Contractor's Daily Report

Contractor ALBAWANI CO.


Contract no. TBC Riyadh - 111 project (G9) Date 16-Jun-17
To the Engineer Project Manager Eng / Shehzad khanzada
Temperature 45C - 25C Contract day 18/11/2014

Contractor's authorized signatory

Name SAAD AL-HAJI Date : 16-Jun-17

Engineers's authorized signatory

Name : Date : 16-Jun-17


ALBAWANICO.

16C22C
Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no. RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 16-Jun-17
To the Engineer Report no. 468
School Name Hadar Elementary for Quran-Boys School Code S10
Temperature 45C - 25C Site Hand-Over Day 19-Dec-15
Weather Humidity

Contractor's Manpower (including Subcontractors)* Plant/Equipment*


Status(Idle
Staff No. Direct Labor No Type Qty. Location orRepair)

Projt. MGR. 1 Supervisor/ Forem 2 Excavator/Poclain/Excavator 0


Engr. MGR. 1 Precast Man 6 Shovel/Loader/Grader 0
Contract MGR. 1 Eq. Operator 3 BOBCAT 0
Precast Manager 1 Carpenter 4 DumpTruck 0
Const. Manager 1 Welder 0 Roller/Compactor 0
Project Control Team 1 Steelfixer 4 PortableGenerator 1
QA/QC 1 MEP 13 MobileCrane 1
Tech. Support 1 Mason 1 TowerCrane 0
Purch & Procurement 1 Painter Labor 4 Pickup 0
Set. Manager 1 Plastering man 0 WaterTanker 0
General
Site Engineer 1 labor 28 WeldingMachine 1
Contractor
Safety/ HSE 1 ForkLift 0
Timekeeper 1 JCB 0
Electro Mechanical Engrs 1 WaterPump 1
Survayor Assistant 1 Bulldozer 1
Guard 3 LevellingMachine 0
Totalstation 0
Container 1
WaterTank 3
Portacabin 0
TemporaryGenset 0

