Documente Academic
Documente Profesional
Documente Cultură
By Christopher Mark1
INTRODUCTION
Longwall pillars perform the essential function of pro- The long and narrow geometry of typical gate entry layouts
tecting the gate entries, which provide the only access to makes a classic squeeze highly unlikely. Second, the abut-
the face. Blockages in the gates disrupt ventilation pat- ment loads applied to longwall pillars are significantly
terns and close off emergency travelways, posing serious greater and more complex than those assumed by tradi-
safety hazards. In addition, the impact of any downtime is tional pillar design methods. Effective longwall pillar
magnified on a longwall because such a high proportion of design requires some knowledge of abutment loads during
the total mine productive capacity is concentrated at the all phases of longwall mining, from development all the
longwall face. way into the tailgate.
Ten years ago, there was very little theory available to The Analysis of Longwall Pillar Stability (ALPS) meth-
assist mine planners in sizing longwall pillars. As many od was developed in 1986 to answer these needs. First,
mines introduced longwalls, they first tried pillar dimen- design estimates of abutment loads were obtained through
sions that had been successful in their previous room-and- an extensive series of underground stress measurements.
pillar developments. All too often the results were unfor- Then, back analyses of longwall case histories was used to
tunate (1, 5, 7, 10).2 Then pillar sizes would be increased develop an empirical relationship between pillar design
over the course of several panels until satisfactory condi- and entry performance. Since it was first presented, the
tions were achieved. Other longwalls experienced diffi- method has been tested by back analysis of a growing
culties only on some panels and were often at a loss to number actual mining case histories. This ongoing field
explain them. Still others settled early on a successful verification process has been the key to the success of the
design, then continued to use it without regard to whether method and its acceptance by the mining industry.
the pillars might be wastefully oversized. The goal of this paper is to discuss practical applica-
Developing a pillar design method for longwalls re- tions of ALPS, in light of the experience that has been
quired some new thinking. The goal of entry protection gained to date. Several of the method's shortcomings are
differs from the traditional function of pillar design, which also described, as are current efforts to improve it and
is to prevent squeezes caused by widespread pillar failure. expand its scope.
The fundamental premise of the ALPS method is that 1. A formula for estimating the load applied to the
there is a strong correlation between pillar performance pillars;
and gate entry stability. Specifically, it has been found that 2. A formula for estimating the load-bearing capacity of
if the pillars maintain a proper load-bearing capacity rela- the pillar system; and
tive to the applied load, then good mining conditions can 3. Calculation of a stability factor (SF) based on a
be maintained. The method, therefore, has three compo- comparison of the load to the load-bearing capacity.
nents:
The ALPS method is applicable to conventional long-
'Mining engineer, Pittsburgh Research Center, U.S. Bureau of wall pillar designs, in which the pillars are expected to
Mines, Pittsburgh, PA. carry the abutment loads to which they are subjected. Ap-
2
ltalic numbers in parentheses refer to items in the list of references
proximately 95 pct of all longwall installations in the
at the end of this paper.
239
Ls =
ALPS divides the loads H2(tan
applied to longwall pillars B)(r /2),
into two parts. These are
development loads, which
are present before longwall and Lss = [(HP/2) -
mining, and abutment loads,
which arrive during {P2/(8 tan B)}} r,
longwall panel extraction.
Development loads are due
to the weight of the
overburden directly above where P = panel width
the pillars and the gate
entries. The tributary area ft.
theory is used by ALPS to
estimate the longwall Figure 1.
Conceptualization of side
development load per foot abutment load used in ALPS.
of gate entry (Ld) as: p = Abutment angle; H =
depth of cover; Ls = side abut-
Ld = ment for critical panels; Lss =
(H) side abutment for
supercritical panels; P = panel
(Wt)(r), width.
