TATA WAKTU

PEMBANGUNAN KANTOR ASSET 1 DI KENALI ASAM JAMBI


ID Task Task Name % Complete Duration Start Finish June 2017 July 2017 August 2017 September 2017
Mode May 28, '17 Jun 4, '17 Jun 11, '17 Jun 18, '17 Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17 Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17
WT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT
1 3% 68 days Fri 6/2/17 Tue 9/5/17
1 Pembangunan Kantor Asset 1 di Kenali Asam
2 1.1 Kantor Kenali Asam (ex GS) 6% 31 days Fri 6/2/17 Fri 7/14/17

3 1.1.1 Engineering 4% 15 days Fri 6/2/17 Thu 6/22/17


4 1.1.1.1 Survey Lapangan 100% 1 day Fri 6/2/17 Fri 6/2/17
5 1.1.1.2 Gambar Desain Arsitektural 0% 10 days Wed 6/7/17 Tue 6/20/17
6 1.1.1.2.1 Gambar Lay out Lt.1 dan Lt.2 0% 2 days Mon 6/5/17 Tue 6/6/17
7 1.1.1.2.2 Gambar Tampak & Perspektif 0% 6 days Wed 6/7/17 Wed 6/14/17
8 1.1.1.2.3 Perhitungan Struktur (Analisis struktur) 0% 6 days Wed 6/7/17 Wed 6/14/17
9 1.1.1.2.4 Gambar 3D (Animasi) 0% 6 days Thu 6/15/17 Thu 6/22/17
10 1.1.1.2.4.1 Desain Interior 0% 6 days Thu 6/15/17 Thu 6/22/17
11 1.1.1.2.4.2 Desain Exterior 0% 6 days Thu 6/15/17 Thu 6/22/17
12 1.1.2 Gambar Konstruksi 0% 16 days Fri 6/23/17 Fri 7/14/17
13 1.1.2.1 Gambar Kerja Sipil dan Struktur 0% 7 days Thu 7/6/17 Fri 7/14/17
14 1.1.2.2 Gambar Kerja Mekanikal 0% 7 days Thu 7/6/17 Fri 7/14/17
15 1.1.2.3 Gambar Kerja elektrikal 0% 7 days Thu 7/6/17 Fri 7/14/17
16 1.1.2.4 Gambar Kerja Utilitas 0% 7 days Thu 7/6/17 Fri 7/14/17
17 1.1.2.5 Desain Landscape 0% 14 days Fri 6/23/17 Wed 7/12/17
18 1.1.2.5.1 Desain Hardscape 0% 7 days Fri 6/23/17 Mon 7/3/17
19 1.1.2.5.2 Desain Softscape 0% 7 days Tue 7/4/17 Wed 7/12/17
20 1.1.3 Pembuatan Dokumen Lelang 27% 6 days Thu 6/15/17 Thu 6/22/17
21 1.1.3.1 RKS 75% 5 days Thu 6/15/17 Wed 6/21/17
22 1.1.3.2 BoQ/MTO 0% 3 days Thu 6/15/17 Mon 6/19/17
23 1.1.3.3 OE/RAB 0% 3 days Tue 6/20/17 Thu 6/22/17
DOKUMEN LELANG DARI
24 1.1.3.4 PR 0% 3 days Tue 6/20/17 Thu 6/22/17 SF KE SCM

25 1.2 Proses Lelang 0% 53 days Fri 6/23/17 Tue 9/5/17

26 1.2.1 Pengumuman Lelang 0% 5 days Fri 6/23/17 Thu 6/29/17


27 1.2.2 PQ 0% 6 days Fri 6/30/17 Fri 7/7/17
28 1.2.3 Aanwidzing 0% 5 days Mon 7/10/17Fri 7/14/17
29 1.2.4 Sampul 1 0% 10 days Mon 7/17/17Fri 7/28/17
30 1.2.5 Evaluasi Teknis 0% 10 days Mon 7/31/17Fri 8/11/17
31 1.2.6 Routing Pejabat berwenang 0% 3 days Mon 8/14/17Wed 8/16/17
32 1.2.7 Sampul 2 0% 2 days Thu 8/17/17 Fri 8/18/17
33 1.2.8 Negosiasi 0% 3 days Mon 8/21/17Wed 8/23/17
34 1.2.9 Penetapan Pemenang 0% 3 days Thu 8/24/17 Mon 8/28/17
35 1.2.10 Pengumuman Pemenang 0% 2 days Tue 8/29/17 Wed 8/30/17
36 1.2.11 Penunjukan Pemenang 0% 2 days Thu 8/31/17 Fri 9/1/17
37 1.2.12 Memo E-Corr SP3MP 0% 1 day Mon 9/4/17 Mon 9/4/17
38 1.2.13 SP3MP/Kontrak 0% 1 day Tue 9/5/17 Tue 9/5/17