Grand Total 18 65 5

Activities and Tasks*


COMPLETEDACTIVITIES ONGOINGACTIVITIES
Percentage Finish
TypeofWork BuildingName StartDate FinishDate TypeofWork BuildingName Activityname StartDate
Complete Date
Excavation MainBuildingGF 23Jan16 2Feb16 Excavation BoundaryWall ExcavationWorkForBoundaryWall 90.00% 14May16
Multipurposehall 5Apr16 16Apr16 SubStructure GateWork R.CConcreteforGradeBeams 85.00% 24Apr17
ElectricRoom 21Sep16 1Oct16 WaterTank BituminousSheetMembraneWaterproofingForWaterTank 95.00% 6Nov16
GuardHouse 15Feb17 15Feb17 BoundaryWall P.CConcreteforBoundaryWall 90.00% 18May16
GateWork 27Nov16 28Nov16 R.CConcreteFootingforBoundaryWall 90.00% 22May16
Sitelayout 13Apr16 24Apr16 Backfilling BackfillingToBottomGradeBeamsForBoundaryWall 55.00% 20Jun16
CollectiveTank 22May17 24May17 SlabOnGrade Multipurposehall R.CConcreteforSlabonGrade 90.00% 2Oct16
SepticTank 22May17 24May17 WaterProofing MainBuildingRF TerrazoTiling 85.00% 2May17
WaterTank 28Sep16 1Oct16 BoundaryWall BituminousSheetWaterproofingforFootings&NeckColumns,Retaining 55.00% 12Jun16
SubStructure MainBuildingGF 17May16 26Dec16 ConcreteWorks RCColumnsforBoundaryWall 35.00% 24Jan17
Multipurposehall 2May16 19Sep16 BlockWork BlockworkforBoundaryWall 55.00% 24Jan17
ElectricRoom 10Oct16 25Feb17 Plaster MainBuildingGF CementInternalPlastering 99.00% 20Dec16
Canteen 10Oct16 21Jan17 Mechanical WaterSupplyPipes 80.00% 25Mar17
GuardHouse 7Mar17 27May17 FloorDrain&CleanOut 80.00% 17Mar17
Backfilling MainBuildingGF 17Aug16 16Sep16 ElectricWaterHeaters 70.00% 3Jun17
Multipurposehall 16Aug16 26Sep16 PipeFitting 85.00% 18Jan17
ElectricRoom 24Nov16 11Mar17 HVACDuct 85.00% 30Jan17
Canteen 20Dec16 11Mar17 VentilationFans 60.00% 2Feb17
Sitelayout 25Apr16 7May16 MainBuildingFF WaterSupplyPipes 65.00% 20Apr17
SlabOnGrade MainBuildingGF 22Sep16 27Dec16 FloorDrain&CleanOut 80.00% 26Mar17
ElectricRoom 13Mar17 13Mar17 ElectricWaterHeaters 65.00% 4Jun17
Canteen 13Mar17 13Mar17 PipeFitting 85.00% 14Feb17
WaterProofing MainBuildingGF 27Jul16 27Dec16 FireExtingushers 80.00% 11Feb17
Precast MainBuildingGF 20Sep16 20Dec16 HVACDuct 85.00% 12Feb17
MainBuildingFF 19Oct16 26Dec16 VentilationFans 60.00% 1Feb17
MainBuildingSF 8Nov16 26Dec16 MainBuildingSF WaterSupplyPipes 65.00% 22Apr17
MainBuildingRF 1Dec16 27Dec16 FloorDrain&CleanOut 75.00% 26Mar17
Multipurposehall 10Oct16 26Apr17 PipeFitting 70.00% 12Feb17
ElectricRoom 12Apr17 1May17 FireExtingushers 80.00% 16Feb17
Canteen 12Apr17 1May17 HVACDuct 85.00% 12Feb17
BlockWork MainBuildingGF 1Nov16 28Mar17 VentilationFans 60.00% 3Feb17
MainBuildingFF 8Nov16 7Feb17 MainBuildingRF PipeFitting 43.00% 29Apr17
MainBuildingSF 4Dec16 12Mar17 Electrical MainBuildingGF IPTelephoneSystemSecondFix(Wires) 90.00% 16Feb17
Plaster MainBuildingFF 24Dec16 27Mar17 DataCommunicationsSystemSecondFix(Wires) 90.00% 16Feb17
MainBuildingSF 1Jan17 20Mar17 LightingSystemSecondFix(Wires) 90.00% 25Jan17
Elevator MainBuildingRF 15Feb17 17May17 WiringDevicesSecondFix(Wires) 90.00% 25Jan17
FireAlarmSecondFix(Wires) 90.00% 16Feb17
MainBuildingFF LightingSystemSecondFix(Wires) 80.00% 25Jan17
WiringDevicesSecondFix(Wires) 80.00% 25Jan17
FireAlarmSecondFix(Wires) 80.00% 19Feb17
DataCommunicationsSystemSecondFix(Wires) 80.00% 16Feb17
IPTelephoneSystemSecondFix(Wires) 80.00% 17Feb17
MainBuildingSF LightingSystemSecondFix(Wires) 80.00% 28Jan17
WiringDevicesSecondFix(Wires) 80.00% 28Jan17
FireAlarmSecondFix(Wires) 80.00% 19Feb17
DataCommunicationsSystemSecondFix(Wires) 80.00% 16Feb17
IPTelephoneSystemSecondFix(Wires) 80.00% 18Feb17
MainBuildingRF LightingSystemSecondFix(Wires) 80.00% 3Mar17
GroundingandBondingforElectricalSystems 45.00% 4Apr17
ElectricRoom LightingSystemFirstFix 63.00% 13May17
WiringDevicesFirstFix 65.00% 13May17
Windows MainBuildingGF AluminumWindows 48.00% 20Mar17
MainBuildingFF AluminumWindows 48.00% 25Mar17
MainBuildingSF AluminumWindows 45.00% 26Mar17
SpaceFrame Multipurposehall Install&SupplySpaceFrame 40.00% 18May17
Tiling MainBuildingGF CeramicTiling 45.00% 26Mar17
PorcelainTiles 80.00% 28Jan17
CeramicTilesforwall 23.00% 26Mar17
MainBuildingFF CeramicTilesforwall 25.00% 24Mar17
CeramicTiling 25.00% 24Mar17
PorcelainTiles 85.00% 30Jan17
MainBuildingSF CeramicTiling 25.00% 25Mar17
PorcelainTiles 80.00% 9Feb17
CeramicTilesforwall 23.00% 25Mar17
Paint MainBuildingGF Paintpreparation 95.00% 14Jan17
Paint(1STCoat) 90.00% 13Feb17
MainBuildingFF Paintpreparation 90.00% 14Jan17
Paint(1STCoat) 90.00% 14Feb17
MainBuildingSF Paint(1STCoat) 90.00% 8Mar17
Paintpreparation 90.00% 18Jan17
MainBuildingRF Paint(1STCoat)forexternal 43.00% 23May17
ExposedAggr. ColourExposedAggregate 98.00% 1Feb16
NoR_TypeOfWork MainBuildingGF PorcelainSkirting 30.00% 3Jun17
HollowMetalFrames 90.00% 23Mar17
MainBuildingFF PorcelainSkirting 25.00% 4Jun17
HollowMetalFrames 90.00% 25Mar17
MainBuildingSF HollowMetalFrames 90.00% 26Mar17
MainBuildingRF HollowMetalFrames 35.00% 16Apr17

Materials delivered to Site*


Item Unit Qty. Approved submittal reference

Contractor's authorized signatory Engineer's authorized signatory


Name: SAAD AL-HAJI Name:
Signature: Signature:
Date: 16-Jun-17 Date: 16-Jun-17
ALBAWANICO.

