Method Statement -Honeycomb Concrete Repair

1.0 OBJECTIVE

Outline the Method statement for Concrete Repair - Honey Comb for structural element.

2.0 SCOPE OF WORK

This method statement shall be used for structural repair for structural elements.

3.0 RESPONSIBILITY

Site Supervisor, Project Engineer,

4.0 MATERIALS

Sika MonoTop R

5.0 HANDLING AND STORAGE OF MATERIALS

Handling - Transport of materials shall be carried out by lorry or other suitable machinery.

Storage Covered and raised above floor level.

6.0 PLANT, MACHINERY AND EQUIPMENT

Mixer machine, wheelbarrows, wire brush, measuring tapes, and other handy tools.

7.0 WORK METHODOLOGY

i. Based on structural layout, mark on existing structure such as concrete honeycomb.


ii. Cut around demarcated honeycomb area to eliminate feather edge.
iii. Surface Preparation - Repair area shall be clean, sound and free from all loosely
adhering particles.
iv. The cement mortar Sika Monotop R should be mixed in a clean drum. Mixing
follow as per product specification.
v. Application - Work wet on wet the mixed mortar well into the rectify substrate, using
a placing suitable tools, compact well. Steel trowel the final coat if required.
vi. On completion carryout joint inspection to sign on inspection checklist for concrete
repair.

8.0 SAFETY & ENVIRONMENTAL PROGRAMME

All HSSE procedure and regulations shall be complied with.


To provide proper and safe access for inspection and working.
Site personnel must be in proper safety working attire e.g. Safety boots and helmets must be
worn at all times.