The two-dimensional
model of the side
where H = depth of
abutment shown in figure
cover ft,
2 is only applicable once
the longwall face is long
Wt = width of the
past by, as in bleeder
pillar system ft,
H tan 0 P/2 entries. From a mining
1-0i 1-.1 standpoint,
..- ----
1... ........... r.
and r = unit weightthe most critical
of the
overburden pcf. abutment loads are the
front abutments (Li)
Abutment loads are the experienced by the pillars at
key to longwall pillar the face ends or T-
design. ALPS began with a junctions. The
simple conceptualization of magnitude of the front
the side abutment (L.) abutment (1 1) is more
proposed by King and difficult to determine
Whittaker (13) and Wilson analytically, because the
(18) (fig. 1). The pillar load transfer at the T-
loading is the wedge of junctions is a complicated
three-dimensional problem.
ALPS assumes that the (13).
front abutment is some It was concluded that
fraction of the side values of B = 21, Fh = 0.5,
abutment, and can be and Ft = 0.7 would yield
represented as appropriately conservative
estimates of the side
Lf = abutment load for
F(Ls longwall pillar design. The
),
where F is a front
abutment factor with a
value of less than 1. It was
thought that two front
abutment factors were
needed, one for a
headgate (or first panel)
front abutment (F h) and
the other for the tailgate
front abutment (Ft).
An extensive program of
field measurements was IPillar A --4.-
conducted to determine Pillar 13--4--- Barrier
values of B and F pillar-.4
appropriate for mining
Figure 2.--Distribution of
conditions in the United side abutment load. H = depth
States. At each of 16 of cover; W, = width of the
longwall panels in 5 mines pillar system; Ls = side
abutment; LA = pillar A
and 4 States, instruments abutment; Ls = pillar B
were installed in the pillars abutment; [-Bp = barrier
to monitor the stress pillar abutment; D = extent
of side abutment influence
increases that occurred as zone; x = distance from edge
the panels were extracted. of longwall panel; 0, =
Details of the field studies abutment stress distribution
function.
have been given elsewhere
1 wt
I_____________D = 9 . 3 ""
1
240
B = [E(Sp)(Ap)1/(C), (10)
where D
= 9.3 4/ H, and where W, is less than D. Where W, is where C = spacing between crosscuts, ft.
greater than D, or where there is no adjacent unmined
panel or barrier pillar, then R = 1. Once the maximum design load (L) has been determin-
Using equations 1 through 5, three loading conditions ed using one of equations 6, 7, or 8, the stability factor
may be defined. The loading experienced by pillars at the (SF) is calculated as:
T-junctions in the headgate, or in the tailgate during first
panel mining, is called headgate loading. Headgate load- SF = B/L. (11)
ing (LH) consists of the development loads plus the first
front abutment: The SF is defined as the total load-bearing capacity of
the longwall pillar system divided by the total applied load.
LH = [Ld + (LO(Fh)(R)] (6) Experience has indicated that although abutment loadings
are not distributed evenly among the pillars (see fig. 2)
Pillars that are expected to protect bleeder entries will and that individual pillars may become overloaded and
be subjected to the development load and the first full side yield, satisfactory tailgate conditions can be maintained as
abutment, or bleeder loading (LB): long the pillar system maintains an adequate overall SF.
The question then becomes, what is an adequate stabil-
LB (1-s)(R)] (7) ity factor? The question is more urgent because pillar
stability per se is not really the issue. Rather, the ALPS
Barrier pillar loads may also be determined from equa- stability factor is to be used as an index to predict gate
tion 7, except that R = 1. The most severe longwall entry stability. The quantitative correlation between ALPS
loading is tailgate loading (L,), experienced during the SF and gate entry performance has been established by
mining of the second and subsequent panels. Tailgate back analysis of longwall case histories.
loading consists of the development load, the first side
abutment, and the second front abutment: VERIFICATION OF THE ALPS METHOD
Lr = [Ld + (1 + Ls)(Ft)1 (8) A total of 90 case histories are now included in the
ALPS data base, some from the literature, but most from
ESTIMATION OF PILLAR LOAD-BEARING personal observations and discussions with mine personnel.
As shown in figure 3, the case histories are distributed all
CAPACITY over the U.S. coalfields.
