Sunteți pe pagina 1din 116

CCIP-030

CI/Sfb A cement and concrete industry publication

UDC
624.072.33:624.012.3/.4

Design of Hybrid Concrete Buildings


Design of Hybrid
Concrete Buildings
Design of Hybrid Concrete Buildings A guide to the design of buildings combining in-situ
and precast concrete

R. Whittle MA (Cantab) CEng MICE


This design guide is intended to provide the structural Robin Whittle has extensive knowledge and experience of designing
H. Taylor FREng, BSc, PhD, CEng, FICE, FIStructE
engineer with essential guidance for the design of structures all types of concrete buildings. He regular contributes to concrete
that combine precast and in-situ concrete in a hybrid industry publications and is a consultant to Arup. He was a member
concrete structure. It introduces the options available for of the project team which drafted Eurocode 2.
hybrid concrete structures, and goes on to explain the key
considerations in the design of this type of structure. Howard Taylor has extensive knowledge and experience of

R. Whittle MA (Cantab) CEng MICE H. Taylor FREng, BSc, PhD, CEng, FICE, FIStructE
designing precast concrete elements and buildings, including
Bearings, interface details, consideration of movement, composite developing alternative production methods. He is a past president
action, robustness and the effects of prestressing are all explained in of the Institution of Structural Engineers and is currently chairman
this guide and design examples are included where appropriate. The of the British Standards Institution Building and civil engineering
importance of overall responsibility and construction aspects are also structures Technical Committee B/525.
described.

CCIP-030
Published January 2009
ISBN 978-1-904482-55-0
Price Group P
The Concrete Centre

Riverside House, 4 Meadows Business Park,


Station Approach, Blackwater, Camberley, Surrey, GU17 9AB
Tel: +44 (0)1276 606 800
www.concretecentre.com

Hybrid cov-.indd 1 29/01/2009 16:43:37


A cement and concrete industry publication

Type 1 Type 2 Type 3


Precast twin wall and lattice girder slab with Precast column and edge beam with in-situ Precast column and oor units with cast in-situ
in-situ concrete oor slab beams

Acknowledgements
The authors would particularly like to thank the following people for their support in the development of this
design guide: Type 4 Type 5 Type 6
In-situ columns or walls and beams with precast In-situ column and structural topping with precast In-situ columns with lattice girder slabs with
Tony Jones Arup oor units beams and oor units optional spherical void formers
Ian Feltham Arup
Typical hybrid concrete options.
The contributions and comments from the Concrete Society Design Group and also from the following Please note this diagram is a repeat of Figure 2.1, page 8.
people are gratefully acknowledged:

John Stehle Laing ORourke


Graham Hardwick John Doyle Construction Ltd
Peter Kelly Bison Concrete Products Ltd
Alex Davie Consultant
David Appleton Hanson Concrete Products
Kevin Laney Strongforce Engineering Plc
Norman Brown British Precast Concrete Federation Ltd

Published by The Concrete Centre


Riverside House, 4 Meadows Business Park, Station Approach, Blackwater, Camberley, Surrey GU17 9AB
Tel: +44 (0)1276 606800 Fax: +44 (0)1276 606801
www.concretecentre.com

CCIP-030
Published January 2009
ISBN 978-1-904482-55-0
Price Group P
The Concrete Centre

Cement and Concrete Industry Publications (CCIP) are produced through an industry initiative to
publish technical guidance in support of concrete design and construction.

CCIP publications are available from the Concrete Bookshop at www.concretebookshop.com


Tel: +44 (0)7004 607777

All advice or information from The Concrete Centre is only intended for use in the UK by those who will evaluate the signicance
and limitations of its contents and take responsibility for its use and application. No liability(including that for negligence) for any
loss resulting from such advice or information is accepted by The Concrete Centre or their subcontractors, suppliers or advisors.
Readers should note that the publications from The Concrete Centre are subject to revision from time to time and should
therefore ensure that they are in possession of the latest version.

Cover photo: Courtesy of Outinord International Ltd.


Printed by Information Press Ltd, Eynsham, UK

Hybrid cov-.indd 2 29/01/2009 16:43:54


Design of Hybrid Concrete Buildings

Contents
1. Introduction 5
1.1 Single point of responsibility 5
1.2 Design considerations 6
1.3 Best practice procurement guidance 6

2. Overview of hybrid solutions 7


2.1 Type 1: Precast twin wall and lattice girder slab with in-situ concrete 7
2.2 Type 2: Precast column with in-situ oor slab 9
2.3 Type 3: Precast column and oor units with cast in-situ beams 10
2.4 Type 4: In-situ columns or walls and beams with precast oor units 12
2.5 Type 5: In-situ column and structural topping with precast beams and
oor units 13
2.6 Type 6: In-situ columns with lattice girder slabs with optional spherical
void formers 14

3. Overall structural design 15


3.1 Robustness 15
3.2 Stability 18
3.3 Diaphragm action 18
3.4 Shear at interface of concrete cast at different times 19
3.5 Interface shear 22
3.6 Shear and torsion design 25
3.7 Long-line prestressing system 26
3.8 Secondary effects of prestressing and the equivalent load method 29
3.9 Temperature effects 29
3.10 Differential shrinkage 29
3.11 Designing for construction 33

Design of Hybrid Concrete Buildi1 1 29/01/2009 16:47:32


4. Bearings and movement joints 34
4.1 Horizontal forces at bearings 34
4.2 Restrained bearings 35
4.3 Movement joints 36
4.4 Actions and restraints 36
4.5 Design considerations 37
4.6 Allowance for anchorage of reinforcement at supports 37
4.7 Bearings that allow limited movement 38
4.8 Connections between precast oors and in-situ concrete beams 42

5. Structural elements and connections 43


5.1 Twin wall construction (type 1) 43
5.2 Precast columns, edge beams and in-situ slabs (type 2) 52
5.3 Biaxial voided slabs 55
5.4 Prestressed hollowcore units 58
5.5 Double tee beams 68
5.6 Stairs 74
5.7 Corbels, nibs and half joints 82

6. Construction issues 87
6.1 Method of construction 87
6.2 Composite action between precast units and in-situ structural topping 89
6.3 Specially shaped standard units 89
6.4 Long and short units adjacent to each other 89
6.5 Differences of camber in double tees 91
6.6 Method of de-tensioning double tee units 91
6.7 Checking strand or wire pull-in for hollowcore units 91
6.8 Placing hollowcore units into the correct position 91
6.9 Production tolerances 92

7. Special structures - case studies 93


7.1 Lloyds of London 93
7.2 Bracken House 100

References 104

Design of Hybrid Concrete Buildi2 2 29/01/2009 16:47:44


List of worked examples
Worked example 1 Hollowcore oor acting as a diaphragm 20
Worked example 2 Interface shear between hollowcore slab and edge beam 23
Worked example 3 Upwards camber on slab due to temperature gradient 30
Worked example 4 Differential shrinkage 31
Worked example 5 Bearing of a hollowcore unit 41
Worked example 6 Vertical tie 56
Worked example 7 Anchorage length of longitudinal tie bar 65
Worked example 8 Dowel bar for connection of precast stairs 80
Worked example 9 Corbel design 84

Design of Hybrid Concrete Buildi3 3 29/01/2009 16:47:44


Design of Hybrid Concrete Buildi4 4 29/01/2009 16:47:45
Introduction 1

1. Introduction
Hybrid construction allows the most appropriate use of different materials and methods
of construction to produce a pleasing and effective form of structure. The search for
greater economy, in terms of material costs and reduced construction time, has resulted
in innovative approaches that seek to combine construction materials and methods to
optimum effect. Hybrid concrete construction (HCC) is one such development that
combines in-situ and precast concrete to maximise the benets of both forms of concrete
construction. Further guidance on the benets of HCC is given in Section 2.1.

This design guide is aimed at the designer and considers a range of hybrid concepts and
the overall structural aspects. It provides design and detailing information for some of the
common systems used and structural elements involved. Where applicable the information
is in accordance with BS EN 1992-1-1 1, together with the UK National Annex (Eurocode 2
is used to refer to BS EN 1992-1-1 throughout this guide unless noted otherwise). This
incorporates a section on the design of members by strut and tie methods, which is
particularly useful when considering hybrid design details. This guide also considers and
refers to the following European Concrete Product Standards for precast concrete elements:
BS EN 133692 Common Rules for Precast Concrete Products
BS EN 11683 Precast Concrete Products Hollowcore Slabs
BS EN 137474 Precast Concrete Products Floor Plates for Floor Systems
BS EN 132245 Precast Concrete Products Ribbed Floor Elements
BS EN 132256 Precast Concrete Products Linear Structural Elements
BS EN 149927 Precast Concrete Products Wall Elements
BS EN 148438 Precast Concrete Products Stairs

1.1 Single point of The use of precast and in-situ concrete may well lead to the design of the individual
responsibility elements by designers working for different companies. Therefore, it is essential that
there should be a single named designer or engineer who retains overall responsibility
for the stability of the structure and the compatibility of the design and details of the
parts and components, even where some or all of the design, including details, of those
parts and components are not carried out by this engineer. This is particularly important
for the design of hybrid structures where misunderstandings as to who is responsible have
occurred.

It is the responsibility of the designer, before incorporating any proprietary system as part
of the structure, to ensure that the assumptions made in the design and construction of
such are compatible with the design of the whole structure. This should include:
an adequate specification for that part.
ensuring that any standard product designed and detailed by the precast
manufacturer, is suitable for that particular structure.
the design of any such part is reviewed by the designer to ensure that it satisfies the
design intent and is compatible with the rest of the structure.

Design of Hybrid Concrete Buildi5 5 29/01/2009 16:47:45


1 Introduction

1.2 Design considerations The design of each component should include consideration of:
its performance in the permanent condition
the construction method and loading
any temporary supports required during construction.

The design should be carried out following the requirement of Eurocode 2, Cl. 1.3, which
assumes:
Structures are designed by appropriately qualified and experienced personnel.
Adequate supervision and quality control is provided in factories, in plants and on site.
Construction is carried out by personnel having the appropriate skill and experience.
The construction materials and products are used as specified in Eurocode 2 or in the
relevant material or product specifications.
The structure will be adequately maintained.
The structure will be used in accordance with the design brief.
The requirements for execution and workmanship given in EN 136709 are complied with.

The design assumptions should generally include the following construction related
information:
sequence of construction
exposure requirements
pour sizes assumed (if appropriate)
concrete strength at time of striking formwork and back-propping requirements
breakdown of loading including allowance for construction loads
loading history assumed.

It should be noted that some of the advice given in this design guide is a result of failures
that have occurred on completed structures.

1.3 Best practice Best Practice Guidance for Hybrid Concrete Construction10 looks at the procurement
procurement guidance process from concept stages through to design and construction, suggesting processes
that allow the capture of best practice. It is supported by a number of case studies. The
guidance explains the benets that result from:
early involvement of specialist contractors
using a lead frame contractor
using best value philosophy
holding planned workshops
measuring performance
trust
close cooperation with an emphasis on partnering.

It is recommended that this guidance document is used to maximise the advantages of


using HCC.

Design of Hybrid Concrete Buildi6 6 29/01/2009 16:47:45


Overview of hybrid solutions 2

2. Overview of hybrid solutions


This section considers a range of possible hybrid concrete construction (HCC). The ideal
combination of precast and in-situ is inuenced by the project requirements. There is a
wide range of possible options, a selection of which is presented here as representative of
current UK practice. This is not intended to be exhaustive, but to reect the spectrum of
possibilities. The planning and detailed design of hybrid structural systems will almost
always require the involvement of specialist precast concrete manufacturers. These
manufacturers are willing and able to assist early in the design process to produce an
efcient design.

There are advantages to using both precast and in-situ concrete summarised in Table 2.1; more
detailed discussion on the benets of concrete can be found in other publications11, 12, 13.
The key to maximising the benets of HCC is to use the most appropriate technique for
each element to produce an economic structure.

Table 2.1 Precast concrete Precast or in-situ concrete In-situ concrete


Benets of concrete.
Economic for repetitive elements Inherent re resistance Economic for bespoke areas
Long clear spans Durability Continuity
Speed of erection Sustainability Inherent robustness
Buildability Acoustic performance Flexibility
High-quality nishes Thermal mass that can be utilised for Services coordination later in
fabric energy storage programme
Consistent colour Prestressing Locally sourced materials
Accuracy Mouldability Short lead-in times
Reduced propping on site Low vibration characteristics
Reduced skilled labour on site

Six of the most regularly used HCC options are shown in Figure 2.1 and are described in
more detail in the remainder of this chapter. They will be referred to by type number
throughout this guide where the detailed design of the various elements is discussed.
Suggested span limits are given for each type of construction. Further guidance for initial
sizing can be found in Economic Concrete Frame Elements14.

2.1 Type 1: Precast twin wall Hybrid concrete wall panels are increasingly being proposed on projects throughout the UK
and lattice girder slab with and are often known as twin wall. They comprise two skins of precast concrete connected
by steel lattices, which are lled with concrete on site, see Figure 2.2. The external skins of
in-situ concrete the twin wall system are factory made, typically using steel moulds. This results in a higher
quality nish than a typical in-situ wall. The panel surface quality is suitable to receive a
plaster nish or wallpaper. The panel surface is not normally architectural concrete and
the colour may not be consistent or easy to specify. Joints are cast using in-situ concrete
and either have to be expressed as a feature or concealed. This option offers potential
advantages to the contractor in terms of speed of construction, as well as reducing the
number of skilled site staff required to construct the walls.

Design of Hybrid Concrete Buildi7 7 29/01/2009 16:47:45


2 Overview of hybrid solutions

Type 1 Type 2 Type 3


Precast twin wall and lattice girder slab with Precast column and edge beam with in-situ Precast column and oor units with cast in-situ
in-situ concrete oor slab beams

Type 4 Type 5 Type 6


In-situ columns or walls and beams with precast In-situ column and structural topping with precast In-situ columns with lattice girder slabs with
oor units beams and oor units optional spherical void formers

Figure 2.1
Typical hybrid concrete options.
Please note this diagram is repeated on the inside
back cover for ease of reference.

Figure 2.2
Type 1 construction,
twin wall erection.
Photo: John Doyle Construction Ltd

Design of Hybrid Concrete Buildi8 8 29/01/2009 16:47:46


Overview of hybrid solutions 2

Often the twin wall system is combined with the use of lattice girder precast soft slabs,
with or without spherical void formers. These provide permanent shuttering for an in-situ
slab that can be relatively easily tted to the wall system. Spans up to 8 m are common
and spans up to 14 m are possible. (The manufacturer should be consulted early on to
ensure the longer spans are viable.)

Potential structural uses of the twin wall system include:


cellular type structures for residential use
walls carrying vertical loads only
shear and core walls; this has significant implications for the design, as discussed in
Section 5.1
retaining walls; this has significant implications for the design, as discussed in Section 5.1
single sided formwork situations, where there is no access to one side of the wall to erect
formwork, for example wall construction on a party wall line against neighbouring buildings.

The major advantage is that it is an in-situ structure, fully continuous and tied together,
but without the need for shuttering on site. Twin wall can also be cast with fully trimmed
openings and with ducts for cables and other services.

Advantages:
Quality finish for walls and soffits.
No formwork for vertical structure and horizontal structure when lattice girder slabs are
used.
Structural connection between wall and slabs is by standard reinforced concrete detail
and inherently robust.
Reduced propping.

Disadvantages:
Propping of precast required prior to sufficient strength gain of in-situ concrete.
The smaller dimension of the precast units is typically a maximum of 3.6 m, so joints
in walls and soffits must be dealt with: expressed or concealed.
Reduced flexibility of layout as this option requires walls rather than columns.

2.2 Type 2: Precast column The combination of an in-situ slab, e.g. post-tensioned at slab, with precast columns
with in-situ oor slab can provide an economic and fast construction system. Precast concrete edge beams
may also be used to avoid edge shutters on site and to allow perimeter reinforcement,
cladding xings or prestressing anchorages to be cast in. This reduces the time required
for reinforcement xing and erecting the formwork.

The maximum span for this form of construction depends largely on whether the in-situ
slab is post-tensioned. For at slabs with spans greater than 10 m punching shear is likely
to be a critical design issue.

Design of Hybrid Concrete Buildi9 9 29/01/2009 16:47:48


2 Overview of hybrid solutions

Where long-span thin slabs are used vibration limits should be checked, see A Design Guide
for Footfall Induced Vibration of Structures15.

This form of construction relies on the structure being braced. This is achieved by the lift
core(s) or separate shear walls.

Advantages:
Columns can be erected quickly.
Quality finish for columns.
Precast edge beam contains post-tensioning anchorages (if required), slab edge
reinforcement and cladding fixings, and avoids need for slab edge shuttering.
Can be used with a variety of in-situ slabs, selected to suit individual project requirements.
More flexible for late changes.

Disadvantages:
In-situ slab requires falsework, formwork and curing time.

2.3 Type 3: Precast column This form of construction allows a high proportion of the structure to be manufactured in
and oor units with cast quality controlled factory conditions off site leading to fast construction on site.

in-situ beams A variety of precast oor products could be used with this type of construction, including
hollowcore units, double tees or lattice girder slabs (with or without spherical void formers)
or bespoke cofferred oor units, see Figures 2.3a and 2.3b. The latter have successfully
been used in high quality buildings designed for energy efciency, where the light ttings,
architectural features and cooling systems have all been incorporated into the unit.

Advantages:
Vertical structure can be erected quickly; no formwork required.
Precast floor structure can be erected quickly; no formwork required.
Quality finish for columns and soffits (although this is not always possible with
hollowcore units).
Structural connection between precast elements is via standard reinforced or post-
tensioned concrete.

Disadvantages:
Precast flooring must be temporarily propped.
Sealing between precast units is required.

10

Design of Hybrid Concrete Buildi10 10 29/01/2009 16:47:48


Overview of hybrid solutions 2

Figure 2.3a
Example of type 3 projects.
Paternoster Square and ofce building.
Photo: John Doyle Construction Ltd

Figure 2.3b
Example of type 3 projects.
Homer Road, Solihull.
Photo: Foggo Associates

11

Design of Hybrid Concrete Buildi11 11 29/01/2009 16:47:49


2 Overview of hybrid solutions

2.4 Type 4: In-situ columns This is a similar form to type 3 discussed above, the key difference being that the columns
or walls and beams with are cast in-situ rather than being precast, see Figure 2.4.

precast oor units The advantage of this form of construction over a fully in-situ concrete structure is the
ability to use long spans (up to 16 m) precast oor units, e.g. hollowcore slabs, double tees.
These obviate the need for slab formwork and provide a relatively lightweight oor. This
construction system does not require the involvement of a specialist subcontractor beyond
the manufacture and supply of the standard precast units.

Figure 2.4
Example of type 4 project, car park, West
Quay, Southampton
Photo: Hanson Concrete Products

Advantages:
Precast floor structure can be erected quickly.
Quality finish for soffits (although this is not always possible with hollowcore units).
Short lead time for standard precast products.

Disadvantages:
Precast flooring must be temporarily propped.
Sealing between precast units is required.

12

Design of Hybrid Concrete Buildi12 12 29/01/2009 16:47:52


Overview of hybrid solutions 2

2.5 Type 5: In-situ column In this form of construction the oor consists entirely of precast elements, which are tied
and structural topping with together with an in-situ structural topping, see Figure 2.5. (A structural topping is now
dened as wearing screed in BS 820416.) The column formwork can be designed as a
precast beams and oor temporary support for the precast beams and slabs to reduce the requirement for propping
units of the precast oor. The joint between the beam and columns and any structural screed is
concreted with the columns to form a monolithic, robust structure.

This system requires particular attention to the connection details between the precast
beam and oor units. It should be ensured that adequate structural ties are provided to
achieve a robust structure.

Advantages:
Precast floor structure can be erected quickly.
Precast beams support precast floor units, minimising floor propping.
Precast quality finish for soffits.
Formwork for in-situ columns can be used to prop precast beams.
Structural connection between precast elements is via standard reinforced concrete.
In-situ structural topping to beam permits beams to be continuous over columns.

Disadvantages:
Downstand beams need to be coordinated with the services distribution.

Figure 2.5
Example type 5 project, Home Ofce
Headquarters, London.
Photo: Pell Frischmann Consulting Engineers Ltd and Bouygues (UK) Ltd

13

Design of Hybrid Concrete Buildi13 13 29/01/2009 16:47:55


2 Overview of hybrid solutions

2.6 Type 6: In-situ columns The main feature of this system is the use of the lattice girder panels to act as permanent
with lattice girder slabs formwork for a at slab. A variation is to include spherical void formers, which reduce the
self-weight of the slab, for only a small reduction in exural strength and stiffness. Lattice
with optional spherical void girders and void former cages are cast into (usually class C40/50) concrete panels
formers containing reinforcement in two directions, providing a precast panel that acts as the
permanent formwork, see Figure 2.6. The slab may be designed as a at slab. If the
spherical void formers are used, they are removed in areas of high shear where a solid
section provides greater shear resistance.

