P lumbing Pipe, Valve & Support Installation Inspection Checklist QCIC-PL-001

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Civil
02. Surveyor
All Piping Drawings & Materials used for
02.01 installation must be in conformance with the
latest approved documents.
UG & Concealed in masonry walls, BS &
02.02
G.I pipe shall be protected against corrosion.
Pipe & Valve Anchors & trust Blocks on
02.03
bends and Tee.
Piping should be tested, 1.5 times the
02.04
systems operating pressure.
02.05 Coordinated piping alignment & level.

02.06 Check Water Hammer Arrestor.


All Ferrous surfaces to painted with Red
02.07
Oxide Paint after installation,
02.08 Valve Tagging & Pipe Identifications.

02.09 Piping Insulation, as required by design.

02.10 System Flushing & Disinfection.

02.11 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________
P lumbing Pumps & Tanks Inspection Checklist QCIC-PL-002

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Surveyor
02. PLUMBING PUMPS & TANKS:
All Piping Drawings & Materials used for
02.01 installation must be in conformance with the
latest approved documents.
UG & Concealed in masonry walls, BS &
02.02
G.I pipe shall be protected against corrosion.
Pipe & Valve Anchors & trust Blocks on
02.03
bends and Tee.
All Mechanical pipe inserts in concrete must
02.04
have puddle flanges.
Piping should be pressure tested, 1.5 times
02.05
the operating pressure.
02.06 Check Motor and Pump Alignment.
Check all piping & valves had been properly
02.07
installed completed.
All Lubrication has been done, prior to start-
02.08
up.
All Ferrous surfaces to painted with Red
02.09
Oxide Paint after installation,
02.10 Valve Tagging & Pipe Identifications.

02.11 Anti-vibration & pipe Flexible are installed.


All Electrical connections, Controls, devices
02.12
and safeties are installed & completed.
02.13 System Flushing & Disinfection.

02.14 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________
P lumbing Equipment Electric H2o Heater Installation Inspection Checklist QCIC-PL-003

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Surveyor
02. ELECTRIC WATER HEATER:
All Piping Drawings & Materials used for
02.01 installation must be in conformance with the
latest approved documents.
02.02 Isolating & Check Valves Installed.
Relief & Drain Valve Installed and
02.03
connected
02.04 Valve Tagging & Identification.

02.05 Piping Insulation as required.


Electrical connection, devices and safeties
02.06
are installed & completed.
02.07 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________
F ire Pump Installation Inspection Checklist QCIC-PL-004

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Surveyor
02. FIRE PUMP:
All Piping Drawings & Materials used for
02.01 installation must be in conformance with the
latest approved documents.
UG & Concealed in masonry walls, BS &
G.I pipe shall be protected against corrosion
02.02
either with Denso tape and/or Anti-rust paint
or approved equal.
All Mechanical pipe inserts in concrete must
02.03
have puddle (G.I or SS) flanges.
Diesel Fire Standby pump or Emergency
02.04 Power shall be provided as alternate power
to supply the Duty & Jockey pumps.
Piping should be pressure tested, 1.5 times
02.05
the operating pressure.
Valves w/ screwed ends shall have unions
02.06 installed adjacent to the valves for ease of
dismantling.
All Ferrous surfaces to painted with Red
02.07
Oxide Paint after installation,
02.08 Proper Ventilation of Pump room
Motor & Pump are properly Lubricated and
02.09
aligned.
02.10 Anti-vibration & pipe Flexible are installed.
All Electrical connections, devices and
02.10
safeties are installed & completed.
02.11 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________
F M 200 Installation Inspection Checklist QCIC-PL-005

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Surveyor
02. FM 200:
All Piping Drawings & Materials used for
02.01 installation must be in conformance with the
latest approved documents.
UG & Concealed in masonry walls, BS &
G.I pipe shall be protected against corrosion
02.02
either with Denso tape and/or Anti-rust paint
or approved equal.
All Floor & Wall openings above ceiling
02.03 must be fully sealed, to prevent leakage and
maintain system integrity.
Pipes & Fittings to be used shall be SCH. 80
02.04
in all cases
Piping should be tested w/ compressed air or
02.05 Nitrogen, 1.5 times the system operating
pressure.
All Ferrous surfaces to painted with Red
02.06
Oxide Paint after installation,
Disable all agent container release
02.07 mechanism until T&C is complete;
reconnect only after Dry Test is carried out
Test the system both with primary &
02.08
standby power.
All Electrical connections, devices, mimic
02.09
panel, safeties are installed and completed.
02.10 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________
Wet Fire Fighting System Installation Inspection Checklist QCIC-PL-006

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Surveyor
02. WET FIRE FIGHTING SYSTEM:
All Piping Drawings & Materials used for
02.01 installation must be in conformance with the
latest approved & design documents.
UG & Concealed in masonry walls, BS &
G.I pipe shall be protected against corrosion
02.02
either with Denso tape and/or Anti-rust paint
or approved equal.
ACV, FCV Tamper & Flow Switches shall
have adequate clearance for servicing and
02.03
wired connected to FACP, and must have a
Test Drain Connected to sewer mains.
All Piping Support and Sprinkler heads
02.04
Spacing must be verified and checked.
Piping should be pressure tested, 1.5 times
02.05
the system operating pressure.
Valves w/ screwed ends shall have unions
02.06 installed adjacent to the valves for ease of
dismantling.
Drain valve shall be installed at low points
02.07 of the system, for draining and connected to
drain piping
All Ferrous surfaces to painted with Red
02.08
Oxide Paint after installation,
Upon completion of all piping, and prior to
02.09 install, Sprinkler heads, Flushing shall be
carried out.
02.10 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________
H VAC Equipment Installation (Exhaust Fan) Inspection Checklist QCIC-HVAC-001