The details of each case history are shown in tables 1
The second component of ALPS is the estimation of and 2. The case histories have been separated into unsuc-
the load-bearing capacity of the longwall pillar system. cessful and successful designs. The unsuccessful designs
For multientry gates, it is first necessary to determine the (table 1) were those in which intolerable entry conditions
strength of the individual pillars. ALPS uses the Bieniaw- occurred, including roof deterioration and falls, severe pil-
ski formula: lar sloughing and floor heave, and in one case even pillar
bumps. In all cases, the problems were apparently caused
SP S1 = S (0.64 + 0.36 w/h), (9) by excessive vertical stresses. Often the mine subsequently
changed the gate entry design, either by increasing the pil-
where S = pillar strength, psi, lar size or by installing more supplemental support.
The successful designs, shown in table 2, are ones in
S1 = in situ coal strength, psi, which no stress-related problems were reported. Most of
these designs have been in use for many years. About
w = pillar width, ft, one-half of the successful designs are from mines that also
reported unsuccessful designs described in table 1. In
and h = pillar height, ft. these cases, the improved ground conditions can only be
As will be discussed, S, = 900 psi is normally used in attributed to a change in pillar design or to a decrease in
the depth of cover.
241
U. Hiawatha, UT . . . . cover,
1,400 ft widths, ft
30,80 height,
9.0 ft width,
550ft 0.35
Pocahontas No. 3, VA 2,000 30,80,30 5.5 600 .36
Imboden, KY ........... 1,800 100,28 6.5 700 .41
Wattis, UT ............... 1,100 50,50 8.0 420 .41
Castlegate, UT ......... 1,600 85 7.0 600 .41
Harlan, KY ............... 1,700 92,52 8.5 500 .42
Blue Creek, AL ......... 2,200 20,120,20 6.5 650 .44
Wadge, CO .............. 1,000 71,41 9.5 640 .45
Powellton, WV ........ 800 41,41 6.0 580 .53
Pocahontas No.3, WV 1,400 42,42,42 4.5 360 .54
Castlegate, UT ......... 1,900 120 7.0 600 .57
Harlan, KY ............... 2,000 92,52 11.0 500 1
.57
A second observation is that ALPS seems to work well Finally, there is a range of stability factors (approxi-
over a wide range of coal seams, locations, and depths of mately 0.5 to 1.3) in which both successful and unsuccess-
cover. Tables 1 and 2 ables also contain examples of two-, ful designs occur. This indicates that other variables, in
three-, four-, and even five-entry systems; designs that addition to the ALPS stability factor, may determine tail-
employed equal-sized pillars; and designs that used pillars gate performance. A later section of this paper discusses
of different sizes. some of the possibilities.
243
0
A A A Arze, Pittsburgh, PA 15236-0070
AK
Case histories
0.25 0.50 0.75 1.00 1.25 1.50 1.75
ALPS STABILITY FACTOR
Figure 4.ALPS stability factors calculated for 80 Iongwall
case histories.
244
ALPS assists the design process by reducing a multitude the same number of entries, but have gone from equal to
of variables (e.g., depth of cover, pillar widths, seam unequal entry centers. ALPS can show how these changes
height, entry width) into a single meaningful design can be made without beginning all over again at the bot-
parameterthe stability factor. The stability factor can be tom of the learning curve.
used in at least four different applications.
OPTIMIZATION
PRELIMINARY DESIGN
Longwall pillars that are too large constitute a needless-
Few things can cause more distress to a new longwall ly wasted resource. An evaluation of survey data collected
operator than to have an otherwise highly successful long- from 70 longwalls in the early 1980's indicated that the
wall slowed by serious ground control problems on its first ALPS stability factor for tailgate loading was greater than
or (more often) second panel. ALPS can give realistic, 1.5 approximately 50 pct of the time (13). In some cases,
conservative estimates of pillar sizes for use in feasibility it was as high as 4.0. The same data also indicated that
studies or initial longwall panel design. Two recent, suc- little improvement in gate entry performance is achieved
cessful examples of preliminary design with ALPS were re- once the stability factor exceeds 15. Design methods can
ported at Kerr-McGee's Galatia Mine in Illinois (8) and at be used to safely reduce oversized pillars, thereby improv-
Wolf Creek Collieries in Kentucky (6) . ing development drivage rates and adding to the life of
ADAPTATION the mine.