The slab may be designed as a at slab, although propping of the panels will be required,
to reduce the overall oor zone of the building and to simplify installation of services. The
quality of the factory produced softs provides the opportunity to take advantage of the
thermal mass properties of the concrete slab by exposing them.

Advantages:
Precast floor structure can be erected quickly; no formwork required.
Structural connection between precast elements is via standard reinforced concrete.
Quality finish for soffits.
More flexible for late changes.

Disadvantages:
Precast flooring must be temporarily propped.

Figure 2.6
Type 6: Lattice girder soft panels used as
permanent formwork.
Photo: John Doyle Construction Ltd

14

Design of Hybrid Concrete Buildi14 14 29/01/2009 16:47:59


Overall structural design 3

3. Overall structural design


This section gives specic guidance on the aspects of structural design that will apply to
most forms of hybrid concrete construction (HCC). HCC requires special design care
because the connections of elements within the structure are unlikely to use standard
in-situ reinforcement details; more detailed guidance is given in Sections 4 and 5 on bearings,
movement joints, various elements and their connections. The designer must be condent
that the details will work satisfactory for all situations that the structure is likely to experience.
The introduction to this design guide emphasizes the importance of a single named
engineer responsible for the design of a hybrid concrete structure. This is particularly
important in the design of the connection details.

3.1 Robustness The design and detailing advice provided in this guide assumes that the structure falls
into Approved Document A17, class 2B (risk group 2B in Scotland) or above. It is essential to
create a robust structure and this may require special details to be developed to allow the
precast elements to be properly integrated.

The UK Building Regulations18 through Approved Document A refers to BS EN 1991-7,


Actions on Structures Accidental Actions19 and Eurocode 2. The full requirements are
given in Eurocode 2, Cl. 9.10, its UK National Annex20 and PD 6687, Background Paper to
the UK National Annexes to BS EN 1992-121. The design of ties should take account of the
minimum reinforcement requirements (related to the tensile strength of concrete) and
the anchorage capacity of the bars.

Continuity of ties
A tie may be considered effectively continuous if the rules for anchoring and lapping bars
given in Eurocode 2, Cl. 8.4 and 8.7 are followed and the minimum dimension of any in-situ
concrete section in which tie bars are provided is not less than the sum of the bar size (or
twice the bar size at laps), twice the maximum aggregate size and 10 mm.

The tie should also satisfy one of the following conditions:


A bar or tendon in a precast member lapped with a bar in connecting in-situ concrete,
bounded on two opposite sides, by rough faces of the same precast member, see
Figure 3.1.
A bar or tendon in a precast concrete member lapped with a bar in in-situ structural
topping or connecting concrete anchored to the precast member by enclosing links.
The combined ultimate tensile resistance of the links should be not less than the
ultimate tension in the tie, see Figure 3.2.
Bars projecting from the ends of precast members joined by any method conforming
with Eurocode 2, Cl. 8.7.
Bars lapped within in-situ structural topping or connecting concrete to form a continuous
reinforcement with projecting links from the support of the precast floor or roof
members to anchor such support to the topping or connecting concrete, see Figure 3.3.

15

Design of Hybrid Concrete Buildi15 15 29/01/2009 16:48:02


3 Overall structural design

Figure 3.1
Continuity of ties: Bars in precast member
lapped with bar in in-situ concrete.

Figure 3.2
Continuity of ties: Anchorage by enclosing Tie
links.

Tie Tie

Figure 3.3 Tie


Continuity of ties: Bars lapped within in-situ
concrete.

Peripheral ties
The peripheral tie should be capable of resisting a design tensile force:

Ftie,per = (20 + 4n0) 60 kN

where
n0 = number of storeys

Internal ties
The internal tie should be capable of resisting a design tensile force:

Ftie,int = [(qk + gk)/7.5](lr /5)(Ft) Ft kN/m

where
(qk + gk) = sum of the average permanent and variable floor loads (in kN/m2)
lr = greater of the distances (in metres) between the centres of the columns,
frames or walls supporting any two adjacent floor spans in the direction of
the tie under consideration, and
Ft = (20 + 4n0) 60 kN
Maximum spacing of internal ties = 1.5lr

16

Design of Hybrid Concrete Buildi16 16 29/01/2009 16:48:02


Overall structural design 3

Horizontal ties to columns and/or walls


Edge columns and walls should be tied horizontally to the structure at each oor and roof
level. The tie should be capable of resisting a design tensile force:

Ftie, fac = Ftie, col = Maximum (Minimum (2Ft; lsFt/2.5); 0.03 NEd)

where
Ftie,fac = in kN/m run of wall
Ftie,col = in kN/column
Ft = as defined in above
ls = floor to ceiling height (in metres)
NEd = total design ultimate vertical load in wall or column at the level considered
Tying of external walls is only required if the peripheral tie is not located in the wall.

Vertical ties
For class 2B and 3 buildings Approved Document A (and similarly the Technical Handbooks
for Scotland for risk group 2B and 3 buildings) has the following requirements:
a) Each column and each wall carrying vertical load should be tied continuously from the
lowest to the highest level. The tie should be capable of carrying a tensile force equal to
the design load carried by the column or wall from any one storey under accidental design
situation (that is loading calculated using BS EN 1990, Eurocode: Basis of Structural
Design22, Expression (6.11b)).
b) Where ties described in a) are not provided a check should be carried out to show that
upon notional removal of each supporting column and wall, and each beam supporting
columns or walls (one at a time in each storey of the building) that the building remains
stable and that the area of floor at any storey at risk of collapse does not exceed 15 per
cent of the floor area of that storey or 70 m2, whichever is the smaller, and does not
extend further than the immediate adjacent storeys.
c) Where the notional removal of such elements would result in damage or is in excess of the
limit above then these elements should be designed as key elements. A key element
should be capable of withstanding a design load of 34 kN/m2 at ultimate limit state
applied from any direction to the projected area of the member together with the reaction
from the attached components, which should also be assumed to be subject to 34 kN/m2.
The latter may be reduced to the maximum reaction that can be transmitted by the
attached component and its connections.

Anchorage of precast oor and roof units and stair members


PD 6687, Background Paper to the UK National Annexes to BS EN 1992-1-1 and BS EN
1992-1-221, Cl. 2.20.2 Anchorage of precast oor and roof units and stair members states that:
a) In buildings that fall into class 2B and 3 as defined in Section 5 of Approved Document A
all precast floor, roof and stair members should be effectively anchored whether or
not such members are used to provide other ties required in Eurocode 2, Cl. 9.10.2.
(Similar requirements apply in Scotland.)
b) The anchorage described in a) should be capable of carrying the dead weight of the
member to that part of the structure that contains the ties.

17

Design of Hybrid Concrete Buildi17 17 29/01/2009 16:48:03


3 Overall structural design

3.2 Stability HCC frames may be designed as either braced or unbraced. The design of unbraced frames
requires extra care to ensure that the joint details can resist the applied moments without
excessive rotation.

3.3 Diaphragm action Where oor diaphragm action is used in the design, type 3 and 4 structures have the
precast elements carrying horizontal shears for diaphragm action to take place. Types 2 and
6 structures have the in-situ oor acting as a diaphragm, and type 1 and 5 structures can
have the diaphragm action shared by the precast units and the in-situ structural topping.

Multi Storey Precast Concrete Framed Structures23 describes the design approaches for
oor diaphragm action formed from different types of precast units supported by tests.
One approach is the use of precast units, either alone or with a structural topping, having
sufcient horizontal shear capacity between them, such that together they can be considered
as horizontal beams with longitudinal steel at each gable and tie steel across the unit-to-
unit joints, see Figure 3.4a.

An alternative method, appropriate to hollowcore oors with no structural topping


considers the hollowcore unit as a member in a virendeel girder and with reinforcement
in the embedment zone in the edge beams acting as the stiffening component in the
virendeel joints, see Figure 3.4b.

Figure 3.4
Typical diaphragm action from precast oor
systems.

a) Floor carrying horizontal forces from wind by beam action b) Floor carrying horizontal forces from wind by virendal action

18

Design of Hybrid Concrete Buildi18 18 29/01/2009 16:48:03


Overall structural design 3

BS EN 1168, Precast Concrete Products Hollowcore Slabs3 has an informative annex that
gives some advice on the design of horizontal diaphragms to carry lateral loads, usually wind
loading. This, in turn, refers to Eurocode 2, Cl. 10.9.3 where the maximum longitudinal
shear stress for grouted connections vRdi is limited to 0.15 MPa for smooth and rough
surfaces, as found at the edges of hollowcore, and 0.1 MPa for very smooth surfaces as
found in the ex-mould nish of bounding edge beams, see Figure 3.2.

A considerable amount of test work has also been carried out on hollowcore diaphragms
and is discussed by Elliott23.

3.4 Shear at interface of Eurocode 2, Cl. 6.2.5 also covers the design approach for shear at the interface between
concrete cast at different concrete cast at different times. A design example (worked example 1) is included here to
illustrate the process, as it is required in many areas of hybrid design where precast and
times in-situ concretes are combined to produce composite sections. The example using
hollowcore without structural topping is a useful one as it is more critical than diaphragms
with any topping.

A further consideration is the shear connection between the hollowcore units and also
between the end unit and the bounding beam. In this case, the connection to the main
support beams and the longitudinal steel in the support beams is usually sufcient to
ensure that the hollowcore units cannot move apart and so the structural model used in
worked example 1 remains valid.

19

Design of Hybrid Concrete Buildi19 19 29/01/2009 16:48:03


3 Overall structural design
Project details Calculated by
RW Job No.
CCIP-030

Worked example 1 Checked by


OB Sheet No.
WE 1/1
Hollowcore floor acting as a diaphragm
Client
TCC Date
April 08

Check the design of the hollowcore diaphragm, without structural topping, carrying wind load to
walls at each end, as shown below.

Edge beam

vs vs

Hollowcore
unit

vs A vs

KEY
vs - Very smooth surface
s - Smooth surface

Section A - A

Plan: 15 m x 9 m with 250 mm thick hollowcore unit

20

Design of Hybrid Concrete Buildi20 20 29/01/2009 16:48:04


Overall structural design 3
Project details Calculated by
RW Job No.
CCIP-030

Worked example 1 Checked by


OB Sheet No.
WE 1/2
Hollowcore floor acting as a diaphragm
Client
TCC Date
April 08

Wind load: 2 kN/m2 (A high wind load)

Assume a 3 m high storey, calculate maximum moment, MEd, from the diaphragm edge wind load/m run.
wd = 1.5 x 3 x 2 = 9 kN/m Q is taken as 1.5
2
MEd = 9 x 15 /8 = 253 kNm

Calculate shear reaction at the diaphragm edges, VEd.


VEd = 9 x 15/2= 67.5 kN

Assume 2 No. hairpins (U bars), 12 mm diameter, in each 1.2 m wide hollowcore unit.

Check shear at interface: vEdi < vRdi Eurocode 2, Cl. 6.2.5


gives:
vEdi = VEd/(z bi) Eurocode 2, Exp.(6.24)
where
= 1
VEd = 67.5 kN at end of diaphragm
d = 0.83 h and z = 0.67 h (assuming elastic stress distribution)
Hence:
z = 0.67 x 9 = 6 m
bi = 250 50 (say) = 200 mm Eurocode 2, Figure 6.8

vEdi = 67.5 x 1000/(6000 x 200 ) = 0.056 MPa

rRdi is limited to 0.10 MPa (> 0.056 MPa OK) Eurocode 2, Cl.10.9.3(12)

Check vRdi (which is unlikely to control); for this example the first and second terms are small and
may be ignored as a first estimate.

vRdi = fyd ( sin + cos ) 0.5 fcd Eurocode 2, Exp.(6.25)


where
= As/Ai
= 0.5 (very smooth surface) Eurocode 2, Cl.6.2.5 (2)
fyd = the design yield strength of reinforcement
As = the area of reinforcement crossing the interface
Ai = the area of the joint
= 90 for reinforcement perpendicular to the joint
= 0.6 (1 fck/250)

21

Design of Hybrid Concrete Buildi21 21 29/01/2009 16:48:04


3 Overall structural design
Project details Calculated by
RW Job No.
CCIP-030

Worked example 1 Checked by


OB Sheet No.
WE 1/3
Hollowcore floor acting as a diaphragm
Client
TCC Date
April 08

For this example:


As = 2 x 2 x 113 = 452 mm2
Ai = 1200 x 200 = 240 000 mm2

Hence:
= 452/240 000 = 0.00188
and:
vRdi = 0.00188 x 500 x (0.5 x 1 + 0)/1.15 0.5 x 0.6(1 - 25/250) x 1 x 25/1.5
= 0.41 4.5 MPa

Use 2 No. hairpins (U bars) - 12 mm diameter

This check demonstrates that Exp. (6.25) is not usually a limiting control.

The design would now normally continue to calculate the tensile steel required in the edge beam to
carry the diaphragm tensile boom force, taking into account that this calculation must also
consider the other actions for the appropriate combination of actions.

3.5 Interface shear For many beams in HCC there is an interface between concrete cast at different times. The
interface may be between precast and in-situ, two precast elements or in-situ concrete with
a construction joint. All interfaces and critical sections in the composite section must be
considered in accordance with Eurocode 2, Cl. 6.2.4 and 6.2.5 (see example in Section 3.4).
Typical interfaces are shown in the Figure 3.5, and typical calculations are presented in
worked example 2.

Figure 3.5
Typical interfaces between precast and in-situ Interface 3 Interface 2
joints. Interface 4

Interface 1

22

Design of Hybrid Concrete Buildi22 22 29/01/2009 16:48:05


Overall structural design 3
Project details Calculated by
RW Job No.
CCIP-030

Worked example 2 Checked by


OB Sheet No.
WE 2/1
Interface shear between hollowcore slab
and edge beam Client
TCC Date
April 08

Consider Example 13.7 in the Precast Eurocode 2: Design Manual24. Interface shear check is between
the edge beam and in-situ concrete provided in the joint (see figure). In this example the contribution
of the horizontal surface is ignored. The shear resistance of the interface between the upstand of
the precast unit and the main body below should also be checked.

Shear interface

600 175 110

200

In-situ concrete

The flange over each hollowcore is cut out and therefore the units should be temporarily propped.
1 No. H16 U-bar is placed in each void to interlock with projecting reinforcement in the edge beam
as shown.

Assume that the compression flange of the edge beam is 600 + 175 + 110 = 885 mm wide.

Check shear at interface according to Eurocode 2, Cl. 6.2.5.

fck = 35 MPa
fy = 500 MPa
Maximum sagging moment, MEd = 267 kNm
Maximum design shear, VEd = 223 kN
bi = 200 mm
d = 540 mm

MEd/bd2fck = 267 x 1000000/(885 x 5402 x 35) = 0.0296

23

Design of Hybrid Concrete Buildi23 23 29/01/2009 16:48:05


3 Overall structural design
Project details Calculated by
RW Job No.
CCIP-030

Worked example 2 Checked by


OB Sheet No.
WE 2/2
Interface shear between hollowcore slab
and edge beam Client
TCC Date
April 08

From Figure B1 of the Precast Eurocode 2: Design Manual24 find value of z (alternatively find z by
calculation or with any suitable design aid):
z = 0.97

vEdi = VEd /z bi Eurocode 2, Exp (6.24)

where
= ratio of the longitudinal force in the new concrete and the total
longitudinal force
= width of new concrete/total flange width
= 775/885 = 0.88
bi = 200 mm

Hence:
vEdi = 0.88 x 223 x 1000/(0.97 x 540 x 200) = 1.87 MPa

vRdi = c fctd + n + fyd ( sin + cos) 0.5 fcd Eurocode 2, Exp (6.25)

where
c = 0.35 and = 0.6 for a smooth surface
n = 0
= 90
fctd = 1 x 2.2/1.5 = 1.47 MPa
= 0.6(1 35/250) = 0.52 Eurocode 2, Exp (6.6N)

vRdi = 0.35 x 1.47 + 0 + x 0.6 x 500/1.15 0.5 x 0.52 x 1 x 35/1.5 (= 6.07 MPa)

vEdi vRdi 0.515 + 260.9

Hence:
(1.87 0.515)/260.9 = 0.005

Now:
= As /Ai
As,req = Ai = 0.005 x 1200 x 200 = 1200 mm2

Using 3 No. voids each containing 1 No. H16 U bar.

As,prov = 3 x 2 x 162 /4 = 1210 mm2 OK

24

Design of Hybrid Concrete Buildi24 24 29/01/2009 16:48:06


Overall structural design 3

3.6 Shear and torsion Shear and torsion are predominately critical at the ultimate limit state and the composite
design sections can be considered to be monolithic if the interface shear calculations have been
carried out appropriately, as discussed in Section 3.4 (see Eurocode 2, Cl. 6.2.4 and 6.2.5).

The variable strut inclination method used in Eurocode 2 is based on the shear load being
applied at the top of the beam element. When it is applied near to the bottom, the load
must be carried up to the top with vertical reinforcement additional to the vertical
reinforcement required by the shear calculation. This is sometimes called hang up steel,
as its effect is to hang up the applied load to the top compression chord of the beam
(Eurocode 2, Cl. 6.2.1(9)), see Figure 3.6.

Figure 3.6
Hang up steel requirement.

Beam shear strut

Slab shear strut

Hang up steel additional to


reinforcement required to carry
shear Eurocode 2, Cl 6.2.1 (9)

Slab shear strut

Types 2, 3 and 4 apply the oor permanent actions to the spine beams at the bottom of
the section and this element of the load must be carried by hang up steel. Whether the
subsequent variable actions should also be covered in this way depends on the form of
the composite connection. In any event, the load only needs to be carried up once to the
top of the truss and the extra link requirement is not onerous.

Where type 5 is used a further check is required for edge beams or where there is out-of-
balance loading on an internal beam.

The edge beam and internal spine beam with unequal loading in this form of construction
must be designed to resist the torsion set up by the eccentric loading. Both the transient
situation during construction and the ultimate limit state must be considered. The joint
between the beam and its support must also be designed to take this torsion, see Figure 3.7.

25

Design of Hybrid Concrete Buildi25 25 29/01/2009 16:48:06


3 Overall structural design

Figure 3.7
Centre of resistance
Design for torsional restraint. of column

Shear centre of beam

h1

h2

For the torsional design of the edge beam, the design torque is equal to the load multiplied
by the distance from its line of action to the shear centre of the edge element Vh1. For the
design of the temporary support system to give equilibrium, the overturning torque is
equal to the torsional force multiplied by the distance from the line of action of the force
to that of the restraining system Vh2.

3.7 Long-line prestressing Many prestressed precast elements are produced by the long-line pre-tensioning system
system on prestressing beds of up to 200 m in length with built-in jack heads at each end, see
Figure 3.8. The normal construction procedure is as follows:
The moulds are placed in a continuous line along the bed (the number depending on
the length of each unit) and end plates are fitted to the required dimensions of the
units to be cast.
The tendons are laid out and stressed from fixed external jack heads. They pass
through each unit as straight horizontal tendons.
The secondary reinforcement is then fixed within each mould.
The concrete is poured into each mould.
When the concrete reaches the required transfer strength (confirmed by test cubes),
the stress is gradually released from the jack heads and is transferred into the concrete
by anchorage bond.

A typical detail of the placing of moulds on the long-line system is shown in Figure 3.9.

26

Design of Hybrid Concrete Buildi26 26 29/01/2009 16:48:06


Overall structural design 3

Figure 3.8
The long-line pre-tensioning system. Gradual detensioning
mechanism Unit moulds or continuously
Stressed strands extruded units

Jack blocks and embedded


cantilever upright in
concrete strong floor

Figure 3.9
Typical detail of placing of moulds on the Unit in mould Strand Mould end plate
long-line system.

Detail of gap between moulds

Debonding tendons
The position of the strands in the section is normally determined by the length of the unit
and the design loading at mid-span. Stress limits are set for the serviceability limit state
(for further information see Precast Eurocode 2: Design Manual24 and Post-tensioned
Concrete Floors Design Handbook25).

Since the tendons are straight the prestress is the same at the end of the units as it is at
mid-span (apart from within the transmission zone), but there is little balance from the
stresses due to permanent actions at the ends. This creates high-tension stresses at the
top of the section that will be a maximum immediately after transfer of prestress. In order
to reduce these stresses locally some of the tendons are debonded by placing tubing over
them at the end of the unit for the required length, see Figure 3.10.