16C22C
Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no. RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 16-Jun-17
To the Engineer Report no. 469
School Name Sowaidi Complex School Code C26
Temperature 45C - 25C Site Hand-Over Day 17-Dec-15
Weather Humidity

Contractor's Manpower (including Subcontractors)* Plant/Equipment*


Status(Idle
Staff No. Direct Labor No Type Qty. Location orRepair)

Projt. MGR. 1 Supervisor/ Forem 1 Excavator/Poclain/Excavator 0


Engr. MGR. 1 Precast Man 10 Shovel/Loader/Grader 0
Contract MGR. 1 Eq. Operator 1 BOBCAT 0
Precast Manager 1 Carpenter 5 DumpTruck 0
Const. Manager 1 Welder 0 Roller/Compactor 0
Project Control Team 1 Steelfixer 2 PortableGenerator 1
QA/QC 1 MEP 12 MobileCrane 0
Tech. Support 1 Mason 4 TowerCrane 1
Purch & Procurement 1 Painter Labor 4 Pickup 0
Set. Manager 1 Plastering man 10 WaterTanker 0
Site Engineer 1 labor 12 WeldingMachine 1
General Contractor Safety/ HSE 1 ForkLift 0
Timekeeper 1 JCB 0
Electro Mechanical Engrs 1 WaterPump 0
Survayor Assistant 2 Bulldozer 0
Guard 3 LevellingMachine 0
Totalstation 0
Container 0
WaterTank 0
Portacabin 0
TemporaryGenset 0