ALPS assists the design process by reducing a multitude the same number of entries, but have gone from equal to
of variables (e.g., depth of cover, pillar widths, seam unequal entry centers. ALPS can show how these changes
height, entry width) into a single meaningful design can be made without beginning all over again at the bot-
parameterthe stability factor. The stability factor can be tom of the learning curve.
used in at least four different applications.
OPTIMIZATION
PRELIMINARY DESIGN
Longwall pillars that are too large constitute a needless-
Few things can cause more distress to a new longwall ly wasted resource. An evaluation of survey data collected
operator than to have an otherwise highly successful long- from 70 longwalls in the early 1980's indicated that the
wall slowed by serious ground control problems on its first ALPS stability factor for tailgate loading was greater than
or (more often) second panel. ALPS can give realistic, 1.5 approximately 50 pct of the time (13). In some cases,
conservative estimates of pillar sizes for use in feasibility it was as high as 4.0. The same data also indicated that
studies or initial longwall panel design. Two recent, suc- little improvement in gate entry performance is achieved
cessful examples of preliminary design with ALPS were re- once the stability factor exceeds 15. Design methods can
ported at Kerr-McGee's Galatia Mine in Illinois (8) and at be used to safely reduce oversized pillars, thereby improv-
Wolf Creek Collieries in Kentucky (6) . ing development drivage rates and adding to the life of
ADAPTATION the mine.
A perfect longwall gate entry design methodology would more gob loading, and a smaller abutment angle. In the
accurately predict tailgate performance in all cases. As ALPS computer program, the abutment angle is preset
figure 4 shows, the ALPS stability factor explains much of at 21, though this may be changed at the user's option.
the variation in gate entry performance, but by no means Can better results be achieved by adjusting the
all of it. This is perhaps not so surprising, because ALPS abutment angle on a site-specific basis?
focuses on geometric parameters (e.g., depth of cover and
pillar dimensions). Including some site-specific geologic The field studies used in the development of ALPS
variables might improve the predictive ability of ALPS. found a range in abutment angles of approximately 10 to
Some possibilities include the caving characteristics of the 25 (13). The studies were not very helpful in identifying
overburden, the in situ coal strength, and the quality of the the causes of the variation, however. Both the largest and
roof rock. the smallest abutment angles were measured at the same
mine. Current Bureau studies may eventually help to bet-
OVERBURDEN CAVING CHARACTERISTICS ter define the effects of overburden geology on abutment
load. Measurements of abutment stresses are being con-
Overburden geology can vary dramatically from long- ducted in several deep-cover longwalls with very different
wall to longwall. For example, figure 5 shows stratigraphic overburden characteristics. In another study, the stiffness
columns from two neighboring Virginia longwalls. Massive of different gob materials is being measured in laboratory
sandstones comprise most of the overburden at the first tests. These results will be used in numerical models of
mine, while weaker shales predominate at the second. abutment load distributions around longwalls.
Subsidence research suggests that such differences in In practice, however, the effect of the abutment angle
geology can have a large effect on surface movements (11), may not always be as significant as it might first appear.
and abutment loads are surely an underground expression To begin with, development loads typically make up almost
of the same phenomena. In general, where the overbur- half of the tailgate loading, and they would not be affected
den is strong, less complete caving, more bridging across by overburden geology. In addition, for subcritical pan-
the gob, and a larger effective abutment angle might be els where the depth of cover is more than twice the panel
350
width, variations in B have relatively little effect on pre-
dicted loads. For example, with a 600-ft-wide panel at
300
KEY 2,000 ft of cover, increasing the abutment angle from 21
Sandstone more than all the way to 90 increases the abutment load by less than
10 ft thick 20 pct and the total load by only about 10 pct.
____________ 1 Sandy shale
Some other factors may affect abutment loads in ways
::::. : : Shale
that might be difficult to simulate by adjusting the abut-
250 _______________ Coals and shales
ment angle. These include the capacity of abandoned pil-
200
0 lars from previous panels to support abutment loads and
the effect of longwall panel width on the ability of strong
z strata to bridge the gob. Evaluating these factors with
0 150 field measurements would also be extremely difficult,
however.
