Documente Academic
Documente Profesional
Documente Cultură
Contents
1. Introduction
Some facts
Indian Power Industry
Industry Structure
Statistics of the scenario in India
Policy
Players in the Industry
2. Government Regulations and policies
Electricity Act 2003
Impact on the Industry
Tariff Policy
Features of the Policy
Recent developments
Norms Rationalised
3. Role of Institutional Players
Central Government
State Government
Central Electricity Authority
Central Electricity Regulatory Commission
State Electricity Regulatory Commission
National Load Dispatch Centre
4. Wind energy basics
What is Wind Energy?
What is a wind Turbine?
5. Growth Potential
Installation cost
Operating and maintenance cost
Financial Institutions
Associations and Societies
34. List of Private wind Farm owners (10 MW and
above ) as of 31-03-2008
35. State wise communication addresses (official)
36. Conclusions
ANNEXURE – I
Project on Installation of Wind energy generators
for Captive use
Detailed project Cost (for 1.00 MW)
ANNEXURE – II
Wind Power density MAP
Wind Resource MAP
Wind Power cumulative capacity MAP
Major Power transmission Locating MAP
Energy Crisis Map
ANNEXURE –III
Comparisons Between Conventional energy and
Wind Power
SOME FACTS
Industry Structure
Power sector structure in India has been very simple yet well
defined. Majority of Generation, Transmission and
Distribution capacities are with either public sector
POLICY
Indian Power Policy framework is designed and developed
under Electricity Act 2003 and National Electricity Policy
2005. Under current policy the Government is keen to draw
private investment into the sector.100% FDI permitted in
Generation, Transmission & Distribution of power and no
discrimination is made in terms of foreign private and
domestic private players. All the companies (domestic and
private) in this particular sector are treated at par.
Incentives like, Income tax holiday for a block of 10 years in
the first 15 years of operation; waiver of capital goods'
import duties on mega power projects (above 1,000 MW
generation capacity) is being provided. Independent
Regulators that exist in Indian power sector are a) Central
Electricity Regulatory Commission for central PSUs
B)centreal electricity regulatory commission for inter-state
issue.
• Tariff Policy
RECENT DEVELOPMENTS
NORMS RATIONALISED
• Central Government
• Formulate National Electricity Policy and National
Tariff Policy
• Formulate national policy on stand alone systems
• Formulate national policy on Rural Electrification
• Make Rules & Procedure for implementing
provisions of Electricity Act 2003
• Appoint Chairpersons& other members of CEA
• State Government
The three examples above are for costs per kilowatt-hour for
a 51 MW wind farm at three different average wind speeds
expressed in meters per second. Cost figures include the
current wind production tax credit.
policies, a global
capacity of more than 1,500,000 MW is possible by the year
2020.
General Situation:
Continental Scenarios:
first time, Europe (32.8 %), North America (32.6 %) and Asia
(31.5 %) account for almost similar shares in new capacity.
However, Europe is still the strongest continent while North
America and Asia are increasing rapidly their shares. The
countries in Latin America and Africa counted for respectively
only 0.6 % and 0.5 % of the total capacity and fell back in
terms of new installations down to respectively only 0.4 %
and 0.3 % of the additional capacity installed worldwide in
the year 2008.
Growth Potential
Investments
Strengths
Weaknesses
Opportunities
Threats
Looking ahead
FINANCIA
140.0
120.0
Rs. 8000 Crore has been set aside in 2008-09 for accelerated
power development and reforms project. The custom duty
on project imports has been reduced from 7.5% to 5%.
Impact on sector
Impact on companies
PREDICTIONS
Government Initiatives
Valuations
cm)
WIND WIND
WIND TURBINE
ELECTRICAL GENERATOR
CONTROLLER
ENERGY STORAGE
ENERGY STEP-UPING
DEVICE
LOAD UTILIZATION
Table-1
The various incentives that are being provided by the central and
the state governments are as per the details given below:
· Accelerated Depreciation
· Capital Subsidy
are-
Constituents
The gas thus produced by the above process in a bio-gas plant
does not contain pure methane and has several impurities. A
typical composition of such gas obtained from the process is as
follows:
Table –II
in India who have a tie up with foreign firms should see that
the level of indenization of the WEGs is increased so that
the plant and machinery cost is reduced.
