including the use of secant
piles (interlocking piles), temporary sheet piles to
4.10.4 Engineering Design stabilise the excavation and top down construction
using diaphragm walls. Diaphragm walls enable
4.10.4.1 Considerations the contractor to commence construction by
excavating and constructing vertical tunnel walls
The structural engineering design of the Dryandra
through the existing surface and then constructing
Road tunnel takes account of:
the tunnel roof. Once the walls and roof are in place,
The existing geotechnical information the contractor can commence construction of the
including the presence of deep areas of highly tunnel oor, starting at the approaches and moving
compressible soils (refer to Chapter B3); towards the middle of the tunnel. The tunnel oor
connects with the tunnel walls forming a watertight
The depth of the water table (located structure within which the contractor can safely work.
approximately 1 m below the existing surface) The walls and oor form the permanent structure,
and the buoyant forces on the tunnel oor; reducing the amount of temporary works required
Proximity of existing infrastructure (specically to enable construction. This top down construction
the GA apron); and was successful at the Breakfast Creek tunnel on the
Inner City Bypass and is proposed for the approved
The constructability of a tunnel under such Tugun Bypass project beneath the runway at Gold
conditions. Coast Airport.

The high ground water table in the area of the 4.10.4.2 Adopted Design
proposed tunnel requires careful assessment
Although there are opportunities for staging some
of the buoyant forces on the tunnel that will act
infrastructure required for the runway project there
on the tunnel oor and try to force the structure
are few opportunities to stage the construction of
out of the ground. The tunnel requires sufcient
the tunnel structure. The rst stage of the Dryandra
structural mass to resist the buoyant forces, which
Road tunnel will include:
is particularly critical on the approach ramps to
the tunnel where there is no tunnel roof. On the Sufcient length to accommodate both north and
approach ramps, ground anchors that hold the south taxiways that comprise the ultimate link
tunnel down were considered. taxiway; and

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-152
FOR PUBLIC COMMENT
The ultimate tunnel structure to accommodate sealed with bitumen seal to prevent erosion and
four lanes of Dryandra Road. provide a safe, all weather running surface suitable
for all vehicles.
Above the tunnel, the pavements for the link taxiway
connecting the new runway with the existing runway
will be constructed in two stages and the roadworks 4.12 Security Fencing
adjoining the tunnel structure may be staged
depending upon trafc demand. The security of the aireld is paramount to
The adopted design is a diaphragm wall tunnel, maintaining safe, reliable Airport operations. As
constructed on the new alignment of Dryandra Road part of the security provisions for the new runway,
with the following specications: a security fence will be provided to delineate
the boundary between airside and the publicly
440 m long tunnel structure (including approach accessible areas (landside) on the Airport. The
ramps into tunnel); current design includes for a security fence
measuring 2 m in height with a three barb extension,
800 mm thick external diaphragm walls, installed
constructed from chainwire fencing materials.
to depth suitable to ensure the walls found against
rm material underlying soft compressible clays; The fence will be located between Kedron Brook
and the new runway and between the FAFA and
800 mm thick central diaphragm wall acting as a
the parallel taxiways. The fence will be continuous
divider between the two trafc ows, installed to
with limited gates or crossing points and will be
depth of diaphragm walls;
monitored during operation of the runway and
900 mm thick tunnel roof, capable of supporting regularly inspected by Airport security staff.
the loading from wide-bodied aircraft that will use
Access beyond the security fence will be required
the link taxiway; and
to allow BAC to continue to manage the remainder
Prestressed anchors installed in the approach of the site west of the NPR. Access beyond the
slabs to resist the buoyant forces from the security fencing will be via controlled gates and
ground water acting against the tunnel oor slab. will require cooperation with security staff. Other
parties, such as the Brisbane City Council (BCC),
The design will provide exibility for future that may have legitimate reasons for gaining access
development of the domestic terminal apron and to the site west of the runway will be permitted to
will provide some opportunity for providing for access via the perimeter road and controlled gates.
increased trafc demand as a result of the ultimate All access will require cooperation with BAC security
development of the FAFA. and will require prior arrangement and possibly an
escort.
4.11 Perimeter Roads Security provisions on Australian airports are subject
to change, and may require the construction of a
To enable the regular maintenance of the aireld, different style of fence or the utilisation of different
security inspections and response to emergencies, monitoring processes. At the time of runway
a series of perimeter roads is required around the opening, the fencing and security provisions
aireld to cater for vehicle trafc. The majority of use installed will reect the current requirements of
of the perimeter roads is by the security ofcers who relevant government agencies.
patrol the fence line of the existing aireld and will
patrol the fence line adjacent the NPR.

The perimeter roads proposed will be 5 m in width


and are designed to cater for re tenders and mid
sized commercial trafc. The road surface will be

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-153
FOR PUBLIC COMMENT
4.13 Airport Lighting 4.13.2 Approach Lighting Structure

The approach lighting structure, if required, will


4.13.1 Approach Lighting measure approximately 660 m from the Moreton
Bay shoreline and is supported by piles, driven into
Approach lighting on the runway centreline is the seaoor. To avoid unnecessary disruption to
provided to enable use of the runway during periods the coastal processes at the shoreline, the structure
of low visibility. Approach lighting provides guidance is designed to be constructed using a crane that
to pilots on approach to the runway, reduces the walks along the structure from one set of piles
risk to the travelling public and improves overall to the next, supported by steel beams that span
Airport efciency during inclement weather. There between the pile bents.
are several standards of approach lighting that are
applicable to the new runway project and each of The main component of the structure measures
the different standards provides a different limit to 3.8 m wide, 660 m long and is located above both
the acceptable operating conditions. the 1 in 1,000 year storm surge level (2.8 m AHD)
and the 1 in 1,000 year signicant wave height
The existing runway at the Brisbane Airport operates (Hs = 2.3 m). To complete the lighting array, there
with an approach lighting system at both ends of are several barrettes that project perpendicular to
the runway. This enables the use of the Airport the centreline of the runway by up to 25 m. These
during inclement weather and low visibility. The barrettes are also tted with directional lights that
lighting design for the new runway provides for: project into the ight path of approach aircraft.
Category 1 approach lighting; The structure will be secured and will be patrolled
regularly by Airport security. The structure provides
Category 2 supplementary and touchdown zone
for access by a light commercial vehicle for
lighting; and
inspections and for maintenance.
Category 3 edge, centreline and threshold lights.
4.13.3 Ground Lighting System
Overall, the lighting system is designed to support low
visibility operations to be ICAO Category 2 capable. Ground lighting on the aireld provides visual clarity
for pilots as they guide aircraft across the aireld.
At the southern end of the runway, the approach Ground lighting systems are generally integrated
lighting is located over an area designated for sand into a complex control system that enables air trafc
lling as part of the runway project. The lights are control to direct aircraft onto the correct taxiway by
located on small structures slightly above the level of turning on or off the relevant lights. The approach
the lled surface. At the northern end of the runway, lighting system (refer above) is integrated into a
the lighting structure is designed to extend into ground lighting system that includes lighting on all
Moreton Bay. The lighting structure that extends areas of the new runway, including:
into the bay will be located on a marine structure,
similar in form to a jetty or pier. Undershoot and touchdown zones at each end;

The approach lights themselves are directional Runway edge, centreline and thresholds;
lights and are directed into the ight path of the
Lead on lights and sensing loops;
approaching aircraft. The lights will generally not be
visible from the land. The lights are connected to Taxiway centreline and edge lights;
the aireld lighting control system and are provided
with a main power supply and supplementary power Stop bars and runway guard lights; and
supply in case of emergency. Movement Area Guidance Signs (MAGS).
The installation of approach lighting may not be The majority of these lights are located either in the
required as improvements in technology relating to pavement (i.e. taxiway centreline lighting) or close
aviation navigation advance.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-154
FOR PUBLIC COMMENT
to ground level (MAGS). The proposed lighting rubble used to construct the seawall. As a result,
system will be incorporated into a complex control sand materials behind the seawall may be eroded
system that incorporates both approach lighting and and the aviation infrastructure supported by the
ground lighting. sand ll may be gradually undermined.

