Documente Academic
Documente Profesional
Documente Cultură
16C22C
Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no. RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 16-Jun-17
To the Engineer Report no. 468
School Name Hadar Elementary for Quran-Boys School Code S10
Temperature 45C - 25C Site Hand-Over Day 19-Dec-15
Weather Humidity
Grand Total 18 65 5
16C22C
Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no. RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 16-Jun-17
To the Engineer Report no. 469
School Name Sowaidi Complex School Code C26
Temperature 45C - 25C Site Hand-Over Day 17-Dec-15
Weather Humidity
SubTotal/Main 19 61 3
0
Subcontractors
Sub Total/Subcon 0 0 0
Grand Total 19 61 3
Activities and Tasks*
COMPLETEDACTIVITIES ONGOINGACTIVITIES
Percentage Finish
TypeofWork BuildingName StartDate FinishDate TypeofWork BuildingName Activityname StartDate
Complete Date
Excavation MainBuilding(A)GF 21Jan16 6Feb16 SubStructure Canteen(A) Install&FixingAnchorBolts 60.00% 2Jan17
MainBuilding(B)GF 5Mar16 17Mar16 P.CConcreteforFootings 60.00% 25Dec16
Canteen(B) 19Nov16 22Nov16 R.CConcreteforFootings 60.00% 1Jan17
GuardHouse(A) 28Aug16 30Aug16 GateWork(B) R.CConcreteforFootings 30.00% 11Jun17
GuardHouse(B) 14Nov16 19Nov16 BoundaryWall(A) Install&FixingAnchorBolts 75.00% 25Oct16
GateWork(A) 2Dec16 2Dec16 P.CConcreteforBoundaryWall 95.00% 4Sep16
GateWork(B) 20May17 22May17 R.CConcreteFootingforBoundaryWall 75.00% 17Sep16
WaterTank(A) 28Aug16 30Aug16 BoundaryWall(B) Install&FixingAnchorBolts 75.00% 30Oct16
BoundaryWall(A) 2Jun16 1Jan17 P.CConcreteforBoundaryWall 95.00% 10Sep16
WaterTank(B) 14Nov16 19Nov16 R.CConcreteFootingforBoundaryWall 75.00% 20Sep16
BoundaryWall(B) 11Jun16 1Jan17 Backfilling Canteen(A) BackfillingToBottomOfSlabOnGrade 50.00% 28Jan17
SubStructure MainBuilding(A)GF 11Feb16 30May16 BackfillingToBottomOfGradeBeams 70.00% 23Jan17
MainBuilding(B)GF 28Apr16 26Jul16 GuardHouse(A) BackfillingToBottomOfGradeBeams 50.00% 23Jan17
ElectricRoom(A) 1Jan17 20Feb17 WaterProofing MainBuilding(A)RF TerrazoTiling 95.00% 20May17
ElectricRoom(B) 26Dec16 21Feb17 Canteen(A) BituminousSheet/PaintWaterproofingforFootings 70.00% 21Jan17
Canteen(B) 1Dec16 14Feb17 BoundaryWall(A) BituminousSheetWaterproofingforFootings&Nec 75.00% 28Sep16
GuardHouse(B) 1Dec16 14Feb17 BoundaryWall(B) BituminousSheetWaterproofingforFootings&Nec 75.00% 5Oct16
GateWork(A) 26Dec16 21Feb17 Precast GuardHouse(B) InstallPrecastConcretePanels 40.00% 18Apr17
WaterTank(A) 4Dec16 2Apr17 BoundaryWall(A) PrecastConcretPanelsforBoundaryWall 75.00% 14Nov16
WaterTank(B) 4Dec16 2Apr17 PrecastConcretColumnsforBoundaryWall 75.00% 13Nov16
Backfilling ElectricRoom(A) 23Jan17 25Feb17 BoundaryWall(B) PrecastConcretColumnsforBoundaryWall 75.00% 13Nov16
ElectricRoom(B) 23Jan17 25Feb17 PrecastConcretPanelsforBoundaryWall 75.00% 14Nov16
Canteen(B) 4Feb17 15May17 ConcreteWorks BoundaryWall(A) R.CConcreteColumnNeck&RetaingWallforBoun 85.00% 15Oct16