SubTotal/Main 19 61 3
0
Subcontractors
Sub Total/Subcon 0 0 0

Grand Total 19 61 3
Activities and Tasks*
COMPLETEDACTIVITIES ONGOINGACTIVITIES
Percentage Finish
TypeofWork BuildingName StartDate FinishDate TypeofWork BuildingName Activityname StartDate
Complete Date
Excavation MainBuilding(A)GF 21Jan16 6Feb16 SubStructure Canteen(A) Install&FixingAnchorBolts 60.00% 2Jan17
MainBuilding(B)GF 5Mar16 17Mar16 P.CConcreteforFootings 60.00% 25Dec16
Canteen(B) 19Nov16 22Nov16 R.CConcreteforFootings 60.00% 1Jan17
GuardHouse(A) 28Aug16 30Aug16 GateWork(B) R.CConcreteforFootings 30.00% 11Jun17
GuardHouse(B) 14Nov16 19Nov16 BoundaryWall(A) Install&FixingAnchorBolts 75.00% 25Oct16
GateWork(A) 2Dec16 2Dec16 P.CConcreteforBoundaryWall 95.00% 4Sep16
GateWork(B) 20May17 22May17 R.CConcreteFootingforBoundaryWall 75.00% 17Sep16
WaterTank(A) 28Aug16 30Aug16 BoundaryWall(B) Install&FixingAnchorBolts 75.00% 30Oct16
BoundaryWall(A) 2Jun16 1Jan17 P.CConcreteforBoundaryWall 95.00% 10Sep16
WaterTank(B) 14Nov16 19Nov16 R.CConcreteFootingforBoundaryWall 75.00% 20Sep16
BoundaryWall(B) 11Jun16 1Jan17 Backfilling Canteen(A) BackfillingToBottomOfSlabOnGrade 50.00% 28Jan17
SubStructure MainBuilding(A)GF 11Feb16 30May16 BackfillingToBottomOfGradeBeams 70.00% 23Jan17
MainBuilding(B)GF 28Apr16 26Jul16 GuardHouse(A) BackfillingToBottomOfGradeBeams 50.00% 23Jan17
ElectricRoom(A) 1Jan17 20Feb17 WaterProofing MainBuilding(A)RF TerrazoTiling 95.00% 20May17
ElectricRoom(B) 26Dec16 21Feb17 Canteen(A) BituminousSheet/PaintWaterproofingforFootings 70.00% 21Jan17
Canteen(B) 1Dec16 14Feb17 BoundaryWall(A) BituminousSheetWaterproofingforFootings&Nec 75.00% 28Sep16
GuardHouse(B) 1Dec16 14Feb17 BoundaryWall(B) BituminousSheetWaterproofingforFootings&Nec 75.00% 5Oct16
GateWork(A) 26Dec16 21Feb17 Precast GuardHouse(B) InstallPrecastConcretePanels 40.00% 18Apr17
WaterTank(A) 4Dec16 2Apr17 BoundaryWall(A) PrecastConcretPanelsforBoundaryWall 75.00% 14Nov16
WaterTank(B) 4Dec16 2Apr17 PrecastConcretColumnsforBoundaryWall 75.00% 13Nov16
Backfilling ElectricRoom(A) 23Jan17 25Feb17 BoundaryWall(B) PrecastConcretColumnsforBoundaryWall 75.00% 13Nov16
ElectricRoom(B) 23Jan17 25Feb17 PrecastConcretPanelsforBoundaryWall 75.00% 14Nov16
Canteen(B) 4Feb17 15May17 ConcreteWorks BoundaryWall(A) R.CConcreteColumnNeck&RetaingWallforBoun 85.00% 15Oct16
GuardHouse(B) 23Jan17 15May17 BoundaryWall(B) R.CConcreteColumnNeck&RetaingWallforBoun 85.00% 22Oct16
GateWork(A) 23Jan17 4Mar17 BlockWork MainBuilding(B)GF BlockWork 95.00% 26Nov16
SlabOnGrade MainBuilding(A)GF 28May16 5Jun16 MainBuilding(B)FF BlockWork 95.00% 24Dec16
MainBuilding(B)GF 6Aug16 13Dec16 MainBuilding(B)SF BlockWork 90.00% 22Jan17
ElectricRoom(A) 3Mar17 9Mar17 Plaster MainBuilding(B)GF CementInternalPlastering 95.00% 29Dec16
ElectricRoom(B) 3Mar17 9Mar17 MainBuilding(B)FF CementInternalPlastering 95.00% 16Jan17
WaterProofing MainBuilding(A)GF 22Mar16 13Jul16 MainBuilding(B)SF CementInternalPlastering 70.00% 20Mar17
MainBuilding(B)GF 14May16 13Dec16 Mechanical MainBuilding(A)GF FloorDrain&CleanOut 80.00% 28Feb17
Precast MainBuilding(A)GF 28May16 25Jul16 FireExtingushers 85.00% 2Mar17
MainBuilding(A)FF 26Jul16 30Nov16 HVACDuct 95.00% 12Nov16
MainBuilding(A)SF 8Sep16 1Dec16 AirDistributionSystem&Testing 95.00% 28Jan17
MainBuilding(A)RF 29Oct16 17Nov16 VentilationFans 60.00% 20Feb17
MainBuilding(B)GF 27Jul16 18Dec16 Diffusers&Grills 80.00% 3Feb17
MainBuilding(B)FF 30Aug16 6Apr17 MainBuilding(A)FF FloorDrain&CleanOut 80.00% 1Jan17
MainBuilding(B)SF 24Dec16 10Apr17 ElectricWaterHeaters 95.00% 18Apr17
MainBuilding(B)RF 29Jan17 9Apr17 FireExtingushers 50.00% 2Mar17
ElectricRoom(A) 14Mar17 27Mar17 HVACDuct 95.00% 24Nov16
ElectricRoom(B) 14Mar17 27Mar17 AirDistributionSystem&Testing 95.00% 1Feb17
GateWork(A) 26Mar17 18May17 VentilationFans 60.00% 21Feb17
ConcreteWorks MainBuilding(A)GF 25Jun16 4Jul16 Diffusers&Grills 85.00% 5Feb17
MainBuilding(A)FF 26Jul16 10Aug16 MainBuilding(A)SF FireExtingushers 80.00% 25May17
MainBuilding(A)SF 17Sep16 18Oct16 FloorDrain&CleanOut 80.00% 9Mar17
