Documente Academic
Documente Profesional
Documente Cultură
installation
maintenance
operation
instructions
Carrier
Air Handling Units
39 HH 100 / 39 HH 500
January, 2000
CONTENTS
MOUNTING and POSITIONING 5
Transport 5
Storage 5
Installation 5
Outride mounting 5
Connections 5
Putting into operation 7
Airhandling units with water humidifiers 8
Airhandling units with steam humidifiers 8
CENTRIFUGAL FANS 9
Mounting 9
Putting into operation 10
ROTATING HEAT EXCHANGERS 10
Mounting 10
Putting into operation 11
COMPUTAIRS 11
Mounting 11
Putting into operation 11
OPERATION and MAINTENANCE 12
Instruction 12
Casing 12
Air filters 12
Air dampers 13
Water humidifiers 13
Eliminators 14
Suice water quantity 14
Concentration increase factor 15
Steam humidifiers 15
Heaters, coolers and heat-recovery batteries 15
Centrifugal fans 16
Sound attenuators 17
Rotation heat exchangers 17
COMPUTAIRS 18
MAINTENANCE 19
AIR HANDLING UNITS 39 HH 100 / 39 HH 500
2=CA #
Before transporting and installing the unit parts, the project draw-
ing should always be studied. In this project drawing, the di-
mensions as well as the sequence of delivery parts is indicated.
Outside mounting
Airhandling units, that are mounted outside, are generally trans-
a = max. 45 ported as described above. Due to this installation in open air,
extra care has to be taken of the cover of the unit and the connec-
a
tion of the unit on the structural roof.
For watertight finishing of the top of the unit, extra provisions
have been made on the several delivery parts. With simple
means, the seams, that have arisen after the sections were
positioned against each other, can be finished.This should
be done with great care in order to prevent flooding at a Iater
stage. Precise instructions about finishing the roof are sup-
plied per project.
Special attention should be paid to the execution of the wa-
tertight connection of the airhandling unit on the structural
roof and roof finishing. Often, a constructive solution is
choosen, in consultation with the architect. With reference to
this matter, instructions (depending on the project), were
discussed and agreed upon beforehand.
Connections
Figure 1
Connecting air-ducts, piping and cabling must be mounted elas-
tic. On designing the airhandling unit, we worked from the start-
For horizontal transport, pallet-carts or the so-called ''transport ing point that air-ducts and cabling should not rest on the unit in
tanks'' can be installed under the mounting frame. The use of order to prevent transmission of vibration (esp. towards heaters
pipes, as rollers, may Iead to damages on the mounting frame. and coolers). If flexible connections have been installed on the
outside of the unit as a coupling between air-inlet / air-outlet and
Storage discharge openings are to be positioned opposite and the dis-
If the airhandling units must be stored during the building activi- tance of the mounting flanges should be kept at about 75% of
ties, all openings should be covered in order to prevent contami- the extended Iength of the supplied flexible connection (Figure
nation. Use tarpaulin in the case of wet storage. See to sufficient 3).
ventilation in order to prevent mould.
75% of the extended length
Installation
The airhandling units should be installed in such a manner ,
that the mounting frame touches the floor equally. If the airhandling
unit is delivered in sections, these sections must be connected
by means of the supplied bolts or steel clamps, after the seal-
ing-strip has been applied (See page 20).
Coolers that are executed with a drip pan for draining con-
densation water, as well as water humidifiers, have a water
tank for collecting water.
can be dismantled
Figure 5
Draining off alone is not sufficient, as there will always re- - does the blade shut well
main some water in the heaters and coolers (Figure 8). - does the blade open completely (if desired)
- does the spring return function in the case of current failure
- inspect the consequence of current failure; some blades
should be open, others shut
PREVENT
FREEZING
Air filters
- have the right filters been installed
- inspect the position of the filters in the slides
- fill the U-tube manometer with fluid (water)
- absolute filters are supplied separately in order to prevent
contamination during transport and putting into operation
Do not place these filters until after the unit has been cleaned
by switching on the fan
- adjust pressure switch or filter indicator (if any)
- shut inspection door well
draining off alone
is not sufficient Heaters
- check the connections on the basis of the project drawing
- inspect the connections for Ieakage
Figure 8 - check if the frost protection thermostat has been mounted
and adjusted correctly
When applying the cabling of electromotors, bute specially
Coolers
the fan motor and the motor for the humidifying pump, there
must be Ieft enough space so that the springy installation of - check the connections on the basis of the project drawing
the motors will not be obstructed (Figure 9). - inspect the connections for Ieakage
- check ifthe p.v.c. syphon (with globe valve) has been mounted
The cabling and mounting of switches, Iighting armatures (note: arrow)
and control apparatus should be done without damaging the - check if the eliminators behind the cooler are positioned
airhadling unit. correctly (may have moved during transport)
Drilling into the panels may Iead to air or water Ieakages.