2. Suitable extension mechanism has to be devised wherein
the benefits of development of wind power can be
disseminated to the rural communities, village panchayats
so that collective organizational skills can be developed.
3. Simple, easy to understand and lucid techniques should be
devised which can help in correct estimation of power
requirement at various power-consuming units.
4. The various agencies providing institutional finance have
got a key role to play by providing finance to the promoters
at concessional rate of interest, repayment period matching
to the level of annual revenue available for repayment of
debt, provision of adequate grace period, rationalization of
the process of creation of charge by the bankers on the
securities of the promoters etc.
5. Simplification of procedure for speedy land/ site allotment
for the wind turbines.
wind speed, wind power density, wind direction etc. The site
should find a mention in the wind energy atlas of India having
potentiality for wind power development. The average yearly
wind speed of the site should be greater than the minimum cut-in
wind speed for the specific WEG proposed to be installed. Micro
sitting at the site should also have been done by MNES or
concerned state level agency. Non agricultural land should
invariably be used for installation of the WEGs. A minimum
distance of 7 times the rotor diameter should be maintained
between 2 adjacent WEGs installed in a single row, whereas a
minimum row to row distance of 3 times the rotor diameter
should be maintained between 2 WEGs. Therefore, approximately
an area of 4.00 acre is required for installation of 1.00 MW
capacity wind power plant. The tentative cost of land and land
development charges for the model project has been considered
at Rs. 4.00 Lakh.
Civil construction:
Table-III
Electricals:
Lakh has been considered for the model project. Apart from it, a
cost of Rs. 0.975 Lakh has also been considered towards cost of
33 KV OHT Line.
A cost of Rs. 25.00 Lakh has been considered for the model
project.
Project Cost:
Table -IV
other civil
structures
5 Electrical and 4.50 4 18.00
Transformers 33
KV
6 Erection and 3.00 4 12.00
Commissioning
7 Other project 25.00 1.00 MW 25.00
cost including
charges for
infrastructure
development @
Rs. 25 Lakh per
MW for 1.00 MW
8 Cost of 33 KV 0.975
OHT Line
( External and
internal) 0.15 KM
assumed approx.
@ Rs. 6.50 lakhs
per KM or as
actual
9 Total 475.98
9. Marketing
10. Insurance:
12. Repayment:
Banks are free to decide the rate of interest within the overall RBI
guidelines . However, for working out the financial viability and
bankability of the model project we have assumed the rate of
interest as 12% p.a.
15. Security:
electricity board.
The results are place in annexures I(a) to VIII(a) and I(b) to VIII(b)
respectively. The project has a margin money component of 25%
with the rate of interest on term loan and working capital as 12%
p.a. and 13% p.a. respectively. The financial indicators for two
different investment scenarios are as under:
Check ANNEXURE-I
DEAL STRUCTURE
One bank may act alone if the project is very small, but will
usually arrange a lending syndicate – this means that a
group of banks will join together to provide the finance,
usually with one bank as the ‘lead arranger’ of the deal. This
is shown in Figure 3.1, where Bank A syndicates the loan to
Banks B, C and D.
Generally, a bank will not lend 100 per cent of the project
value and will expect to see a cash contribution from the
borrower – this is usually referred to as ‘equity’. It is typical
to see 25 to 30 per cent equity, and 70 to 75 per cent loan
(money provided by the bank as their investment).
Occasionally, a loan of 80 per cent is possible.
the debt payments. This is called the debt service cover ratio
(DSCR) and is the ratio of cash available at the payment date
to the debt service costs at that date. For example, if €1.4
million is available to make a debt payment (repayment and
interest) of €1 million, the DSCR is 1.4:1.
The interest rate is often 1-1.5 per cent above the base rate
at which the bank borrows their own funds (referred to as
the interbank offer rate). In addition, banks usually charge a
loan set-up fee of around 1 per cent of the loan cost, and
they can make extra money by offering administrative and
account services associated with the loan. Products to fix
interest rates or foreign exchange rates are often sold to the
project owner.