The control system that controls the lighting will be A new seawall will be constructed east of the
operated out of two Aerodrome Lighting Equipment Cribb Island Jetty to the mouth of Serpentine Inlet
Rooms (ALERs). These rooms house the control during construction of the NPR (refer Figure 4.3).
equipment, power facilities and standby power The seawall will prevent erosion of existing sand ll
facilities required to operate the ground lighting materials placed during construction of the current
and the approach lighting. The ALERs are located Brisbane Airport infrastructure and protect the
adjacent the northern and southern ends of the NPR from erosion caused by wave and tide action.
new runway. Each ALER is air-conditioned and
is expected to have a maximum electrical load 4.14.2 Proposed Seawall Alignment and
requirement of 800 kVA, of which 500 kVA is Construction
required to run the control equipment.
The alignment of the new eastern seawall follows
4.13.4 Construction Staging the alignment of the existing rubble seawall from the
Cribb Island Jetty to the mouth of Serpentine Inlet, a
The lighting design adopted during the preliminary distance of approximately 1.5 km.
design is consistent with the current best practice
for aireld lighting. It may be necessary to adjust the The seawall is a graded rock structure, placed on
lighting design at the time of construction to reect geotextile over the existing ground. The crest of
current CASA or ICAO practices. In addition, it may the seawall will be constructed to approximately
be possible to stage construction of the lighting 3.6 m (AD) to provide protection of the NPR and
system with some associated modications to the existing infrastructure during storm tide events.
operation of the aireld. Assessment of the existing rock materials undertaken
during preliminary design showed the rock materials
4.14 Seawall of the existing seawall would be unsuitable for use in
construction of the new seawall. Quarried rock will
be used for construction of the new seawall, and the
4.14.1 Existing Conditions existing seawall materials will be used as ll in other
parts of the NPR construction (following removal of
The northern boundary of Brisbane Airport coincides
steel scrap and concrete rubble contaminants).
with the western shoreline of Moreton Bay. At a
point along the shoreline approximately north-west
of the NPR centreline, the remnant Cribb Island 4.15 Rescue and Fire Fighting
Jetty forms a structural divide between eastern Services
and western parts of the shoreline boundary. The
eastern part of the shoreline boundary is located
very close to the northern extent of the NPR. A new rescue and re ghting facility will be located
adjacent the midway point of the 3,600 m runway,
The existing seawall to the east of the Cribb Island in the FAFA (refer Figure 4.3). The new runway
Jetty is roughly constructed from dumped rubble, requires a dedicated re station in order to comply
and currently provides minimal protection of aviation with the required response time to an emergency on
infrastructure from erosion caused by wave and the new runway of three minutes (CASA). The re
tide effects. BAC has undertaken monitoring of the station will provide car parking facilities for staff and
existing seawall and has identied some erosion have public access to the back of the re station.
to the east of the Cribb Island Jetty. The existing
seawall does not provide a geotextile layer between Existing and proposed response procedures are
the sand ll materials of Brisbane Airport and the discussed in Chapter D8.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-155
FOR PUBLIC COMMENT
4.16 Services of 5 m separation between the independent
supplies by placing them either side of the
perimeter road.
4.16.1 Introduction
4.16.2.2 Dryandra Road
The construction of the NPR will require existing
services to be relocated and both temporary and The location of the proposed link taxiway severs
new permanent services to be installed. The Dryandra Road and with it all of the existing
construction staging will govern the sequence in services to the GAA. The existing services include:
which service installations will occur, commencing electrical, water, sewer and telecommunications,
with services related to the 14/32 runway followed which are located either side of Dryandra Road and
by services within the proposed link taxiways and supply the GAA, the adjacent developments (i.e.
nishing with the new services required to operate Qantas Catering) and the facilities beyond.
the new runway. New services will be installed alongside the new
alignment of Dryandra Road in a permanent,
4.16.2 Existing Services
combined services corridor that links the services
There are a number of existing services that in the domestic terminal precinct with the GAA.
are within the footprint of the new taxiway and The combined service corridor will be located
runway pavement and will be affected by any alongside Dryandra Road and will continue beneath
ground treatment, specically where large ground the link taxiway embankment. Additional capacity
settlements are expected. To ensure that the Airport for services will be provided through the Dryandra
can continue to operate during construction, these Road tunnel structure to enable future service
services need to be relocated prior to consolidation augmentation, should it be required. During the
as they will be damaged by excessive settlements. construction phase, temporary service connections
There are three main areas where existing services will be provided into any existing infrastructure,
will be affected and require relocation: such as the existing buildings located at the GAA
and Qantas Catering facility. The contractor
The western end of the 14/32 runway; will ensure that supply of critical services is not
interrupted during construction and operations.
Dryandra Road; and
4.16.2.3 Link Taxiways
The link taxiway, adjacent to the General Aviation
Area (GAA). Existing services currently cross beneath the main
runway and taxiways A and B and into the access
For all locations, the service design and construction
road to the GAA tenants. These services are
sequencing is paramount to providing continuous
located beneath the proposed link taxiway and need
supply to all Airport users and to ensure that the
to be moved from beneath the taxiway footprint.
Airport remains operational during construction.
The proposal is to move these services which
4.16.2.1 14/32 Runway (Western End) include: sewer mains, water and electrical to the
north in a new common service corridor and a new
The existing services located at the western end crossing under taxiway B, temporarily necessitating
of the 14/32 runway include water, electrical and its closure during construction.
telecommunication cabling which supply the radar
facility from two independent supplies. These
services will be replaced with new services in a
new service corridor from the GAA, beneath the
14/32 runway and then parallel to the existing
perimeter road on the northern side of the 14/32
runway. The new services will connect back into
the radar station. The design will allow a minimum

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-156
FOR PUBLIC COMMENT
4.16.3 New Services 4.17 Landscaping
There are requirements for temporary and
permanent new services to be installed within 4.17.1 Existing landscape features
the construction of the NPR. The anticipated
loads that the new runway will place on existing Landscape features that dominate the visual
utilities infrastructure (i.e. sewer, water, electrical, experience for Airport users are the planted
communications) has been taken into account casuarina plantation and Airport Drive. The
by BAC in preliminary planning and at this stage, casuarina plantation between Airport Drive and
augmentation of existing supplies is not anticipated Kedron Brook Floodplain contains planted swamp
as part of the new runway project. she oaks and marine plants and Airport Drive
consists of a linear corridor of planted gardens
4.16.3.1 Temporary Services and maintained lawn areas. The landscape
assessment and proposed mitigation is discussed in
The temporary services required to construct the
Chapter B13.
new runway include electrical, telecommunications,
sewer and water supplies to service the two
construction camps and batching facilities
proposed for the site. The proposed location of the
construction camps are within the vicinity of existing
service routes, thereby allowing the existing service
to be extended to supply these temporary facilities.
The demands envisaged by the construction camps
can be catered for by the existing network without
signicant upgrades.

4.16.3.2 Permanent Services

The major permanent electrical demand of the


new runway project is required to supply the
aireld lighting. The supply for the aireld lighting is
provided to two proposed ALERs from where the
power and control systems will be distributed to
the proposed runway. Indicative maximum loading
requirements for each equipment room is 800 kVA.
BAC is able to supply this load from the existing
Airport network.

The new re station requires services which will


include: electrical, telecommunication, sewer and
water. These services will be diverted from the GAA
area along the re station access road to service the
facility. The demand on services of the new re station
can be supplied from the existing Airport capacity.