Twin-coil heat exchangers
Damages to the internal insulation are to be repaired imme-
- check if the system has been filled with the correct glycol
diately.
medium
Carefully remove bore-chip, as this may cause serious cor- - inspect the direction of rotation of the pumps
rosion, especially in the sections where moisture exchange - further, see: heaters and coolers
takes place.
Rotating heat exchangers
WARNING! Never use the airhandling unit as - is the direction of rotation of the rotor correct
workplatform or storage space. - inspect the operation of the non-return brake
- inspect and adjust thenumbers of revoiution
Water humidifiers
apply cabling - checkthe connections, on the basis of the project drawing
not too tight - have the eliminators on the inlet and outlet been mounted
correctly
- have the cells (if any) been placed in the slides correctly
- has the syphon been mounted correctly
- fill the water tank
- the float valve should close as soon as the water has
reached the indicated Ievel in the unit (5 mm below the
funnel-shaped overflow)
? - shut the inspection door well
Steam humidifiers
- has the steam supply pipe been mounted correctly. In the
case of pipes Ionger than 10 m, an extra steam trap should
be placed
?
Putting into operation airhandling units with water humidifi- Put the cooling unit (if applied) into operation by opening the
ers. valves and switching on the control. After a few days of opera-
tion, the condensation pipe and the functioning of the p.v.c.
After the items mentioned before have been checked, the
syphon should be checked. If necessary, clean the syphon
airhandling unit can be put into operation.
(Figure 12).
First check if the pre-heater can provide heat to prevent freezing
when the fan is started.
Switch on the fan and check the direction of rotation of the fan
according the arrow on the ventilator casing (Figure 10).
WARNING! Never allow the pump to run without watch rotation direction
measure the absorbed
water!
current on 3 phases
no steam condensation
Figure 11 Figure 14 at the end of the function
AIR HANDLING UNITS 39 HH 100 / 39 HH 500
2=CA '
strainer
?
?
?
syphon with
non-return valve
deflection equally divided
Figure 15 Figure 18
Remove the brackets that were applied for transport
(Figure 19).
strainer ?
drain for
cleaning syphon
Figure 17
Figure 20
AIR HANDLING UNITS 39 HH 100 / 39 HH 500
2=CA
After mounting, check if the fan can move freely without mak- Putting into operation
ing contact with the rigid installation parts. The feeding cable Before putting the ventilator into operation, one must make sure
towards the motor must be mounted with enough space in that the motor has been connected correctly. Especially for pole-
all directions for the same reason (Figure 21). reversable and adjustable motors, the enclosed wiring diagram
of the motor should be studied. Note the direction of rotation of
the fan according the arrow on the fan casing (Figure 22).
apply cabling not
too tight
Immediately after the fan has been put into operation, the
absorbed current must be measured over the three sepa-
rate phases. The absorbed current should be approximately
equal in all phases and in accordance with the data on the
motor shield. The thermal fuses must be adjusted to the
nominal values.
Figure 21 Figure 22
Duct connection
extract air side
sealing strip
purging sector
belt drive
motor bracket
actuator
yellow marking tape
motor cable for identification of purging sector
Figure 23
Figure 28
Air filters
Panel filters
AIR FLOW Depending on the contamination, the filtermats should be
DIRECTION
checked every month and cleaned if necessary. An indication of
this contamination is the pressure drop.
Cleaning the panel filter can be done by:
- beating and vacuuming
- using compressed air
- washing in water up to about 40 degrees Centigrade.
?
clean thoroughly In the case of strong contamination, change the filtermats once
a year. Note that during mounting and changing the filtermats,
these are mounted correctly and with the right mutual sealing.
The side of the filtermat with a rough, open structure is directed
to the dirty air side and the smooth side towards the clean air
Figure 26
side (against the wire screen of the panel) (Figure 29).
Inspection of the internally applied insulation
Though the insulation has been provided with a protective top
Iayer, it may be damaged due to mechanical causes. Find the
cause of this damage and if necessary, prevent further damage.