EXPERIENCE
After the initial cost of a turbine is paid off, the only on-going
cost is maintenance; the fuel is free. How long do wind
turbines take to pay for themselves? The answer to this
question depends on a lot of factors, such as how often the
wind blows, how much money homeowners can save by
generating their own electricity, and how much a
commercial wind farm can sell their energy for.
A. Installation Costs
at one location.
Calculations
The total annual cost will be the initial cost of the turbine
spread out over the lifetime of the turbine plus the annual
operating expenses.
Source: BTM-consult
The wind regime at the chosen site, the turbine hub height
and the efficiency of production determine power production
from the turbines. So just increasing the height of turbines
has resulted in higher power production. Similarly, the
methods for measuring and evaluating the wind speed at a
given site have improved substantially in recent years and
thus improved the site selection for new turbines. However,
the fast development of wind power capacity in countries
such as Germany and Denmark implies that, by now, the
best wind sites in these countries have been taken and that
new on-land turbine capacity will have to be erected at sites
Looking at the cost per rated capacity (per kW), the same
decline is found in the period 1989 to 2004, with the
exception of the 1,000 kW machine in 2001. The cause is
related to the size of this specific turbine: with higher hub
height and larger rotor diameter, the turbine is equipped
with a slightly smaller generator, although it produces more
electricity. This fact is particularly important when analysing
turbines built specifically for low and medium wind areas,
where the rotor diameter is considerably larger in
comparison to the rated capacity. As shown in Figure 1.4,
the cost per kW installed also rose by 20 per cent in 2006
compared to 2004.
cent of the total levelised cost per kWh produced over the
lifetime of the turbine. If the turbine is fairly new, the share
may only be 10-15 per cent, but this may increase to at least
20-35 per cent by the end of the turbine’s lifetime. As a
result, O&M costs are attracting greater attention, as
manufacturers attempt to lower these costs significantly by
developing new turbine designs that require fewer regular
service visits and less turbine downtime.
• Insurance;
• Regular maintenance;
• Repair;
• Spare parts, and
• Administration.
Figure 1.6, shows how total O&M costs for the period
between 1997 and 2001 were split into six different
categories, based on German data from DEWI. Expenses
pertaining to buying power from the grid and land rental (as
in Spain) are included in the O&M costs calculated for
Germany. For the first two years of its lifetime, a turbine is
usually covered by the manufacturer’s warranty, so in the
German study O&M costs made up a small percentage (2-3
per cent) of total investment costs for these two years,
corresponding to approximately 0.3-0.4 c€ /kWh. After six
years, the total O&M costs increased, constituting slightly
less than 5 per cent of total investment costs, which is
equivalent to around 0.6-0.7 c€/kWh. These figures are fairly
similar to the O&M costs calculated for newer Danish
turbines (see below).
Source: DEWI.
Figure 1.7 shows the total O&M costs resulting from a Danish
study, and how these are distributed between the different
O&M categories, depending on the type, size and age of the
turbine. For a three-year-old 600 kW machine, which was
fairly well represented in the study, approximately 35 per
cent of total O&M costs covered insurance, 28 per cent
regular servicing, 11 per cent administration, 12 per cent
repairs and spare parts, and 14 per cent for other purposes.
In general, the study revealed that expenses for insurance,
regular servicing and administration were fairly stable over
time, while the costs for repairs and spare parts fluctuated
considerably. In most cases, other costs were of minor
importance.
Figure 1.7 also shows the trend towards lower O&M costs for
new and larger machines. So for a three year old turbine, the
O&M costs decreased from around 3.5 c€/kWh; for the old 55
kW turbines to less than 1 c€/kWh for the newer 600 kW
machines. The figures for the 150 kW turbines are similar to
the O&M costs identified in the three countries mentioned
above. Moreover, Figure 1.7 shows clearly that O&M costs
increase with the age of the turbine.
Source: Risø
Source: Risø
Figure 1.10 shows the calculated unit cost for different sizes
of turbines, based on the same assumptions used in the
previous section: a 20-year lifetime is assumed for all
turbines in the analysis and a real discount rate of 7.5 per
annum is used. All costs are converted into constant 2006
prices. Turbine electricity production is estimated for two
wind regimes - a coastal and an inland medium wind
position.