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Project: KANTOR KENALI ASAM &
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Fri 6/9/17
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 1
TATA WAKTU
PEMBANGUNAN KANTOR ASSET 1 DI KENALI ASAM JAMBI
ID Task Task Name % Complete Duration Start Finish June 2017 July 2017 August 2017 September 2017
Mode May 28, '17 Jun 4, '17 Jun 11, '17 Jun 18, '17 Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17 Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17
WT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT
1 3% 68 days Fri 6/2/17 Tue 9/5/17
1 Pembangunan Kantor Asset 1 di Kenali Asam
2 1.1 Kantor Kenali Asam (ex GS) 6% 31 days Fri 6/2/17 Fri 7/14/17

3 1.1.1 Engineering 4% 15 days Fri 6/2/17 Thu 6/22/17


4 1.1.1.1 Survey Lapangan 100% 1 day Fri 6/2/17 Fri 6/2/17
5 1.1.1.2 Gambar Desain Arsitektural 0% 10 days Wed 6/7/17 Tue 6/20/17
6 1.1.1.2.1 Gambar Lay out Lt.1 dan Lt.2 0% 2 days Mon 6/5/17 Tue 6/6/17
7 1.1.1.2.2 Gambar Tampak & Perspektif 0% 6 days Wed 6/7/17 Wed 6/14/17
8 1.1.1.2.3 Perhitungan Struktur (Analisis struktur) 0% 6 days Wed 6/7/17 Wed 6/14/17
9 1.1.1.2.4 Gambar 3D (Animasi) 0% 6 days Thu 6/15/17 Thu 6/22/17
10 1.1.1.2.4.1 Desain Interior 0% 6 days Thu 6/15/17 Thu 6/22/17
11 1.1.1.2.4.2 Desain Exterior 0% 6 days Thu 6/15/17 Thu 6/22/17
12 1.1.2 Gambar Konstruksi 0% 16 days Fri 6/23/17 Fri 7/14/17
13 1.1.2.1 Gambar Kerja Sipil dan Struktur 0% 7 days Thu 7/6/17 Fri 7/14/17
14 1.1.2.2 Gambar Kerja Mekanikal 0% 7 days Thu 7/6/17 Fri 7/14/17
15 1.1.2.3 Gambar Kerja elektrikal 0% 7 days Thu 7/6/17 Fri 7/14/17
16 1.1.2.4 Gambar Kerja Utilitas 0% 7 days Thu 7/6/17 Fri 7/14/17
17 1.1.2.5 Desain Landscape 0% 14 days Fri 6/23/17 Wed 7/12/17
18 1.1.2.5.1 Desain Hardscape 0% 7 days Fri 6/23/17 Mon 7/3/17
19 1.1.2.5.2 Desain Softscape 0% 7 days Tue 7/4/17 Wed 7/12/17
20 1.1.3 Pembuatan Dokumen Lelang 27% 6 days Thu 6/15/17 Thu 6/22/17
21 1.1.3.1 RKS 75% 5 days Thu 6/15/17 Wed 6/21/17
22 1.1.3.2 BoQ/MTO 0% 3 days Thu 6/15/17 Mon 6/19/17
23 1.1.3.3 OE/RAB 0% 3 days Tue 6/20/17 Thu 6/22/17
DOKUMEN LELANG DARI
24 1.1.3.4 PR 0% 3 days Tue 6/20/17 Thu 6/22/17 SF KE SCM

25 1.2 Proses Lelang 0% 53 days Fri 6/23/17 Tue 9/5/17

26 1.2.1 Pengumuman Lelang 0% 5 days Fri 6/23/17 Thu 6/29/17


27 1.2.2 PQ 0% 6 days Fri 6/30/17 Fri 7/7/17
28 1.2.3 Aanwidzing 0% 5 days Mon 7/10/17Fri 7/14/17
29 1.2.4 Sampul 1 0% 10 days Mon 7/17/17Fri 7/28/17
30 1.2.5 Evaluasi Teknis 0% 10 days Mon 7/31/17Fri 8/11/17
31 1.2.6 Routing Pejabat berwenang 0% 3 days Mon 8/14/17Wed 8/16/17
32 1.2.7 Sampul 2 0% 2 days Thu 8/17/17 Fri 8/18/17
33 1.2.8 Negosiasi 0% 3 days Mon 8/21/17Wed 8/23/17
34 1.2.9 Penetapan Pemenang 0% 3 days Thu 8/24/17 Mon 8/28/17
35 1.2.10 Pengumuman Pemenang 0% 2 days Tue 8/29/17 Wed 8/30/17
36 1.2.11 Penunjukan Pemenang 0% 2 days Thu 8/31/17 Fri 9/1/17
37 1.2.12 Memo E-Corr SP3MP 0% 1 day Mon 9/4/17 Mon 9/4/17
38 1.2.13 SP3MP/Kontrak 0% 1 day Tue 9/5/17 Tue 9/5/17