The proposed Dryandra Road realignment and the


tunnel located under the link taxiways will require
road lighting and signalling. The electrical demand
from the road and tunnel are not signicant and can
be supplied by the existing network on the Airport.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-157
FOR PUBLIC COMMENT
Part 2 Temporary Works 4.19 Dredge Selection

4.19.1 Introduction
4.18 Temporary Works
Introduction Dredging describes the operation of extracting
materials from the ocean/river bed and recovering
the material for another purpose. Dredging is
In addition to the permanent works required for
currently used routinely in the greater Brisbane
the operation of the NPR, signicant temporary
area for varied tasks including extracting material
infrastructure is required to enable the construction
from Moreton Bay for use in construction and for
of the project. As the project will be constructed
maintenance/deepening of existing channels leading
using a dredge to supply ll material, the majority of
to the Port of Brisbane. There are a number of
temporary infrastructure for the project is centred
different dredging methods that can be applied,
around the dredge and the reclamation process.
depending upon the size of the project and the
To enable the construction of the project, the constraints under which the dredge can work,
successful contractor will provide all necessary including operational, environmental and
infrastructure, including any temporary structures or economic constraints.
works. The design and detail of the temporary works
The dredging industry is a specialised industry that
is dependent upon the contractors construction
is predominantly based overseas in South East Asia,
technique and proposed methodology and
the Middle East and Europe. Most of the major
specically for this project, the type, style and size of
dredging contractors have carried out work in
the dredge proposed to undertake the reclamation.
Australia previously and some maintain marketing
Specically, to enable construction, the contractor ofces in Australia and specically in Brisbane. The
will require: international market for dredging work is buoyant
with large projects in the Middle East (specically
Suitable dredging footprint for extracting 15 Mm3 Dubai) and Singapore presently accounting for
of material for construction; signicant numbers of the international dredging
eet. The Brisbane Airport project will compete
Dredge mooring suitable for the dredge to moor
against these international projects to secure a
while pumping sand on the site;
suitable dredge to carry out this project.
Dredge pipeline to carry sand material from the
An assessment of the dredging work methods
dredge (moored) to the reclamation site;
was undertaken to establish the most likely
All temporary structures required to support the dredge method for the new runway project.
dredge pipeline; and The assessment also includes an assessment
of the dredging plant that might be available
Large settlement ponds on the site to manage within the proposed construction timeframes
the supernatant water that is delivered to the site (refer Chapter A5) to complete the project. This
during the reclamation process. assessment of dredging plant informs the design of
all temporary infrastructure required to support the
This section outlines the likely designs of temporary
dredging and reclamation process as all temporary
works on the site based upon reasonable
infrastructure is dependent upon the type, style,
assumptions on the type and size of the dredge
size, capacity and operation of the dredge.
(refer to section 4.19). Minor temporary works
such as Contractor access roads are discussed in
Chapter A5.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-158
FOR PUBLIC COMMENT
4.19.2 Previous Dredging/Reclamation at 1. A large TSHD with direct pumping:
Brisbane Airport
Extracting the material from the sea bed;
There have been two signicant dredging/
Storing the extracted material within the hopper
reclamation projects undertaken on the
of the dredge;
Brisbane Airport site:
Sailing to a designated mooring/pump-out site;
The rst dredging/reclamation was undertaken
and
in the early 1980s by the Australian Government
(Department of Works) to establish the current Pumping the material directly to the project site
domestic terminal and runway and taxiway system. using on board pumps.
This project required approximately 16 Mm3 of
sand dredged from Middle Banks in Moreton This dredging work method relies on the use
Bay. The dredging method employed for this initial of a large trailer suction hopper dredge that is
dredging required the use of two dredges and the capable of holding sufcient material within the
Boggy Creek rehandling basin. A Trailer Suction hopper of the dredge and has sufcient pumping
Hopper Dredge (TSHD) Humber River extracted power to pump sand material directly to the
sand from Middle Banks and deposited the sand project site.
into a rehandling basin constructed in the mouth
of Boggy Creek (in the Brisbane River). From this 2. A large TSHD with rehandling:
rehandling basin, a Cutter Suction Dredge (CSD)
Extracting material from the sea bed;
Wombat extracted the sand from the rehandling
basin and pumped it directly to the project site in a Storing the extracted material within the hopper
manner similar to that described as work method of the dredge;
two (refer section 4.19.3).
Sailing to a designated rehandling basin that is
The second dredging/reclamation was constructed to contain the dredged material in
undertaken during the development of the order that it can be rehandled;
International Terminal (circa 1990) where
approximately 4 Mm3 of sand was dredged from Dumping the extracted material into the
Middle Banks and placed upon the current site rehandling basin where it is contained
of the international terminal. As with the previous temporarily;
dredging campaign, the Boggy Creek rehandling Using a CSD to continuously extract material
basin was used in rehandling sand extracted from the rehandling basin; and
from Middle Banks. The extraction at Middle
Banks was by two TSHDs (Lelystaad and Pump the material directly to the project site
Resolution) and the rehandling was by a using on board pumps.
CSD (Kunara).
This dredging work method uses two dredges
Since the dredging/reclamation for the International and relies on the establishment of a large
Terminal Project, the Boggy Creek rehandling basin rehandling basin in a suitable location, close
has been lled with spoil materials with some levels to the project site. The rehandling basin is an
of contamination and it is unsuitable for use as a excavated basin within the sea bed and acts to
rehandling basin. contain all of the dredged material temporarily
while the material is rehandled to the project site.
4.19.3 Types of Dredging Work Methods
This work method allows for the continuous (or
There are two main types of dredging method near continuous) supply of dredged material from
available to this project. Both work methods have the rehandling basin to the project site.
different requirements in terms of temporary works
and potential environmental impacts as follows:

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-159
FOR PUBLIC COMMENT
Both of these options are possible and can deliver 4.19.4 Design Dredge
the required ll material to the project site. The use
of a large TSHD using a direct pump-out to the In considering the preferred dredging work method
project site (work method 1) is the preferred method of extraction by TSHD and direct p
for this project. Direct pumping from a TSHD ump-out to the project site and the limited dredging
provides the most efcient method of sand delivery, eet that is likely to be available to complete the
with the highest production rate and lowest cost. works, an assessment of the dredging eet and
the specications of the preferred vessels was
Direct pumping from a TSHD also avoids the undertaken with a view to selecting a design
requirement to construct a rehandling basin. dredge that would be used in the design of all
An assessment of reusing the previous rehandling temporary works.
basin at Boggy creek was completed and would
require relocation of approximately 1.1 Mm3 of This approach will require the contractor to conrm
marine silts and clays. The environmental issues the design of temporary works once a dredge
associated with dredging the marine silts and is selected during procurement of the dredging/
clays would prove difcult to manage during reclamation.
establishment of the rehandling basin. In addition, Within the dredging eet of TSHDs available to
the use of a large TSHD is expected to be more the project, there are a number of different sizes of
efcient and will provide a higher production rate TSHDs, which generally relates to the length, hopper
than work method two. The higher production rate size and dredging mark (or draught) of the dredge.
will result in a shorter production period and lower Table 4.19 shows the available TSHDs that may be
cost per cubic metre of material. suitable for use on the project. When assessing the
On this basis, the use of a TSHD directly pumping suitability of the available dredges, several physical
to the project site is the preferred dredging work constraints were considered including:
method for this project. Hopper volume (which relates to the production
rate of the dredge and how long it will take to
reclaim the site);

Table 4.19: Physical Characteristics of the Dredge Fleet.