Source: Risø
Karnataka
Andhra Pradesh 50.650
5.4 115.6 22.500
121.0 52.460
7.80081.430
113.54200.400
121.3 170.930
0.8 264.750
0.0 187.000
0.0 1030.120
4
Maharasthra
Karnataka 198.060
7.1 577.5196.545
584.6 2.000
7.075 6.250
837.95 48.750
845.0 545.100
264.7 483.600
187.0 276.075
173.10 1756.380
1184.45
2
Rajasthan 9.110 8.380 44.440 129.580 93.860 74.525 111.750 70.450 542.095
Kerala 2.0 0.0 2.0 2.125 0.23 2.35 0.0 8.7 12.50 23.00
Tamil Nadu 806.860 46.960 132.905 355.145 688.330 860.655 564.960 391.900 3847.715
Madhya Pradesh 0.6 39.7 40.3 0.590 56.00 56.59 17.4 69.25 0.00 187.69
West Bengal 1.000 - - - - 0.250 0.500 - 1.750
Maharashtra 8.4 992.9 1001.3 8.980 1471.3 1480. 483.6 276.07 82.00 1837.85
Others 1.300 - - - - - - - 1.300
3 5
TOTAL (MW) 1347.715 284.535 238.955 607.680 1114.615 1748.160 1772.760 1583.505 8697.9
Rajasthan 6.4 351.7 358.1 6.350 465.65 471.9 111.7 70.45 132.20 670.97
9
Tamil Nadu 19.4 2873.1 2892.5 19.355 3440.1 3459. 565 391.90 250.30 4132.72
4
West Bengal 1.1 0.0 1.1 1.750 0.0 1.75 0.5 0.0 0.00 1.10
Others 1.6 0.0 1.6 1.6 0.0 1.6 0.0 0.0 0.00 3.20
Total (All India) 69.6 5271.0 5340.6 73.165 7041.2 7114. 1773 1583.5 829.90 9587.14
6 0
CENTRAL INCENTIVES
A. Indirect Taxes
I. Custom Duty for Wind Energy Equipments and
Components (Notofication No.21/2002-custom
dated 01.03.2002, as amended by Notification
No.11/2006 –customs dated 01.03.2006)
Rat
Description of Goods
e
i) Wind operated electricity generators upto 30
5
kW and wind operated battery chargers upto 30
%
kW
ii) Parts of wind operated electricity generators
for manufacturer/maintenance of wind operated
electricity generators, namely :
5
a) Special bearing %
b) Gear Box 5
c) Yaw components %
d) Wind turbine controllers 5
e) Parts of the goods specified at (a) to (d) %
above 5
f) Sensors %
g) Brake hydraulics 5
h) Flexible coupling %
i) Brake calipers 25
%
25
%
25
%
25
%
iii) Blades for rotor of wind operated electricity 5
generators for the %
manufacturers/maintenanceof wind operated
electricity generators.
iv) Parts for the manufacturer/maintenance of 5
blades for rotor of wind operated electricity %
generation
v) Raw materials for manufacturer of blades for 5
rotor of wind operated electricity generators %
Conditions :
(a) If the importer at the time of importation
furnishes in all cases, a certificate to the Dy.
Commissioner of Customs or Assistant Commissioner
of Customs as the case may be, from an officer not
below the rank of Deputy Secretary to the
Government of India in the Ministry of Non-
Conventional Energy Sources recommending the
grant of this exemption and in the case of the goods
at (ii) to (v) the said officer certifies that the goods
are required for the specified purposes; and
(b) Furnishes an undertaking to the said Dy.
Commissioner of Customs Assistant Commissioner to
the effect that -
(i) in the case of wind operated electricity generators
upto 30 kW, or wind operated battery chargers
upto 30 kW, he shall not sell or otherwise dispose
off, in any manner, such generators or chargers
for a period of two years from the date of
importation.
(ii) in case of other goods specified at (ii) to (v), he
shall use them for the specified purpose, and
(iii) in case he fails to comply with sub-conditions (i)
or (ii), or both conditions, as the case may be, he
shall pay an amount equal to the difference
between the duty leviable on the imported goods
but for the exemption under this notification and
system.
For other
district
Rs.3.78
per unit
for
injection
on 33kV
or 11 kV
system &
Rs.3.89
per unit
for
injection
in EHV
system.