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Project: KANTOR KENALI ASAM &
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Fri 6/9/17
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 1
TATA WAKTU
PEMBANGUNAN KANTOR ASSET 1 DI KENALI ASAM JAMBI
ID Task Task Name % Complete Duration Start Finish June 2017 July 2017 August 2017 September 2017
Mode May 28, '17 Jun 4, '17 Jun 11, '17 Jun 18, '17 Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17 Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17
WT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT
1 3% 68 days Fri 6/2/17 Tue 9/5/17
1 Pembangunan Kantor Asset 1 di Kenali Asam
2 1.1 Kantor Kenali Asam (ex GS) 6% 31 days Fri 6/2/17 Fri 7/14/17

3 1.1.1 Engineering 4% 15 days Fri 6/2/17 Thu 6/22/17


4 1.1.1.1 Survey Lapangan 100% 1 day Fri 6/2/17 Fri 6/2/17
5 1.1.1.2 Gambar Desain Arsitektural 0% 10 days Wed 6/7/17 Tue 6/20/17
6 1.1.1.2.1 Gambar Lay out Lt.1 dan Lt.2 0% 2 days Mon 6/5/17 Tue 6/6/17
7 1.1.1.2.2 Gambar Tampak & Perspektif 0% 6 days Wed 6/7/17 Wed 6/14/17
8 1.1.1.2.3 Perhitungan Struktur (Analisis struktur) 0% 6 days Wed 6/7/17 Wed 6/14/17
9 1.1.1.2.4 Gambar 3D (Animasi) 0% 6 days Thu 6/15/17 Thu 6/22/17
10 1.1.1.2.4.1 Desain Interior 0% 6 days Thu 6/15/17 Thu 6/22/17
11 1.1.1.2.4.2 Desain Exterior 0% 6 days Thu 6/15/17 Thu 6/22/17
12 1.1.2 Gambar Konstruksi 0% 16 days Fri 6/23/17 Fri 7/14/17
13 1.1.2.1 Gambar Kerja Sipil dan Struktur 0% 7 days Thu 7/6/17 Fri 7/14/17
14 1.1.2.2 Gambar Kerja Mekanikal 0% 7 days Thu 7/6/17 Fri 7/14/17
15 1.1.2.3 Gambar Kerja elektrikal 0% 7 days Thu 7/6/17 Fri 7/14/17
16 1.1.2.4 Gambar Kerja Utilitas 0% 7 days Thu 7/6/17 Fri 7/14/17
17 1.1.2.5 Desain Landscape 0% 14 days Fri 6/23/17 Wed 7/12/17
18 1.1.2.5.1 Desain Hardscape 0% 7 days Fri 6/23/17 Mon 7/3/17
19 1.1.2.5.2 Desain Softscape 0% 7 days Tue 7/4/17 Wed 7/12/17
20 1.1.3 Pembuatan Dokumen Lelang 27% 6 days Thu 6/15/17 Thu 6/22/17
21 1.1.3.1 RKS 75% 5 days Thu 6/15/17 Wed 6/21/17
22 1.1.3.2 BoQ/MTO 0% 3 days Thu 6/15/17 Mon 6/19/17
23 1.1.3.3 OE/RAB 0% 3 days Tue 6/20/17 Thu 6/22/17
DOKUMEN LELANG DARI
24 1.1.3.4 PR 0% 3 days Tue 6/20/17 Thu 6/22/17 SF KE SCM

25 1.2 Proses Lelang 0% 53 days Fri 6/23/17 Tue 9/5/17

26 1.2.1 Pengumuman Lelang 0% 5 days Fri 6/23/17 Thu 6/29/17


27 1.2.2 PQ 0% 6 days Fri 6/30/17 Fri 7/7/17
28 1.2.3 Aanwidzing 0% 5 days Mon 7/10/17Fri 7/14/17
29 1.2.4 Sampul 1 0% 10 days Mon 7/17/17Fri 7/28/17
30 1.2.5 Evaluasi Teknis 0% 10 days Mon 7/31/17Fri 8/11/17
31 1.2.6 Routing Pejabat berwenang 0% 3 days Mon 8/14/17Wed 8/16/17
32 1.2.7 Sampul 2 0% 2 days Thu 8/17/17 Fri 8/18/17
33 1.2.8 Negosiasi 0% 3 days Mon 8/21/17Wed 8/23/17
34 1.2.9 Penetapan Pemenang 0% 3 days Thu 8/24/17 Mon 8/28/17
35 1.2.10 Pengumuman Pemenang 0% 2 days Tue 8/29/17 Wed 8/30/17
36 1.2.11 Penunjukan Pemenang 0% 2 days Thu 8/31/17 Fri 9/1/17
37 1.2.12 Memo E-Corr SP3MP 0% 1 day Mon 9/4/17 Mon 9/4/17
38 1.2.13 SP3MP/Kontrak 0% 1 day Tue 9/5/17 Tue 9/5/17

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Project: KANTOR KENALI ASAM &
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Fri 6/9/17
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 1