Class of Vessel Name Operating Hopper Volume Dredging Dredge Length


TSHD Company (cubic metres) Mark Draught Pumps kW Overall
(metres) Discharging (metres)
Jumbo Vasco Da Gama Jan De Nul 33,125 14.60 16,000 200.66
Jumbo WD Fairway* Boskalis 35,508 12-15 10,000 232.35
TSHD
Large Queen of the Boskalis 22,258 10-12 12,000 171.60
TSHD Netherlands*
Large Pearl River (new) Dredging 24,000 (new) 10.8 14,000 182.00
Pearl River (old)* International 17,000 (old)
Large Queen of Penta Ocean 24,000 10.5 12,000 166.70
Penta-Ocean
Large HAM 318 Van Oord 23,000 13.00 11,000 176.00
Large Rotterdam Van Oord 21,656 11.33 12,000 180.40
Large Volvox Terranova Van Oord 20,016 11.20 12,200 164.10
Medium Gerardus Mercator Jan de Nul 18,047 11.51 14,000 152.20
Medium Nile River Dredging 16,989 10.59 13,786 149.43
International
Medium Amsterdam Van Oord 16,830 10.37 10,400 159.65
Source: Baggerman Associates
* TSHD which have worked previously in Australia.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-160
FOR PUBLIC COMMENT
Vessel draught (which relates to the dredges The key ndings of the Study were that the direct
ability to navigate through the existing channels impacts of large scale sand extraction scenarios
into the Brisbane River); and such as disturbance to benthic fauna, potential
degradation of water quality and impacts on
Dredge pumping power (which relates to the
Indigenous cultural heritage and shing activity
dredges ability to pump the reclaimed material were considered to be relatively minor and of a
to the project site). temporary nature. The indirect impacts associated
Dredging efciency is typically optimised by with the long term removal of shallow sand banks
adopting the largest dredge vessel class that can considered in the Study including changes
access the reclamation site and that will allow to wave conditions, tidal currents and potential
adequate control at the pump-out location to be alterations to ecological communities were also
maintained. This strategy has been adopted for expected to be small.
reclamation associated with the NPR. On the basis of these ndings, the Queensland
The jumbo class dredges listed in Table 4.19 have Government indicated it would support a range
a dredging mark or draught of around 15 m. The of proposed sand extraction activities from the
channels leading into the Brisbane River have a total available sand resources in Moreton Bay
minimum declared depth of 14 m (below LAT) and (approximately 3,770 Mm3) subject to environmental
are unsuitable for continuous use of a Jumbo class impact assessment processes. The BAC was
dredge. If a Jumbo class dredge was used it would directed to investigate the Middle Banks area of
be conditional on tidal range and payload and would Moreton Bay in relation to the NPR infrastructure
not prove economical over the life of the project. project.

The large class TSHD have a draught of around 4.20.2 Project Requirements and
12 m, which is suitable for continuous use in the Investigations
channels leading into the Brisbane River. These large
class dredges also have sufcient pumping power A volume of approximately 15 Mm3 of
to pump the dredged material a distance of around unconsolidated marine sand is required to be
7 km, without the use of a booster station. In addition, placed on the NPR site in order to:
their hopper volume provides adequate production Consolidate the soft compressible soils found on
rates to complete the dredging and reclamation task the project site;
economically and within a suitable timeframe.
Provide a stable platform to enable the
On the basis of this assessment, a typical large construction of the runway pavements; and
class dredge will be used as the design dredge for
the preliminary design of all temporary works on the Elevate the site to provide ood immunity.
project.
Figure 4.20a shows the Middle Banks investigation
area nominated in the EIS in relation to other
4.20 Dredging Location and Dredge features in Moreton Bay such as Moreton Island.
Footprint Selection

4.20.1 Background

As outlined in Chapter A3, the Queensland


Government undertook a Moreton Bay Sand
Extraction Study from 2001-2005 to determine the
environmental and economic issues relating to sand
extraction in the Bay.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-161
FOR PUBLIC COMMENT
Figure 4.20a: Middle Banks Investigation Area.

el
nn
Central

ha
lC
Banks

ar
Pe
Investigation area
Middle Banks
Redcliffe

Moreton Island
Moreton Bay
Bramble Bay
Port
reclamation
area
Mud
Island
Proposed
Runway Luggage Point
Brisbane
Airport St Helena Island
0 1 2 4 Kilometres

A series of investigations were carried out in the Water quality modelling to assess the impact
Middle Banks area of Moreton Bay in 2005 and of any plume caused by the dredge during
2006 as part of this EIS/MDP process to determine dredging.
where in the Middle Banks area the required volume
of material could be sourced, and to assess the A detailed description of the ndings of each
impacts the removal may have on the marine investigation and the resultant modelling or
environment. In summary, investigations included: assessment is presented in Volume C.

Bathymetric Survey (25 m spacing) over 4.20.3 Proposed Dredge Footprint


Middle Banks to conrm ocean depth and
Based on the information obtained from the
ocean surface contours;
investigations, a dredge footprint at Middle Banks
Sub-bottom proling through seismic surveys has been identied from which the required 15 Mm3
to derive an interpreted level of the Pleistocene of ll material will be sourced and is shown in
surface at Middle Banks; Figure 4.20b.

Offshore geotechnical sampling using continuous


marine vibrocoring (16 boreholes sampled to an
average depth of 10.4 m);

Seagrass and benthic habitat survey of


Middle Banks using an underwater video
system; and

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-162
FOR PUBLIC COMMENT
Figure 4.20b: Location of Dredge Footprint at Middle Banks (Source: Arup).

N
Middle Banks
Dredge Footprint

Middle
Banks

Moreton Island
Moreton Bay

Port of
Brisbane

Luggage Point
Brisbane
Airport
0 1 2 4 Kilometres

The footprint has been selected on the basis of Avoiding potential conicts with other users
the following: of the Bay. To reduce impact/conict with
other users of the Bay, the proposed dredging
Targeting Holocene (clean) sand deposits
footprint avoids the areas within Middle Banks
that will produce superior quality ll that are currently used by several commercial
material. The absence of ner silts and clays extractive industry operators (in approved permit
in the dredged material minimises water quality areas) and an area along the southern portion of
impacts from turbidity at Middle Banks during Middle Banks known to be used by commercial
dredging and reclamation. shing trawlers.
Avoiding or minimising impacts to marine Maintaining water quality. Numerical
ecology. The dredge footprint has been modelling has been undertaken as part of the
selected to avoid areas of high environmental Draft EIS/MDP to assess and recommend best
signicance within Middle Banks to the greatest management practices to minimise impact of
extent practicable. The overall impacts on turbid plumes on water quality and ecological
marine ecology are minimised by selecting a values.
narrow and deep dredge footprint rather than
a shallow footprint over a larger area. Minimising impacts to coastal processes.
Numerical modelling has been undertaken as
Logistical advantages to the dredge part of the Draft EIS/MDP to assess any impacts
contractor. A long, linear footprint in water on physical processes such as waves and tidal
greater than 8 m depth minimises the duration of currents that may cause erosion or other impacts
each dredge cycle and minimises the overall time on nearby shorelines.
required to complete the dredging campaign.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-163
FOR PUBLIC COMMENT
Avoiding potential impacts on cultural sites and associated sand delivery pipeline
heritage. Restricting dredging to Holocene alignments from the identied mooring to the
age sediments reduces potential impacts on construction site.
indigenous cultural heritage values that may
exist in the older Pleistocene surface. 4.21.2 Investigation into Mooring Sites