L.L1
100
COAL STRENGTH
50
Probably the single question most often asked by ALPS
users is: What value should be used for the in situ coal
0
strength? Like the abutment angle, the in situ coal
MINE A MINE B strength is soft-wired in the ALPS computer program, with
Figure 5.Stratigraphic columns from neighboring Virginia a value of 900 psi. The author's experience is that little is
iongwalls. A, 60 pct of overburden is massive sandstone; B, to be gained by adjusting the coal strength. There are a
expected, while
25 pct of overburden is massive sandstone. number of possible explanations.
weaker conditions might result in more complete caving,
246
The traditional method for determining the in situ coal the uniaxial compressive strength does not correlate very
strength has been to apply a size-effect scaling factor to well with the internal friction angle, the most important
the strength of small coal specimens tested in the lab (4). triaxial strength parameter. Other issues associated with
Two serious drawbacks largely invalidate this laboratory estimating the strength of squat pillars are addressed in
test approach. First, it is very difficult to determine a
another paper in these proceedings (14).
meaningful specimen-size coal strength. Laboratory tests
on coal are notoriously unreliable because of sampling Fortunately, it may be that while the laboratory strength
bias, integrity loss during specimen preparation, and platen varies considerably from seam to seam, the in situ strength
effects during testing. An example of the problems with is more consistent, as suggested by figure 6. Barton and
laboratory testing was recently provided by a Kentucky Bandis (2) observed a similar scale effect on the strength
operator who was trying to carry out a longwall feasibility of rock joints. In their classic statistical study of pillar
study. Three different consultants were called in to carry performance, Salmon and Munro (16) also found that a
out compressive strength tests on coal specimens from the single coal strength parameter could be used for design
same coal seam. The average values reported back were throughout the South African coalfields, despite the wide
2,700, 5,000, and 8,500 psia range approximately as great range in compressive strengths reported there (4). There
as that reported for all U.S. coal seams put together (17). is similarly little indication that the predictive capability of
Better sampling and testing procedures can improve ALPS could be improved by considering variations in coal
consistency, but leave the second problem of the size ef- strength.
fect. There is now considerable evidence that the size- One aspect of pillar strength that does appear to have
effect scaling factor varies considerably from seam to immediate practical implications for longwall pillar design
seam. As figure 6 shows, 2-in specimens from the Pitts- is the effect of time. It is well known that the strength of
burgh coalbed are approximately twice as strong as similar rock decreases the longer the load is applied. In long-
specimens from the Pocahontas No. 3 coalbed. The dis- walls, the maximum design loading at the tailgate is ap-
parity in strength is rapidly reduced as the specimen size plied for a relatively short time. As stated earlier, the
is increased because of the different size effects in the two design criterion for this application is an ALPS stability
seams. factor in the 1.0-1.3 range. It should be expected that
Yet another problem is that the uniaxial compressive long-term applications, such as bleeders or mains, should
strength may not be very important when considering the have other criteria. At one gassy Pittsburgh Seam
strength of the large width-to-height ratio pillars typical of longwall, four separate bleeder systems had been blocked
longwalls. It is widely accepted that the strength of such by roof falls. Analysis indicated that the problems
squat pillars is largely triaxial strength derived from the occurred when the stability factor dipped below 1.5. It
confinement that is generated within them. Laboratory appears that such long-term applications may require the
stability factors originally suggested by Bieniawski (1.5-2.0).
The effect of time also becomes more important when
U) designing for super longwall panels because of the longer
period of time that the gates will be in use.
z KEY
n Data from Pittsburgh
Seam [Hustrulid (55)] GATE ENTRY STABILITY
U) Data from Pocahontas No. 3
Seam [Wang (/04)]
Abutment loads and pillar mechanics relate directly to
.