It should be noted that the bottom strand should not be debonded, as it ensures that the
concrete near the end of the unit has less chance of being damaged. It is advisable to
provide two links just beyond the debonding point in the beam span to restrain anchorage
stresses. Two 10 mm diameter links, the rst at 100 mm from the debonding point and
the second 40 mm beyond that, are typically sufcient. The proximity of the links to the
bonding position ensures sufcient restraint to bursting even if the transmission zone is
less than that assumed in design in accordance with Eurocode 2.

27

Design of Hybrid Concrete Buildi27 27 29/01/2009 16:48:07


3 Overall structural design

Figure 3.10
Typically 7 - 8 protruding links
Typical detail showing the debonding of a
strand. Extra links at
debonding point

Fully bonded stressed strand Debonded strand

Debonding is used in double tee design because it is such a simple and cost-effective
option. An alternative to debonding some of the tendons is to deect them at the ends of
the unit. This method is very seldom adopted, as it requires special features to be built into
the long-line system to take account of the vertical forces involved.

The difference between the effects of straight bonded and debonded tendons is shown in
Figure 3.11.

Figure 3.11
Comparison between straight bonded,
debonded and deected tendons.
Unit with straight bonded tendons Unit with straight debonded tendons

Moments from quasi-permanent loading

Moments from prestress

Balance of moments

Resulting camber

28

Design of Hybrid Concrete Buildi28 28 29/01/2009 16:48:07


Overall structural design 3

Prestressed units camber because of the hogging moment provided by the prestress. A pre-
tensioned prestressed beam with no camber, unless it has a very short span or is debonded,
should be viewed with caution. Camber is equivalent to the deection of a reinforced
concrete beam; in fact for a permanent and variable action balanced by prestress, the
upwards camber would be less than the downward deection of the reinforced section.
This is because the prestressed section would be uncracked and stiffer than the cracked
reinforced beam. Thus, camber should not be a problem but should be allowed for when
setting oor levels. An estimate of camber should be obtained from the manufacturer of
the prestressed unit. It will be affected by the strength of concrete at the time of transfer.

Debonding has the advantage of reducing camber, as the debonded prestressed moment
diagram is closer to the permanent load diagram than the fully bonded one. The typical
camber of a fully bonded 16 m double tee beam carrying car park loading is 35 to 45 mm
and this can be reduced by debonding to the range of 10 to 25 mm. Debonding, however,
reduces the net prestress at the support and this reduces the design shear strength, but
for double tees this reduction is seldom a critical design issue.

3.8 Secondary effects of The occasions where secondary effects (sometimes referred to as parasitic effects) need to
prestressing and the be considered relate to indeterminate frames and continuous beams/slabs. The most likely
example for HCC is where post-tensioned slabs are used. Section 5.6 of the Post-tensioned
equivalent load method Concrete Floors Design Handbook25 describes the phenomena and the use of the equivalent
load method.

3.9 Temperature effects The deection of a oor in response to a temperature gradient can be large and this can
result in rotational movements at supports, which can produce unwanted local damage
such as cracking and spalling. This problem is particularly acute in uninsulated roofs, often
found in car parks. The following simple calculation, worked example 3, gives an idea of the
magnitude of the displacements. Further guidance can be found in Movement, Restraint and
Cracking in Concrete Structures26.

3.10 Differential shrinkage When an in-situ screed is added onto a rst stage cast oor of either reinforced or pre-
stressed construction, the shrinkage of the screed after its initial hydration will develop a
compressive strain in the top of the rst stage cast and will induce a downwards deection
in the span of the composite unit and, if the oor is of continuous construction, a hogging
moment at the supports. Note that these effects are of importance at the serviceability
limit state only, as at the ultimate limit state these imposed strains will have little effect.

Figure 3.12 shows how the strains are built up through the height of the composite section
for a given free differential shrinkage strain, fds. The nal curvature, , is constant across
the section. Design equations can be developed as follows:

29

Design of Hybrid Concrete Buildi29 29 29/01/2009 16:48:07


3 Overall structural design

Figure 3.12 fds


The effect of differential shrinkage across a
section. cp
i

p
yi,b In-situ

ci yp,t

Precast

Force equilibrium:
i Ei Ai = p Ep Ap (1)

p = i Ei Ai /Ep Ap

Section equilibrium (EI = M):


(Ei Ii + Ep Ip) = i Ei Ai ( yi,b + yp,t) (2)

Strain equilibrium:
fds = i + ci + cp + p = i + yi,b + yp,t + p

= (fds - (i + p))/(yi,b + yp,t)

= (fds - (i + i Ei Ai /Ep Ap))/(yi,b + yp,t) (3)

Project details Calculated by


RW Job No.
CCIP-030

Worked example 3 Checked by


OB Sheet No.
WE 3/1
Upwards camber on slab due to
temperature gradient Client
TCC Date
April 08

Calculate the upwards deflection of a 16 m span 300 mm deep simply supported floor resulting from
a temperature gradient of 20C with the upper surface being the hotter. Assume that the gradient
is linear and steady state, and that the temperature coefficient for concrete, , is 10 x 10-6.

The curvature, , from this temperature gradient is


= 20 x /300
= 20 x 10 x 10-6/300
= 0.67 x 10-6

The curvature is constant along the length of the unit.

From the second moment area theorem, the mid-span deflection:


= x l2/8
= 0.67 x 8000 x 4000/1000000
= 21.4 mm

30

Design of Hybrid Concrete Buildi30 30 29/01/2009 16:48:07


Overall structural design 3

Combining (2) and (3):


{yi,b + yp,t + (fds - (Ei Ii + Ep Ip)) (1/Ei Ai + 1/Ep Ap)/(yi,b + yp,t)} = fds

= fds /{yi,b + yp,t + (Ei Ii + Ep Ip) (1/Ei Ai + 1/Ep Ap)/(yi,b + yp,t)} (4)

i = fds /{1 + Ei Ai /Ep Ap + (yi,b + yp,t)2 Ei Ai /(Ei Ii + Ep Ip)} (5)

p = fds /{1 + Ep Ap /Ei Ai + (yi,b + yp,t)2 Ei Ai /(Ei Ii + Ep Ip)} (6)

From equations (4) to (6) all the strains, stresses and forces can be determined.

Worked example 4 describes the method for determining the effect of differential
shrinkage where in-situ concrete is placed on a precast concrete T section.

Project details Calculated by


RW Job No.
CCIP-030

Worked example 4 Checked by


OB Sheet No.
WE 4/1
Differential shrinkage
Client
TCC Date
April 08

Calculate the effect of differential shrinkage in a beam constructed in two stages as shown below.
The element is simply supported and 20 m span. The free differential shrinkage strain is 0.0002.

B785 mesh
1000

100

50

B283 mesh

In-situ concrete 300


2 x 2 No 7.9 super strand

Precast concrete

150

B785 fabric in in-situ concrete


B283 fabric in precast concrete flange
2 x 2 No. 7.9 mm super strand in precast rib

31

Design of Hybrid Concrete Buildi31 31 29/01/2009 16:48:08


3 Overall structural design
Project details Calculated by
RW Job No.
CCIP-030

Worked example 4 Checked by


OB Sheet No.
WE 4/2
Differential shrinkage
Client
TCC Date
April 08

In-situ concrete
fck,in = 25 MPa, fcm,in = 33 MPa, creep coefficient, = 1.5 Eurocode 2, Table 3.1
Ec,in,long = 22 [fcm,in/10]0.3/(1 + ) and Cl.3.1.4
= 22 x (33/10)0.3/(1 + 1.5)
= 12.59 GPa

Section properties, including the reinforcement, are as follows:


Ain = 112 x 103 mm2
Iin = bd3/12 = 1000 x 1003/12
= 87.5 x 106 mm4
yinbar,b = 52.1 mm
zin,b = 1680 x 103 mm3

Precast concrete
fck,p = 50 MPa, fcm,p = 58 MPa, Creep coeficient, = 1 Eurocode 2, Table 3.1
Ec,p,long = 22 x (58/10)0.3/(1 + 1) and Cl.3.1.4
= 18.64 GPa

Section properties, including the tendons and reinforcement, are as follows:


Ap = 101.5 x 103 mm2
Ip = 1220 x 106 mm4
ypbar,b = 237.4 mm
ypbar,t = 112.6 mm
zp,t = 10900 x 103 mm3

Curvature
Using expression (4) above:
Curvature:
1000 x 0.0002
=
52.1 + 112.6 + (12.59 x 87.5 x 106 + 18.64 x 1.22 x 109) x (1/(12.6 x 112 x 103) + 1/(18.6 x 101.5 x 103))
( 50 + 112.6
)
= 0.00058/m

Deection
Deflection from differential shrinkage
= l 2/8
= 0.00058 x 202/8
= 29 mm

32

Design of Hybrid Concrete Buildi32 32 29/01/2009 16:48:09


Overall structural design 3

3.11 Designing for Designers should take into account the stability of the structure during construction:
construction Precast elements are heavy. Bearings must be adequate and be robust enough to
withstand normal unit fixing operations including landing and barring (see Section 6.7).
Beams must be securely fixed and have adequate safe bearing at each end to avoid
overturning, excessive deflection or collapse when the precast elements are placed.
Consideration must be given to the unequal loading when precast elements are being
placed.
Where precast elements are tilted or twisted to allow them to be placed in their final
position consideration should be given to ensuring there is sufficient clearance to
place the unit and achieving the minimum end bearing required in the final position.
Special requirements, such as special fixing techniques, temporary measures or sequencing,
should be clearly conveyed.

33

Design of Hybrid Concrete Buildi33 33 29/01/2009 16:48:09


4 Bearings and movement joints

4. Bearings and movement joints


The design of bearings and joints for hybrid concrete construction (HCC) is critical to the
serviceability and lasting integrity of the structure. Careful design can avoid problems
which lead to deterioration of joints, which ultimately compromise the whole safety of
the structure.

Where a bearing is introduced between precast elements or between precast and in-situ
elements great care is required to take account of all the forces and movements that may
be imposed on the elements connected to the bearing. In addition consideration must be
given to:
how the robustness of the structure is attained
effects of composite action
practical tolerances
temperature changes
shrinkage
differential settlement
effects of repeated changes in imposed deformations
ensuring construction meets the assumption made in design.

The decision to design a full continuity joint or one that allows some movement is critical.
The design must then follow the decision to reach a practical and lasting solution. The joint
detail must be robust and must not deteriorate with time due to the effects of movement.

Joints that are designed to be monolithic are considered in Chapter 5.

4.1 Horizontal forces at Horizontal forces at a bearing can reduce the load carrying capacity of the supporting
bearings member considerably by causing premature splitting or shearing. The forces may be due to
creep, shrinkage and temperature effects or may result from misalignment, lack of plumb
or other causes. Allowance should be made for these forces in designing and detailing by
the provision of:
a) bearings that allow limited movement or
b) suitable lateral reinforcement in both the supporting and supported members or
c) sufficient continuity reinforcement through the joint to resist the lateral forces.

Where type a) bearings are used then conservatively the horizontal design force should
be taken as 20 per cent of the vertical force. A more detailed assessment may show this
force can be reduced. For type b) and c) bearings the design horizontal force should be
not less than half of the design vertical force on the bearing.

Unless top and bottom continuity reinforcement is provided precast oor slabs, e.g. hollowcore
slabs, spanning more than 8 m should be supported on elastomeric bearings, e.g. neoprene.

34

Design of Hybrid Concrete Buildi34 34 29/01/2009 16:48:09


Bearings and movement joints 4

These can normally be attached to the support surface. They allow:


the forces resulting from variation of bearing surfaces to be absorbed
any small horizontal movements to be absorbed without causing cracking and
limited rotation (as a result of cyclic upward and downward deflection) of the precast
slab.

Where top and bottom continuity reinforcement is provided, to make a homogenous


joint it may be acceptable not to provide elastomeric bearings. In this case great care
must be taken in construction to ensure that the precast element is not damaged during
placing and that it can absorb the movements that take place during and after construction
without damage.

4.2 Restrained bearings For bearings that offer signicant restraint to sliding or rotation, e.g. dry bearing on concrete
or mortar bedding, actions due to creep, shrinkage, temperature, misalignment, lack of
plumb and other things must be taken into account in the design of adjacent members.
Further guidance on creep, shrinkage and temperature effects can be found in Movement,
Restraint and Cracking in Concrete Structures26.

The effect of such actions may require transverse reinforcement in supporting and supported
members, and/or continuity reinforcement for tying elements together. They may also
inuence the design of the main reinforcement in such members. Such joints are not con-
sidered suitable for external situations or for spans greater than 8 m for internal situations.

It should be noted that it is unlikely that a dry connection without bedding material will
have a uniform contact surface and that concentrated loading will result that may cause
local cracking.

For joints with bedding material, e.g. mortar, concrete, polymers, relative movement
between the connected surfaces should be prevented during hardening of the material.

The bearing width should not be greater than 600 mm unless specic measures are taken
to obtain a uniform distribution of the bearing pressure.

In the absence of other specications, the bearing strength, fRd, of a dry connection should
not exceed 0.4 fcd and the average bearing stress between plane surfaces should not
exceed 0.3 fcd.

The bearing strength for joints with bedding material should not exceed the design strength
of the bedding material, fbed 0.85 fcd where fcd is the lower of the design strengths for
supported and supporting members.

35

Design of Hybrid Concrete Buildi35 35 29/01/2009 16:48:10


4 Bearings and movement joints

4.3 Movement joints It is possible to deal with movement at bearings using movement joints, and care should
be given to the design and construction, as for bridge decks, to minimise the risk of
failures. In general it is recommended to seek solutions that do not require movement
joints. Figure 4.1 describes potential failure mechanisms that can occur even with a
structural topping.

Figure 4.1
Examples of potential failures at movement Expanding material
to plug gap
joints.
If the bearing material creates large friction
Movement
forces (use neoprene or similar to avoid
this), this can lead to large tension stresses
in both the support and the precast slab
or beam.
Friction can
cause cracking

If no plug, hard material


can prevent rotation
If the space between the precast slab or
beam and the face of the supporting
member is not adequate for the required
Rotation movement or if in time it it lls up with
hard material, then cracking can occur.

If the effects of movement and/rotation


Rotation
cause the line of action to move too close
to the edge of the support, local spalling
can occur.
Rotation can
cause spalling

4.4 Actions and restraints


4.4.1 Action effects In addition to the effects of direct loading (imposed variable and permanent actions) the
following action effects on the elements supported by the bearing must be considered:
shrinkage (both long term and early thermal)
temperature changes (both seasonal and short term)
creep.

36

Design of Hybrid Concrete Buildi36 36 29/01/2009 16:48:10


Bearings and movement joints 4

4.4.2 Restraints In addition to the above action effects the following restraints must be considered:
internal, e.g. from reinforcement, differential shrinkage
edge restraints
end restraints.

For detailed consideration of these effects and restraints refer to Movement, Restraint and
Cracking in Concrete Structures26.

4.5 Design considerations When designing bearings the following details should be checked:
calculation of the bearing area
bearing layout
the detail of the reinforcement in the end of the supported member
the detail of the reinforcement in the supporting member
tolerances
construction issues especially any additional forces imposed on the bearing through
barring the units into final position, see Section 6.8.

4.6 Allowance for The design and detailing of the reinforcement at supports is critical. The supported member
anchorage of reinforcement has to be designed to bear safely onto the support without spalling of the end cover and
also to sustain any forces that may come from shrinkage of the oor, through shortening
at supports of the oor, if prestressed, and from thermal, live and further dead load movements, see
also Section 4.1.

Prestressed members used for ooring are commonly pre-tensioned and the main prestressed
steel continues to the end of the member. Reinforcement in supporting and supported
members should be detailed to ensure effective anchorage, allowing for deviations, see
Figure 4.2.

di = ci + ai with horizontal loop bars


di = ci + ai + ri with vertically bent bars
ci = nominal concrete cover
ai = a deviation (see Section 4.8)
ri = radius of bend (see Table 4.1)

37

Design of Hybrid Concrete Buildi37 37 29/01/2009 16:48:10


4 Bearings and movement joints

Figure 4.2
Effect of reinforcement on bearing d2 > a1 + D a3 c3
dimensions.

r3

r2

c2 > a1 + D a2 d3

Table 4.1 Bar diameter Minimum radius of bend


Minimum bend radii for reinforcement to
avoid damage to reinforcement. 16 mm 2
> 16 mm 3.5

4.7 Bearings that allow Bearings that allow limited movement, e.g. neoprene pads, not only distribute the bearing
limited movement forces over uneven supports but also allow limited rotational and longitudinal movement
of the supported member to take place. The bearing pad also denes the area of load
transfer and thus has a direct effect on the detailed design of the ends of the supporting
and supported members.

4.7.1 Design of the bearing In the absence of other specications, the bearing strength, fRd = fbed 0.85 fcd where fbed is
area the design strength of the bearing material may be used.

4.7.2 Bearing layout The layout of a bearing is critical to its successful execution. The concrete surfaces must be
separated in areas where load transfer is not intended and must be bedded appropriately
where load transfer is required. To ensure that spalling does not take place in the contact
area at the end of the supported and supporting concrete, the provision of sufcient bearing
length must be provided. This should allow for constructional tolerances and ensure the
overlap of reinforcement between the supporting and supported concrete. The required
allowances are shown in the Figure 4.3 and are described in Eurocode 2, Cl. 10.9.5.2. These
will lead to the design of minimum bearing shelf and nib sizes.

38

Design of Hybrid Concrete Buildi38 38 29/01/2009 16:48:11


Bearings and movement joints 4

Figure 4.3
Critical dimensions for bearings. > Da2 + Da3

b1

a1
a1 a2 + Da2
a3 + Da3
a

The nominal length, a, of a simple bearing may be calculated as:

a = a1 + a2 + a3 + (a22 + a32)

where
a1 = net bearing length with regard to bearing stress = FEd /(b1fRd) but not less
than the values in Table 4.2
FEd = design value of the support reaction
b1 = net bearing width
fRd = design value of the bearing strength
= 0.85fcd
a2 = distance assumed ineffective beyond outer end of supporting member
(see Table 4.3)
a3 = distance assumed ineffective beyond outer end of supporting member
(see Table 4.4)
a2 = allowance for distance between supporting members (see Table 4.5)
a3 = allowance for deviation of the length of the supported member
= ln /2500
ln = length of member in mm

Table 4.2 Relative bearing stress, Eda/fcd 0.15 0.15 to 0.4 > 0.4
Minimum value of a1 (mm).
Line supports (oors and roofs) 25 30 40
Ribbed oors and purlins 55 70 80
Concentrated supports (beams) 90 110 140
Key:
a Ed is the design bearing stress

39

Design of Hybrid Concrete Buildi39 39 29/01/2009 16:48:11


4 Bearings and movement joints

Table 4.3 Relative bearing stress, Eda/fcd 0.15 0.15 to 0.4 > 0.4
Distance a2 (mm) assumed ineffective from
outer end of supporting member. Reinforced concrete C30/37
Line 5 10 15
Concentrated 10 15 25
Reinforced concrete < C30/37
Line 10 15 25
Concentrated 20 25 35
Key
a Ed is the design bearing stress

Table 4.4
Detailing of reinforcement Type of support
Distance a3 (mm) assumed ineffective from
outer end of supported member. Line Concentrated
Continuous bars over support 0 0
(restrained or not)
Straight bars, horizontal loops, 5 15, but not less than end cover
close to end of member
Tendons or straight bars 5 15
exposed at end of member
Vertical loop reinforcement 15 End cover + inner radius of bend

Table 4.5 Support material a2


Allowance for deviations for the clear distance
between the face of the supports. Precast concrete 10 l /1200 30 mm
Cast in-situ concrete 15 l /1200 + 5 40 mm
Note:
l is clear distance between supports in mm

An example calculation is shown in worked example 5.

40

Design of Hybrid Concrete Buildi40 40 29/01/2009 16:48:11


Bearings and movement joints 4
Project details Calculated by
RW Job No.
CCIP-030

Worked example 5 Checked by


OB Sheet No.
WE 5/1
Bearing of a hollowcore unit
Client
TCC Date
April 08

A 1.2 m wide hollowcore slab seated on an in-situ concrete nib, treated as a non-isolated member.
The length of hollowcore unit is 9 m. The in-situ concrete beam is class C35/45 concrete.

