Customer case

Asian hydrogen plant


Steam Reformer Assessment/Optimization

Hydrogen plant capacity


increases 10% after optimization
In todays market, no plant can really afford to operate below design capacity.
Topsoes reformer optimization gave us the 10% more capacity we needed to
get back on track.
Section Chief at Asian hydrogen plant

Challenge Solution Outcome


An Asian hydrogen plant was having Topsoe engineers examined the Topsoes reformer assessment and
trouble achieving its full design data and decided that a reformer subsequent optimization solved the
capacity.To reach capacity, the plant optimization would be the best plants problem. The corrected burner
would have had to increase reformer course of action. While trimming matrix resulted in far less scattering
tube temperatures to above their the reformer, the team discovered of the tube wall temperatures (TWT)
design temperature, which would an erroneous ignited burner matrix. almost halving the difference
shorten the lifetime of the tubes. The Adjusting this to ensure optimal between the hottest and coldest
company asked Topsoe to look at the performance opened the door areas. This enabled the plant to
reformer and find a solution. to operation at 110% of nominal increase its margin on maximum TWT
capacity without exceeding the and, ultimately, to boost capacity
tubes design temperature. by more than 10% with potential
for further reformer performance
optimization

Get in touch today


topsoe.com/contact
Haldor Topsoe A/S, cvr 41853816 | CCM | 0032.2016/Rev.2
Asian hydrogen plant

1000 The graphs show TWTs before and after


reformer furnace improvements. The first
graph shows high and fluctuating TWTs at
990 100% load, while the second shows more
uniform TWTs at 110% load, with potential for
further reformer performance optimization
980 (pink color).

970
Temperature, C

960

950

940

Tube wall temperature before trimming


930 Linear regression
Design temperature

920
0 20 40 60 80 100 120 140
Reformer tube number
Reformer tube wall temperature before trimming, 100% load

1000

990

980

970
Temperature, C

960

950

940

Tube wall temperature after trimming


930 Linear regression
Design temperature

920
0 20 40 60 80 100 120 140
Reformer tube number
Reformer tube wall temperature after trimming, 110% load