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Surveyor
02. Electrical
02.01 Check for material approval
02.02 Frame support & Anti-vibration
Air Duct Support connection; back draft
02.03
damper, gaskets
02.04 Duct sealant, flexible joint

02.05 Insulation (equipment, connection)

02.06 Belt and pulley / direct drive


Filter (location, accessibility; if it is
02.07
required on drawings)
02.08 Fire damper as per drawing approved
Duct installation as per specification and
02.09
drawing approval
02.10 Electrical (cable, switch, earthing)
Interlocking devices, connection as per
02.11
specification and drawing approval.
Emergency stop devices; if required per
02.12
specifications and drawings
02.13 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________
H VAC Equipment Installation (FCU, Split Unit) Inspection Checklist QCIC-HVAC-002

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or

In Coordination with :
01. Civil
02. Electrical

02. Surveyor
Air Duct Connection for ducted split
02.01
only
02.02 Duct flexible joint for ducted split only

02.03 Base support & anti-vibration


02.04 Piping connection for electrical
02.05 Filter drier for gas if required

02.06 Refrigerant pipe and insulation


Filter (location, accessibility) & pressure
02.07
gauge and oil gauge if required.
02.08 Drain pan and connection
Thermostat (Location, connection) in
02.09
addition also if required per specs.
Electrical connection (cable, switch,
02.10
earthing)
02.11 Electrical heater, heating coil
02.12 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________
H VAC Equipment Installation (Package Unit) Inspection Checklist QCIC-HVAC-003

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Civil
02. Surveyor
03. Electrical
Anti vibration pad as per approved
02.01
drawing
02.02 flexible Duct Support, connection
Duct sealant, flexible joint, sound
02.03
attenuator
Insulation (equipment, connection) and
02.04
cladding if required
02.05 Volume, Fire Damper connection
02.06 Filter (location, accessibility)

02.07 Drain pan and connection


02.08 Thermostat (Location, connection)
02.09 Electrical (cable, switch, earthing)

02.10 Electrical heater

02.11 Supply and return grills

02.12 Fresh air intake on roof


02.13 Sensor, Air temperature/flow, humidity
02.14 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:


____________________________________________Page 1 of 1_________________________________________________
H VAC Hydronic Piping Installation Inspection Checklist QCIC-HVAC-004

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Surveyor
02. HVAC Hydronic Piping:
All Piping Drawings & Materials used for
02.01 installation must be in conformance with the
latest approved documents.
All Piping connections to all Equipments are
02.02
properly installed and complete.
Piping system had been Pressure tested &
02.03
accepted.
All Piping valves are operational, and are set
02.04
fully open.
02.05 Strainers are clean and are easily accessible.
Drain piping is completed & drainage
02.06
system functional
All Air vents are and relief valves are
02.07
installed and functional.
02.08 System Flushing & Disinfection.

02.09 All Insulations are installed and completed.

02.10 Air is purged from the system

02.11 Temperature & Pressure Gauges Installed.

02.12 Valve Tagging & Labeling.

02.13 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________
H VAC Testing and Balancing Inspection Checklist QCIC-HVAC-005

Project Name : _____________________ Drawing No. : _______________


Code : _____________________ MSS No. : __________________
Floor : _____________________ Location : __________________
Area : _____________________ Ref. Specs : _________________

Inspected (ITL) by :_________________ Date:__________ Attachment:__________________


Sub-
QA/QC Consultant Date of
Item Description of work Contract Remarks
Engineer Inspector Inspection
or
In Coordination with :
01. Surveyor
02. HVAC Testing & Balancing:
Check permanent power, water, Drainage,
02.01
Controls, are available & functional.
Architectural Doors, Ceiling, Windows,
02.02
Floors and partitioning are completed.
Check system & installation are completed
02.03
& ready for start-up for T&C
System cleanliness, Strainers, Filters,
Bearings, Belts, Alignments, Balancing
02.04
Dampers & Valves are checked & controls
are functional.
Check terminal units Plenums, FCU, VAV,
Heaters, 2/3 way valves controls, Fire,
02.05
Smoke Dampers are functional and
accessible
Approved Design Data, As-built Drawings,
02.06
are readily available for verification.
Examine, Adjust & Record Motors, Fans,
02.07 Pump & other Equipt capacity & its
performance to meet design requirements.
Ducting, Plenum boxes, Flexible ducts are
02.08
air tight.
Check equipt. Operating safety, thermostat
response, Sensors Response, Changeover,
02.09
Speed Controls, Settings, Interlocks and
controls.
02.10 Work completed and acceptable

Consultant Remarks:

Site Engineer: Consultant Engineer: QA/QC Engineer:

Date: Date: Date:

____________________________________________Page 1 of 1_________________________________________________