BlockWork MainBuilding(A)GF 31Aug16 20Apr17 ElectricWaterHeaters 95.00% 18Apr17
MainBuilding(A)FF 8Oct16 4Feb17 HVACDuct 90.00% 2Dec16
MainBuilding(A)SF 8Nov16 27Feb17 AirDistributionSystem&Testing 90.00% 21Feb17
Plaster MainBuilding(A)GF 17Oct16 1May17 VentilationFans 60.00% 23Feb17
MainBuilding(A)FF 9Nov16 6Feb17 Diffusers&Grills 60.00% 12Feb17
MainBuilding(A)SF 2Dec16 26Apr17 MainBuilding(A)RF PipeFitting 50.00% 19Mar17
MainBuilding(B)GF FloorDrain&CleanOut 80.00% 12Mar17
FireHoseCabinates 70.00% 13Mar17
FireExtingushers 50.00% 26May17
HVACDuct 80.00% 8Dec16
AirDistributionSystem 75.00% 19Mar17
VentilationFans 60.00% 29Apr17
Diffusers&Grills 50.00% 1May17
MainBuilding(B)FF VentilationFans 33.00% 29Apr17
Diffusers&Grills 33.00% 1May17
FloorDrain&CleanOut 80.00% 9Mar17
FireHoseCabinates 80.00% 11Mar17
FireExtingushers 53.00% 22May17
HVACDuct 85.00% 24Dec16
AirDistributionSystem 70.00% 19Mar17
MainBuilding(B)SF FireExtingushers 50.00% 6May17
WaterSupplyPipes 90.00% 10Mar17
FloorDrain&CleanOut 80.00% 10Mar17
HVACDuct 80.00% 11Apr17
AirDistributionSystem 80.00% 9Apr17
PipeFitting 95.00% 9Mar17
MainBuilding(B)RF PipeFitting 50.00% 6May17
Elevator MainBuilding(A)RF InstallSteelworkSupportForElevators 85.00% 4Apr17
ElectricTractionElevators 33.00% 8Apr17
Electrical MainBuilding(A)GF WiringDevicesSecondFix(Wires) 95.00% 25Jan17
DataCommunicationsSystemSecondFix(Wires) 30.00% 1Apr17
IPTelephoneSystemSecondFix(Wires) 30.00% 2Apr17
MainBuilding(A)FF IPTelephoneSystemSecondFix(Wires) 90.00% 22Apr17
WiringDevicesSecondFix(Wires) 90.00% 2Mar17
DataCommunicationsSystemSecondFix(Wires) 90.00% 30Mar17
MainBuilding(A)SF DataCommunicationsSystemSecondFix(Wires) 95.00% 24Apr17
IPTelephoneSystemSecondFix(Wires) 90.00% 24Apr17
LightingSystemSecondFix(Wires) 95.00% 9Feb17
LightingSystemThirdFix(Fixtures) 20.00% 1Jun17
WiringDevicesSecondFix(Wires) 95.00% 30Mar17
MainBuilding(A)RF GroundingandBondingforElectricalSystems 30.00% 25Apr17
LightingSystemSecondFix(Wires) 80.00% 30Mar17
MainBuilding(B)GF IPTelephoneSystemFirstFix(Pipes) 98.00% 16Jan17
WiringDevicesFirstFix(Pipes) 98.00% 16Jan17
WiringDevicesSecondFix(Wires) 50.00% 27Mar17
DataCommunicationsSystemFirstFix(Pipes) 98.00% 16Jan17
DataCommunicationsSystemSecondFix(Wires) 30.00% 30Mar17
MainBuilding(B)FF FireAlarmSecondFix(Wires) 50.00% 1Apr17
IPTelephoneSystemFirstFix(Pipes) 95.00% 21Jan17
IPTelephoneSystemSecondFix(Wires) 20.00% 10Jun17
LightingSystemSecondFix(Wires) 98.00% 28Feb17
WiringDevicesFirstFix(Pipes) 95.00% 21Jan17
WiringDevicesSecondFix(Wires) 50.00% 30Mar17
DataCommunicationsSystemFirstFix(Pipes) 95.00% 21Jan17
DataCommunicationsSystemSecondFix(Wires) 20.00% 10Jun17
MainBuilding(B)SF FireAlarmSecondFix(Wires) 50.00% 3Jun17
DataCommunicationsSystemFirstFix(Pipes) 80.00% 21Jan17
LightingSystemSecondFix(Wires) 40.00% 1Jun17
WiringDevicesFirstFix(Pipes) 80.00% 21Jan17
WiringDevicesSecondFix(Wires) 30.00% 2Jun17
MainBuilding(B)RF LightingSystemSecondFix(Wires) 20.00% 11Jun17
Windows MainBuilding(A)GF AluminumWindows 37.00% 18Jan17
MainBuilding(A)FF AluminumWindows 37.00% 20Mar17
MainBuilding(A)SF AluminumWindows 37.00% 25Mar17
Tiling MainBuilding(A)GF PorcelainTiles 90.00% 24Dec16
MainBuilding(A)FF PorcelainTiles 98.00% 13Mar17
MainBuilding(A)SF PorcelainTiles 98.00% 27Mar17
Ceiling MainBuilding(A)GF SolidGypsumCeiling 20.00% 8Jun17
MainBuilding(A)FF SolidGypsumCeiling 70.00% 30May17
MainBuilding(A)SF SolidGypsumCeiling 55.00% 30May17
Paint MainBuilding(A)GF Paint(1STCoat) 40.00% 31Dec16
MainBuilding(A)FF Paint(1STCoat) 70.00% 18Apr17
MainBuilding(B)GF Paintpreparation 90.00% 2Mar17
MainBuilding(B)FF Paintpreparation 90.00% 12Mar17
ElectricRoom(A) Paint(1STCoat) 90.00% 27May17
ElectricRoom(B) Paint(1STCoat) 90.00% 27May17
ExposedAggr. MainBuilding(A)RF ColourExposedAggregate 30.00% 26Apr17
MainBuilding(B)RF ColourExposedAggregate 50.00% 2May17
NoR_TypeOfWork MainBuilding(A)GF PorcelainSkirting 85.00% 22Mar17
MainBuilding(A)FF PorcelainSkirting 95.00% 26Mar17
MainBuilding(A)SF PorcelainSkirting 95.00% 1Apr17

