Important Features of Bankable

Power Purchase Agreements


For Renewable Energy Power Projects

A bankable power purchase agreement (PPA) is


essentially a long term offtake agreement executed
with a creditworthy offtaker and having a sufficient
tenor to enable repayment of debt by providing an
adequate and predictable revenue stream.
10 Important Features to Include or
Consider for a Bankable PPA:
1. Dispatch Risk be no limitation or additional with no access to the market and
There are two structures generally approvals required to transfer funds thus should be limited to significant
accepted by lenders for to offshore accounts as required. events. The agreement should
mitigating the risk that the offtaker provide that if the PPA is terminated
may not dispatch the generating 4. Change in Law or for any reason, then in case of
facility. Change in Tax transfer of the facility to the offtaker,
The agreement should explicitly the offtaker shall provide a
Take or Pay: The offtaker pays a state which party takes the risk of termination payment at least equal
fixed tariff comprising a capacity the law or tax regime changing to the full amount of the power
charge (a fixed amount that is paid after the date of the agreement in producers outstanding bank debt,
for available capacity - no dispatch such a way as to diminish the and in the case of the
required) and an output charge (an economic returns of the offtakers default, a return on
amount paid in respect of energy transaction for such party (e.g., equity.
actually delivered). This permits the increase in taxes on power
power producer to cover its fixed producers reducing the producers 8. Assignment
costs with the capacity charge, returns). In order for PPAs to be The PPA should allow collateral
including debt service, fixed bankable, most lenders require the assignment of the agreement to
operating costs, and an agreed offtaker to take this risk. the power producers lenders with
equity return. the right to receive notice of any
5. Force Majeure default and to cure such default.
Take and Pay (typical for wind The agreement should excuse the Additional step-in rights are
and solar): The offtaker must take, power producer from performing its generally set forth in a separate
and pay a fixed tariff for all energy obligations if a force majeure event direct agreement between the
delivered (no dispatch required). If (an event beyond the reasonable lenders and the offtaker.
energy cannot be physically taken control of such party) prevents such
by the offtaker and output is performance. The allocation of 9. Offtaker Payment Support
curtailed, energy will be costs and risk of loss associated with Depending upon the size of the
calculated and paid for on a a force majeure event will depend project and the creditworthiness of
deemed delivered basis. on the availability of insurance and the offtaker and the development
in some cases the degree of of the energy sector in a certain
2. Fixed Tariff political risk in the country/region. country, short term liquidity
It is important that the revenue of instrument, a liquidity facility and/
any PPA, whether take or pay or 6. Dispute Resolution or a sovereign guaranty will be
take and pay, be a fixed amount The agreement should provide for required to support the offtakers
per kWh generated to adequately offshore arbitration, in a neutral payment obligations.
cover the cost of operating the location, under rules generally
facility, repay the debt and provide acceptable to the international 10. Transmission or
a reasonable return on equity. community (e.g. UNCITRAL or LCIA Interconnection Risk
or ICC). The PPA should indicate which party
3. Foreign Exchange bears the risk of connecting the
In order to avoid subjecting the 7. Termination and facility with the grid and transmitting
power producer to currency risk, the Termination Payments power to the nearest substation.
PPA should be either denominated The PPA should set out clearly the The more significant these risks (due
in or linked to an exchange rate of basis on which either party may to terrain, distance, populated
the currency of the power terminate the PPA. Termination by areas), the more the lenders will
producers debt, and there should the offtaker may leave the project require the offtaker to bear all or a
significant portion thereof.