A full discussion of these factors is contained in Investigation of the suitability of the mooring sites
Volume C. was undertaken to identify a preferred location
for the dredge mooring and the pipeline route.
The investigation was undertaken to identify
4.21 Mooring Locations and all the major engineering, dredge operations,
Pipeline Route Options environmental and logistical issues with each of the
locations. The identication of a preferred mooring
location is a balance between the attributes of the
4.21.1 General
mooring location and the pipeline route.
Prior to beginning investigations into potential
The four mooring location and pipeline alignment
mooring locations for the dredge, a broad overview
options are shown on Figure 4.21 and are
of possible dredge mooring locations was
described as:
undertaken based upon previous experience with
dredging at the Brisbane Airport and the constraints Boggy Creek;
placed upon the site in terms of Port operations and
existing bathymetry of the Brisbane River and the Koopa Channel;
nearshore areas of Moreton Bay.
Juno Point; and
To determine potential mooring options the following
Luggage Point.
basic requirements for the dredge mooring were
identied: Regardless of the mooring location, operation of
the dredge will require construction of a temporary
Maximum dredge pumping distance between
mooring to allow the dredge vessel to moor safely
6 km and 7 km;
while discharging. The mooring could include a
Water depth for independent dredge piled structure located in the Brisbane River, in
manoeuvring around 13 m to 14 m (below LAT); suitable water depth to allow dredge access during
all parts of the tidal cycle. Alternatively, use of
Protection from prevailing weather conditions temporary anchor blocks may also sufce. A nal
would be an advantage; and mooring design would need to await nomination of
the dredge by the successful dredging contractor
Alignment of the delivery pipeline through areas
after tender. From the mooring to the project site,
with suitable geotechnical conditions to allow
the pipe route will require an access track and low
maintenance access.
height embankment for the length of the pipeline.
Upon considering these basic requirements, it was The low height embankment and access track will
concluded that the mooring would be limited to be constructed from granular materials. Both the
sites within the Brisbane River mouth either in or mooring structure and access track/embankment
immediately adjacent the main shipping channel will be temporary in nature.
as all other near-shore areas did not provide deep
All four pipeline alignments from the mooring
water access within the required pumping distance.
facility were designed to have the same destination
Further investigations into likely mooring locations within the Airport site. This point is known as the
led to the identication of four potential mooring convergence point and is located between the end of
the existing 01/19 runway and the end of the 14/32
runway. This convergence point is considered the

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-164
FOR PUBLIC COMMENT
Figure 4.21: Dredge Mooring Location and Pipeline Routes.

N
0 100 200 300 400 500m

NEW PARALLEL RUNWAY DRAFT EIS/MDP NEW PARALLEL RUNWAY DRAFT EIS/MDP A4-165
FOR PUBLIC COMMENT FOR PUBLIC COMMENT
most appropriate location for the dredge pipeline to extensive dredging through the shallow river oor
cross beneath the proposed taxiway link from the surrounding the rehandling basin to provide an
existing runway and the 14/32 taxiway. This crossing access slot for the dredge vessel into the proposed
point will be carefully designed to ensure aviation mooring. The amount of spoil generated from
operations are not compromised. From this location capital dredging of the area would be approximately
the pipeline will head north-west to the remainder of 250,000 cubic metres (m3) of material. Geotechnical
the reclamation site. analysis of this area shows acidity and heavy
metals are present in the upper layers of the marine
In the restricted access areas at the end of the sediments, as well as soft marine clays from
runways the pipeline will be clear of the Runway End recent deposition during storm and ood events.
Safety Areas (RESA) and the Obstacle Limitation If dredged, the contaminated silts and marine clays
Surface (OLS). The pipeline will be specically would need to be disposed and stored in a dredge
designed to ensure conict with existing services spoil treatment area above high water mark.
and the existing approach lighting systems is
minimised. The potential to increase the pipe Pipeline route
wall thickness or the composition of the pipe will
The sand delivery pipeline from the mooring at
be investigated to reduce maintenance access
Boggy Creek would pass under the existing Bulwer
requirements for the pipeline.
Island oil pipeline. Buoyancy devices would be
Further and more detailed information about required to oat the sand delivery pipeline between
existing conditions at each of the mooring locations the shoreline adjacent to the vessel mooring location
is contained in the various chapters of Volume B and the dredge vessel itself. The sand delivery
Airport and Surrounds. pipeline would cross the foreshore and run parallel
with the southern boundary of the Luggage Point
4.21.3 Mooring Site Assessment Wastewater Treatment Plant.

4.21.3.1 Boggy Creek The delivery pipeline would also cross Main Beach
Road (Myrtletown), which is the only access for
Boggy Creek estuary is located to the west of the
the Luggage Point Wastewater Treatment Plant.
Brisbane River and opposite the Port of Brisbane.
This crossing would need to be designed and
The creek is cut off from marine trafc by a pipeline
constructed to allow access to the plant at all times
used to transport oil from tankers to the Bulwer
Island Oil Renery. The Boggy Creek location is With the exception of the narrow mangrove-lined
a sheltered location, removed from the shipping Jubilee Creek, the pipeline route does not traverse
channels. The total length of the sand delivery areas with signicant or noteworthy biodiversity value.
pipeline from a potential mooring at Boggy Creek
and the convergence point on the runway site is Summary
approximately 2,400 m. The use of Boggy Creek requires capital dredging
Mooring location of contaminated marine sediments to establish
a suitable mooring. Storing, managing and
Boggy Creek was used during the previous two stabilising this contaminated material would be
sand reclamation projects undertaken at Brisbane difcult and expensive.
Airport. The dredging method previously employed
required a rehandling basin at the mouth of Boggy The pipeline route from Boggy Creek to
Creek. The rehandling basin is a deeper basin the Airport is suitable and any access and
dredged into the oor of the creek to enable sand to environmental issues associated with its
be deposited temporarily prior to rehandling to the construction can be managed.
reclamation area. The basin does not allow sand
On the basis of disturbing, storing and managing
to ow into the river and is surrounded on all sides
contaminated silts during capital dredging, the
by the higher river oor. Boggy Creek will require
use of Boggy Creek is not preferred.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-166
FOR PUBLIC COMMENT
4.21.3.2 Koopa Channel The direct disturbance and indirect impacts on
mangroves from installation of the pipeline and
Koopa Channel is an old bar cutting located
access track would be signicant with the Koopa
north-east of the entrance channel to the Brisbane
Channel option. The intertidal at area is also
River. The site is the furthest from the proposed
identied as a signicant wader bird roosting area
reclamation site, with a required maximum pumping
which would be disturbed during installation of the
distance of 7 km, which is at the maximum extent of
pipe and during maintenance activities.
the economic capabilities of large TSHDs.
Summary
Mooring location
The mooring location is exposed and may
In order to moor a large TSHD clear of the main
not allow all weather operation of the dredge.
shipping channel it would be necessary to dredge
Capital dredging required is extensive and the
a slot clear of the channel. This capital dredging
contaminated dredge spoil would be problematic
would produce an estimated volume of 130,000 m3
to manage. Clean materials extracted during
of dredge spoil. Geotechnical investigations show
capital dredging could be managed on the
the upper layers of the marine sediment (upper
Airport site with some of the materials potentially
2 m) at the Koopa Channel location contain some
suitable for use within the runway project.
heavy metals (Nickel) but lower net acidity due
to natural buffering. Marine clays and coarse to The pipeline route for the Koopa Channel option
medium grained sand were found at deeper levels results in direct disturbance of mangrove habitat
in the boreholes surveyed at the site. Contaminated and wader bird habitat. The pipeline route
material dredged during the establishment of the would prove difcult and expensive to construct
dredge slot would need to be transferred to a spoil and decommission.
disposal area on land above high water mark. Clean
clay material and gravely sand could be stored and On the basis of the exposed mooring and
re-used on the Brisbane Airport site. environmental impacts associated with the pipeline,
the Koopa Channel option is not preferred.
Of the four mooring locations, Koopa Channel is
4.21.3.3 Juno Point
most exposed and vulnerable to weather conditions
that may potentially impact on the dredge pump-out Juno Point is located to the north of Luggage Point
operations. The site would require heavier breasting outside the main shipping channel. The site is
dolphins and additional fore/aft moorings during slightly closer to the reclamation site than the Koopa
adverse conditions. Channel option but still would require a pumping
Pipeline route distance of greater than 6.3 km.