Third Allowed Allowed Allowed Allowed Allowed Allowed Allowed Allowed Allowed
Party under under under under under under under under under
Sale Electricity Electricit Electricity Electricit Electricity Electricity ActElectricity Electricit Electricit
Act 2003y ActAct 2003y ActAct 20032003 subjectAct 2003y Acty Act
subject to2003 subject to2003 subject toto regulationsubject to2003 2003
regulation subject regulation subject regulation framed byregulation subject subject
framed byto framed byto framed byrespective framed byto to
respective regulatio respective regulatio respective SERCs respective regulatio regulatio
SERCs n framedSERCs n framedSERCs SERCs n framedn framed
by by by by
respectiv respectiv respectivrespectiv
e SERCs e SERCs e SERCs e SERCs
Other Industry E.D. No No # PowerExemption
Incen- Status Exempte electricity electricity evacuation from
tives d, Duty for 5 Duty for 5 arrangement, electricity
Demand yrs yrs Approach Duty
cut 30% Road, @50%
of Electricity for 7
windfarm Duty, Loan toyears
installed cooperative
capacity societies
Penalty 10 paise10 paiseRs. 0.40 27 paise25 paise5 paise25 paise
on per kVArhper Per kVArh per kVArh per kVArh per uearper
kVArh upto 10%kVArh up w.e.f. kVArh if
consum & 25 paiseto 10% 01/04/200 the
-ption per kVArhand 20 6 withration of
above 10% paise per escalation kVArh
KVArh of 5% perdrawn to
above year KWh
10% exported
is upto
10% and
50 paise
per
KVArh
for more
than
10%.
2 Gujarat 9675
3 Karnataka 6620
4 Kerala 875
6 Maharashtra 3650
7 Orissa 1700
8 Rajasthan 5400
Total 45195
1 Andaman & 14 2 1
Nicobar
2 Andhra 65 4 35
Pradesh
3 Arunachal 9 0 -
Pradesh
4 Assam 8 1 -
5 Chhattisgar 3 - -
h
6 Goa 1 - -
7 Gujarat 62 3 38
8 Haryana 7 1 -
9 Himachal 10 1 -
Pradesh
10 Jammu & 9 2 -
Kashmir
11 Jharkhand 2 - -
12 Karnataka :
MNES 50 14 21
Stations 19 - 8
KPCL
Stations
13 Kerala 27 2 16
14 Lakshadwee 10 - 8
p
15 Madhya 36 6 7
Pradesh
16 Maharashtr 91 4 32
a
17 Manipur 5 1 -
18 Mizoram 5 - -
19 Orissa 11 - 6
20 Punjab 11 - -
21 Pondichery 4 - -
22 Rajasthan 38 - 7
23 Sikkim 3 - -
24 Tamil Nadu 67 3 44
25 Tripura 3 - -
26 Uttaranchal 11 - 1
27 Uttar 7 4 -
Pradesh
28 West 10 - 1
Bengal
1 Bhimunipatnam, Dist.Vishakapatnam
2 Jamalamadugu, Dist.Cuddapah
3 Kadavakallu, Dist.Ananthapur
4 Kondamithipalle, Dist.Kurnool
5 M.P.R. Dam, Dist.Ananthapur
6 Nallakonda, Dist.Ananthapur
7 Nazirabad, Dist.Rangareddy
8 Pampanoorthanda, Dist.Ananthapur
9 Ramagiri, Dist.Ananthapur
10 Thirumalaypalli, Dist.Cuddapah
11 Vajrakarur, Dist.Ananthapur
Gujarat
12 Amrapar, Dist.Junagadh
13 Bamanbore II, Dist.Rajkot
14 Bhandariya, Dist.Bhavnagar
15 Dhank, Dist.Rajkot
38 Horti, Dist.Bijapur
39 Jogimatti, Dist.Chitradurga
40 Kamkarhatti, Dist.Belgaum
41 Kanderayanahalli, Dist.Haveri
42 Kappatta Hills, Dist.Gadag
43 Mannikeri, Dist.Belgaum