Actions
Self weight = 3.33 kN/m2
Variable load = 4 kN/m2
Partitions = 1 kN/m2
Finishes = 0.7 kN/m2

Bearing stress
FEd = 9 x 1.2 x {1.35 (3.33 + 0.7) + 1.5(4 + 1)}/2 = 69.9 kN
Assume a 30 mm wide neoprene bearing.
Ed = 69.9 x 1000/(30 x 1200) = 1.94 MPa
Ed/fcd = 1.94/(0.85 x 35/1.5) = 0.098

Geometry
Minimum value of a1 from Table 4.1 for a line support is 25 mm.
Hence:
a1 = 30 mm OK
a2 = 5 mm Table 4.2
a3 = 5 mm Table 4.3
a2 = 15 mm Table 4.4
a3 = 9000/2500 = 4 mm say 5 mm
The reinforcement in the in-situ concrete nib is assumed to be 20 mm vertically bent with a
nominal cover of 20 mm.
d2 = c2 + a2 + r2
= 20 + 15 + 3.5 x 20 = 105 mm
a2 + a2 d2
a2 + a2 = 105 mm

Allowance for clearance at end of unit


a2 + a3 15 + 4 mm = 19 mm say 20 mm

The bearing stress should also be checked for the hollowcore unit.
20

H20 bar

10 30 105
20

41

Design of Hybrid Concrete Buildi41 41 29/01/2009 16:48:11


4 Bearings and movement joints

Figure 4.4
Typical methods to avoid spalling of bearing
corners.

Chamfer option Lowered support area option

Spalling of the support is avoided if a large chamfer is provided on the outer corner or
alternatively a local part of the bearing shelf is lowered, see Figure 4.4.

This and the compressed thickness of any bedding material in the bearing must be sufcient
to avoid contact, taking into account any long-term movements, deection, hogging and
if the oor is laid to a fall for any reason, the difference in angle of the oor softs at its
end and that of the bearer beam. Neoprene is recommended as a suitable material for
bearings but other materials may be used (see also PCI Design Handbook27).

In an HCC situation, the bearing may be in a different state when it carries construction
actions and when it is fully constructed and carries superimposed permanent actions and
variable actions. These interactions should be considered and very soft bearing materials
may be inappropriate if the nal objective is to have a fully continuous connection.

4.8 Connections between Type 3 and 4 systems that use precast oors with in-situ beams do not always have a
precast oors and in-situ direct bearing since the in-situ concrete is often cast against the precast unit. The oor is
propped and the formwork for the edge beam is xed. The steel protruding from the oor
concrete beams units is incorporated into the reinforcement of the edge beam that is then cast. The con-
tinuity steel must be fully anchored in both the in-situ and precast concrete. Consideration
should be given to the possibility of tension occurring in the bottom steel at the support.
This can be caused by temperature and shrinkage effects. The design of the interface for
shear requires the provision of hang-up steel as the shear load in the oor is concentrated
near to the bottom of the section. This is described in Eurocode 2, Cl. 6.2.1 (9) and is also
shown in Figure 3.6.

42

Design of Hybrid Concrete Buildi42 42 29/01/2009 16:48:12


Structural elements and connections 5

5. Structural elements and connections


5.1 Twin wall construction Twin wall panels comprise two skins of precast concrete, connected by steel trusses,
(type 1) which hold the precast skins apart at a constant spacing to produce a wall of a particular
thickness. Figure 5.1 shows a typical view of a twin wall panel system.

Figure 5.1
Typical example of a twin wall panel.
Photo: John Doyle Construction Ltd

The panels are supplied to site, erected and then lled with in-situ concrete to form a
solid concrete wall. The trusses, therefore, also act to hold the skins together against the
pressure exerted by the in-situ concrete before this has cured. A typical layout is shown in
Figure 5.2. The precast skins function as permanent formwork.

The precast skins contain the main horizontal and vertical reinforcement for the wall, in
the form of a cross-sectional area of fabric or bars, which can be specied by the designer.
However, starter bars and continuity reinforcement must be provided within the in-situ
concrete.

Figure 5.2
Simple layout of a twin wall system.

The precast skins are


connected and spaced
by steel lattice

Main horizontal and


vertical reinforcement
for the wall is fitted
within the precast skins

43

Design of Hybrid Concrete Buildi43 43 29/01/2009 16:48:12


5 Structural elements and connections

The twin wall system is often combined with a precast concrete permanent shuttering
system, e.g. lattice girder slabs. This allows the minimum use of temporary formwork on
site. The wall system is ideally combined with a precast lattice or composite slab oor, as
the in-situ element of both the wall and oor can be combined to produce a monolithic
structure.

5.1.1 Manufacturing process The precast skin on one side of the panel is cast horizontally on a steel mould, with the
trusses projecting. After curing, the assembly is rotated so that the trusses face down and
can be cast into the pour for the precast skin on the other side, see Figure 5.3.

Figure 5.3
Precasting sequence for twin wall
manufacture.

a) One side of panel cast with outer face down with trusses projecting upwards

b) Assembly then turned over and the second side of panel cast with outer face down

Fabric reinforcement, which can be specied by the designer, is cast into each precast
skin, see Figure 5.4. A 60 mm thick precast skin could accommodate, for example:
25 mm cover to external face (or as appropriate to meet durability bond and fire
requirements)
16 mm vertical bar
8 mm horizontal bar
10 mm cover to internal face (whilst not required for durability in the permanent
condition, some cover here is advisable).

Clearly, walls that require larger bar sizes to achieve required levels of reinforcement, or
walls in exposed conditions, will in turn need thicker precast skins to achieve required covers.

Overall panel thickness


The nal wall thickness can range typically from 200 to 350 mm in total width, although
thicker walls are possible. A typical 250 mm panel thickness may comprise:
60 mm precast skin
130 mm gap for in-situ concrete, starter bars, continuity reinforcement
60 mm precast skin.

44

Design of Hybrid Concrete Buildi44 44 29/01/2009 16:48:13


Structural elements and connections 5

Figure 5.4
Twin wall connection with a lattice girder slab.

Precast concrete

Lattice reinforcement

In-situ concrete

Vertical reinforcement

Slab reinforcement

In-situ concrete

Lap length Vertical reinforcement

Tie reinforcement

With two layers of reinforcement an overall wall thickness less than 250 mm is difcult
to achieve. This is because the precast skin thickness is typically 50-70 mm each side
(plus tolerance), and the thickness of the in-situ concrete in between must accommodate
starter and continuity reinforcement with sufcient space for the concrete to ow around
the bars, see Figure 5.5. With one layer of reinforcement it is possible to reduce the overall
section thickness to 200 mm. It is worth noting that, due to the manufacturing process,
tolerances on the inside faces of the precast skin are easily controlled and can reduce the
space available for in-situ concrete or starter bars by 10-15 mm each side. Tolerance for
the hybrid panel to be erected over the starters is a related issue and it is advisable to use a
single row of starters, rather than one row each side as for a traditional in-situ wall.

45

Design of Hybrid Concrete Buildi45 45 29/01/2009 16:48:13


5 Structural elements and connections

Figure 5.5
The available space for vertical continuity
reinforcement is restricted.
Photo: Hanson Concrete Products

Overall panel sizes


Typically the maximum panel dimensions are 10 m x 3.5 m as shown in Figure 5.6. These
dimensions are often limited by the capacity of the lifting equipment, transportation or
size of moulds. The minimum dimension of a panel is typically 1.20 m.

Figure 5.6
Typical twin wall maximum panel dimensions.

10 m max.

3.5 m max.

3.5 m max. 10 m max.

46

Design of Hybrid Concrete Buildi46 46 29/01/2009 16:48:13


Structural elements and connections 5

5.1.2 Planning implications A key impact of introducing twin wall panels, as with many prefabricated forms of
construction, is to increase the amount of coordination required early in the programme.
To assist in this planning it is advised that the points below are considered.

Which walls are twin walls?


Agreement on the extent of twin walls is likely to involve architect, client, contractor, and
structural and services engineers. Until fully dened, this decision may have an impact on
the design programme an issue that should be communicated to the proposer of the
system (often the contractor).

Manufacturers requirements and their impact on co-ordination


Often the twin wall manufacturer will require the following to be fully dened before
commencing manufacture:
dimensioned CAD wall elevations showing all walls to be manufactured
locations of all cast-ins (e.g. junction boxes, conduit)
locations and sizes of all holes and cut-outs (e.g. for services, drainage, builders work,
windows, downstand beams)
reinforcement to be cast into the precast skins
locations and details of any bend-out bars required
information showing which side of the panel is to be propped (to permit the prop
attachments to be cast in).

To produce CAD elevations showing this level of detail, the design of the services must be
well progressed (and any builders work holes assumptions agreed and recorded); the
architect must have frozen the wall layout; all suspended and ground slab levels, soft
levels and upstands/downstands must be fully dened and frozen; and the contractor
must have dened a pour sequence so that the side to be propped can be identied. The
designer should allow for the additional time required to coordinate the work.

Detailing continuity rebar at joints


The catalogues of the twin wall manufacturer often show a number of typical joint details
where fabric or loose bars are used, within the in-situ concrete, to provide reinforcement
continuity. It is important to realise that the designer is responsible for detailing and
scheduling such bars despite what may be implied in the catalogues.

Checking of fabrication drawings


It is important that the designer checks the key panel layout drawings. The twin wall
manufacturer produces shop drawings for each panel. They are likely to be presented to
the designer just as the project begins on site. A plan for checking these should be set up
in advance to avoid the conuence of site queries with panel drawing checking creating
possible resourcing difculties at a key project stage.

47

Design of Hybrid Concrete Buildi47 47 29/01/2009 16:48:15


5 Structural elements and connections

5.1.3 Site erection and lling The panels are typically propped on one side only, using typically two pushpull props to
achieve verticality. This requires a cast base slab on at least one side of the wall. If panels
are being erected before the whole slab is cast, coordination with the contractors pour
sequence will be required. Where no slab is adjacent, e.g. walls inside lift shafts, there
should be a clear method statement on how these panels will be safely erected.

The methods of xing the continuity reinforcement, particularly if the walls are acting as
shear walls, should be clearly stated. The contractor should provide a method statement
for the following:
At panel base level, how the panel is fitted over the projecting reinforcement in the
lower slab taking account of the accepted tolerances. Figure 5.7 indicates other points
that should be considered.
At top of panel, how the vertical continuity reinforcement is fixed. One method may
be to tie horizontal fixing bars onto the trusses (say two each side) and tie the vertical
projecting bars onto those. The alternative proposal of pushing them into the wet in-situ
concrete is not recommended. A template for the vertical bars should be considered to
ensure that the next lift of wall panel will fit over them correctly.
For the fabric reinforcement at joints between adjacent panels at the same level, how
this is held in position within the pour (see Figure 5.8).

Figure 5.7
Typical issues to consider in the layout design.

Decide which side props


should be positioned

Decide from which level


the wall should spring

Consider tolerances
for starter bars

48

Design of Hybrid Concrete Buildi48 48 29/01/2009 16:48:15


Structural elements and connections 5

Figure 5.8
Plan view showing horizontal continuity Use of U-bars or links recommended
reinforcement. to ensure reinforcement remains
in correct position during concreting

Distance to 1st truss Check sufficient lap length


is typically 340 mm with reinforcement in skin

As the precast skins take up a fair proportion of the overall width of the wall, the gap
between them is often very narrow in comparison to their height. This may make it difcult
to remove all the air when concreting (blowing out) and the contractor should provide
specic proposals for this. Due to the very low volume of in-situ concrete required to ll
the walls on site, the contractors preference may be to erect a large number of wall panels
at one level, before arranging a concrete pour to ll them. As the precast skins are functioning
as permanent formwork, resisting the pressure of the wet in-situ concrete, the wall manu-
facturers catalogue may have rate of rise limits typically less than 1 m/hr. Coupled with
the low ll volume, this leads to a relatively slow lling process on site, and one that the
operatives may be tempted to speed up! The operatives should be made aware of and
respect the wall manufacturers rate of rise limits. The panels are typically erected on
chocks to leave a gap at the base of around 30 mm. This is the principal means of checking
that the in-situ concrete reaches the base of the pour. Timbers acting as grout checks are
placed along each side at the base of the panel.

Precast lattice girder slab units


Figure 5.9 shows a typical section of a composite oor using precast lattice girder units.
The lattice girder is cast into (usually class C40/50) concrete reinforced with high-yield
reinforcement. The width of the precast slab is typically 2.4 m with a depth of 50 mm or
75 mm. They are used for spans of up to 10 m (larger spans are possible with careful
planning).

Figure 5.9
Section showing typical lattice girder oor. In-situ
concrete

Lattice

Precast
concrete
slab

Main steel
Distribution steel

49

Design of Hybrid Concrete Buildi49 49 29/01/2009 16:48:15


5 Structural elements and connections

Figure 5.10
Typical details of a lattice girder. Top bar 8 mm to 14 mm dia.

Diagonal bar 4.5 mm to 7 mm dia.

Bottom bar typically 5 mm dia.

The design of the lattice girder is dependant on the thickness of the composite oor, nal
loading and propping system. Typical details of a lattice girder are shown in Figure 5.10.

Figure 5.10 shows a typical layout of a 2.4 m wide unit containing four sets of lattice girders.

Propping to support the self-weight and in-situ concrete can be reduced or eliminated by
increasing the stiffness of the slabs through increasing the diameter of the reinforcement to
the top of the lattices and/or reducing the spacing of the lattices. Unpropped spans of up
to 5 m can be achieved depending upon the design loads and the overall depth of the slab.

Temporary propping is required where the end bearing is small. An example of this is at
end supports where the slab unit is seated on just one leaf of the wall.

Normally the minimum cover to the reinforcement will be 20 mm; however, the cover to
the reinforcement can be adjusted to meet the specic bond, durability and re resistance
requirements for individual contracts.

5.1.4 Design of panels Design moments


Design moments about the minor axis of a wall should be considered even where central
bars are placed in the joint, as these do not represent a hinge.

Flexural, shear and axial design


When checking the strength of a section of a wall more than a full lap length from a joint
the full width of section may be included. Otherwise just the in-situ part should be considered.
If the whole section is in compression, it is reasonable to assume that the full section can
provide axial resistance.

Lap lengths
At the top and bottom of the wall there will be a lap between the main vertical
reinforcement and the vertical continuity reinforcement, see Figure 5.4. When the
distance between these bars is greater than 4 or 50 mm the lap length should be
increased by a length equal to the space between the bars (Eurocode 2, Cl. 8.7.2(3)).

50

Design of Hybrid Concrete Buildi50 50 29/01/2009 16:48:16


Structural elements and connections 5

Minor axis bending


If the decision to use a single row of starters has been adopted, minor axis bending on such
walls should be checked. If signicant, the decision should be revisited with potential
impacts on wall thickness, as noted above.

Horizontal joint between panels stacked one above the other (no slab
adjacent)
Horizontal joints commonly occur, for example, in lift shaft walls, or in walls adjacent to
risers, stairs, or double-height spaces. At the panel joint level, effective design to resist
minor axis buckling moments would tend towards the use of two rows of vertical continuity
reinforcement (one layer on each face) within the in-situ portion of the wall. Due to the
position of the continuity bar within the in-situ portion, and the possible tolerance and
positional control issues, a realistic effective depth should be used in assessing the moment
capacity of the wall at this point, see Figure 5.11.

Figure 5.11 C
Detail at an unrestrained horizontal panel
joint in compression.

The tendency to buckle


under compression at an
unrestrained horizontal
joint, is resisted by the
vertical continuity
reinforcement, acting at
a reduced lever arm.

5.1.5 Concrete and nishes Concrete mix


The nature of the in-situ concrete mix used to ll the panels on site should be considered.
As the gap between the precast skins may be as little as 100 mm for a 250 mm wall, and
starters and continuity reinforcement may protrude into this gap, using a vibrator poker
may be difcult or impossible. The use of self-compacting concrete should be considered.
A smaller aggregate size, for example 10 mm, may also be appropriate.

Surface nish
Typically, the use of steel moulds gives the external faces of the panels a smooth nish.
The nish quality is suitable to receive a plaster nish or, on request, wallpaper. It should be
noted, however, that the nish is not architectural concrete as colour is not consistent
or easily specied.

51

Design of Hybrid Concrete Buildi51 51 29/01/2009 16:48:16


5 Structural elements and connections

5.1.6 Detailing Vertical joints between adjacent panels at same level


At junctions between adjacent panels and at corner junctions, horizontal continuity
reinforcement is recommended within the in-situ portion. Detailing this reinforcement in
the form of fabric or prefabricated cages is likely to be the easiest way of xing it within the
pour. As noted above, the designer should be responsible for detailing this reinforcement.
It should be noted that the presence of the trusses at a typical distance of 340 mm from
the ends of each panel effectively constrains the volume in which continuity reinforcement
can be provided. If the forces applied to the wall are such that they cause signicant shear
or tensile forces to develop at the vertical panel joints, the suitability of twin wall panels
as a design solution may need to be revisited.

Interface with reinforced concrete ground slab.


It is important to obtain the contractors pour sequence for the ground slab at locations
where the ground slab steps (changes level) this will often dene the panel base level.
Agree with the contractor whether the panel will sit on the higher-level slab, or on the
lower-level slab with the higher-level slab poured up against the wall. Also agree details
at the edge of slabs or at lift pits. Agree from which side the panels are to be propped. It is
likely that the twin wall panels will need to be installed over projecting starter bars cast into
the foundations. As well as the use of a template and the consideration for using a single
row of starters, as noted above, the starters will need to coordinate with the horizontal
continuity reinforcement provided at locations of vertical joints between panels. This
means ve or six layers of reinforcement locally overlapping within the gap between the
panels a potential congestion issue, see Figure 5.12.

Figure 5.12
Horizontal continuity reinforcement to t
with twin wall reinforcement.

Horizontal continuity reinforcement


lowered into position after placing
twin walls. This must be detailed to
miss the wall trusses

5.2 Precast columns, edge The type 2 system uses precast columns and edge beams, often with a prestressed in-situ
beams and in-situ slabs oor slab. The complex xing of steel and anchorages in the edge strips is more safely
and accurately carried out in the precast concrete factory. The use of precast concrete
(type 2)
columns speeds up the time between the casting of the oor plates. The precast edge
strip is supported on the same shutter system that is used for the oor.

52

Design of Hybrid Concrete Buildi52 52 29/01/2009 16:48:17


Structural elements and connections 5

5.2.1 Column to oor joint The column to oor joint in this form of construction is assumed to be semi-monolithic,
i.e. the in-situ concrete is cast up to the surface of the column or a fully grouted connection
is made.

It may be desirable that levelling devices, for example nuts and wedges, having no load
bearing function in the completed structure should be slackened, released or removed as
necessary. Where this is necessary, the details should be such that inspection (to ensure
that this has been done) can be carried out without undue difculty.

The design of the vertical continuity or tying reinforcement requires careful consideration.
Three examples are shown in Figure 5.13.

Where a central dowel bar, as shown in Figure 5.13, is also acting as a vertical tie, the load
on the grouted connection between the slab and the dowel bar can be signicant. The
designer should ensure that the detail can carry this load either by design or through testing.

Bearing under the precast column


In the absence of more accurate information (derived from a comprehensive programme of
suitable tests), the area of concrete that should be considered in calculating the strength of
the joint should not be greater than 90 per cent of the area of column assumed to be in
contact with the joint, unless specic means are taken to ensure that no voids exist in the
grout. The strength of the concrete in the precast column may be taken as fcd (= 0.85fck/1.5).
The area of any bar passing through the joint should be deducted from the bearing area. The
design force of such a bar may be deducted from the applied force on the bearing when
calculating the capacity of the concrete provided that the bar has sufcient anchorage
beyond the joint.

Grouting
The contractor should provide a method statement for the grouting work. This should
ensure that no pockets of air are trapped in the ducts and that the interface between the
base of the column and support is fully grouted. Trials may be necessary to demonstrate
the method.

Maximum compression through oor


For axial load with moment transfer Eurocode 2, Cl. 6.7 limits the compression within the
slab. Exp. (6.63) is modied to:

FRdu = Ac0,eff fcd (Ac1/Ac0,eff) 3.0 fcd Ac0,eff

where
Ac0,eff = 0.9 x Ac0
Ac0 = area of precast column
fcd = design strength of the slab
Ac1 = (h/2 + b1) (h/2 + d1)
h = depth of slab
b1 = breadth of the precast column
d1 = depth of the precast column

53

Design of Hybrid Concrete Buildi53 53 29/01/2009 16:48:17


5 Structural elements and connections

a) Column shoe

b) Column bar coupler

Hole grouted before


placing column Grouting ring

Bars welded to dowel


table and column
reinforcement

c) Central dowel bar

Figure 5.13
Typical column oor connections.

54

Design of Hybrid Concrete Buildi54 54 29/01/2009 16:48:17


Structural elements and connections 5

Where moment is transmitted through the joint Ac0,eff should be reduced to 0.9 x the
area of the stress block shown in Figure 5.14, where Ac0,eff = 0.9 b1 x 2(d1/2 - e).