Replace damaged insulation. Make sure that the top Iayer of the rough/open
insulation Iies under the panel rim (Figure 27). structure
AIR FLOW
DIRECTION
Figure 29
For airtight sealing, the panels are provided with tape, check this
tape for potential damages (if necessary, renew).
Figure 27
AIR HANDLING UNITS 39 HH 100 / 39 HH 500
2=CA !
Applying seal-
ing strip side
withdrawal
filters
AIR FLOW
DIRECTION
Figure 32
Figure 30
Water humidifiers
Filters with an efficiency up to 55% according ASHRAE
discolouration test are placed in slides. WARNING! Of each airhandling unit with a water hu-
midifier, the quality of the sluice water must be estab-
High-efficiency filters are placed in frames.
Iished and calculated, as well as the acceptable in-
The highest-efficiency filters are placed in frames with spe- crease factor. With reference to ''sluice water quan-
cial sealings and after mounting of the filters, all seams at tity and increase factor, see pages 14 and 15.
the side of the air inlet must be sealed with metal tape (Fig-
ure 31). Weekly inspect the working of the drain connections for the
water supply floating valve. Formation of Iime and mud may
be detrimental to the working of the water supply valve.
In all circumstances, the water Ievel in the tank must be main-
tained, without water floating in the funnel-shaped overflow
pipe.
With a non-operating circulation pump, the water Ievel is
5 mm under the overflow pipe.
During the humidifying season, weekly inspect the sluice
water quantity (Figure 33).
Metal tape
Figure 31
This can be done from the space at the side of the air inlet of the
filters.
The quality of filtering is partly determined by the careful posi-
tioning and sealing of the bag filters.
Special filters
Maintenance instructions can be obtained on request. Figure 33
AIR HANDLING UNITS 39 HH 100 / 39 HH 500
2=CA "
Weekly inspect the flexible connections between pump and AIR FLOW
casing for potential leakage. DIRECTION
Spray humidifiying sections type WK and WL
Twice a year, the tank of the humidifier has to be cleaned on the
inner side. A ir
Compact humidifiying sections type BM
The humidifying mats are taken out of the compact humidifying
sections. If only slight contamination has occured (depending
on the quality of the water), the removed mats can be cleaned by
beating and replaced after drying. In the case of serious con-
tamination, and/or when the mats mentioned are worn out, new
mats must be placed in the cassettes.
Figure 34
Draw off the water tank; clean the entire section with water
and a soft brush, rinse with water. Do not use hard or sharp
materials in order to prevent damages to the protection Iayer Eliminators
and/or the insulation. Check the surface of the sections and The dismounting of the eliminators is done in the humidifier,
if necessary, repair the damages. which is accessable through the access panel. ln certain cases,
it may be necessary to partly dismount the spray humidifying
For maintenance and removal of water eliminators see page
racks (Figure 35).
6. Re-fill the water tank after cleaning. Check if the water
tank is filled up to the indicated Ievel. Do not start the pump
until after the filling of the tank has been completed.
Should the nozzle be stopped up, unscrew the nozzle head after
which it can be cleaned easily.
The bearings of the pump are water-greased and require,
therefore, no special maintenance. The bearings of the di-
rectly coupled motor have a service Iife of at Ieast 16,000 AR FLOW
operation hours. In the case of Ieakage from the shaft seal- DIRECTION
ing of the pump (the so-called mechanical seal) this seal-
ing can be replaced. See instructions of pump sup-
plier.
Because of this evaporation, the water Ievel is Iikely to fall. Steam Humidifiers
This is prevented by means of the automatic supply of fresh
water through the floating ball valves. Every season, clean the strainer in the steam supply of the con-
trol valve.
However, this water also contains salts and other solid subs-
tances, this causing an increasing concentration of these Of the steam humidifiers with strainer built-in the steamtrap, the
substances in the tank, which is referred to as increase condensation exhaust-valve (that is built-in as well) and the in-
concentration. side of the steamtrap, should be cleaned at the same time. Also
inspect the ball Iock for possible damage and, if necessary,
By constantly sluicing a certain quantity of water, the concen- replace the ball valve and float.
tration in the tank can be kept under control. In order to achieve
this, the necessary sluice water quantity is to be calculated Inspect the control valve, condensate drain and distribution pipe
(Figure 36). twice a year.