44 Mavinhunda, Dist.Belgaum
45 Sangundi, Dist.Bijapur
46 Subramanyahalli, Dist. Bellary
Kerala
47 Kanjikode, Dist.Palakkad
48
Kulathumedu, Dist. Idduki
50 Kukru, Dist.Betul
51 Mahuriya, Dist.Shajapur
52 Nagda, Dist. Dewas
53 Sendhwa, Dist.Khargon
54 Valiyarpani, Dist. Khargon
Maharshtra
55 Alamprabhupathar, Dist.Kolhapur
56 Amberi, Dist.Satara
57 Bramanawel, Dist.Dhule
58 Dhalgaon, Dist.Sangli
59 Dongarwadi, Dist.Sangli
60 Gudepanchgani, Dist.Sangli
61 Kavdya Dongar, Dist.Ahmadnagar
62 Khandke, Dist.Ahmadnagar
63 Kolgaon, Dist.Ahmadnagar
64 Kotoli, Dist.Kolhapur
65 Lonavla, Dist.Pune
66 Matrewadi, Dist.Satara
67 Motha, Dist.Amravathi
68 Sautada, Dist.Beed
69 Takkarmauli, Dist.Dhule
70 Thoseghar, Dist.Satara
71 Vankusawade, Dist.Satara
72 Vijayadurg, Dist.Sindhudurg
Orissa
73 Damanjodi, Dist.Koraput
74 Puri, Dist.Puri
Rajasthan
75 Devgarh, Dist.Chittourgarh
76 Jaisalmer, Dist.Jaisalmer
77 Phalodi, Dist.Jodhpur
Tamil Nadu
78 Achamkuttam, Dist.Thirunelveli
79 Alagiyapandiyapuram, Dist.Thirunelveli
80 Andipatti, Dist.Madurai
81 Ayikudi, Dist.Thirunelveli
82 Edayarpalayam, Dist.Coimbatore
83 Ennore, Dist.Chengelpet
84 Maivadi, Dist.Coimbatore
85 Manglapuram, Dist.Thirunelveli
86 Mettukadai, Dist.Periyar
87 Naduvakurichi, Dist.Thirunelveli
88 Onamakulam, Dist.Tuticorin
89 Ottapidaram, Dist.Tuticorin
90 Pongalur, Dist.Ciombatore
91 Pulavadi, Dist.Coimbatore
92 Pusaripatti, Dist.Coimbatore
93 Puliyamkulam, Dist.Thirunelveli
94 Sankaneri, Dist.Thirunelveli
95 Ovari, Dist.Thirunelveli
96 Vakaikulam, Dist.Tuticorin
West Bengal
SERVICE PROVIDERS
O&M Agencies
Sl. Name
No.
1 Batliboi enXco Pvt. Limited
7 M.P.Windfarms Limited
162, Maharana Pratap Nagar, Zone-II,
Bhopal - 462 011
Tel : 0755-553681, 555479 Fax : 0755-550481
E-mail : mpwl@sancharnet.in
8 Pentagon WTG Services
10 MW and Above
As on 31.03.2008
Sl. Name of Owner Total
No. (MW)
10
C Mahendra Exports Ltd 13.750
4
10
Textool Co. Ltd 13.400
5
10
Rajapalayam Mills Ltd. 13.300
6
10
V.M. Salgaonkar & Bro Pvt. Ltd. 13.300
7
10
Y Mahabaleswarappa & Sons 13.300
8
10
Sree Narasimha Textiles Ltd. 13.200
9
11
Echjay Industries Pvt. Ltd. 13.050
0
11
Shriram City Union Fin. 13.050
1
11
Mahanagar Developers 12.800
2
11
SCM Creations 12.750
3
11
Metal Powder Co. Ltd 12.575
4
11
KRBL Limited 12.500
5
11
Tirupur Textiles Pvt. Ltd. 12.500
6
11
Shriram Investments Ltd 12.450
7
11
Best International 12.400
8
11
Prabhu Spinning Mills (P) Ltd. 12.300
9
12
Bellary Iron Ores Pvt. Ltd. 12.250
0
12
Era Infrastructure (India) Limited 12.150
1
12
Velatal Spinning Mills Ltd 12.110
2
12
Advik-Hi-Tech Pvt. Ltd. 12.100
3
12
Ansal Properties & Infrastructure Ltd 12.000
4
12
Avinash N Bhosale 12.000
5
12
Tamilnadu Petro Products 12.000
6
12
Cheran Spinners Ltd. 11.900
7
12
Suzlon Towers & Structures Limited 11.750
8
12
Sambandam Spinning Mills 11.625
9
13