Mooring location
The sand delivery pipeline for Koopa Channel would
travel in a south-west direction crossing the foreshore As with Koopa Channel, in order to moor a large
at Juno Point. This alignment requires the pipeline to TSHD clear of the main shipping channel at Juno
cross an area of land with unsuitable soft soils which Point it would be necessary to dredge a slot clear of
would restrict access for pipe maintenance and the channel. This capital dredging would produce
construction of the associated access road. an estimated volume of 220,000 m3 of dredge spoil.
A corridor of mangroves would need to be cleared Geotechnical investigations show the upper layers
at Juno Point to accommodate the pipeline. The of the marine sediment at Juno Point are similar to
total length of pipeline that would traverse the Boggy Creek with elevated levels of Tributyl-Tin (TBT)
mangrove areas is about 900 m. The pipeline would and Mercury (Hg). The soils also show high potential
also need to traverse Jubilee Creek. The channel acidity. Marine clays and silty sand were found at
crossing would be achieved by using a series of deeper levels in the marine sediment. The material
wooden piles and cross members to elevate the removed during the establishment of the dredge
pipeline above the creek.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-167
FOR PUBLIC COMMENT
slot would need to be transferred to a spoil disposal Pipeline route (Juno A) option results in direct
area on land above high water mark. Clean clay and disturbance of mangrove habitat and wader bird
sand material could be stored and re-used on the habitat. The pipeline route would prove difcult
Brisbane Airport site. and expensive to construct and decommission.

Juno Point is exposed to adverse weather conditions Pipeline route (Juno B) could be constructed and
that may potentially impact on the dredge pump-out any access and environmental issues could be
operations. This would need to be considered in the managed during the dredging campaign.
design of the mooring dolphins at this location as
On the basis of the exposed mooring location, the
outlined with the Koopa Channel option.
difculty in handling the dredge spoil from capital
Pipeline route dredging the Juno Point options are not preferred.

Two pipeline options from the Juno Point mooring 4.21.3.4 Luggage Point
location were explored in the preliminary design
(Juno A and Juno B). The Luggage Point site is situated to the south of
Luggage Point, between the treatment plant outfall
The rst (Juno A) is directly west over the intertidal and the oil tanker wharf. Initial discussions with
mud ats and mangrove area. Similar to the Koopa the Harbour Master indicate that this location for
Channel alignment, this pipeline alignment will cross a discharge point will not cause adverse impact
areas of land known to have unsuitable soft soils to Port of Brisbane shipping operations. The
that will make the construction and maintenance of total length of the sand delivery pipeline from the
the sand delivery pipeline problematic. Placement mooring to the convergence point is 2,400 m with a
of the pipeline in this environment would involve maximum pumping distance of 6 km.
the direct disturbance as well as indirect impacts
Mooring site
on mangrove communities. The intertidal ats at
Juno Point are identied as a signicant wader The proposed mooring site is located at the edge
bird roosting area which would be disturbed of the swing basin for the Port of Brisbane and as
during installation of the pipe and during manned such the water depth is sufcient for the dredging
maintenance activities. vessel to moor without additional capital works
dredging. Preliminary investigations indicate that the
The second option (Juno B) from the mooring
dredge operation at Luggage Point will not adversely
at Juno Point is to oat the pipeline in a westerly
interfere with the operations of the swing basin
direction towards Luggage Point. Buoyancy devices
or the adjacent oil berth. The Luggage Point site
would oat the sand delivery pipeline between the
affords some protection from adverse weather and
shoreline and the dredge vessel. This alignment
should allow all weather operations of the dredge.
will impact a small section of mangroves but would
largely minimise ecological impacts. From this Pipeline route
location the pipeline will follow the same route along
the Luggage Point Wastewater Treatment Plant Buoyancy devices will be used to oat the sand
(described below for the Luggage Point alignment). delivery pipeline between the dredge vessel
and foreshore. The pipeline route will cross the
Summary wastewater outfall channels (open concrete
structures) and precede north-west over the existing
The mooring location at Juno Point is exposed
drying beds, thereby avoiding the low lying silt
and may not allow all weather operation of the
basin to the north-east. A steel structure will be
dredge. Capital dredging required is extensive
constructed over the existing outfall channels so that
and the contaminated dredge spoil would be
the outfall channels are not impacted (refer section
problematic to mange. Clean materials extracted
4.23). Initial indications from Brisbane Water indicate
during capital dredging could be managed on the
that this route will be acceptable and any access/
Airport site with some of the materials suitable for
egress and operational issues can be managed.
use within the runway project.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-168
FOR PUBLIC COMMENT
Construction of the pipe route may involve Suitable ground conditions for the pipeline; and
disturbance of ll materials placed during previous
Relatively sheltered site.
Airport developments or during operation of the
Luggage Point Wastewater Treatment Plant. The pipeline route from this location to the
Specically, the pipe route traverses an area used to reclamation site is the most direct of the options
dispose of biosolids from the wastewater treatment and does not require a booster station. The land
plant. The biosolids area is capped and the pipe is owned by Brisbane Water and initial discussions
route will traverse this area with minimal disturbance suggest that the Luggage Point Wastewater
with the pipeline placed above the existing surface Treatment Plant will accommodate this pipeline
wherever possible. Any disturbed materials will within their facility.
be tested and treated appropriately during this
construction of the pipeline. As with the Boggy A more comprehensive comparative analysis of
Creek pipeline alignment, with the exception of the benets and disadvantages of the four mooring
the narrow mangrove-lined Jubilee Creek drain, locations and pipeline routes is contained in
the pipeline route does not traverse areas with Chapter B1.
signicant or noteworthy biodiversity value.

Summary 4.22. Dredge Mooring Design


The use of Luggage Point requires no capital
dredging and this is a signicant advantage of 4.22.1 Dredge Operations
this proposal.
During operations, the dredge will interact with
The pipeline route from Luggage Point to commercial shipping into the Port of Brisbane.
the Airport is suitable and any access and Marine safety will be of interest to the Harbour
environmental issues associated with its Master who will monitor the dredge operations
construction can be managed. Special attention for compliance with all statutory requirements.
will be required to ensure the BCC Wastewater Under Queensland Legislation, the dredge will be
Treatment Plant can be operated without operated within the Brisbane pilotage area and
impediment during the dredging campaign. must either carry a licensed marine pilot or be under
the command of a master who holds a pilotage
On the basis of the relative ease of establishing exemption certicate for the area. Traditionally, the
the mooring and the suitability of the pipeline majority of ships berth into the current to ensure
route, this option is preferred. steerage at low absolute speeds and increase safety
during mooring. The mooring will enable the dredge
4.21.4 Preferred Option to berth into the current on both ebb and ood tides
The preferred location for the discharge point of the and under all possible tidal and weather conditions.
dredged sand is at Luggage Point (refer Figure 4.21). The preferred mooring location at Luggage Point is
The advantages of this location include: located on the north-west side of the swing basin
No capital dredging required; for the Port of Brisbane. The swing basin has a
declared depth, at lowest astronomical tide (LAT), of
No clearing or trimming of mangroves required 14 m which is sufcient to allow a fully laden dredge
except mangroves fringing the Jubilee Creek to moor at any time during the tide cycle. The
Drain that will be restored following completion of dredge will be in operation 24 hours per day for the
the dredge pump-out activity; duration of the reclamation period (between 12 and
18 months refer Chapter A5 Construction). The
Reduced impact on tidal creeks, intertidal ats
proposed Luggage Point mooring will only be used
and public access routes;
as the discharge point for the dredge. All servicing,
refuelling and any maintenance works on the dredge
will be carried out at a berth in the Port and will be

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-169
FOR PUBLIC COMMENT
Figure 4.22: Dredge Mooring Site Plan.