Figure 5.14
Stress block in slab where moment is CL of column
transmitted from column.
d1

e = M/N CL of compression
block

fcd

2 x (d1/2 - e)

5.2.2 Vertical tie For class 2B and 3 buildings (risk group 2B and 3 in Scotland) the vertical tie must be
designed to take the full oor load in tension under accidental loading conditions. The
partial factors for the accidental combination of actions are equal to 1 (see BS EN 1990,
and UK National Annex, Table NA.A1.3), see worked example 6.

If a central dowel bar system is considered for such a oor, i.e. span > 7 m, it should be
effectively continuous throughout the height of the building. Full tension mechanical
couplers should be used where joints are required.

5.3 Biaxial voided slabs Figure 5.15 shows a typical section of a composite oor using precast lattice girder units with
spherical void fomers (biaxial voided slabs). The lattice girder and the void former cages
are cast into a (usually class C40/50) concrete panel containing reinforcement in two
directions. The width of the precast slab is typically 2.4 m with a depth of 50 mm or 70 mm.

Normally the minimum cover to the reinforcement will be 20 mm; however, the cover to
the reinforcement can be adjusted to meet the specic bond durability and re resistance
requirements for individual projects.

Figure 5.15
Typical layout of biaxial voided slab.
Photo: Cobiax Technologies Ltd

55

Design of Hybrid Concrete Buildi55 55 29/01/2009 16:48:22


5 Structural elements and connections
Project details Calculated by
RW Job No.
CCIP-030

Worked example 6 Checked by


OB Sheet No.
WE 6/1
Vertical tie
Client
TCC Date
April 08

Consider a 9 m x 9 m flat slab floor 300 mm thick with imposed variable load of 3 kN/m2 and
finishes of 1 kN/m2.

Actions
The total design force in vertical tie
FEd = Gk + Ad Eurocode, Table NA.A1.3
= 9 x 9 x {(25 x 0.3 + 1.0) + (0.5 x 4) = 851 kN.

Resistance
Using a column shoe system: 4 No 25 mm bars will provide a resistance of
FRd = s fyk As
= 1.0 x 500 x 252 x 4 x /4/1000 = 981 kN
FRd > FEd OK

Use 4 No 25 mm bars

5.3.1 Slab geometry Initial sizing can be determined from manufacturers literature. The manufacturer literature
will also advise the size of the spheres available, the spacing requirements and the general
conguration of the slab.

5.3.2 Flexural design The benet of the reduced self-weight should be taken into account in the design. The
design may assume a at slab model, which has been demonstrated as appropriate through
testing of the slabs. A check should be carried out to ensure that the concrete compression
zone remains outside of the depth of spherical void formers. Where this is not the case, as
in heavily loaded slabs, the manufacturers will be able to offer appropriate guidance on
determining the permissible compression zone that can be used in the calculation of the
exural strength.

5.3.3 Shear design Testing has been carried out to determine the shear strength of this type of slab, alongside a
theoretical assessment of the reduction in the shear plane due to the inclusion of the voids.
The manufacturers recommend that shear strength of a solid slab of the same depth should
be reduced by a factor of between 0.55 and 0.6 to obtain the design shear resistance for
the voided slab, see Figure 5.16.

For punching shear it is recommended that the void formers are left out where the design
shear stress exceeds the reduced shear resistance of a voided slab, see Figure 5.16. Punching
shear checks may then be carried out on the solid slab areas around the columns.

56

Design of Hybrid Concrete Buildi56 56 29/01/2009 16:48:23


Structural elements and connections 5

Figure 5.16
Typical layout with nal reinforcement in
place.
Photo: Cobiax Technologies Ltd

5.3.4 Deection control Manufacturers have carried out testing to determine the reduced stiffness of the slabs due
to the voids. Conservatively, the stiffness of the voided slab may be taken as 0.87 times
the stiffness of a solid slab, although in some congurations the factor may be increased
to 0.96. The manufacturers have data available to take advantage of these situations.

When using a nite element analysis, the stiffness of the slab (by adjusting the modulus
elasticity) can be reduced accordingly. The use of the span-to-effective depth rules of
Eurocode 2 is not valid for this form of construction since it is not clear how the slab
stiffness is incorporated in the manufacturers design expressions.

5.3.5 General considerations Splice bars are used across the panel joints so that the slab may be designed as a continuous
member. Figure 5.16 shows a typical layout including the nal reinforcement.

Buoyancy of voids
Whilst the concrete is being place and vibrated, the buoyancy force can reach the displaced
weight. The void formers are held in place by:
firm tying of the void former to the lower and upper reinforcement
casting of concrete in several stages (normally two, but three may be required where
the voids are larger than 360 mm).

Slab edges
Voids are not normally provided near slab edges to ensure a robust and continuous edge
detail.

57

Design of Hybrid Concrete Buildi57 57 29/01/2009 16:48:24


5 Structural elements and connections

5.4 Prestressed hollowcore Prestressed hollowcore units are produced by an extrusion or slipform process with a
units typical width of 1200 mm, in lengths of up to 200 m. Each length is prestressed before
casting. After curing, the units are sawn to the required length. Figure 5.17 shows a typical
production layout.

It should be noted that where the only reinforcement in the units is the prestressing
strands, as is common, it makes the support zone particularly vulnerable since this is
where the maximum stresses due to bearing, shear and anchorage occur. The design
should be in accordance with Eurocode 2.

Figure 5.17
Typical hollowcore unit production.

Hollowcore units have lateral edges provided with a longitudinal prole in order to make
a shear key for transfer of vertical shear through joints between contiguous elements. For
diaphragm action these joints are designed to resist horizontal shear.

Hollowcore units are often specied from manufacturers tables rather than designed from
rst principles. These tables are based on assumed loading, support and reinforcement
details, and where the actual situation varies from that assumed in the tables, e.g. the
existence of concentrated loads or different re rating, detailed calculations should be
made to verify such units are appropriate.

BS EN 11683 describes the requirements and the basic performance criteria and species
minimum values where appropriate. It covers terminology, performance criteria, tolerances,
relevant physical properties, special test methods and special aspects of transport and
erection. Reference should also be made to Precast Prestressed Hollowcore Floors28.

An example of the design of a hollowcore unit is given in Precast Eurocode 2: Worked


Examples29.

5.4.1 Anchorage of Resistance at the end of the hollowcore unit relies on the interaction of shear and bond,
prestressing tendons therefore it is very important to understand the end prestressing conditions of hollowcore
units. Figure 5.18 shows how the stress in the prestressing wires or strands and the moment
of resistance, builds up from the end of a unit and further guidance is given in Eurocode 2,
Cl. 8.10.2.2.

58

Design of Hybrid Concrete Buildi58 58 29/01/2009 16:48:29


Structural elements and connections 5

5.4.2 Transmission length The transmission length, lpt, for the prestressing wires or strands is that length required to
transmit the full prestress, p. lpt is dened in Eurocode 2, Cl. 8.10.2.3 where pt1 and lpt1
are the values at transfer and pt2 and lpt2 are the values after all losses (as shown in
Figure 5.18). The ultimate design strength of the tendon requires further anchorage length.
The slope of the line between pt2 and pd is less than that for the transmission length, lpt2,
because the tendon reduces in size as it is stressed. The reverse is true within the transmission
length over which there is a wedging effect. One reason for assuming a linear build-up of
stress is because any exural stress in this region will tend to reduce the section size and
nullify the wedge effects.

Figure 5.18
Build-up of stress in prestressing wires or Tendon stress
strands from end of unit.
pd
pt1

pt2

Distance from
end of unit

I pt1

I pt2

I bpd

5.4.3 Cracking length The cracking length, lcr, is the distance from the end of the unit to the point where the
bottom bre stress resulting from all actions (bending, prestress and horizontal forces at
the bearings) equals fctd. Figure 5.18 shows the components of actions and the net effect on
the bottom bre stress. Note that if lcr is less than lpt2, the prestress is reduced.

Figure 5.19 indicates the results from the example given in the Precast Eurocode 2: Worked
Examples29.

The following points are of particular note:


Consider all action effects to determine where the unit is likely to crack.
Where dry or mortar bearings are used large horizontal forces may arise from
temperature and shrinkage effects.
In this example the horizontal force at the bearing may cause cracking close to the end
of the unit, before lcr is reached, see Figure 5.19(d).

If cracking does occur close to the support, the shear resistance is likely to be exceeded.

59

Design of Hybrid Concrete Buildi59 59 29/01/2009 16:48:30


5 Structural elements and connections

Figure 5.19
CL CL
Build-up of bottom bre stress in concrete of unit of unit
Support
from end of unit.
Bottom Bottom
fibre fibre
stress stress
fb,m = Mx/Zb
Support fb,P = P/Ac + Pe/Zb

a) Stress due to flexure b) Stress due to prestress

CL
Support of unit

Bottom
fibre
stress

fb,H = H/Ac + Hyb/Zb

c) Stress due to horizontal force at support

Bottom
fibre
stress Possible overstress
CL
near end of unit
of unit
Compression
0
fctd Tension
l cr

fb,Net = fb, M + fb,P + fb,H

d) Net bottom fibre stress showing cracking length, lcr

5.4.4 Total anchorage length The total anchorage length, lbpd, is the distance from the end of the unit to the point
beyond which the full design resistance of the wires or strands can be obtained, as shown
in Figure 5.18.

5.4.5 Tendon slip at ends of When the prestress is transferred from the anchor blocks to the hollowcore units, there is
units anchorage bond along the full length of the strand, apart from the transmission length at
each end of the prestressing line. The concrete is then cut into the required lengths and at
each end a further transmission length is introduced. Although expressions have been
developed to determine the relationship between the end slip of the strands and the
transmission length, it has been shown27 that, for hollowcore units that have been sawn,
there is no simple relationship between transmission length and initial slip at these positions.
This is discussed further in Section 6.6.

60

Design of Hybrid Concrete Buildi60 60 29/01/2009 16:48:30


Structural elements and connections 5

Shear tension Horizontal splitting cracks


crack

Anchorage Large crack


slip close to
support

a) Anchorage bond failure b) Shear tension failure c) Horizontal splitting cracks

Figure 5.20
Types of end failure.

5.4.6 Types of end failure Figure 5.20 shows the three typical types of end failure that may occur. It should be
noted that types a) and b) can interact, one reducing the resistance of the other.

5.4.7 Anchorage bond failure Anchorage bond failure, see Figure 5.20a, may occur due to cracking close to the support
which does not allow the full anchorage resistance to develop and strands start to slip.
This causes the crack to grow until the unit fails. The most common cause of anchorage
failure is when the end of the unit is subject to movement relative to its bearing. This may
be the result of the effects of one or more of the following:
shrinkage
temperature changes
humidity changes
vertical loading.

It is important that the designer considers each of these possible effects. This is especially
important for units with spans greater than 8 m. Reference should be made to
Movement, Restraint and Cracking in Concrete Structures26.

5.4.8 Shear resistance Cracked sections


The cracked shear resistance should be checked at positions likely to be cracked at the
ultimate limit state. The position at which this check should be carried out is at a distance
lcr from the end of the unit, see Section 5.4.3. The shear tension resistance is calculated in
accordance with Eurocode 2, Exp (6.2a and b) together with UK National Annex:

VRd,c = [0.12k(100l fck)1/3 + 0.15cp]bwd

with a minimum of

VRd,c = (0.035k3/2 fck1/2 + 0.15cp)bwd

61

Design of Hybrid Concrete Buildi61 61 29/01/2009 16:48:31


5 Structural elements and connections

where
k = 1 + (200/d)0.5 2.0
l = Asl /bwd 0.02 (normally = 0 since the distance to the end of the unit
< lbpd + d)
cp = NEd/Ac < 0.2fcd (NEd should be taken as p times the prestress force)

Uncracked sections
Shear tension failure, see Figure 5.20, occurs when the tension in the webs of the slab
becomes too high causing a sudden failure. For a circular core section the critical section
for a shear tension failure is likely to be at h/2 from the inner face of the support, see
Figure 5.21. For oval core shapes the critical section is likely to be closer to the bottom of
the section.

Figure 5.21
Critical section for shear tension failure.

Critical position

For circular core shapes = h /2


s For oval core shapes say h /3

The shear tension resistance is calculated in accordance with Eurocode 2, Exp (6.4):

VRd,c = I bw/S {(fctd)2 + lcp fctd }0.5

where
I = second moment of area
bw = width of the cross-section at the centroidal axis
S = first moment of area above and about the centroidal axis
l = lx/lpt2 1.0
lx = distance of the section considered from the starting point of the transmission
length
lpt2 = upper bound value of the transmission length of the prestressing element
according to Exp (8.18) of Eurocode 2
cp = concrete compressive stress at the centroidal axis due to prestress (this
should include p = 0.9)

For cross-sections where the width varies over the height, the maximum principal stress may
occur on an axis other than the centroidal axis. In such cases the minimum value of the
shear resistance should be found by calculating VRd,c at various axes in the cross-section.

(Note: At the time of writing a revision to this expression was being considered by the
Eurocode 2 Committee in discussion with the Committee for BS EN 1168.)

62

Design of Hybrid Concrete Buildi62 62 29/01/2009 16:48:31


Structural elements and connections 5

5.4.9 Further design checks BS EN 1168, Precast concrete products Hollowcore slabs3 sets out further design checks
that are required:
Prevention of horizontal splitting cracks (Cl. 4.3.3.2.1)
Combined shear and torsion (Cl. 4.3.3.2.2)
Shear capacity of longitudinal joints (Cl. 4.3.3.2.3)
Punching shear capacity (Cl. 4.3.3.2.4)
Transverse bending caused by concentrated loads (Cl. 4.3.3.2.5)
Additional torsion where one long edge cannot deflect (Cl. 4.3.3.2.6)

It is also critical that the requirments for bearings, see Section 4, are fully satised,
otherwise there is a danger of deterioration of the supporting nibs and ends of the
hollowcore units that could lead to a shear and anchorage failure of the hollowcore units.

5.4.10 Lateral distribution of Floors are not always uniformly loaded; they often are required to carry point loads and
vertical loads line loads from partitions to supporting beams. BS EN 1168, Appendix C, Transverse Load
Distribution, charts factors that can be used to determine the loads on units adjacent to
the loaded unit. These charts are for use with units in oors with no or one free edge. They
apply to units without structural topping and are therefore conservative for units with
structural topping. BS EN 1168, Cl. 4.3.3.2 provides a method of assessing transverse
tensile stresses in the hollowcore units that are un-reinforced in the transverse direction.

5.4.11 Multi-span without Longitudinal tie bars


structural topping Hollowcore units should be connected to the supports or to the adjacent oor bay by means
of longitudinal tie bars. Tie arrangements should realise the structural integrity and meet
the requirements with regard to:
diaphragm action
transverse distribution of vertical loads
differential settlements
restrained deformation
robustness (in accordance with Section 3.2).

The longitudinal tie bars should be equally distributed and their spacing should not normally
exceed 0.6 m at edge supports and 1.2 m at intermediate supports.

The ties pass through grouted longitudinal joints between units, see Figure 5.22, provided
that they are anchored into the members supporting those units (see also section 3.1), or
in the concreted cores of the units, see Figure 5.23; in either case it important that the
bars are xed in the correct position, as shown. If the latter method is used, note that it is
essential that, after removing the top ange, the open core is thoroughly cleaned to allow
good bonding of the new and old concrete.

63

Design of Hybrid Concrete Buildi63 63 29/01/2009 16:48:32


5 Structural elements and connections

Figure 5.22
Placing tie bars between hollowcore units.

h/2

2, Limits to the 2,
25 mm placing of tie 25 mm Limits to the
bar placing of tie
bar

40 mm

a) With grouting key at top b) With grouting key at bottom

Figure 5.23
Placing tie bars in hollowcore unit.
h/2

Normal limits to
placing of tie bar

The yield load of the tie bars anchored in any core of a unit or between units should not
exceed 80 kN and the total yield load per unit should not exceed 160 kN. If the yield load
for a tie bar between units is greater than 30 kN, hooked bars should be used. In such cases
the anchorage length should not be less than 75, as shown in Figure 5.24. Otherwise
straight bars may be used with a minimum anchorage length of 100.

Figure 5.24
Minimum length of tie bar between units.

h/2

75 lcr

The anchorage length of a tie bar should not be less than lcr (see Section 5.4.3). The anchorage
length should normally be sufcient to anchor the yield load of the tie bar (see also Precast
Prestressed Hollowcore Floors28). In order to prevent progressive collapse the anchorage
length should be increased by lb in accordance with Table 5.1 (see worked example 7).

Table 5.1 Concrete grade


Additional anchorage length, lb, for ribbed tie
bars with regard to design against progressive C20/25 C30/37
collapse. Grout 13 10
Concrete 11 9

64

Design of Hybrid Concrete Buildi64 64 29/01/2009 16:48:32


Structural elements and connections 5
Project details Calculated by
RW Job No.
CCIP-030

Worked example 7 Checked by


OB Sheet No.
WE 7/1
Anchorage length of longitudinal tie bar
Client
TCC Date
April 08

Consider the use of 20 mm size straight bars with C30/37 grout.


lcr = 1080 + 10 x 20 = 1280 mm For example 10 of
Precast Eurocode 2:
Worked Examples29
Minimum length of 10 = 10 x 20 = 200 mm.

Use anchorage length = 1280 mm

Where further strengthening of the support zone is required the tie bars should be anchored
to transfer their yield load at any cracked section within the critical support zone. In such
situations the tie bar should be placed above the mid-height of the hollowcore unit to
provide moment capacity and should be anchored with a hook. An additional anchorage
length, ladd, should be provided to ensure the shear transfer between the in-situ concrete
or grout and the hollowcore unit.

ladd = Fst/fctu

where
Fst = tensile capacity of the tie arrangement in one core or joint
fct = tensile strength of the in-situ concrete or grout
u = perimeter is of the core or 2h for anchorage in joints (h is height of the
hollowcore unit)

Alternatively, straight bars may be used. In this case the anchorage length should be
increased to lcr + lbd (see Eurocode 2, Cl. 8.4.4) (+lb) for anchorage in concreted cores
and to lcr + 100 for anchorage in grouted joints.

Connections to walls
If the wall supports more than three oors, it is advisable to provide hollowcore units with
slanted ends and for the ties to be anchored in the concrete cores (not between units) as
shown in Figure 5.25. It is important that the reinforcement is detailed to interlock as shown.
If the wall supports less than three oors, it will normally be satisfactory for the units to
have a square cut, but the reinforcement details should be as shown in Figure 5.25. Details
that do not provide a mechanical link should not be used.

65

Design of Hybrid Concrete Buildi65 65 29/01/2009 16:48:33


5 Structural elements and connections

a) Edge support b) Intermediate support

Figure 5.25
Connections to walls.

In-situ concrete

In-situ
concrete

a) Edge support b) Internal support

Figure 5.26
Connections to beams.

Connections to beams
Typical connections to beams are shown in Figure 5.26.

Connections to ledge beams


The continuity tie reinforcement should interlock with the reinforcement of the supporting
beam. A typical detail is shown in Figure 5.27. The ange width of the supporting ledge
beam should be limited to the continuous solid section at the ends of the hollowcore
units or conned to the depth of their top anges.

66

Design of Hybrid Concrete Buildi66 66 29/01/2009 16:48:33


Structural elements and connections 5

Figure 5.27 Transverse tie bars


Typical detail for connections to ledge beam.

/b (+D/b) /cr

Figure 5.28
Typical detail showing the tie reinforcement
within the structural screed.

Tie reinforcement within structural screed Tie reinforcement within hollowcores

Tension lap length

a) For Class 2A structures b) For Class 2B and over structures

Figure 5.29 Tying reinforcement within hollowcores


Typical detail showing connection of tying
reinforcement to an edge beam.

Tension lap length

a) For Class 2A structures b) For Class 2B structures

5.4.12 Multi-span with Figure 5.28 shows a typical detail where the tie/exural reinforcement is placed within
structural screed the structural screed.

Where the structural screed is used to provide the tie and exural continuity reinforce-
ment it should be adequately tied to the perimeter ties. Figure 5.29 shows a typical detail
for this.

5.4.13 Dimensions The permitted deviations are specied in BS EN 1168, which are complementary to those
given in Eurocode 2. BS EN 1168 provides further restrictions with respect to cover based
on the geometry of the hollowcore units. The following are extracts from that standard.