Transport Corporation of India Ltd. 11.500
0
13
Usdev International Ltd 11.330
1
13
Bhoruka Power Co. Ltd. 11.300
2
13
Subhash Projects & Mktg 11.285
3
13
Saurashtra Fuels Pvt. Ltd. 11.250
4
13
DCW Limited 11.200
5
13
Revathi Equipment Ltd 11.150
6
13
Ruchi Soya Industries Ltd. 11.050
7
13
Walden Properties Pvt Ltd 11.050
8
13
Texmo Industries 10.840
9
14
Charisma Builders 10.800
0
14
Rajpalayam Mills 10.750
1
14
Emco Limited 10.500
2
14
Energy Infratech Pvt Ltd 10.500
3
14
Maris – Karnatka 10.500
4
14
Elecon Engineering Co. Ltd. 10.450
5
14
Srei Infrastructure Finance Ltd. 10.400
6
14
Khatau Narbheram & Co 10.250
7
14
Kandagiri Spinning Mills 10.125
8
14
UTI Ltd. 10.125
9
15
APSRTC 10.000
0
15
Deepak Ferti.& Petrochem.Corpn Ltd. 10.000
1
15
Era Constructions India Ltd 10.000
2
15
Lanco Infratech Ltd 10.000
3
15
Nuclear Power Corpn. of India Ltd 10.000
4
15
Sri Ranganathar Industries P. Ltd. 10.000
5
3841.5
TOTAL
10
3) Gujarat 4) Karnataka
Director, Managing Director,
Gujarat Energy Development Karnataka Renewable
Agency(GEDA), Energy Development Ltd.
Block No. 11 & 12, 4th Floor (KREDL),
Sector - II No.19, Maj.Gen. A.D.
Udyog Bhawan, Loganadhan INA Cross,
Gandhi Nagar - 382 017 Queens Road,
Email : info@geda.org.in Bangalore – 560 052
Tel : 080-2282220-1
Fax : 080-2257399
Email : kredl@blr.vsnl.net.in
5) Kerala 6) Lakshadweep
Director, Agency for Non- Executive Engineer (Ele.)
conventional Energy and Union Territory of
Rural Technology(ANERT),
Lakshadweep, Department
P.B.No. 1094,
Kesavadasapuram, of Electricity,
Thiruvananthapuram - Kavaratti - 682555,
695004, Tel : 04896-262127
Tel : 0471-2449854, Fax : 04896-262936,
2440121-2 262140
Fax : 0471-2449854
Email : anert@vsnl.com
7)Madhya Pradesh 8) Maharashtra
Managing Director,Madhya Director,
CONCLUSIONS
ANNEXURE-I
Commissioning
7 Other project cost 25 1 25
including charges for
infrastructure
development @ Rs.25.00
Lakh per MW for 1.00
MW
8 Cost of 33 KV OHT Line ( External and 0.98
internal) 0.15 KM assumed approx. @ Rs. 6.50
lakh per KM or as actual
9 Total 475.98
(Rs. Lakh)
Qty. or
Rate/unit
S.No. Description no. of Amount
(Rs.Lakh)
units
Purchase of land,
Lump sum 4.00
1 land development 4.00
amount acres
and fencing charges
Supply of WEG of
2 250 kW capacity 100.00 4 400.00
each
Packaging ,
handling, loading ,
transportation,
3 1.00 4 4.00
unloading and
insurance cover till
erection of WEGs
Foundation and
4 3.00 4 12.00
other civil structures
5 Electrical and 4.50 4 18.00
Transformers 33 KV
Erection and
6 3.00 4 12.00
Commissioning
Other project cost
including charges for
infrastructure
7 25.00 1 25.00
development @ Rs.
25.00 Lakh per MW
for 1.00 MW
Cost of 33 KV OHT
Line ( External and
internal) 0.15 KM
8 0.98
assumed approx. @
Rs. 6.50 lakh per KM
or as actual
9 Total 475.98
ANNEXURE-II
ANNEXURE-III