With steam distribution pipes in the sub atmospheric pressure
systems (air side) flooding can occur due to the condensation
Concentration increase factor
end steamfunction
start new airhandling
function
Function qs/qv
Figure 36
A filter will not always be placed at the extract side ofthe extract
part of the Twin-Coil heat exchangers. Yearly inspection of this 2 - 4 cm
section is required.
Coolers and extract part of the Twin-Coil heat exchangers may
show condensation of water, check if the floats in the syphon of
the condensation drain still operate correctly (Figure 39).
Figure 40
See to it that the belts do not make contact with the guard, if any
applied.
ruller
balance pulleys
Drain for cleaning syphon
Figure 39
Water pollution will hardly ever occur. This pollution can only be
remedied by specialised companies.
Water filled heaters are often provided with a frost protection
thermostat. Check the adjustment of this thermostat at the be- Figure 41
ginning of the winter season and see to it that the correct control
evices are taken into account.
The V-belt pulleys applied. are provided with taper Iockbushes
Heat exchangers filled with glycol should each year be inspected and can be removed without the use of special equipment. In
for the correct percentage of glycol in the water. order to dismount the pulleys, we proceed as follows:
Unscrew and take out the allen screws; In order to dismount the
taper lockbushes, firmly drive one of these screws into the coun-
Centrifugal fans tersunk hole of the pulley, this will cause the pulley of the taper
Bearings Iockbush to come Ioose.
Double inlet centrifugal ventilators are provided with ball bear- For mounting, proceed as follows: Insert the taper Iockbush into
ing blocks with grease nipple. At reasonably clean operation the pulley and make sure that the pulley and Iockbush coincide,
and at temperatures below 50 degrees Centigrade, the origi- Ioosely screw in the allen screws. Shove the whole onto the
nal supply of grease is sufficient for the entire service Iife of spindle, balance and subsequently screw in the allen screws
the bearings. Further supply of grease is not necessary and, equally .
in fact, unadvisable. The bearings normally have a service
Iife of about 25,000 operating hours.
Without consulting the supplier, it is not advisable to change
the speed of the fan. If a higher number of revolutions is
Under strongly divergent working conditions, Iike for instance required, one should take into account whether the avail-
high temperatures or severely polluted air, additional greas- able motor power is sufficient. The Ioad of the bearings, as
ing may be necessary. In these cases, the supplier should well as the Ioad of the fan should be re-calculated by the
be consulted with regards to greasing intervals, the quantity supplier.
of grease and the quality of the bearing grease. Once a year, check the anti-vibration isolators and flexible
The service Iife of ball bearings of electromotors is at Ieast connections for breakage or damages (Figure 42).
25,000 operating hours.
inspection points
The ball bearings scan be reached by taking off the bearing
shields of the electromotor. The grease used is ''Shell Alvania
3'' or a similar kind.
Transmission
After the fan has been put into operation, but also after the mount-
ing of the new V-belts, check, within one week, and then 14 days
Iater, the tension of the belts and if necessary adjust them (Fig-
ure 40).
Subsequently check the tension of the V-belts every three months
as well as the quality of the belts.
With regards to the bearing Ioad, one must see to it that no
excessive tension is applied; it must be possible to push-in the
V-belts for about 4 cm according to the profile and core distance inspection points
of the pulleys (Figure 41). Figure 42
AIR HANDLING UNITS 39 HH 100 / 39 HH 500
2=CA %
Check all bolts and nuts, as well as the fastenings of the flexible Rotating heat exchangers
connections on the flanges of the fan and casing.
Rotation
Inspect the fan for unbalance once a year. Remove dust
from the inlet cones and impeller. Dirt in the impeller may Once a year, inspect the high and Iow number of revolutions
Iead to unbalance. If serious contamination has occured (if necessary: adjust).
check the functioning of the filters and if necessary, improve
the filtering quality . The number of revolutions can be easily established by
counting the revolutions per minute. For the high number of
Inlet-vane control revolutions, maintain about 1O rpm.
Fans provided with ''inlet-vane control'' must be inspected every
three months in order to see if the blades still function appropri- When standing still, rotating heat exchangers unilaterally
take in moisture and dust.
ately. In order to check this, stop the ventilator and inspect the
operating of the actuator, the suspension and blades by operat- The non return coupling that is mounted on the reduction unit of
ing the ''inlet-vane'' (open - closed) (Figure 43). the drive motor, must be inspected for correct operation as well.
