ANALYSIS OF RATES FOR SUB BASE, BASE OF ROAD.

MRS, BI-
ANNUAL PERIOD (1st FEBRUARY, 2015 TO 31st JULY, 2015) DISTRICT
LAYYAH
Unit= 100 Cft
1 Cost of sub base material. 100 Cft
Extra 25% Qty for compect thickness. 25 Cft
125 Cft @Rs. 3035.70%Cft Rs.3794.63
Carriage charges from Sakhi Serwar to
site of work.
Total lead(169+5)=174 K.M 174 K.M

i Carriage charges upto 0-10 K.M 10 KM


10 KM @Rs. 530.00 Rs.530.00
ii Carriage charges upto 11-200 K.M. 164 KM
164 KM @Rs. 18.70 P-Km Rs.3066.80
Total Rs.3596.80

Rs. 3596.80
Total. Rs.7391.43
Add: 20% Additional cost & carriage of Rs. 1478.29
loose material.

Total Rs.8869.72

2 Cost of base course of crushed stone. 100 Cft


Extra 22% Qty for compect thickness. 22 Cft
122 Cft @Rs. 4702.50%Cft Rs.5737.05
Carriage charges from Sakhi Serwar to
site of work.
Total lead(169+5)=174 K.M 174 K.M
i Carriage charges upto 0-10 K.M 10 KM
10 KM @Rs. 530.00 Rs.530.00
ii Carriage charges upto 11-200 K.M. 164 KM
164 KM @Rs. 18.70 P-Km Rs.3066.80
Total Rs.3596.80

Rs. 3596.80
Total. Rs.9333.85
Add: 22%Additional cost & carriage of Rs. 2053.45
loose material.

Total Rs.11387.30
ANALYSIS OF RATES FOR EARTH WORK LEAD UPTO ONE MILE.
Unit 1000 Cft
1 Earthowrk in ordinary soil for
embankments lead upto ft. (30 m),
including ploughing and mixing with
blade or disc harrow or other suitable
equipment, compaction by mechanical
means at optimum moisture content
and dressing to designed section,
complete in all respects:-iii) 85%
maximum modified AASHO dry
density lead upto one mile.

Rs.4055.90
2 Transportation of earth all types when
the total distance, including the lead
covered in the item of work, is more
than rate of earthwork, without
deducting 1000 ft. (300 m) the lead
covered in the item of a) upto mile
(400 m).

Rs.1917.00
3 b) for every 330 ft. (100 m) beyond
mile (400 m) upto one mile. (1.6 Km.)
12 Unit @Rs. 66.60 Rs.799.20
Total Rs. 6772.10

Sub Engineer
Sub Divisional Officer, Executive Engineer,
Provincial Buildings Sub Division, Provincial Buildings Division,
Layyah. Muzaffargarh.
ABSTRACT OF COST FOR CONSTRUCTION OF METTELED ROAD 12' WIDE. MRS, BI-ANNUAL
PERIOD (1st FEBRUARY, 2015 TO 31st JULY, 2015) DISTRICT LAYYAH
UNIT. 10FT
1 Earthowrk in ordinary soil for
embankments lead upto ft. (30 m),
including ploughing and mixing with
blade or disc harrow or other suitable
equipment, compaction by mechanical
means at optimum moisture content
and dressing to designed section,
complete in all respects:-iii) 85%
maximum modified AASHO dry
density lead upto one mile.

1 x 10-0/1 x(2-4/1 +3-6/1) x -1/1 = 3000 Cft


-2/1
Total = 3000 Cft
Deductions.
Sub Base 1 x 10-0/1 x 1-2/1 x -1/2 = 600 Cft
Base 1 x 10-0/1 x 1-2/1 x -1/2 = 600 Cft
Edging 2 x 10-0/1 x -1/4 x -3/4 = 38 Cft

= 1238 Cft
Net Qty 3000 (-) 1238 = 1762 Cft @ 6772.10%oCft Rs.11932.44

2 Providing and laying Sub base course


of approved quality.
1 x 10-0/1 x 1-2/1 x -1/2 = 600 Cft
TOTAL = 600 Cft @ 8869.72%Cft Rs.53218.32

3 Providing and laying road edging of 3"


(75 mm) wide 9" (225 mm) deep brick
on end, complete in all respects.

2 x 10-0/1 = 200 Rft


Total = 200 Rft @ 29.30P-Rft Rs.5860.00

4 Providing and laying Base course of


approved quality.
1 x 10-0/1 x 1-2/1 x -1/2 = 600 Cft
TOTAL = 600 Cft @ 11387.30%Cft Rs.68323.80

5 Providing and laying bituminous


priming coat, using 10lbs. kerosene oil
and 10 lbs. binder per 100 Sft.or 0.5 Kg
601-6 kerosene and 0.5 Kg binder per
square metre.

1 x 10-0/1 x 1-2/1 = 1200 Sft


TOTAL = 1200 Sft @ 890.30%Sft Rs.10683.60
6 Providing and laying bituminous tack
coat, using 10 lbs. of bitumen per 100
Sft (0.49 Kg of bitumen per sq.m.)

1 x 10-0/1 x 1-2/1 = 1200 Sft


TOTAL = 1200 Sft @ 555.10%Sft Rs.6661.20
7 Providing and laying plant premixed
bituminous carpet,including
compaction and finishing to required
camber, grade and density. (i) 3%
Bitumen 2" thick.

1 x 10-0/1 x 1-2/1 = 1200 Sft


TOTAL = 1200 Sft @ 2797.00%Sft Rs.33564.00
TOTAL Rs.190243.36

Rate per Rft = Rs.190243.36 /100 = 1902.43

Say. = 1902.00 Per Rft.