67

Design of Hybrid Concrete Buildi67 67 29/01/2009 16:48:33


5 Structural elements and connections

5.4.14 Tolerances for The maximum deviations, unless declared by the manufacturer, shall satisfy the following:
construction purposes slab length 25 mm
slab width 5 mm
slab width for longitudinally sawn slabs 25 mm

5.4.15 Minimum concrete The minimum cover cmin to the nearest concrete surface and to the nearest edge of the
cover and axis distances of core, as stated in BS EN 1168 shall be:
for the exposed face, the one determined in accordance with Eurocode 2, Cl. 4.4.1.2;
prestressing steel for preventing longitudinal cracking due to bursting or splitting and in the absence of
specific calculations and/or tests as follows:
when the nominal centre to centre distance of the strands 3: cmin = 1.5;
when the nominal centre to centre distance of the strands < 2.5: cmin = 2.5;
cmin may be derived by linear interpolation between the values of above

where is the strand diameter (mm). In the case of different diameters of strand, the
average value shall be used for .

5.5 Double tee beams Double tee beams are ribbed units, usually with two ribs in each 2.4 m wide unit. Other
widths can be provided. It is also possible to obtain an inverted trough unit with the ribs at
each unit edge. The double tee is the lightest precast unit for spans in the 9 to 20 m range
thus requiring a lighter support structure than hollowcore, for example, see Figure 5.30.
Alternatives to double tees exist in the form of multi-rib units, usually with three ribs.

a) Without structural screed b) With structural screed

Figure 5.30
Typical double tee units.

68

Design of Hybrid Concrete Buildi68 68 29/01/2009 16:48:34


Structural elements and connections 5

The shape of the of the double tee unit is particularly suitable and economical for pre-
stressing because of the high position of the neutral axis, which maximises the lever arm,
and because the ratio of the top and bottom bre modulus is similar to the concrete to
steel modular ratio.

Double tee units can be procured in a variety of depths, from 300 to 800 mm and even
beyond, but the most common unit is 600 mm deep as this conveniently carries ofce
loading to 12 m and car park loading to 16 m. The most common application of double
tee units is in car park structures. The top ange is usually 50 or 60 mm deep and the ribs
taper from a minimum of 140 mm at the base, widening towards the underside of the top
table, the taper of 1 in 20 each side allowing for easy lifting out of a xed mould. There are
variations to dimensions as some manufacturers have xed moulds set for the full depth,
e.g. 800 mm, and t pallets inside to make units of less depth; thus the shallower the unit is,
the wider the bottom of the web. It is advisable to check what dimensions are available from
the manufacturers at the time of design, although these variations are not usually critical.

In order to achieve maximum economy, grids should be at 2.4 m modules, 7.2 m being the
most common. Specially shaped units, to cover irregular grid areas, narrow or tapering
units, units with splayed ends and notched units to t round columns and others, can be
supplied.

Double tee units are normally designed by the precast manufacturer and a typical example
of this is given in the Precast Eurocode 2: Worked Examples29.

BS EN 13224, Precast Concrete Products Ribbed Floor Elements5 provides the specication
for materials, production, properties, requirements and methods of testing for ribbed oor
elements. This includes a section on permitted deviations and minimum dimensions.

5.5.1 Self-stressing moulds A less common system for manufacturing double tees is by using self-stressing moulds.
These can incorporate deected strands (see Taylor30).

5.5.2 Welded joints Welding is commonly used in double tee construction as tests and experience show that
the welded connection between anges is the only method of connection that is positive,
taking account of differential camber, and that gives excellent long-term performance
with respect to controlling cracking at the ange joints in car park construction from the
rolling loads (see Figure 5.31).

In car parks it is common for the weld plates and the welded cross-bar to be in stainless
steel with the anchor bars beneath the concrete surface in mild steel. Manufacturers have
procedures for ensuring the stainless to mild steel welds are made correctly, and account
for the higher temperatures required with stainless steel. This can result in more expansion
of surface mounted plates and spalling on site.

69

Design of Hybrid Concrete Buildi69 69 29/01/2009 16:48:34


5 Structural elements and connections

Figure 5.31
Typical double tee connection details.

100 x 40 shear connector


with 25 bar in welded
connection

100 x 100 steel plate


anchored into double tee unit
(The plate should be welded
to the anchorage bar)

Where welding is permitted it should be the responsibility of an erection subcontractor


and carried out before the structure, including any areas immediately below, is released
for access by other trades. Thus safety issues with respect to personnel (arc eye) and re
in debris beneath are controlled.

It is essential to ensure that the erection subcontractor is experienced in welding work,


that modern gas shielded weld procedures are used by trained and tested welders and
that site procedures take account of welding hazards with respect to shielding from arcs
and in the removal of any ammable material from the workplace.

Weld inspection procedures should be agreed with the welder. End connectors are critical
and should all be de-slagged and inspected. The number of ange connectors usually
allows inspection to be on an agreed statistical basis.

5.5.3 Structural topping Double tee secondary reinforcement usually consists of end cages, which commonly pro-
trude from the top surface of the unit to bond into the structural topping, and a special
light fabric in the top table (ange), sometimes held in place by ve or seven stressed
wires. To assist shear ow from the rib to ange at the ends, it is also usual to provide
some transverse steel in the ange at the end, see Figure 5.32.

70

Design of Hybrid Concrete Buildi70 70 29/01/2009 16:48:34


Structural elements and connections 5

Steel end plate with


internal anchor for May protrude into
tie to support structural topping Lifter position decided
by supplier

Transverse bars for


shear flow with flange

U-bars to close links


at end of web.

Upper strand layer


may be debonded Link cage nominally
10 mm at 50, 100 &
200 ctrs in end 2d of
unit to aid anchorage
of strands
Lower strand layer
should never be
debonded

End U-bar or anchored


angle to restrain spall
potential at end of rib

Figure 5.32
Typical double tee end detail. Where the designer has designed the double tee oor as a slab in accordance with Eurocode 2,
Cl. 6.2.1 (4) minimum shear reinforcement is not required when VEd VRd,c. Apart from the
main stressed strands, double tee beams often only have reinforcement in the form of a
light fabric in the top ange to control shrinkage and transportation stresses and a light
end cage in the web to control transfer transmission zone stresses.

Structural concrete screed with fabric reinforcement is often provided for the nal structure.
This is also used to augment the welded connections between units. The lateral shear con-
nectors, which should be welded, provide lateral continuity between the double tee units
and can spread concentrated loads from one unit to another. The fabric size is dened by
the need for transverse ties (they augment the welded shear connection tie capacity) and
in some cases for load distribution of point loads on the oor to adjacent units.

5.5.4 Transverse distribution Floors are often required to carry point loads and line loads from partitions to supporting
of concentrated loads beams. Eurocode 2, Cl. 10.9.3 (5) states that transverse distribution of loads should be
based upon analysis or tests. The designer should check any test report carefully to ensure
that it covers the specic design situation. It is not recommended that differences between
the deection of units are removed by jacking and then welding the shear keys. Any shear
forces resulting from such an operation or any other load variation should be considered
in the design of the connections.

71

Design of Hybrid Concrete Buildi71 71 29/01/2009 16:48:35


5 Structural elements and connections

It is recommended that the width of slab assumed to contribute to the support of concen-
trated loads (including partitions in the direction of the span) should not exceed the width
of three precast units and joints, plus the width of the loaded area, or extend more than a
quarter of the span on either side of the loaded area. In some forms of construction, for
example long span wide units, these limits may be inappropriate and more detailed con-
siderations should be made. Where there is a reinforced structural topping the width of
four precast units and joints may be allowed to contribute. Elliott23 gives further information.
Double tee oors can be designed either to carry line partition loads by providing extra
strength in the unit beneath or by a 2D elastic analysis. The double tee deck can be taken
as being comprised of a two-way beam grillage with the beam stiffness in one direction
and the ange stiffness from the full ange depth in the other, even where the anges
between adjacent double tees meet.

Double tee beams can be provided with additional reinforcement, for example links and
additional longitudinal steel for more than the normal one hour of re resistance, shear
reinforcement for exceptionally heavily loaded cases and top steel for cantilever ends.

5.5.5 Tying requirements Typical end and side connections are shown in Figure 5.33; these connections can be part
of the tying strategy of the complete design.

Free standing double tee beams with end and side shear connectors should always be put on
elastomeric bearings. A mortar bed may only be used if sufcient reinforcement is provided
through the joint to ensure that it behaves monolithically as shown in Figure 5.33, see
also Section 4.1. The welded connection in Figure 5.33a is formed from two surface plates
with anchoring reinforcement welded to it cast into and anchoring around the beam
longitudinal steel, and in the double tee rib anchoring to the end cage. A surface plate is
then placed on top and welded down with llet welds. This anchorage can be used as part
of the transverse tying of the structure.
Figure 5.33
Typical double tee connection detail.

End of web End of flange


End connector with
welded tie bar
Structural
topping

Double tee

a) Standard double tee support b) Support of double tee with full continuity.
with welded connection Note: Temporary support of beam may be required

72

Design of Hybrid Concrete Buildi72 72 29/01/2009 16:48:35


Structural elements and connections 5

Double tees cast into in-situ edge beams should have protruding steel as a tie and this
steel should be taken far enough into the double tee to ensure that it is fully lapped with
the stressed reinforcement.

5.5.6 Half joints To create half joints the ends of double tee units may be scarfed, as shown in Figure 5.34.
Ends should not be scarfed to more than two-thirds of their depth, for example a 600 mm
deep unit may be scarfed to 400 mm. Scarng allows the edge beams to still support the
double tee in the temporary situation and be no deeper than the double tee itself. The scarf
may also be extended so as to provide a convenient path for services between double tee
ribs. Figure 5.34 shows typical reinforcement in a scarfed end. Debonding should never
be applied to the bottom strands in the rib or to the strands immediately above a scarf.

Figure 5.34
Double tee with scarfed end.

Strut and tie (1) Strut and tie (2)

Reinforcement and anchorage provided for struts and tie layouts 1 and 2

Strand must be
present and must
not be debonded

Chamfer allows inclined tie to


be in optimum position

Strand must not be debonded

Strand must not be debonded

Only additional reinforcement for the mechanism of strut and tie is shown.
This figure is to be read with Figure 5.32

5.5.7 Billet support of double A variant of the half joint support is to use a billet protruding from the rib at the end of
tee units the double tee at a high level, as shown conceptually in Figure 5.35.

This has the advantage that a nibbed bearer beam is not required and that the bearer beam
does not need hang up steel. A disadvantage is that the bearer beam has no restraint to
rotation from the bearing force of the double tee at its soft. This lack of restraint should
be considered in the temporary condition, when there may be out-of-balance moments
on the bearer beam and in the permanent condition for edge beams, or beams supporting

73

Design of Hybrid Concrete Buildi73 73 29/01/2009 16:48:36


5 Structural elements and connections

Figure 5.35
Support of double unit using billet connection. Tie

Strut
Double tee

Tie

The tension in the vertical tie will be about


double the value of the compression forces

oor spans of varying length on each side. Where there is a permanent torsion applied to
the beam, the connection to the supporting column should be capable of providing tor-
sional xity. This should not be a problem if the bearer beam and column are in-situ concrete,
but this would be an important design consideration if the bearer beams are precast.

The billet assembly can be purchased as a proprietary item. The designer should ensure
that the tting is adequate, meets the specication and is suitable for use in the UK.
Galvanised ttings can have corrosion problems in chloride bearing environments so
expert advice should be sought before the ttings are used in swimming pool roofs, car
parks and exposed coastal locations.

Finally, the tting has to be incorporated into the double tee in such a way that it interacts
with the other reinforcement in the unit to develop the strut and tie action, conceptually
illustrated in Figure 5.35. Internal tie forces required for robustness may also have to be
carried by the tting. These may not have been considered in the development of the
tting, particularly if it was manufactured overseas where the traditions of tying structures
may not be the same as in the UK.

5.5.8 Transportation of long Two beams are usually supplied in a load and should be secured in such a way that holding-
double tee beams down straps do not bear on the top ange edges. The site access must be rm without
irregularity. Careless handling and the loading of the top anges with site construction
material can crack the top ange of a unit, typically at the ends at the interface between
the ange and web. Such cracking is unsightly rather than hazardous in the long term and
the manufacturer can be consulted to suggest repair procedures that should be carried
out before the structural topping is cast.

5.6 Stairs Precast concrete stairs are produced to be incorporated within many forms of
construction. This section considers their use within in-situ and precast concrete frames.
Their use has become common, especially within design and build contracts, where the
speed of construction is a benet.

74

Design of Hybrid Concrete Buildi74 74 29/01/2009 16:48:36


Structural elements and connections 5

It should be noted that stairights are the primary means of escape if a building is subject
to re or explosion and thus the robustness of the structure is vital.

BS EN 14843, Precast Concrete Products Stairs8 provides the specication for materials,
production, properties, requirements and methods of testing for precast stairs. This includes
a section on production tolerances and minimum dimensions. It also describes terms and
denitions that are used. With regard to detailing it requires the technical documentation
to include the construction data, such as the dimensions, the tolerances, the layout of
reinforcement, the concrete cover, the expected transient and nal support conditions, and
lifting conditions. In particular, the technical documentation must include the maximum
acceptable gap between components when erected to ensure the design overlap of the
reinforcement is achieved, see Eurocode 2, Cl. 10.9.4.7.

When considering the use of any proprietary system it is essential to consider:


how the stairflight is adequately tied to the adjacent parts of the structure
sequence of construction
temporary works involved
chain of responsibility in achieving the final structure (often the temporary actions, say
due to props, are the critical design condition).

The following procedure and points should be followed.


The working drawings should include complete propping instructions related to the
cube strength of the in-situ concrete (in any event a minimum of four floors should be
propped).
The sequence of construction and grouting-up instructions (if required) should be stated
on the drawings. The method of levelling should be determined and agreed with the
contractor and the method stated on the drawing.
The waist dimension should not be less than 100 mm.
For a precast stair flight on an in-situ landing nib section the precast flight should be
positioned first before the in-situ landing is cast up against it.

5.6.1 Single stair ights Figure 5.36 shows the main features of a typical single stair ight.

Figure 5.36
Typical single stair ight. Tread

Going

Riser Waist

75

Design of Hybrid Concrete Buildi75 75 29/01/2009 16:48:36


5 Structural elements and connections

Production tolerances
The tolerances are given in BS EN 13369, Common Rules for Precast Concrete Products2
and BS EN 148438, table 1, see Table 5.2. Unless stricter tolerances are given in the
project specication these should apply.

Table 5.2 Target dimension of the cross-section in the direction La cb


Tolerances for stairs. to be checked (mm) (mm)
L 150 mm +10
L 400 mm -5 5
15 +15
-10
Key:
a The difference between two consecutive risers must not exceed 6 mm.
b The minimum concrete cover dened in BS EN 14843, Cl. 4.3.7 must take into account the depth of any concrete removed by a nishing
process. The positioning of reinforcement shall ensure that the minimum cover dened in BS EN 14843, Cl. 4.3.7 is achieved.

Minimum dimensions
The minimum dimensions given in Table 5.3 should apply.

Table 5.3 Dimension Minimum dimension (mm)


Minimum dimensions for stairs.
Thickness of a step or landing 45a
Thickness of a wall 80
Thickness of a parapet 60
Wall thickness of a hollow element 45
Plan dimension of a column 120
Key:
a Special care should be taken to ensure the correct position of the reinforcement

5.6.2 Top and bottom Where precast stair ights are used supported on in-situ landings, the landings should be
supports with in-situ cast against the precast ight. This avoids the problems of tolerances where precast ights
are placed on in-situ landings previously cast. Temporary propping will also be required for
connections the precast stairs, see Figure 5.37. Figure 5.38 shows alternative preferred arrangements
of the reinforcement at the joints.

Figure 5.37
Temporary support of precast stairs.
In-situ concrete
In-situ concrete
Precast stair flight

Precast stair flight

Temporary 2 way
braced props
Temporary 2-way
braced props

Note: It is important that the temporary braced props are supported by a permanent structure.

76

Design of Hybrid Concrete Buildi76 76 29/01/2009 16:48:37


Structural elements and connections 5

Screed
H12 bar

Screed
H12 bar

a) Connection with dowel bar only


Screed
H12 bar

b) Connection with hanging and dowel bar

Figure 5.38
Preferred arrangements of reinforcement for
connection with in-situ concrete.

5.6.3 Top and bottom Layout


supports with precast Figure 5.39 shows the preferred dimensions for the detailing of the top joint between a
precast stair ight and a precast support.
concrete
The design of the bearings shall be in accordance with Eurocode 2, Cl. 10.9.5 and due
allowance shall be made for erection tolerances. For the application of this rule, two
classes of stair nibs are dened:
Class A: The stair nib is manufactured with the design end cover in accordance with
BS EN 14843, Cl. 4.3.1.1.
Class B: The stair nib is similar to Class A but with reduced end cover. In this case the full
concrete cover is achieved on site with a non shrink mortar. The result shall be in accordance
with Eurocode 2, Section 4.

Recommended bearing type


The recommended bearing type for precast stairs to precast concrete supports is a 10 mm
thick mortar bedding.

77

Design of Hybrid Concrete Buildi77 77 29/01/2009 16:48:37


5 Structural elements and connections

90 15

10
90 15

100 min

100 min
15 90

a) Landing with sloping interface


10
100 min
90 15

15 90
90 min

10
100 min

15 90

b) Landing with square interface c) Wall with square interface

Figure 5.39
Preferred dimensions for top joint between
stairight and precast support.
Design and supervision considerations
The following should be considered during the design and construction process:
an allowance for a very generous impact factor on self-weight (say 2 or 3) of the
precast flight
checking the consequence if the support is assumed to be at the edge of the in-situ nib
(or designing seating layer to even out the loading)
failure mode in shear and hanging tension behind the nib
the construction procedure and temporary propping loads are properly understood
ensuring that the concrete reaches the required strength
no shims are included
the reinforcement is checked prior to concreting.

Lapped horizontal connection


Figure 5.40 shows a preferred layout of reinforcement. This may not be the easiest way
to construct an acceptable cage but ensures that the dimensions and the positioning of
the loop and link reinforcement is correct.

78

Design of Hybrid Concrete Buildi78 78 29/01/2009 16:48:37


Structural elements and connections 5

Tie reinforcement in structural topping

375 15

Tie reinforcement in structural topping

15 375

Figure 5.40
Preferred layout of reinforcement for precast
joints.

Figure 5.41
Dimensions to allow for dowel hole. 120

35 Screed
40

70

120

Figure 5.42
Reinforcement arrangement for dowel
connection. Screed
375 15

15 375

Dowel connection
To provide sufcient room for a dowel hole the dimensions of the nib need to be as shown
in Figure 5.41.

Figure 5.42 shows the preferred layout of reinforcement for dowel connections, and
worked example 8 shows a typical calculation.

79

Design of Hybrid Concrete Buildi79 79 29/01/2009 16:48:38


5 Structural elements and connections
Project details Calculated by
RW Job No.
CCIP-030

Worked example 8 Checked by


OB Sheet No.
WE 8/1
Dowel bar for connection of precast stairs
Client
TCC Date
April 08

Consider a 1.5 m wide stair flight spanning 4 m, with a vertical spacing between precast units of 10 mm
and using a 20 mm diameter bar for the dowel. The tying force, FEd required should be at least the
permanent action of the stair flight.

Actions
Assume average vertical thickness of stair flight is (150 + 100)2 = 350 mm
Self weight of stair flight
FEd = 25 x 0.35 x 1.5 x 4 = 52.5 kN

Resistance
It can be shown that the maximum dowel force, FRd, is
FRd = b2.(fcd.fyd).{(1 + 2) - }
Asfyd/3 (shear resistance of the dowel)
where
= 3(e/b) x (fcd/fyd)
e = equal to half the vertical spacing between the units
Hence:
e = 10/2 = 5 mm
= 3 x (5/20) x {(0.85 x 40/1.5)/(500/1.15)} = 0.171
and
FRd = 202 x (0.85 x 40/1.5 x 500/1.15) x {(1 + 0.1712) 0.171}/1000 = 33.5 kN
( x 202/4) x (500/1.15)/(3 x 1000) = 78 kN
FRd = 33.5 kN

No reqd = 52.5/33.5 = 1.57

Use 2 No. 20 mm dia. dowel bars

5.6.4 Top and bottom Steel angles are used to allow the stair ight to rest directly onto walls or oor units, see
supports using steel angles Figure 5.43.

Figure 5.43
Support using steel angles.

80

Design of Hybrid Concrete Buildi80 80 29/01/2009 16:48:38


Structural elements and connections 5

Full strength weld to


reinforcement to angle. Structural screed
Lap with structural
Structural
reinforcement.
Structural topping reinforcement

Structural
reinforcement

In-situ structure Full strength weld of reinforcement to angle.