Inspection F re
sh
A ir
Exh
aus
tA
ir
Figure 45
Rotor
Through access panels in the adjoining ducts or through in-
spection doors in the adjoining sections, both sides of the rotor
Figure 43 should be inspected every month. Should the surfaces be
strongly contaminated, they can be cleaned as follows:
Type rotor EG-RG (basic material rotor, glassfibre):
WARNING! This should be done when the fan is out Using compressed air or clean with the use of an industrial
of operation. vacuum cleaner. If, due to oil and grease particles in the air,
dust has formed on the surface, use chemical solvents, how-
lnspect the play of all the blades as well as the margin of the ever, only after consulting.
rotation points of ''inlet-vane control'' are provided with p.v.c. bear-
ings and require no greasing. When serious contamination or Type rotor: ET -RT (basic material rotor, aluminium foil):
dust formation occurs, clean the ''inlet-vane''. Only grease the Using compressed air or clean with the use of an industrial
rotation points of the transmission mechanism between actua- vacuum cleaner.
tor and inlet-vane every three months (use oil). In the case of serious contamination, inspect the filters and
if necessary, renew the sealing of the filters. If necessary,
Sound attenuators one should consider the use of filters of better quality.
Under normal circumstances, sound attenuating splitters re-
quire no maintenance. Yet it is recommendable to inspect the The adjustment of the sealing should be done with a slowly
absorption material of the splitters once a year for potential dam- turning rotor in order to prevent the sealing from being pressed
ages and fibres that may have come off. This in order to prevent onto the rotor. This will Iead to damages to the rotor.
obstruction of the rest of the installation (Figure 44). Bearings
The bearings of the rotor have Ionglife greasing and require,
therefore no maintenance.
Drive motor
V-belts made of polycord material must be joined with special The fan spindle resp. motor spindle is provided with bear-
apparatus. On this matter, consult our Service Department. ings with Ionglife greasing and therefore, require no mainte-
nance. Inspect the quality of the V-belt every three months.
The actuator is also provided with bearings with Ionglife greas- Also inspect the anti-vibration isolators (if any) for possible
ing. cracks between the rubber and the steel mounting plates.
Inspect the operation of the motor support, the rotation points Inspect the flexible connections between fan and cooling unit
and the spring. for possible cracks and check the fastening of the flanges. Check
the cooling coil as well as the fan and fanwheel for dust and if
necessary, clean with a vacuum cleaner. In case of excessive
dirt, inspect the filter for its air tightness and the position of the
Computair filter in the mounting slides.
Depending on the demands with regards to the computer room,
the maintenance of the (in principle) movable ''computairs'', will
be handled on the spot, or in a room outside the computer
room. Before commencing with this maintenance, the filter resis-
tance is read off the U-tube or needle manometer. The mea-
sured resistance is compared to the final pressure drop as
given by the supplier. Final pressure drop: 1.6 x initial pressure
drop + 40 Pa (Figure 46).
For maintenance, the door on the access side of the unit is
removed by Iifting it and then taking it out. Types with hinging
doors can also be supplied (depending on the type).
Maintenance
Season
Putting into
operation
Functiona l Division Apparatus Items of control
Every Every 1 3 6 12
w e ek se ason months months months months
in and outside coating
General locks/hinges
Casing
Apparatus w ith
flexible connections
INDIRECTLY coupled
speed of the rotor
motors
non-return device
Rotating V-belt transm ission
heat-exchangers motor support
bearings
dust
bearings direct transm ission
Motors
bearings indirect transm ission
bearings
shaft sealing
Pumps
pump/casing connections
rotating at long stand still
Inlet-vane control damper couplings
A ir dampers dust
Moving parts
Gravity shutters bars
actuators adjusting bolts
dust
Heater
frost protection thermostat
Coolers
cooling m edium
Non-moving parts Heat recovery unit
syphon
dust
A ttenuators
attenuating material
sluice water
concentration increase factor
water quality
General
float valve
syphon
lim e-form ation
S pray hum idifiers nozzles
Humidifiers Compact humidifiers mats
cells
Cell hum idifiers
distribution pipes
E lim inators lim e/rust
strainer
length of steam fum e
S team humidifiers
control
condensation discharge
P anels pressure drop
Bags pressure drop
Filters
High-efficiency pressure drop
filter floor
AIR HANDLING UNITS 39 HH 100 / 39 HH 500
2=CA
Case connection
M8x100
LCU M8x60
3D-2 M8x70
+Large washers x 2
Figure 48
module height
gasket 6x15 A
where possible
seal with mastic
module width
Figure 47 Figure 49