Project Code: 4YG - 04700 Report Date : 10-Jun-2017 Saturday No. of Day Report No. DPR- 640
Proj Start Date 2014 Contract Period 1 Year Calendar Day AM PM Fine
Weather
Estimate Completion Date 14-Nov-2017 Remain Period 158 Calendar Day 6~8 8~10 10 ~12 12~2 2~4 4~6 Rain
Work Force
Office
Trades PM PE SSE Site Engr QA/QC QS Admin Safety Security Site Store Driver Surveyer Geotech Workers Mason Carpenter Smith Welder
Staff
Today 1 3 1 1 3 2 1 17 9 32 59 2
Steel Roofing D&W Ceiling Water
Trades Scaffolder Painter Aluminium Total
Erector worker Installer worker Proofing
Today 4 135
Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks
Excavator 60 Ton Crane Car Crane
Dozer 50 Ton Crane Folk Lift
1.5 Ton Roller 25 Ton Crane Rummer 1
Boom Lift Generator Truck
Material Delivery On Site
Quantity Quantity Quantity
Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total
Project Code: 4YG - 04700 Report Date : 10-Jun-2017 Saturday No. of Day Report No.
Test Item Remarks
Sampl
e
LTI Free Day UA,UC Near Miss FAI MTC LTA Daily TBT Conducted
HSE How to motivate work practices for employees.
715940 0 0 0 0 0 By Safety Officer
IV Other Work
Special Event
Visitors Site
Purpose
on Site Instruction
Project Manager
FO-OP-01 REV-00 Project Engineer Prepare By: Site EngineerPage: 2/6
Daily Report
Rebar fixing & Formwork installation at 2nd Floor Beam&Slab Formwork installation at Main Fish Tank Formwork installation for Exhibit 1.1