SCALE A 0 100 200 250m

SCALE B 0 20 40 60 80 100m

NEW PARALLEL RUNWAY DRAFT EIS/MDP NEW PARALLEL RUNWAY DRAFT EIS/MDP A4-170
FOR PUBLIC COMMENT FOR PUBLIC COMMENT
coordinated by the Dredge Captain. No servicing experience, the length of piles to a consolidated
or maintenance works will be carried out at the Pleistocene basement (rm surface) will be in the
Luggage Point mooring. order of 30 m.

The dredge mooring must be suitable as a temporary To accommodate the design dredge, the proposed
structure for use during the reclamation only. discharge mooring will be constructed from two
breasting dolphins located to suit the particular
4.22.2 Mooring Layout and Operation dredge (refer Figure 4.22). The two dolphins will be
located at about third points of the berthed dredge.
The proposed layout of the dredge mooring has
Flexibility in the design will enable dredge lengths
been determined by the proximity of a number of
up to a maximum of 200 m.
existing features:
Each dolphin will typically be constructed from
The BP Crude Oil Wharf;
twelve 1,000 mm diameter by 16 mm wall thickness
The commercial shipping channel; steel piles driven to a minimum depth of 16 m or
to a suitable set. These steel piles will be placed
The efuent outfall structure from BCCs Luggage on a 3 m grid. As these dolphins are temporary
Point Wastewater Treatment Plant; structures, no concrete pile caps are proposed and
instead twin steel frames will hold the piles in place
The navigation lead marks No. 3F and No. 3R
and transfer the dredge berthing loads to the piles
which dene the channel in the Pelican Banks
via a twin cone parallel motion fender. These fenders
Reach; and
are relatively soft to reduce the magnitude of berthing
The location of BCCs rising sewer main from the reactions on the dolphins, in the light of the poor
Port of Brisbane to the Luggage Point Wastewater foundations for these structures. A typical dolphin
Treatment Plant beneath the Brisbane River. will require a 150 tonne capacity bollard for mooring
of the dredge, mounted on the upper transfer frame,
The dredge mooring is positioned to minimise and a top platform and access ladder for handling of
impact upon the above facilities and to minimise mooring lines and maintenance.
interaction between the dredge during operations/
reclamation. The BCC sewer rising main passes Lighting the mooring dolphins during the hours of
through the proposed site of the discharge berth darkness will be to the requirements of the Regional
as shown on Figure 4.22. This existing pipeline is Harbour Master incorporating standard solar
a 350 mm nominal diameter polyethylene pipeline powered ashing lights, the details of which will be
between Fisherman Islands and Luggage Point determined during detailed design. On completion
installed by directional drilling during 2000/2001. of the dredging operation the mooring dolphins will
The approximate location of this pipeline is known be dismantled and the steel piles extracted to return
based on as constructed plans from BCC, however the site to its previous condition.
a survey to establish its exact location will be
The mooring design assumes the dredges discharge
required prior to construction of the mooring to
point is located on the bow of the ship and this
ensure that the proposed works do not interfere
discharge point will mate with a oating exible
with this pipeline.
discharge pipeline when the dredge berths.
The ground conditions in the vicinity of the A single anchor pile will secure the connection end
mooring is underlain Holocene sediments of the oating discharge pipeline when the dredge is
comprising a muddy sand surface layer about absent. Allowance in the design has been made for
1 m deep and a muddy sand uvial delta deposit the dredge to moor in either direction (upstream or
up to 7 m deep overlying a deep estuarine silt/clay downstream) by including two oating pipelines which
deposit. These materials are prevalent in the lower connect to the main discharge pipeline via an
Brisbane River area and are extremely weak in on-shore valve station. The dredge crew will operate
engineering terms. Based upon the preliminary the valve station to direct the ow of supernatant
geotechnical investigations and on regional water at the commencement of each pump-out cycle.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-171
FOR PUBLIC COMMENT
BCC has noted that scour and erosion occurs on The pipeline selection, installation, maintenance
the shoreline adjacent the Wastewater Treatment and removal will be the responsibility of the
Plant as a result of vessel wash, predominantly dredging contractor.
associated with vessels manoeuvring in the swing
basin. To ensure that the dredge does not cause Typically, the pipeline specication is as follows:
erosion on the shoreline, concrete matting (or An average pipeline diameter of 1,000 mm;
similar treatment) protection will be installed on the
shoreline to protect it against vessel wash. The The pipeline will be constructed from 12 m to
detail of this protection works will be determined 15 m lengths of pipe supplied by truck;
during detailed design of the mooring.
The pipe lengths will be bolted and the joints
Bed erosion is also possible below the water level sealed by gaskets;
against the edge of the existing swing basin. Some
The pipeline will be most efcient when laid
minor bed erosion is evident adjacent the oil tanker
straight, with a minimum number of bends;
berth, possibly as a result of propeller wash from
the vessel itself and tugs manoeuvring the oil The pipeline will be rotated at regular intervals
tankers into place. To combat the possibility of during the delivery phase by conventional
erosion caused by the bow thrusters on the dredge, excavators or cranes;
concrete matting will be considered along the
edge of the swing basin, immediately adjacent the The pipeline will require a 5 m wide gravel
location of the thrusters. In a similar manner, if the formation and a 5 m wide access track to be
existing sewer, constructed beneath the Brisbane constructed along its entire length suitable for
River, is located in an area where some erosion is installation, maintenance, inspection and rotation
possible, concrete matting or other protective works of the pipeline; and
can be installed to ensure that the sewer is not
Fencing will be provided along the length of the
exposed or damaged during dredging.
pipeline with screening where required.

4.23 Pipeline Design and Temporary 4.23.2 Pipeline through Luggage


Structures Point Wastewater Treatment Plant

This pipeline alignment crosses into and out of


Luggage Point Wastewater Treatment Plan. To allow
4.23.1 Introduction
this pipeline to traverse the plant without causing any
The dredged sand will be transported from the impact to the operation of the plant a road crossing
moored dredge to the project site via a continuous and an elevated pipeline structure are required.
steel pipeline. This pipeline will connect to the
The elevated pipeline structure is required to
dredge discharge point on the bow of the ship via
cross the Luggage Point Wastewater Treatment
one of two exible rubber oating lines located at
Plants twin concrete efuent channels which form
each end of the mooring. At the foreshore these
the southern boundary of the plant. The efuent
oating lines are connected to the main discharge
channels are founded on the natural soil and have
pipeline through a valve station and Y piece. From
experienced some differential movement. To avoid
this Y piece a single steel pipeline will be installed
any further movement of the efuent channels the
to the project site on an alignment which passes
discharge pipeline will be supported above the
through Luggage Point Wastewater Treatment Plant,
channels and at a sufcient distance from them to
over an existing open drain and through part of the
avoid any additional loading.
operating Airport.
The discharge pipeline will be generally laid on
the ground surface. At the channel crossing,
the pipeline will be elevated on embankments to