Lap with structural reinforcement.

Figure 5.44
Bottom and top support details using steel The angle provides the bearing onto the supporting structure but often does not have any
angles.
joint continuity reinforcement. The designer should ensure that the design of the precast
unit incorporating such a steel angle is adequate for the particular situation and provides
an adequate tie to the structure. One method of achieving this is to weld reinforcement to
the steel angle and anchor it to the structure through the screed. Typical top and bottom
details are shown in Figure 5.44.

The tension forces transmitted from the angle to the reinforcement within the precast
unit in the top joint requires links welded to the bottom of the top angle. These should be
designed to resist the forces from the angle with the force of the support at the worst
possible position, i.e. when the joint between units is the widest permitted by the tolerances.

The stability of the staircase before the screed has been cast is not normally considered
by the manufacturer. It is essential to ensure that any temporary supports are provided
and clearly identied in the construction sequence. One example is to provide a positive
tie between the ight and the landing by reinforcement welded to the bearing angle (at
the precast factory) to lap with the fabric in the structural topping.

5.6.5 Stairs with integral Stair ights can be provided with an upper or lower integral landing as shown in Figure 5.45.
landings It is important that an insert (typically 50 mm) is provided on the top surface of the
landing. This allows the top nish to be laid uniformly over the whole of the landing
surface, avoiding any steps, due to construction and installation tolerances. In order to
establish an adequate tie to the supporting structure the reinforcement projecting from
the precast unit should interlock with that of the support.

81

Design of Hybrid Concrete Buildi81 81 29/01/2009 16:48:38


5 Structural elements and connections

Figure 5.45
Stairs with integral landings.

50 mm recess for
Bar inserted to lap with finish surface Temporary 2 way
wall reinforcement braced props

Two horizontal bars


inserted within
U bar to lap with
wall reinforcement
In-situ wall

a) Stair flight with integral lower landing

50 mm recess for Bar inserted to lap with


finish surface wall reinforcement

Two horizontal bars inserted


within U bar to lap with
wall reinforcement
In-situ wall

Temporary 2 way
braced props

b) Stair flight with integral upper landing

5.7 Corbels, nibs and half Corbels, nibs and half joints are common to many forms of hybrid concrete construction.
joints The correct position of and cover to the reinforcement is critical to the performance of
this type of element. The design should carefully specify the requirements through the
layout and reinforcement detail drawings.

Corbels should be designed using strut and tie models when 0.4hc ac hc or as cantilevers
when ac > hc, see Figure 5.46 for denitions of hc and ac. Unless special provision is made
to limit the horizontal forces on the support, a minimum horizontal force of HEd should be
combined with the vertical force FEd. Reference should be made to Section 4.1 concerning
the value of HEd.

5.7.1 Design by strut and tie Corbels, nibs and half joints are examples where non-linear strain distribution exists. For
model such situations design using strut and tie models is appropriate. Eurocode 2, Cl. 6.5 provides
advice and stress limitations for the struts and nodes.

82

Design of Hybrid Concrete Buildi82 82 29/01/2009 16:48:39


Structural elements and connections 5

Figure 5.46
Layout of strut and tie for a typical corbel.

FEd
ac

HEd aH
Ftd

ac

z0
s d hc

Strut and tie model for a corbel


Figure 5.46 shows the layout of the strut and tie layout for a corbel.

The following procedure may be adopted to check the strength of the corbel:
The stress in the strut of width x should be limited to Rd,max = 0.34fck(1-(fck /250)),
see Eurocode 2, Exp (6.56). The value of x effects the angle of the strut and hence the
force in the strut.
The position of the top of the strut should be determined by the resolution of FEd and
HEd, and the depth to Ftd (aH), as shown in Figure 5.46.
The angle and width of strut may be found by iteration or by use of the charts given in
Figure 5.36 of the Manual for the Design of Concrete Building Structures to Eurocode 231.
It is recommended that z0 should not exceed 0.75d.
The bearing stress under the load should not exceed 0.48 fck(1- (fck /250)), see Euro-
code 2, Exp (6.61).
Check the tie force, Ftd = Ftd + HEd where Ftd is the horizontal component of the strut
force caused by FEd.
The total area of secondary links should be at least 0.5 area required to resist Ftd, see
worked example 9.

83

Design of Hybrid Concrete Buildi83 83 29/01/2009 16:48:39


5 Structural elements and connections
Project details Calculated by
RW Job No.
CCIP-030

Worked example 9 Checked by


OB Sheet No.
WE 9/1
Corbel design
Client
TCC Date
April 08

Design ultimate load FEd = 300 kN, fck = 40 MPa, distance to the centre of the tension reinforcement
is assumed to be 45 mm. The width of the corbel is 300 mm, other details are as shown below.

300 kN bc = 300

175
160
60 kN
Ftd
45
g

a b
Z0 605

605 650
o
67.64 Z
400

x/2 y
300
x = 120

a) Chosen solution b) Geometry of solution

Actions
HEd = 0.2 FEd = 0.2 x 300 = 60 kN

Geometry
y = 175 + 60/300 x 45 = 184 mm
z = (1842 + 6052) = 632.4 mm
= sin -1 (120/(2 x 632.4)) = 5.44
= tan -1 (184/605) = 16.92
= 90 5.44 16.92 = 67.6
z0/d = (184 tan 67.6)/605 = 0.73 < 0.75 OK

Strut design
Maximum stress in the strut is:
Rd,max = 0.34 fck(1-(fck 250)) = 0.34 x 40 x (1 40/250) = 11.4 MPa Eurocode 2, Exp.(6.56)
For an angle of strut to the horizontal of 67.6 and strut force is:
FEd = 300/sin 67.6 = 325 kN
Hence the stress:
Ed = 326 x 1000/(120 x 300) = 9.1 MPa
Rd,max > Ed OK

Note: Further iteration could be carried out to maximise the strut efficiency.

84

Design of Hybrid Concrete Buildi84 84 29/01/2009 16:48:40


Structural elements and connections 5
Project details Calculated by
RW Job No.
CCIP-030

Worked example 9 Checked by


OB Sheet No.
WE 9/2
Corbel design
Client
TCC Date
April 08

Reinforcement
The tension force in the reinforcement:
Ftd = Ftd + HEd = 300 cot 67.6 + 60 = 183 kN
Area of reinforcement required:
As,req = 183 x 1000/(500/1.15) = 421 mm2
Try H20 bars:
No. reqd = 421/( x 202/4) = 1.34

Use 2 H20 bars

Area of secondary links required = 421/2 = 211 mm2


Try H8 links:
No. reqd = 211/(82 x /4) = 5.2

Use 5 H8 links

See the figure below for layout of reinforcement in accordance with The Standard Method of
Detailing Structural Concrete32.

2 H20 bars

H32 bar

5 No
H8 links

Strut and tie model for nibs


Where a nib is connected to the bottom of a beam, Figure 5.47 shows the arrangement
of strut and ties for a given arrangement of reinforcement.

The angle of the strut should be determined by the position of the centre of the bottom
corner bar of the beam, up to the point of intersection of the resultant of the applied
forces and the centre of the tension bar in the nib.

It should be noted that the reaction, Ft2d in the link bar is FEd (zb + ac)/ zb. The value of zb
may be taken as 0.8 db. Note this force is in addition to any shear force in the beam link.

85

Design of Hybrid Concrete Buildi85 85 29/01/2009 16:48:40


5 Structural elements and connections

Figure 5.47
Nib connected to bottom of beam.

db

F Ed
Zb ac

F t2d
HEd

F t1d

Zn

Strut and tie model for half joints


Figure 5.48 shows the arrangement of struts and ties for a typical half joint. The addition
of a diagonal bar is not considered essential but does provide a more direct route for the
Figure 5.48 forces and better crack control (see also PD 668721 and The Standard Method of Detailing
Layout of strut and ties for a typical half joint. Structural Concrete32).

Full depth links to resist total


reaction equally spaced
Tension anchorage hh

Distance between edge of bearing


and inside of bar to be a minimum
of the bar diameter or 0.75 x cover,
whichever is greater

Cranked bars improve crack control


a) Section

Tension lap

Horizontal U bar with


standard mandrel size

Nominal links at 150


b) Plan

86

Design of Hybrid Concrete Buildi86 86 29/01/2009 16:48:41


Construction issues 6

6. Construction issues
6.1 Method of construction The performance of an HCC structure may be affected signicantly by the construction
method. In order to achieve consistency between design and construction of structures it is
important for the designer to include a method statement as part of the project specication
indicating the assumptions regarding construction. This will bring clarity to the project
and set a benchmark for pricing. The contractor is, of course, free to submit an alternative
price based on different assumptions, if any, from the original design. In this process, the
performance criteria agreed with the client should not be compromised.

Although precast elements generally require less propping than in-situ elements, it is
important to note that the forces in the props are also generally higher and therefore
more care is required when considering the temporary works.

Static equilibrium during construction


BS EN 1991-1-6 Eurocode 1: Actions on Structures Part 1-6: General Actions Actions
during Execution33 and BS 5975, Code of Practice for Formwork34 provide information on
the design of temporary works. The designer should also consider transient situations, for
example the effect of temporary overturning forces during construction. BS EN 1990,
Eurocode: Basis of Structural Design22, Table A1.2(A) describes the load factors that should
be used. Figure 6.1 shows the single arrangement that includes both equilibrium (EQU)
and structural resistance (STR).

Figure 6.1
Temporary loading during construction.
Overturning 1.35* G k,f + 1.5 Qk, c

Qk,c Construction
Resisting 1.15* G k,b

Resistance
beam

G k,f floor

G k,b

* Check that using a factor of 1.0 for both favourable and unfavourable
does not give a more unfavourable effect

87

Design of Hybrid Concrete Buildi87 87 29/01/2009 16:48:41


6 Construction issues

For type 5 form of construction (see Figure 2.1) the in-situ concrete is used to knit the
precast oor and beams together. The support of the precast oor should be designed as a
bearing in the temporary case and, even though the bearing will eventually be part of an
integral system, it will benet from neoprene pads beneath the oor elements. The outer
edge of the supporting beam should include a chamfer to eliminate spalling when the
oor is loaded onto the precast beam and the full load comes onto the combined system.
The chamfer also gives a visually clean edge to the joint between the precast and in-situ
concrete if the precast unit is ribbed a double tee for example. The support and restraint
of the beam onto the column should also be considered in the temporary situation, as
this connection may not be fully made before the in-situ composite concrete is placed.

For construction types 3 and 4, see Figure 2.1, the precast oor is supported on some
form of propped system before the in-situ edge beam is poured. The props should be
designed for the construction loading and a means to gradually release the supported load
onto the composite oor should be devised with back propping if necessary to support
the oors above.

The deection of the shuttering of the in-situ edge beam during casting should be considered.
If the oor and edge beam shuttering are supported from separate propping systems
during the pouring of the in-situ concrete the support struts of the in-situ area will take
up load and may shorten slightly. The oor is on a different set of props and will not
shorten as no extra load is applied to it. This can result in cracking of the top of the oor
near to the support as the moment from the wet concrete is applied. To avoid this risk
entirely, the same support system should be used for the oor and edge beam shutter,
see Figure 6.2.

A neat lower end to an embedded oor unit can be achieved by forming a small groove
in the in-situ concrete. This allows the edge of the in-situ to ll properly, avoids the
likelihood of spalling and masks any slight difference in the soft level, see Figure 6.3.

Figure 6.2
Support for connection.

a) Separate support systems can cause cracking in precast unit. b) Common support of precast floor and insitu beam.

88

Design of Hybrid Concrete Buildi88 88 29/01/2009 16:48:42


Construction issues 6

Figure 6.3
In-situ/precast joint showing groove detail. Construction joint

Groove detail

6.2 Composite action The preparation of the base is of paramount importance. The surface of the precast units
between precast units and should be left rough during production and contained shot blasting equipment (which will
avoid damaging the unit) used to prepare the surface, unless it can be shown that there
in-situ structural topping will be adequate bond. All loose debris should be removed. Where required, the joints
between the units should be grouted at least one day before the screed is placed.

6.3 Specially shaped Hollowcore units are manufactured to a 1200 mm module and double tees are normally to
standard units a 2400 mm module. It is possible to introduce narrow units into a layout or units tapered
in plan if the building layout requires it. In the case of hollowcore, these are cut after manu-
facture, but double tees are cast to the required dimensions. In such cases, the manufacturer
will be able to advise on how to detail the special units so that they are sufciently robust
to be delivered and incorporated into the building successfully and to ensure that exposed
softs look acceptable. In the case of long span units, for example, it may be preferable
to take up a required taper in the last two units rather than have the last unit tapering
excessively. Double tees can also be cast as single tees allowing a greater taper in plan
than can be provided in a double tee unit, see Figure 6.4.

6.4 Long and short units In situations where long and short units are side by side, for example where lift and stair
adjacent to each other cores shorten spans, differential cambers can produce difculties. This is particularly the
case with long span double tees, for example in car parks. A clear span double tee car park
unit may have a camber of 30 mm whereas the unit next to it, spanning from a common
bearing position at one end to a ramp or stair core, may be 12 m long and have a camber
of 10 mm. This difference in level is usually accommodated in practice by bearing the
non-common end of the shorter span at a higher level than the long span unit, as shown
in Figure 6.5. The designer should consult with the manufacturer to obtain an estimate of
these cambers and mark the drawings accordingly.

89

Design of Hybrid Concrete Buildi89 89 29/01/2009 16:48:42


6 Construction issues

Figure 6.4
Specially shaped standard units.

Key
Web
beneath

Figure 6.5
Long and short unit adjacent to each other.

30 mm camber

15 mm camber

Outer supports at same level

Inner supports set approx. 15 mm


higher to reduce camber step
between long and shorter unit

90

Design of Hybrid Concrete Buildi90 90 29/01/2009 16:48:42


Construction issues 6

6.5 Differences of camber In some countries, it is considered good practice to jack double tee anges at mid-span to
in double tees even out camber differences. This is sometimes carried out by casting loops of reinforcement
that protrude from the anges, vertically at mid-span, which are then used as purchase
points for a crowbar or jack. While the built-in stresses from this process do not affect the
ultimate strength of the structural system because of plasticity at the ultimate limit state, it
is not recommended, as it can induce local cracking in the anges, see also Section 5.5.4.

6.6 Method of de-tensioning Double tee units should always be de-tensioned using release jacks that release all of the
double tee units tendons simultaneously and gradually. This is standard practice in the UK, but not throughout
the world. Engineers should be aware of the different practices and ensure that gradual
release is specied and carried out. Otherwise bond checks should be carried out.

6.7 Checking strand or wire Hollowcore units are almost unique in that they are manufactured in a continuous length
pull-in for hollowcore units and are sawn to the required length only after the concrete has reached the appropriate
strength. The de-tensioning process only de-tensions the strands at each end gradually
whereas at the saw cuts a gradual release of tendon stress is not possible. The integrity of
the anchorage bond of the tendons can be checked by examining the pull-in of the strands
at the ends of the unit. Assuming that the anchorage length is in the order of 1000 mm
and that the build-up of strain is linear in that length, as stated in Eurocode 2, a pull-in
design value of 2 mm can be calculated. However, this does not allow for the thickness of
the saw-cut and in practice the measured pull-in is normally less than 1 mm. Manufacturers
should check pull-in on units routinely and reject any with excessive pull-ins.

6.8 Placing hollowcore On site, hollowcore units are often lifted into their nal position using clamp lifting devices
units into the correct that clamp onto the sides of the unit near to each end. The clamp arms are of such a width
that a unit cannot be placed exactly next to an already erected adjoining unit; thus, when
position the lifting device is removed, the unit has to be moved laterally to close up the gap. This
is often accomplished by moving the unit, or barring it with a crowbar. While this may
not cause damage to a short span light unit, there is a risk of breaking a corner of a long
span unit.

Manufacturers recognise that barring of long span and heavy units is not good practice and
provide other means of lifting hollowcore units for this situation, e.g. L shaped lifting
arms or lifting loops cast into the hollowcore units. Lifting loops should be used for the
last unit that has to t into an exact space. If lifting clamps are used, the unit would have
to be placed at an angle, resting on the edge of the previously placed unit, while the clamps
are removed and then barred until it drops into place.

Guidance on the safe practice of barring is given in Code of Practice: For the Safe Erection
of Precast Concrete Flooring and Associated Components35.

91

Design of Hybrid Concrete Buildi91 91 29/01/2009 16:48:43


6 Construction issues

6.9 Production tolerances Production tolerances are specied in BS EN 13369, Common Rules for Precast Concrete
Products2, Cl. 4.3.1.1. For crosssectional dimensions L, the permitted deviation is L, and
for position of reinforcing steel, prestressing steel and for the design cover c the permitted
deviation is c. The permitted deviations of cross-sections for structural elements are
reproduced in Table 6.1.

Table 6.1 Target dimension of the cross-section in the direction L c


Permitted deviations of cross-section. to be checked (mm) (mm)
L 150 mm + 10 5
-5
L = 400 mm 15 + 15
- 10
L 2500 mm 30 + 30
- 10
Notes:
1. Linear interpolation may be used for intermediate values.
2. L and the positive values of c (upper permitted deviation) are given to ensure that deviations in cross-sectional dimensions and in position
of the reinforcement do not exceed values covered by the relevant safety factors in the Eurocodes.
3. The negative values of c (lower permitted deviation) are given for durability purposes.
4. In particular, functional specicities of the products may require tighter tolerances.
5. The given values may be modied by product standards.

The upper permitted deviation for the location of the reinforcement may be determined as
the mean value of the bars or strands in a cross-section over 1 m in width, e.g. slabs and
walls.

The design cover c of the reinforcement shall be at least the minimum cover, cmin, plus
the permitted deviation , cdev, or the producers guaranteed deviation, whichever is lower.

For principal dimensions other than cross-sectional dimensions:

L = (10 + L/1000) 40 mm

where
L is the target size of the linear measure expressed in millimetres

Other types of tolerances may be given by product standards together with the values of
the related permitted deviations, e.g. camber of beams. These values will not include the
deformation effects of any applied load or of prestressing. In the verication of the measured
deviations, such deviations shall be taken into account by computing their value for the
test situation, including all the relevant time-related effects.

92

Design of Hybrid Concrete Buildi92 92 29/01/2009 16:48:43


Special structures - case studies 7

7. Special structures - case studies


This chapter describes two projects that relied upon hybrid concrete construction to
realise an architectural requirement: Lloyds of London36, 1986, and Bracken House37, 1992.

Both these buildings were constructed within a traditional contract procedure led by the
architect. The design engineers and contractors found solutions to ensure that the architects
intent was achieved with the most suitable use of materials. This required very close
cooperation between engineer and architect, with a particular contribution from the
specialist precaster. The input of the contractor to the design solution was small on these
projects.

One of the most important themes common to both projects related to the design of the
structural joints. These were designed either to be:
made of in-situ concrete that connected precast elements to in-situ elements or other
precast elements, allowing for reasonably large construction tolerances or
made with close tolerance templates that ensured that great care had to be taken to
construct them correctly.

7.1 Lloyds of London In 1977 the Committee of Lloyds decided to redevelop their site located either side of
Lime Street, London. Architects Richard Rogers & Partners, with Ove Arup & Partners as
structural and service engineers, won a competition by dening a design strategy rather
than a building. The key points were that it:
allowed for maximum flexibility of use
gave continuity of trading and preserved the Lloyds tradition
did not rely exclusively on providing a new Room as quickly as possible but gave
Lloyds a means of maintaining expansion of business in the short term. The Room is
the heart of Lloyds and is where the underwriters work.

Two important architectural features included in the design brief were:


to show the columns cleanly throughout their height both on the external face and
within the atrium as shown in Figure 7.1.
to show an exposed soffit of diagrid beams at 1.8 m centres.

The resulting design produced a rectangular ring oor with a central atrium. The span of
the oor was 16.2 m (9 x 1.8 m) with a oor-to-oor height of 4.5 m. The oor depth was
1500 mm of which 1150 mm was structural. Prestressed in-situ beams span between
external columns and those at the atrium as shown in Figure 7.2. Further prestressed
beams were required in the corner areas of the building and precast concrete was used for
the column brackets, bearing yokes and stub columns.

7.1.1 Achieving a clean column The design included in-situ columns with precast brackets to support the oors, see
appearance Figure 7.3a and 7.3b.

93

Design of Hybrid Concrete Buildi93 93 29/01/2009 16:48:43


7 Special structures - case studies

Figure 7.1a Figure 7.1b


Lloyds of London redevelopment, external view. Lloyds of London redevelopment, internal view.
Photo: Copyright Arup Photo: Copyright Arup

94

Design of Hybrid Concrete Buildi94 94 29/01/2009 16:48:43


Special structures - case studies 7

Precast yoke

Structural topping Prestressed inverted U beam

Stub column

Steel permanent formwork panels

Precast bracket

Figure 7.2
Layout of the oor components.