GuardHouse(B) 23Jan17 15May17 BoundaryWall(B) R.CConcreteColumnNeck&RetaingWallforBoun 85.00% 22Oct16
GateWork(A) 23Jan17 4Mar17 BlockWork MainBuilding(B)GF BlockWork 95.00% 26Nov16
SlabOnGrade MainBuilding(A)GF 28May16 5Jun16 MainBuilding(B)FF BlockWork 95.00% 24Dec16
MainBuilding(B)GF 6Aug16 13Dec16 MainBuilding(B)SF BlockWork 90.00% 22Jan17
ElectricRoom(A) 3Mar17 9Mar17 Plaster MainBuilding(B)GF CementInternalPlastering 95.00% 29Dec16
ElectricRoom(B) 3Mar17 9Mar17 MainBuilding(B)FF CementInternalPlastering 95.00% 16Jan17
WaterProofing MainBuilding(A)GF 22Mar16 13Jul16 MainBuilding(B)SF CementInternalPlastering 70.00% 20Mar17
MainBuilding(B)GF 14May16 13Dec16 Mechanical MainBuilding(A)GF FloorDrain&CleanOut 80.00% 28Feb17
Precast MainBuilding(A)GF 28May16 25Jul16 FireExtingushers 85.00% 2Mar17
MainBuilding(A)FF 26Jul16 30Nov16 HVACDuct 95.00% 12Nov16
MainBuilding(A)SF 8Sep16 1Dec16 AirDistributionSystem&Testing 95.00% 28Jan17
MainBuilding(A)RF 29Oct16 17Nov16 VentilationFans 60.00% 20Feb17
MainBuilding(B)GF 27Jul16 18Dec16 Diffusers&Grills 80.00% 3Feb17
MainBuilding(B)FF 30Aug16 6Apr17 MainBuilding(A)FF FloorDrain&CleanOut 80.00% 1Jan17
MainBuilding(B)SF 24Dec16 10Apr17 ElectricWaterHeaters 95.00% 18Apr17
MainBuilding(B)RF 29Jan17 9Apr17 FireExtingushers 50.00% 2Mar17
ElectricRoom(A) 14Mar17 27Mar17 HVACDuct 95.00% 24Nov16
ElectricRoom(B) 14Mar17 27Mar17 AirDistributionSystem&Testing 95.00% 1Feb17
GateWork(A) 26Mar17 18May17 VentilationFans 60.00% 21Feb17
ConcreteWorks MainBuilding(A)GF 25Jun16 4Jul16 Diffusers&Grills 85.00% 5Feb17
MainBuilding(A)FF 26Jul16 10Aug16 MainBuilding(A)SF FireExtingushers 80.00% 25May17
MainBuilding(A)SF 17Sep16 18Oct16 FloorDrain&CleanOut 80.00% 9Mar17
BlockWork MainBuilding(A)GF 31Aug16 20Apr17 ElectricWaterHeaters 95.00% 18Apr17
MainBuilding(A)FF 8Oct16 4Feb17 HVACDuct 90.00% 2Dec16
MainBuilding(A)SF 8Nov16 27Feb17 AirDistributionSystem&Testing 90.00% 21Feb17
Plaster MainBuilding(A)GF 17Oct16 1May17 VentilationFans 60.00% 23Feb17
MainBuilding(A)FF 9Nov16 6Feb17 Diffusers&Grills 60.00% 12Feb17
MainBuilding(A)SF 2Dec16 26Apr17 MainBuilding(A)RF PipeFitting 50.00% 19Mar17
MainBuilding(B)GF FloorDrain&CleanOut 80.00% 12Mar17
FireHoseCabinates 70.00% 13Mar17
FireExtingushers 50.00% 26May17
HVACDuct 80.00% 8Dec16
AirDistributionSystem 75.00% 19Mar17
VentilationFans 60.00% 29Apr17
Diffusers&Grills 50.00% 1May17
MainBuilding(B)FF VentilationFans 33.00% 29Apr17
Diffusers&Grills 33.00% 1May17
FloorDrain&CleanOut 80.00% 9Mar17
FireHoseCabinates 80.00% 11Mar17
FireExtingushers 53.00% 22May17
HVACDuct 85.00% 24Dec16
AirDistributionSystem 70.00% 19Mar17
MainBuilding(B)SF FireExtingushers 50.00% 6May17
WaterSupplyPipes 90.00% 10Mar17
FloorDrain&CleanOut 80.00% 10Mar17
HVACDuct 80.00% 11Apr17
AirDistributionSystem 80.00% 9Apr17
PipeFitting 95.00% 9Mar17
MainBuilding(B)RF PipeFitting 50.00% 6May17
Elevator MainBuilding(A)RF InstallSteelworkSupportForElevators 85.00% 4Apr17
ElectricTractionElevators 33.00% 8Apr17
Electrical MainBuilding(A)GF WiringDevicesSecondFix(Wires) 95.00% 25Jan17