Contractor's authorized signatory Engineer's authorized signatory


Name: SAAD AL-HAJI Name:
Signature: Signature:
Date: 16-Jun-17 Date: 16-Jun-17
ALBAWANICO.

16C22C

Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no. RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 16-Jun-17
To the Engineer Report no. 468
School Name Hazm Intermediate School School Code S39
Temperature 45C - 25C Site Hand-Over Day 19-Dec-15
Weather Humidity

Contractor's Manpower (including Subcontractors)* Plant/Equipment*


Status(Idleor
Staff No. Direct Labor No Type Qty. Location Repair)

Projt. MGR. 1 Supervisor/ Forem 2 Excavator/Poclain/Excavator 0


Engr. MGR. 1 Precast Man 0 Shovel/Loader/Grader 0
Contract MGR. 1 Eq. Operator 1 BOBCAT 0
Precast Manager 1 Carpenter 0 DumpTruck 0
Const. Manager 1 Welder 1 Roller/Compactor 0
Project Control Team 1 Steelfixer 0 PortableGenerator 1
QA/QC 1 MEP 12 MobileCrane 0
Tech. Support 1 Mason 5 TowerCrane 0
General Contractor Purch & Procurement 1 Painter Labor 3 Pickup 1
Set. Manager 1 Plastering man 0 WaterTanker 1
Site Engineer 1 labor 45 WeldingMachine 1
Safety/ HSE 1 ForkLift 0
Timekeeper 1 JCB 0
Electro Mechanical Eng 1 WaterPump 1
Survayor Assistant 2 Bulldozer 0
Guard 1 LevellingMachine 1
Totalstation 1
Grand Total 17 69 7