Tolerance pocket with


steel inserts

Precast yoke

Stainless steel
flange
Dip groove
Precast
bracket
Steel plate with
shear studs under
In-situ node
Steel dowel

Figure 7.3a left


Precast concrete bracket connection.
Schematic layout of brackets.
Waterproofing detail
Figure 7.3b above
Prefabricated bracing Precast concrete bracket connection.
Elastomeric bearings Precast bracket and yoke.
Photo: Copyright Arup

95

Design of Hybrid Concrete Buildi95 95 29/01/2009 16:48:48


7 Special structures - case studies

7.1.2 Precast brackets The design of the bearing had to full a number of functions:
to carry the vertical load from the floor while allowing for relative rotation as the floor
and bracket deflected, see Figure 7.4a
to transmit the wind and stability forces from the main building into the bracing
system via the bracket, see Figure 7.4b
to restrain the bracket from rotating in plan because this provided stability restraint to
the column at each level, see Figure 7.4c
to allow construction tolerance.

Figure 7.4
Design of bearings.

a) Bearing allowing rotation between filter


and bracket

b) Bearing restrains column c) Bearing transmits shear from building


into bracing

It was decided that all the forces should be carried on the top face of the bracket. The
vertical loads were transmitted through elastomeric bearings. The bearing was bonded to
a plate that was screwed down on an epoxy levelling bed and so could be replaced if
necessary. The horizontal forces were transmitted through four steel dowels. The load on
the dowels was too great to transmit directly into the concrete, so steel bearing-plates
were cast into the top surface of the bracket with welded shear studs projecting down to
transmit horizontal load into the brackets, see Figure 7.3a.

96

Design of Hybrid Concrete Buildi96 96 29/01/2009 16:48:50


Special structures - case studies 7

Connection of precast bearing to column


The way the bracket was connected to the column was one of the key points in its design.
It was essential that this provided a straightforward construction operation, and the details
had to have a proper architectural quality. The solution chosen was to make the bracket an
extension of a ring that would be formwork for the column at that point. The ring would
identify the bracket on the column, visually, and express the connection. The main bracket
reinforcement passed into the column zone within the ring where it turned up and down,
while the ring itself contained nominal reinforcement.

The ring gave two possible sequences of construction:


The bracket could be placed on the column formwork and the columns and the bracket
filled together.
The column could be cast first up to the soffit of the bracket, then the bracket placed
and concreted.

The second solution was chosen because it was thought that it would be too difcult to
hold the ve tonne bracket and column form in place with sufcient accuracy, since this
took place outside the slab. The details of the bracket and column prole were worked out
with the contractor to give grout tight joints while having the necessary visual articulation.
The top of the column was slightly tapered to draw the bracket into the correct position
on a sealing strip.

Because the brackets and some of the columns were heavily reinforced, great care had to
be taken in the design and detailing to ensure that there was no clash. The fact that the
columns were circular made the problem worse. The steel was detailed and xed, with
templates, to precise dimensions that gave a clearance of a few millimetres. As is often
the case with such a sensitive and potentially disruptive detail, so much care was taken
that all went well.

7.1.3 Connection of precast A precast yoke was designed to transmit the loads from the in-situ prestressed beam to
bearing to in-situ prestressed the precast bracket, see Figure 7.3b. The bearing and pockets in the precast bearing were
designed to allow the elastic shortening of the prestressed U-beams to take place before
inverted U-beams grouting the precast yoke. However, the action of prestressing relieved the props of some of
the load of the beam grid and transferred it to the bracket. This applied a moment to the
column that caused an inward horizontal displacement. It was found to be better to grout
the dowels before prestressing, which restrained the column against this displacement. The
columns were pre-cambered outwards to allow for the prestress shortening of the U-beam.
When a oor was cast it was propped down through two levels to limit the amount of load
applied to the bracket and hence rotation.

97

Design of Hybrid Concrete Buildi97 97 29/01/2009 16:48:50


7 Special structures - case studies

7.1.4 Stability The main building contains none of the usual lift, stair and riser cores that can be used for
stability, as these were provided through the satellite towers. A form of bracing between
some of the columns was chosen, see Figure 7.5.

Where the bracing was required extra connections were built into the precast brackets.

Floor grid construction


The oor-to-oor height is 4.5 m, of which 1.5 m is the oor itself. Both the structure and
the services are exposed, with no false ceilings. Air is supplied through the raised oor and
extracted at high level through the light ttings. The return air is taken out through ducts
at stub column level. The permanent formwork panels were made of proled metal sheets
welded to pressed channels, see Figure 7.6. The channels were lipped on the underside to
support the anchors for service hangers in the zone of the stub columns. A typical section
through the oor is shown in Figure 7.7.

Figure 7.5
Main building stability system. T5

T3 T4

T6
T2

T1

98

Design of Hybrid Concrete Buildi98 98 29/01/2009 16:48:50


Special structures - case studies 7

Figure 7.6
Permanent formwork panel with acoustic trays.
Photo: Copyright Arup

Figure 7.7
Typical section through oor. Structural slab Floor finish
50

300
100
60

440 1500
Permanent formwork
Stub columns
& acoustic insulation

550
Diagrid beams

300
1800

The subcontractor developed a formwork system to produce the diagrid beams, see
Figure 7.8. Their design was based on folded and welded steel frames with ply faces.
Neoprene gaskets were built into the metal sections that also formed rebates at joint lines.
The components were xed together with bolts and wedges with adjustment for tolerance.
The reinforcement cages were supported on purpose-made plastic cradles bolted down to
the soft form. These ensured accurate cover, and the threaded insert could be used later to
restrain the top of partitions. This formwork was excellent; it gave a rst-class nish and could
be put together and taken apart very quickly. It was the key to success of this subcontract.

99

Design of Hybrid Concrete Buildi99 99 29/01/2009 16:48:51


7 Special structures - case studies

Figure 7.8
Diagrid beam formwork system.
Photo: Copyright Arup

7.1.5 Points of interest This was a bespoke building and although time of construction was of the essence, the
budget was generous.
The interaction between client, architect and engineer was crucial and favoured the
traditional form of contract.
Much time and effort was spent to provide the most suitable form of construction and
materials, but the contractor provided very little input to the development.
The subcontractor developed a very efficient formwork system.
Precast and in-situ concretes were used appropriately to ensure maximum benefit to
the aesthetics, speed of construction and accuracy of construction.
Considerable effort and money was spent on setting up mock-ups and prototypes to
identify the most appropriate form of construction.
Where it was made clear that great accuracy was required in construction it was
achieved without fuss.

7.2 Bracken House Bracken house is on Cannon Street close to St Pauls Cathedral, London. In 1986 Obayashi
appointed Michael Hopkins as architect and Ove Arup as structural and service engineers to
redevelop a building designed by Sir Albert Richardson. When this was listed it was decided
to retain the two wings of the building and rebuild the centre block. From an engineering
point of view one of the main features of the design was the integration of the structure
and services in the centre block and the way this linked to the construction of the facade.
The design was based on the principle of a wheel in which circumferential primary services
routes around the outside of the building and inside the atrium connect to radial secondary
routes running between radial beams, see Figure 7.9.

100

Design of Hybrid Concrete Buildi100 100 29/01/2009 16:48:53


Special structures - case studies 7

Figure 7.9
Combined structure and services concept.

The concept wheel Structural organisation

Ceiling
extract

Supply

Floor services supply


between structure

Extract

The outer circumferential route is supplied from risers located in the cores between the
wings and the centre block. The inner circumferential ring connects to air exhaust risers
contained within quadrant shaped columns in the corners of the atrium, see Figure 7.10.

For speed of construction the beams were precast, whereas the columns were cast in-situ
because their construction had no time penalty. Alternating in-situ and precast permitted a
very simple connection detail; the beam swelled out at the column position and a pocket was
left out at this point: the column reinforcement passed through the pocket (see Figure 7.11),
which was concreted up before casting the next lift of column. The beams are 650 mm
deep and span 12 m from a column at the atrium to a column that is set back 4.2 m from
the facade, and then continue with a reduced depth of 350 mm on to a support at the
facade. In each of the quadrant corners, eight radial beams are supported on a continuous
corbel that springs from the quadrant columns. There are no circumferential beams. The
structural slab is in-situ concrete placed on metal decking permanent formwork between
the precast beams.

101

Design of Hybrid Concrete Buildi101 101 29/01/2009 16:48:55


7 Special structures - case studies

Above: Figure 7.10


Radial beams and quadrant-shaped column at
atrium corner.
Photo: Copyright Arup

Above right: Figure 7.11


Column beam connection.
Photo: Copyright Arup

The soft of the slab is above the soft of the beam and this zone is used for false ceiling,
sprinklers, lighting, and the extract air plenum, see Figure 7.12. The zone above the 150 mm
slab is used for the oor-based air supply, electrical power and communications. The raised
oor is 300 mm above the beam.

Figure 7.13 shows the oor layout during construction.

Figure 7.12
Typical section through oor zone.
Floor finish Air supply, electrical services and communications

300

950
150 650

250

False ceiling Precast concrete radial beams


Lighting, sprinkers and air extraction

In-situ concrete slab on metal decking

102

Design of Hybrid Concrete Buildi102 102 29/01/2009 16:48:55


Special structures - case studies 7

Figure 7.13
Floor layout during construction.
Photo: Copyright Arup

7.2.1 Points of interest Apart from the plan of the site and the retention of the wings, the most important factor
governing the design was the St Pauls height rule, which restricted the height of the
building to that of the wings to avoid obstructing the view of the cathedral. To fit six
floors within the superstructure height available, while maintaining the clear heights
and raised floor depth required of a modern City office, the depth of the floor zone had
to be as small as possible. The result is a 12 m clear span, with a 950 mm overall, which
provides a clear zone of 300 mm for telecommunications and small power.
By placing the slab towards the middle of the beams the benefit of T-beam action is
lost, but it is this, combined with the radial interleaving of structure and services, that
leads to the minimum possible depth of the structural and services zone. The financial
benefit of the extra floor that this allowed far outweighed the reduction in structural
efficiency.
Similar to the Lloyds contract, the interaction between client, architect and engineer
was crucial and favoured the traditional form of contract.
Precast and in-situ concretes were used appropriately to ensure maximum benefit to
the aesthetics, speed of construction and accuracy of construction. Metal decking
permanent formwork for the slab was chosen for its simplicity and ease of construction.
As the structural slab was in the middle of the floor zone, the metal decking was hidden
by the false ceiling.
There was a strong belief that the joints between precast concrete units should be in
in-situ concrete and that the architecture should reflect this principle.

103

Design of Hybrid Concrete Buildi103 103 29/01/2009 16:48:59


References

References
1 BRITISH STANDARDS INSTITUTION, BS EN 1992-1-1, Eurocode 2: Design of concrete structures-
Part 1-1: General rules and rules for buildings, BSI, 2005.
2 BRITISH STANDARDS INSTITUTION, BS EN 13369, Common rules for precast concrete products,
BSI, 2004.
3 BRITISH STANDARDS INSTITUTION, BS EN 1168, Precast concrete products - Hollowcore slabs,
BSI, 2005.
4 BRITISH STANDARDS INSTITUTION, BS EN 13747, Precast concrete products - Floor plates for
oor systems, BSI, 2005.
5 BRITISH STANDARDS INSTITUTION, BS EN 13224, Precast concrete products - Ribbed oor
elements, BSI, 2004.
6 BRITISH STANDARDS INSTITUTION, BS EN 13225, Precast concrete products Linear structural
elements, BSI, 2004.
7 BRITISH STANDARDS INSTITUTION, BS EN 14992, Precast concrete products Wall elements:
Production properties and performances, BSI, 2007.
8 BRITISH STANDARDS INSTITUTION, BS EN 14843, Precast concrete products Stairs, BSI, 2006.
9 BRITISH STANDARDS INSTITUTION, BS EN 13670, Execution of concrete structures, BSI, due 2008.
10 GOODCHILD, C. and Glass, J. Best practice guidance for hybrid concrete construction. The Concrete
Centre, 2002, Ref. TCC/03/09.
11 THE CONCRETE CENTRE. Hybrid concrete construction. The Concrete Centre, 2005, Ref. TCC/03/010.
12 THE CONCRETE CENTRE. Precast concrete in buildings. The Concrete Centre, 2007, Ref. TCC/03/031.
13 THE CONCRETE CENTRE. Concrete framed buildings. The Concrete Centre, 2006, Ref. TCC/03/024.
14 GOODCHILD, C.H. Economic concrete frame elements. The Concrete Centre, 2008, Ref. CCIP-025.
15 WILFORD, M. and YOUNG, P. A design guide for footfall induced vibration of structures. The Concrete
Centre, 2006, Ref CCIP-016.
16 BRITISH STANDARDS INSTITUTION, BS 8204, Screeds, bases and in-situ oorings, BSI, 2003.
17 DEPARTMENT FOR COMMUNITIES AND LOCAL GOVERNEMENT, Building regulations (England
and Wales) Approved document A (2004). DCLG, revised 2006.
18 THE BUILDING REGULATIONS 2000 (Amended), Statutory Instrument 2000 No 2531 Building
and Buildings, The Stationery Ofce, 2000.
19 BRITISH STANDARDS INSTITUTION, BS EN 1991-1-7, Eurocode 1: Actions on structures Part 1-7:
General actions Accidental actions, BSI, 2006.
20 BRITISH STANDARDS INSTITUTION, UK National Annex to Eurocode 2: Design of concrete structures
Part 1-1: General rules and rules for buildings, BSI, 2005.
21 BRITISH STANDARDS INSTITUTION, PD 6687: Background paper to the UK national annexes to
BS EN 1992-1, BSI, 2006.
22 BRITISH STANDARDS INSTITUTION, BS EN 1990, Eurocode: Basis of structural design, BSI, 2002.
23 ELLIOTT, K S. Multi storey precast concrete framed structures. Blackwell Science, 1995.
24 NARAYANAN, R. Precast Eurocode 2: Design manual. British Precast, 2007.
25 CONCRETE SOCIETY. Technical Report 43: Post-tensioned concrete oors design handbook, second
edition. CS, 2005.
26 CONCRETE SOCIETY. Technical Report 67: Movement, restraint and cracking in concrete structures.
CS, 2008.
27 MARTIN, L. and PERRY, C. PCI design handbook, sixth edition. Precast/Prestressed Concrete
Institute, 2004.

104

Design of Hybrid Concrete Buildi104 104 29/01/2009 16:49:01


References

28 INTERNATIONAL FEDERATION FOR PRESTRESSING. FIP Recommendations: Precast prestressed


hollowcore oors. Thomas Telford, 1988.
29 NARAYANAN, R. Precast Eurocode 2: Worked examples. British Precast, 2008.
30 TAYLOR, H. Strand deection systems in pretensioned, prestressed concrete. The Structural
Engineer, Vol. 70, No. 5, March 1992.
31 INSTITUTION OF STRUCTURAL ENGINEERS. Manual for the design of concrete building structures
to Eurocode 2. IStructE, 2006.
32 INSTITUTION OF STRUCTURAL ENGINEERS/CONCRETE SOCIETY. The Standard Method of
Detailing Structural Concrete, third edition. IStructE, 2006.
33 BRITISH STANDARDS INSTITUTION, BS EN 1991-1-6, Eurocode 1: Actions on structures Part 1-6:
General actions Actions during execution, BSI, 2005.
34 BRITISH STANDARDS INSTITUTION, BS 5975, Code of practice for formwork, BSI 1996.
35 PRECAST FLOORING FEDERATION. Code of practice: For the safe erection of precast concrete
ooring and associated components. PFF, 2007.
36 RICE, P. and THORNTON, J. Lloyds redevelopment. The Structural Engineer, Vol. 64, No. 10,
October 1986.
37 UNKNOWN. Inside job: Bracken House. Architects Journal, 27 May 1992, pp. 2637. Anon.

105

Design of Hybrid Concrete Buildi105 105 29/01/2009 16:49:02


Design of Hybrid Concrete Buildi106 106 29/01/2009 16:49:02
Design of Hybrid Concrete Buildi107 107 29/01/2009 16:49:02
Design of Hybrid Concrete Buildi108 108 29/01/2009 16:49:02
Design of Hybrid Concrete Buildi109 109 29/01/2009 16:49:02
Design of Hybrid Concrete Buildi110 110 29/01/2009 16:49:02
Design of Hybrid Concrete Buildi111 111 29/01/2009 16:49:02
Design of Hybrid Concrete Buildi112 112 29/01/2009 16:49:02
A cement and concrete industry publication

Type 1 Type 2 Type 3


Precast twin wall and lattice girder slab with Precast column and edge beam with in-situ Precast column and oor units with cast in-situ
in-situ concrete oor slab beams

Acknowledgements
The authors would particularly like to thank the following people for their support in the development of this
design guide: Type 4 Type 5 Type 6
In-situ columns or walls and beams with precast In-situ column and structural topping with precast In-situ columns with lattice girder slabs with
Tony Jones Arup oor units beams and oor units optional spherical void formers
Ian Feltham Arup
Typical hybrid concrete options.
The contributions and comments from the Concrete Society Design Group and also from the following Please note this diagram is a repeat of Figure 2.1, page 8.
people are gratefully acknowledged:

John Stehle Laing ORourke


Graham Hardwick John Doyle Construction Ltd
Peter Kelly Bison Concrete Products Ltd
Alex Davie Consultant
David Appleton Hanson Concrete Products
Kevin Laney Strongforce Engineering Plc
Norman Brown British Precast Concrete Federation Ltd

Published by The Concrete Centre


Riverside House, 4 Meadows Business Park, Station Approach, Blackwater, Camberley, Surrey GU17 9AB
Tel: +44 (0)1276 606800 Fax: +44 (0)1276 606801
www.concretecentre.com

CCIP-030
Published January 2009
ISBN 978-1-904482-55-0
Price Group P
The Concrete Centre

Cement and Concrete Industry Publications (CCIP) are produced through an industry initiative to
publish technical guidance in support of concrete design and construction.

CCIP publications are available from the Concrete Bookshop at www.concretebookshop.com


Tel: +44 (0)7004 607777

All advice or information from The Concrete Centre is only intended for use in the UK by those who will evaluate the signicance
and limitations of its contents and take responsibility for its use and application. No liability(including that for negligence) for any
loss resulting from such advice or information is accepted by The Concrete Centre or their subcontractors, suppliers or advisors.
Readers should note that the publications from The Concrete Centre are subject to revision from time to time and should
therefore ensure that they are in possession of the latest version.

Cover photo: Courtesy of Outinord International Ltd.


Printed by Information Press Ltd, Eynsham, UK

Hybrid cov-.indd 2 29/01/2009 16:43:54


CCIP-030
CI/Sfb A cement and concrete industry publication

UDC
624.072.33:624.012.3/.4

Design of Hybrid Concrete Buildings


Design of Hybrid
Concrete Buildings
Design of Hybrid Concrete Buildings A guide to the design of buildings combining in-situ
and precast concrete

R. Whittle MA (Cantab) CEng MICE


This design guide is intended to provide the structural Robin Whittle has extensive knowledge and experience of designing
H. Taylor FREng, BSc, PhD, CEng, FICE, FIStructE
engineer with essential guidance for the design of structures all types of concrete buildings. He regular contributes to concrete
that combine precast and in-situ concrete in a hybrid industry publications and is a consultant to Arup. He was a member
concrete structure. It introduces the options available for of the project team which drafted Eurocode 2.
hybrid concrete structures, and goes on to explain the key
considerations in the design of this type of structure. Howard Taylor has extensive knowledge and experience of

R. Whittle MA (Cantab) CEng MICE H. Taylor FREng, BSc, PhD, CEng, FICE, FIStructE
designing precast concrete elements and buildings, including
Bearings, interface details, consideration of movement, composite developing alternative production methods. He is a past president
action, robustness and the effects of prestressing are all explained in of the Institution of Structural Engineers and is currently chairman
this guide and design examples are included where appropriate. The of the British Standards Institution Building and civil engineering
importance of overall responsibility and construction aspects are also structures Technical Committee B/525.
described.

CCIP-030
Published January 2009
ISBN 978-1-904482-55-0
Price Group P
The Concrete Centre

Riverside House, 4 Meadows Business Park,


Station Approach, Blackwater, Camberley, Surrey, GU17 9AB
Tel: +44 (0)1276 606 800
www.concretecentre.com

Hybrid cov-.indd 1 29/01/2009 16:43:37

S-ar putea să vă placă și