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-172
FOR PUBLIC COMMENT
ensure a 500 mm minimum clearance between the 4.23.3 Airport Drain Crossing
pipeline and the top of the efuent channel walls
is maintained. Gabion walls at each end of the The pipeline continues from the boundary of the
crossing are proposed to control the movement of ll Wastewater Treatment Plant, along the existing
against the existing works and to limit the free span ground surface to the existing Airside drain. At this
length. A concrete seat at each abutment will fully location a signicant drainage channel, which drains
support the pipe without requiring pipe stiffening. the eastern side of the Airport, needs to be crossed.
This existing tidal channel has well developed
The pipeline crossing will be constructed from mangroves growing on either side.
approximately 48 m of fully welded pipeline, with
25 m of this pipeline being a clear span over the The pipeline crossing for this drain will be similar to the
efuent channels. A thicker pipe may be required crossing of the efuent outfall channels. The pipeline,
to allow for pipe abrasion as rotation of the pipe in pedestrian bridge and/or pipe bridge will be threaded
this location will not be feasible. Bare steel pipe through the mangroves to minimise the environmental
should be acceptable as the pipe is accessible for impact and will span between the grassed banks
monitoring and maintenance. of the channel on each side. On completion of the
reclamation process the pipeline will be recovered and
A steel pedestrian bridge with security fence and the mangroves reinstated.
gate will be required alongside the pipeline for
inspection of the pipeline and to enable dredging 4.23.4 Airport Runway and Taxiway
personnel to cross the efuent channels. Details Crossing
of a self-supporting pipe arrangement are included
The pipeline alignment continues northwest
in Figure 4.23. Alternatively, a pipe bridge could
where it is required to cross the end of the main
be provided and the standard discharge pipeline
01/19 runway approach and pass under two
supported on this bridge. A cross-section of a
taxiways. Due to the risk of any pipeline incident
possible pipe bridge is also included in Figure 4.23.
affecting aircraft operation, no failure of this section
A Council access road runs along the north side of discharge pipeline can be tolerated and access to
of the efuent channels to the efuent outfall at the pipeline will be restricted to periodic inspections
Luggage Point and active sludge lagoons north of by the contractor.
the access road. It is necessary to maintain this
The pipeline throughout this section will be a straight in
access track during the reclamation period and the
alignment and polyurethane lined, anged steel pipe.
design allows for a temporary access road crossing
It will be installed during a runway closure. An access
which passes over the dredge pipeline.
road will not be provided along this length of pipeline
This ramped road crossing over the pipeline will be as access to this area is restricted and all surface
located in the vicinity of the sealed road leading to inspections will be undertaken on foot.
the truck washdown area with the Luggage Point
If properly designed, this pipeline will not require
Wastewater Treatment Plant and connect back to the
maintenance during the reclamation but will require
existing access track via a temporary access road.
monitoring on the polyurethane lining. Monitoring
The crossing will be constructed by lling either side
would be undertaken using a video camera
of the dredge pipeline with selected ll. This will be
passed through the pipeline. The ability of the
capped with gravel and asphalt to form a ramp. This
polyurethane lining to resist sand slurry abrasion,
temporary ramp and diversion will allow access to be
combined with regular monitoring of the condition
maintained into the truck washdown area, efuent
of the polyurethane lining, will provide sufcient
discharge channels and sludge lagoons.
conrmation of the performance of this pipeline.
Following completion of the reclamation operation,
Following completion of the dredging programme,
the pipeline will be removed, the elevated structure
this pipeline can be recovered where possible. A
dismantled and the sealed pavement and gravel
short section of the pipeline, installed beneath
access track reinstated.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-173
FOR PUBLIC COMMENT
Figure 4.23: Luggage Point Wastewater Treatment Plant Outfall Channel Crossing.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-174
FOR PUBLIC COMMENT
Taxiways A and B might be abandoned and left (refer section 4.19). The bunds that dene storage
in place for use as a future service duct. If it is within the ponds will be approximately 2.0 m
abandoned, the pipeline will be lled with sand or high, providing a maximum storage depth of
foam concrete to protect against future subsidence. approximately 1.5 m. The earth bunds will be lined
with a plastic high density polyethylene material to
minimise seepage of supernatant through the walls
4.24 Sediment Ponds
of the ponds.

Hydraulic placement methods used throughout The inlet and outlet structures of each sediment
the NPR reclamation will result in large volumes of pond are constructed within the earth bund along
reclamation supernatant water, the water used to the perimeter of the ponds. The inlets and outlet
transport sand materials from the dredge vessel of each sediment pond are used to control the rate
to the reclamation site. To assist in managing of supernatant ow into the ponds from adjacent
the quantity and quality of the supernatant water, reclamation cells and out of the ponds to the
temporary sediment ponds will be constructed Kedron Brook Floodway Drain and Serpentine Inlet
to provide short term storage of reclamation Drain receiving waters. Adjustable weir structures
supernatant. The ponds will provide storage to will be used at each inlet and outlet to provide
accommodate the interface between the 8 hour control of pond inow and outow and maintain
dredge discharge cycle and the 6 hour semi-diurnal suitable storage volume and retention time within
tidal cycle, upon which the supernatant release is the ponds. Adjustment of the weir crest height will
based (refer Chapter A5). The ponds also provide be used to control pond inow and outow.
treatment of supernatant water for removal of Localised erosion of bund material and in situ soils
entrained suspended solids prior to release to at pond inlets and outlets will be controlled by
receiving waters. construction of temporary inlet/outlet protection.
Temporary sediment ponds will be constructed The inlets and outlets to the sediment ponds will
in two locations. The southern sediment pond is be protected with rock lled wire mattresses (reno
located adjacent the Kedron Brook Floodway Drain, mattresses) over in situ soils and areas of the bund
to the south of the NPR and discharges to Kedron susceptible to erosion. The design of Kedron Brook
Brook Floodway Drain. Floodway Drain and Serpentine Inlet Drain includes
rock protection on the base of the channels to further
The northern sediment pond is located adjacent reduce the potential for erosion of bed materials
the existing 14/32 taxiway system and the existing during reclamation for the NPR.
perimeter road. The northern pond will discharge
supernatant to Serpentine Inlet Drain, which crosses Movement of supernatant in the ponds is controlled
beneath the existing 14/32 runway. Figure 4.24 by construction of ow bafes within the open water
shows the location of each temporary sediment pond. body. The ow bafes extend the ow length within
the ponds and increase the hydraulic retention
The temporary sediment ponds will be constructed time of supernatant within the ponds. These two
above the existing ground surface level. The functions of the pond bafes jointly improve the
construction of the ponds aims to minimise the suspended solids treatment performance of the
potential for disturbance of acid sulfate and ponds by providing increased time for particles
potential acid sulfate soils. Storage within the to settle from suspension. The bafes may be
ponds is provided by construction of earth bunds constructed either by formation of additional earth
along their perimeter. The volume of storage bunds within the pond perimeter, or by erection
required within the ponds is dened by the of a geotextile fabric cover over a structural frame
selection of dredge equipment and the dredging (welded wire mesh) (refer Figure 4.24).
operations. It is anticipated that the minimum
required storage volume required is approximately
230,000 m3, based on preliminary dredge selection

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-175
FOR PUBLIC COMMENT
Construction of the sediment ponds is included in
the early works phase of NPR development. While
the primary function of the ponds is to manage
supernatant during reclamation for the NPR, the
ponds will be functional during the clearing phase to
provide treatment and control of stormwater release.
Following completion of hydraulic placement
of sand ll, the ponds will be decommissioned.
During the decommissioning process the earth
bunds (constructed from in situ soil materials or
imported ll) will be excavated, the inlet and outlet
structures will be dismantled and sand ll will be
mechanically placed in the ponds, displacing any
water remaining in the ponds. Materials recovered
during decommissioning of the ponds, including in
situ soils (imported ll) used for bund construction
and rock ll from reno mattress and rock protection
will be used during subsequent civil works for NPR
construction.

A detailed discussion on the operation of the


sediment ponds is included in Chapter A5 and a
detailed discussion on water quality is included in
Chapter B8.

NEW PARALLEL RUNWAY DRAFT EIS/MDP


A4-176
FOR PUBLIC COMMENT
Figure 4.24: Sediment Pond Location.

N
N

SCALE A 0 100 200 250m


SCALE B 0 50 100 125m

NEW PARALLEL RUNWAY DRAFT EIS/MDP NEW PARALLEL RUNWAY DRAFT EIS/MDP A4-177
FOR PUBLIC COMMENT FOR PUBLIC COMMENT

S-ar putea să vă placă și