Activities and Tasks*


COMPLETEDACTIVITIES ONGOINGACTIVITIES
Percentage Finish
TypeofWork BuildingName StartDate FinishDate TypeofWork BuildingName Activityname StartDate
Complete Date
Excavation MainBuildingGF 10Mar16 26Mar16 SubStructure Sitelayout Submit&InstallBaseCoarse 40.00% 22May17
Multipurposehall 5Apr16 21Apr16 Mechanical MainBuildingGF FloorDrain&CleanOut 98.00% 15Jan17
ElectricRoom 26Jun16 25Sep16 ElectricWaterHeaters 98.00% 9Jan17
GuardHouse 26Jun16 4Jul16 PlumbingFixtures 50.00% 25Jan17
GateWork 10Sep16 28Sep16 VentilationFans 50.00% 2Feb17
CollectiveTank 28Aug16 30Aug16 Diffusers&Grills 87.00% 2Feb17
SepticTank 13Sep16 15Sep16 SplitUnits 79.00% 3Jan17
WaterTank 4Sep16 7Sep16 MainBuildingFF FloorDrain&CleanOut 95.00% 15Jan17
BoundaryWall 17May16 15Oct16 ElectricWaterHeaters 98.00% 15Jan17
SubStructure MainBuildingGF 4Apr16 31May16 PlumbingFixtures 50.00% 25Jan17
Multipurposehall 23Apr16 2Jun16 VentilationFans 50.00% 1Feb17
ElectricRoom 13Oct16 19Dec16 Diffusers&Grills 90.00% 1Feb17
Canteen 23Jul16 19Sep16 SplitUnits 73.00% 3Jan17
GuardHouse 20Jul16 31Aug16 laboratoryEquipment 20.00% 10Apr17
GateWork 9Oct16 23Nov16 MainBuildingSF VentilationFans 50.00% 3Feb17
CollectiveTank 1Sep16 8Jan17 Diffusers&Grills 90.00% 3Feb17
SepticTank 17Sep16 8Jan17 SplitUnits 63.00% 3Jan17
WaterTank 8Sep16 15Oct16 FloorDrain&CleanOut 95.00% 15Jan17
BoundaryWall 21May16 1Nov16 ElectricWaterHeaters 98.00% 15Jan17
WaterTank(B) 10Sep16 8Jan17 PlumbingFixtures 50.00% 25Jan17
Backfilling MainBuildingGF 1May16 30May16 MainBuildingRF AHUEquipemnts&Testing 95.00% 17Jan17
Multipurposehall 17May16 9Jun16 ElevatedWaterTanks&Testing 80.00% 19Mar17
ElectricRoom 6Nov16 18Dec16 BoosterWaterPumps&Testing 80.00% 16Mar17
Canteen 17Aug16 26Sep16 GeneralDutyValvesforWaterBasedFireSuppress 82.00% 12Feb17
GuardHouse 22Aug16 7Sep16 Multipurposehall HVACDuct 80.00% 4Feb17
GateWork 3Dec16 12Mar17 FireExtingushers 50.00% 23Mar17
BoundaryWall 9Jun16 25Oct16 FloorDrain 90.00% 8Feb17
SlabOnGrade MainBuildingGF 7Jun16 11Jul16 Vent 95.00% 10Feb17
Multipurposehall 16Jun16 19Jun16 ElectricWaterHeaters 98.00% 3Mar17
ElectricRoom 8Jan17 8Jan17 PlumbingFixtures 40.00% 2May17
Canteen 23Oct16 26Oct16 Diffusers&Grills 35.00% 11May17
GuardHouse 23Oct16 26Oct16 VentilationFans 75.00% 12Feb17
GateWork 12Mar17 13Mar17 SplitUnits 40.00% 5Mar17
WaterProofing MainBuildingGF 30Apr16 11Jun16 PackageUnit 90.00% 6Mar17
MainBuildingFF 27Feb17 1Mar17 Canteen FloorDrain 90.00% 1Mar17
MainBuildingSF 4Mar17 7Mar17 ElevatedWaterHeaters 80.00% 16Mar17
MainBuildingRF 16Nov16 4Feb17 PlumbingFixtures 30.00% 2May17
Multipurposehall 9May16 24Apr17 FireExtinguisher 50.00% 15Mar17
ElectricRoom 5Nov16 7May17 SplitUnit 50.00% 1Apr17
Canteen 16Aug16 3May17 GuardHouse ElevatedWaterHeaters 70.00% 16Mar17
GateWork 24Nov16 20May17 PlumbingFixtures 25.00% 2May17
BoundaryWall 1Jun16 12Dec16 FireExtinguisher 50.00% 20Mar17
Precast MainBuildingGF 19Jun16 16Aug16 WindowsUnit 50.00% 13Mar17
MainBuildingFF 30Jun16 18Sep16 GateWork ElevatedWaterHeaters 85.00% 16Mar17
MainBuildingSF 20Jul16 2Oct16 PlumbingFixtures 30.00% 2May17
MainBuildingRF 1Oct16 16Oct16 FireExtinguisher 50.00% 20Mar17
Multipurposehall 6Aug16 12Oct16 SplitUnit 50.00% 28Mar17
ElectricRoom 20Dec16 21Dec16 Sitelayout PipeFitting&Valves 80.00% 5Feb17
Canteen 26Oct16 19Nov16 FirePumps 90.00% 16Jan17
GuardHouse 29Oct16 17Nov16 SiameseConnection 85.00% 25Feb17
GateWork 4Dec16 12Dec16 DrainagePipes 98.00% 9Feb17
BoundaryWall 24Aug16 16Dec16 FloorDrain 90.00% 6Feb17
ConcreteWorks Multipurposehall 9Jan17 11Mar17 Electrical MainBuildingGF IPTelephoneSystemThirdFix(Fixtures) 96.00% 7Apr17
GateWork 27Feb17 13Mar17 AudioCommunicationsTerminalEquipment 96.00% 5Apr17
BoundaryWall 28May16 1Nov16 LightingSystemThirdFix(Fixtures) 96.00% 28Mar17
BlockWork MainBuildingGF 6Aug16 13Dec16 WiringDevicesThirdFix(Fixtures) 96.00% 1Apr17
MainBuildingFF 30Aug16 13Dec16 FireAlarmThirdFix(Fixtures) 96.00% 1May17
MainBuildingSF 1Oct16 13Dec16 DataCommunicationsSystemThirdFix(Fixtures) 96.00% 6Apr17
Multipurposehall 15Dec16 1Jan17 MainBuildingFF AudioCommunicationsTerminalEquipment 96.00% 19Mar17
Canteen 9Dec16 12Dec16 LightingSystemThirdFix(Fixtures) 96.00% 30Dec16
GuardHouse 12Dec16 2Jan17 WiringDevicesThirdFix(Fixtures) 96.00% 13Mar17
GateWork 22Mar17 30Mar17 FireAlarmThirdFix(Fixtures) 96.00% 20Mar17