=5,718d -0.5 longwall pillar stability. Two other factors must be con-
2 sidered in a successful gate entry design: roof rock quality
a
Based on pillar design alone, mine A and mine B both ditch effort in difficult conditions, leading to a false
seemed like candidates for tailgate failure. When roof correlation between heavy support and failed designs.
quality and support were considered, however, mine C was Further statistical analyses will refine these relation-
actually at greater risk than mine A. Serious tailgate roof ships. The ultimate goal is to develop guidelines for se-
control problems later did occur at both mines B and C, lecting the appropriate ALPS stability factor, and the arti-
while mine A remained untroubled. ficial support, based on site-specific geologic evaluations.
Preliminary indications are that these factorsroof qual-
ity and artificial supportexplain the bulk of the variability 80
in figure 4. Recent research has focused on incorporating
them into the ALPS design methodology. Geotechnical 70
surveys have now been conducted at nearly 50 longwalls to
ROOF RATING
7
search attention since the 1970's, pillar extraction with
continuous miners remains an important section of the
NUMBER OF CASES
U.S. coal industry. Approximately 25 pct of all under-
ground mines still include pillar retreat in their roof con-
5
Successful
trol plans. Pillar extraction was also responsible for at
least 10 pet of all roof fall fatalities during a recent 9-year Unsuccessful
4
period (15) . Retreat pillaring also generates abutment tributary area
loading
loads that are essentially similar to those created by long- Unsuccessful
wall mining. A current Bureau research project is investi- abutment
2
gating whether the ALPS approach can be modified to aid loading
in the design of pillar retreat sections.
A literature review yielded 26 case histories of pillar
0
retreat mining Nineteen cases were determined to be
unsuccessful because of pillar squeezes, severe pillar
sloughage, pillar bumps, or other problems. In nearly all
0.25 0.5 0.75 1.0 1.25 1.50 175 2.0 2.25
unsuccessful cases, the troubled section was abandoned.
All cases were analyzed using a modified version of ALPS, APRS STABILITY FACTOR
called Analysis of Pillar Retreat Stability (APRS). The Figure 8.Preliminary results from analysis of pillar retreat
results are shown in figure 8. It appears that a retreat case histories using modified version of ALPS.
pillar design may require a greater stability factor than
does longwall mining, perhaps 1.5. The greater stability
factor may be explained by the longer time that a pillar geology in design performance, again using the RCS. An-
line is subjected to the maximum abutment loading. other task is to adjust the APRS program to better ac-
Further research, including a program of underground commodate the complicated three-dimensional panel geo-
site visits, is ongoing. These visits will address the role of metries that are typical of pillar sections.
CONCLUSIONS
The ALPS method has found wide acceptance within many leading mining schools have included the ALPS
the mining industry. More than 200 copies of the ALPS
computer program have been distributed, with users found method in undergraduate, graduate, and extension courses.
at almost every U.S. coal company employing the longwall Current research continues to build upon the ALPS
technique. ALPS has been used to help size pillars for approach. The next big step will be the incorporation of
new longwalls in Illinois, West Virginia, Colorado, roof rock quality and artificial support into complete
Alabama, and Kentucky. Mining consultants and regula- longwall gate entry and pillar retreat mining design
tory agencies have also made extensive use of ALPS, and packages.
REFERENCES
1.Artier, R. L. Pillar DesignContinuous Miner Butt Section and 3.Barton, T. M., and C. Mark. Field Evaluation of Three Longwall Pillar
Longwall Development Section. Paper in Proceedings of the 4th Confer- Systems in a Kentucky Coal Mine. BuMines RI 9283, 1989, 13 pp.
ence on Ground Control in Mining. WV Univ., Morgantown, WV, 1985, 4.Bieniawski, Z. T. Rock Mechanics Design in Mining and Tunneling.
pp. 160-165. Balkema, 1984, 272 pp.
2.Barton, N., and S. Bandis. Effects of Block Size on the Shear 5.Brass, J. F. The Evolution of a Longwall System to Suit the Deep Mines
Behavior of Jointed Rock. Paper in Issues in Rock Mechanics, Proceed- in Alabama. Paper in Longwall-Shortwall Mining, State of the Art.
ings of the Twenty-Third Symposium. Univ. CA, Berkeley, CA, 1982, Soc. MM. Eng. AIME, 1981, pp. 179-182.
pp. 739-760.
249