DataCommunicationsSystemSecondFix(Wires) 30.00% 1Apr17
IPTelephoneSystemSecondFix(Wires) 30.00% 2Apr17
MainBuilding(A)FF IPTelephoneSystemSecondFix(Wires) 90.00% 22Apr17
WiringDevicesSecondFix(Wires) 90.00% 2Mar17
DataCommunicationsSystemSecondFix(Wires) 90.00% 30Mar17
MainBuilding(A)SF DataCommunicationsSystemSecondFix(Wires) 95.00% 24Apr17
IPTelephoneSystemSecondFix(Wires) 90.00% 24Apr17
LightingSystemSecondFix(Wires) 95.00% 9Feb17
LightingSystemThirdFix(Fixtures) 20.00% 1Jun17
WiringDevicesSecondFix(Wires) 95.00% 30Mar17
MainBuilding(A)RF GroundingandBondingforElectricalSystems 30.00% 25Apr17
LightingSystemSecondFix(Wires) 80.00% 30Mar17
MainBuilding(B)GF IPTelephoneSystemFirstFix(Pipes) 98.00% 16Jan17
WiringDevicesFirstFix(Pipes) 98.00% 16Jan17
WiringDevicesSecondFix(Wires) 50.00% 27Mar17
DataCommunicationsSystemFirstFix(Pipes) 98.00% 16Jan17
DataCommunicationsSystemSecondFix(Wires) 30.00% 30Mar17
MainBuilding(B)FF FireAlarmSecondFix(Wires) 50.00% 1Apr17
IPTelephoneSystemFirstFix(Pipes) 95.00% 21Jan17
IPTelephoneSystemSecondFix(Wires) 20.00% 10Jun17
LightingSystemSecondFix(Wires) 98.00% 28Feb17
WiringDevicesFirstFix(Pipes) 95.00% 21Jan17
WiringDevicesSecondFix(Wires) 50.00% 30Mar17
DataCommunicationsSystemFirstFix(Pipes) 95.00% 21Jan17
DataCommunicationsSystemSecondFix(Wires) 20.00% 10Jun17
MainBuilding(B)SF FireAlarmSecondFix(Wires) 50.00% 3Jun17
DataCommunicationsSystemFirstFix(Pipes) 80.00% 21Jan17
LightingSystemSecondFix(Wires) 40.00% 1Jun17
WiringDevicesFirstFix(Pipes) 80.00% 21Jan17
WiringDevicesSecondFix(Wires) 30.00% 2Jun17
MainBuilding(B)RF LightingSystemSecondFix(Wires) 20.00% 11Jun17
Windows MainBuilding(A)GF AluminumWindows 37.00% 18Jan17
MainBuilding(A)FF AluminumWindows 37.00% 20Mar17
MainBuilding(A)SF AluminumWindows 37.00% 25Mar17
Tiling MainBuilding(A)GF PorcelainTiles 90.00% 24Dec16
MainBuilding(A)FF PorcelainTiles 98.00% 13Mar17
MainBuilding(A)SF PorcelainTiles 98.00% 27Mar17
Ceiling MainBuilding(A)GF SolidGypsumCeiling 20.00% 8Jun17
MainBuilding(A)FF SolidGypsumCeiling 70.00% 30May17
MainBuilding(A)SF SolidGypsumCeiling 55.00% 30May17
Paint MainBuilding(A)GF Paint(1STCoat) 40.00% 31Dec16
MainBuilding(A)FF Paint(1STCoat) 70.00% 18Apr17
MainBuilding(B)GF Paintpreparation 90.00% 2Mar17
MainBuilding(B)FF Paintpreparation 90.00% 12Mar17
ElectricRoom(A) Paint(1STCoat) 90.00% 27May17
ElectricRoom(B) Paint(1STCoat) 90.00% 27May17
ExposedAggr. MainBuilding(A)RF ColourExposedAggregate 30.00% 26Apr17
MainBuilding(B)RF ColourExposedAggregate 50.00% 2May17
NoR_TypeOfWork MainBuilding(A)GF PorcelainSkirting 85.00% 22Mar17
MainBuilding(A)FF PorcelainSkirting 95.00% 26Mar17
MainBuilding(A)SF PorcelainSkirting 95.00% 1Apr17
16C22C
Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no. RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 16-Jun-17
To the Engineer Report no. 468
School Name Hazm Intermediate School School Code S39
Temperature 45C - 25C Site Hand-Over Day 19-Dec-15
Weather Humidity