Plaster MainBuildingGF 27Oct16 2Jan17 DataCommunicationsSystemThirdFix(Fixtures) 96.00% 19Mar17
MainBuildingFF 3Oct16 3Jan17 IPTelephoneSystemThirdFix(Fixtures) 96.00% 20Mar17
MainBuildingSF 1Nov16 3Jan17 MainBuildingSF FireAlarmThirdFix(Fixtures) 92.00% 20Mar17
Multipurposehall 11Jan17 8Apr17 DataCommunicationsSystemThirdFix(Fixtures) 92.00% 19Mar17
Canteen 21Feb17 21Feb17 IPTelephoneSystemThirdFix(Fixtures) 92.00% 19Mar17
GuardHouse 21Feb17 21Feb17 AudioCommunicationsTerminalEquipment 92.00% 19Mar17
GateWork 4Apr17 12Apr17 LightingSystemThirdFix(Fixtures) 92.00% 20Mar17
Mechanical ElectricRoom 4Feb17 5Feb17 WiringDevicesThirdFix(Fixtures) 92.00% 12Mar17
Elevator MainBuildingRF 26Nov16 29Dec16 MainBuildingRF SubMainDistributionBoard 90.00% 9Mar17
Electrical ElectricRoom 20Dec16 29Apr17 Panelboards 90.00% 1Feb17
Doors MainBuildingFF 18Jan17 20May17 LightingSystemThirdFix(Fixtures) 90.00% 6Apr17
MainBuildingSF 18Jan17 18May17 LowVoltageElectricalPowerConductorsandCables 90.00% 16Jan17
ElectricRoom 6Feb17 13Feb17 LightingUnits(allbuilding) 90.00% 6Apr17
Canteen 25Mar17 23Apr17 Multipurposehall Panelboards 80.00% 25Jan17
GuardHouse 27Feb17 1May17 LightingUnits 60.00% 4Jun17
GateWork 14Feb17 2May17 PublicAdressSystemTirdFix 60.00% 3Jun17
Windows MainBuildingGF 27Dec16 25Feb17 IPTelephoneSystemThirdFix 60.00% 3Jun17
MainBuildingFF 28Dec16 23Mar17 FireAlarmSystemThirdFix 60.00% 3Jun17
MainBuildingSF 28Dec16 23Mar17 LightingSystemThirdFix 90.00% 23Apr17
MainBuildingRF 27Jan17 28Jan17 WiringDevicesThirdFix 40.00% 1Jun17
ElectricRoom 9Feb17 14Feb17 Canteen WiringDevicesThirdFix 85.00% 27May17
Canteen 25Jan17 27May17 LowVoltageElectricalPowerConductorsandCables 13.00% 22Dec16
GuardHouse 25Jan17 3Jun17 Panelboards 85.00% 16Feb17
GateWork 14Mar17 3Jun17 GuardHouse IPTelephoneSystemThirdFix 65.00% 3Jun17
Skylights MainBuildingRF 1Jan17 1May17 LightingSystemThirdFix 80.00% 28May17
SpaceFrame Multipurposehall 19Oct16 5Nov16 WiringDevicesThirdFix 45.00% 4Jun17
GateWork 11Jan17 12Jan17 Panelboards 85.00% 28Apr17
Tiling MainBuildingGF 15Nov16 22May17 LightingUnits 75.00% 28May17
MainBuildingFF 19Nov16 14May17 GateWork Panelboards 50.00% 16May17
MainBuildingSF 22Nov16 5May17 Sitelayout LowVoltageCables 50.00% 9Feb17
MainBuildingRF 18Feb17 19Feb17 Doors MainBuildingGF HollowMetalDoors 98.00% 18Jan17
Multipurposehall 26Mar17 4Jun17 Multipurposehall HollowMetalDoors 80.00% 2May17
Canteen 1Mar17 17Apr17 Windows AluminumWindowFrames 80.00% 18Jan17
Ceiling MainBuildingFF 12Oct16 1Jun17 AluminumWindows 53.00% 1May17
MainBuildingSF 23Jan17 28May17 Ceiling MainBuildingGF Gypsumceilingsuspensionsystem 99.00% 11Feb17
Paint ElectricRoom 21Jan17 25Feb17 Multipurposehall FalseCeilingSuspension(Canteen) 80.00% 24May17
ExposedAggr. MainBuildingRF 10Nov16 7Feb17 Paint MainBuildingGF FinalCoatPaint 80.00% 14Mar17
Multipurposehall 27Nov16 30Jan17 MainBuildingFF FinalCoatPaint 75.00% 14Mar17
ElectricRoom 22Jan17 28Jan17 MainBuildingSF FinalCoatPaint 60.00% 20Mar17
Canteen 12Dec16 24Jan17 MainBuildingRF FinalCoatPaintforexternal 85.00% 3Apr17
GuardHouse 21Jan17 22Jan17 Multipurposehall Paint(1STCoat) 70.00% 11Jan16
GateWork 22Jan17 2Feb17 Canteen Paint(1STCoat) 63.00% 13May17
Sitelayout 13Dec16 6Apr17 GuardHouse Paint(1STCoat) 53.00% 15May17
NoR_TypeOfWork ElectricRoom 4Feb17 13Feb17 GateWork Paint(1STCoat) 55.00% 4Jun17
Handrail MainBuildingGF PipeandTubeRailings 95.00% 6Apr17
MainBuildingFF PipeandTubeRailings 95.00% 21Feb17
MainBuildingSF PipeandTubeRailings 95.00% 23Feb17
Landscape Sitelayout PrecastConcreteCurbs 50.00% 11Jan17
Furniture MainBuildingGF Lockers 10.00% 28May17
MainBuildingFF Lockers 10.00% 28May17
MainBuildingSF Lockers 15.00% 28May17
NoR_TypeOfWor MainBuildingGF Signage 15.00% 4Apr17
GranitSkirting 96.00% 16May17
MainBuildingFF GranitSkirting 75.00% 16May17
Signage 15.00% 4Apr17
MainBuildingSF GranitSkirting 55.00% 27May17
MainBuildingRF CurtainWalls 77.00% 5Feb17
InstallFlagpoles 60.00% 6Mar17
InstallationofGlass 90.00% 10Apr17
HollowMetalFrames 53.00% 15May17
Multipurposehall StairMarbleFinishes 95.00% 3Apr17

Materials delivered to Site*


Item Unit Qty. Approved submittal reference

Contractor's authorized signatory Engineer's authorized signatory


Name: SAAD AL-HAJI Name:
Signature: Signature:
Date: 16-Jun-17 Date: 16-Jun-17