Documente Academic
Documente Profesional
Documente Cultură
(Session 5)
1
Outline
2
Work Center
Defined
3
Typical Scheduling and Control
Functions
6
Example of Job Sequencing: FCFS
7
4 + 11 + 14 + 15
Mean flow time= = 11days
4
0 + 1 + 8 + 11
Average lateness= = 5days
4
8
Example of Job Sequencing: SPT
Jobs (in order Processing Due Date
Suppose
Supposeyouyouhave
havethe
thefour
four of arrival) Time (days) (days hence)
jobs
jobsto
tothe
theright
rightarrive
arrivefor
for A 4 5
processing
processingon onone
onemachine
machine B 7 10
C 3 6
D 1 4
What
Whatis
isthe
theSPT
SPTschedule?
schedule? Do
Doall
allthe
thejobs
jobsget
getdone
doneon
ontime?
time?
Answer: Shortest Operating Time Schedule
Jobs (in order Processing Due Date Flow Time
No,
No,Jobs
JobsAA
of arrival) Time (days) (days hence) (days)
and
andBBare
are
D 1 4 1 going
C 3 6 4 goingtotobe
be
late
late
A 4 5 8
B 7 10 15
9
Example of Job Sequencing: EDD
Jobs (in order Processing Due Date
Suppose
Supposeyouyouhave
havethe
thefour
four of arrival) Time (days) (days hence)
jobs
jobsto
tothe
theright
rightarrive
arrivefor
for A 4 5
processing
processingon onone
onemachine
machine B 7 10
C 3 6
D 1 4
What
Whatis isthe
theearliest
earliestdue
duedate
date
first
firstschedule?
schedule? Do
Doall
allthe
thejobs
jobsget
getdone
doneon
ontime?
time?
Answer: Earliest Due Date First
Jobs (in order Processing Due Date Flow Time No,
No,Jobs
JobsCC
of arrival) Time (days) (days hence) (days) and
andBBare
are
D 1 4 1 going
goingtotobe
be
A 4 5 5 late
late
C 3 6 8
B 7 10 15
10
Example of Job Sequencing: CRM
Jobs (in order Processing Due Date
Suppose
Supposeyouyouhave
havethe
thefour
four of arrival) Time (days) (days hence)
jobs
jobsto
tothe
theright
rightarrive
arrivefor
for A 4 5
processing
processingon onone
onemachine
machine B 7 10
C 3 6
D 1 4
What
Whatis
isthe
theCR
CRschedule?
schedule? Do
Doall
allthe
thejobs
jobsget
getdone
doneon
ontime?
time?
What
Whatis
isthe
theLCFS
LCFSschedule?
schedule? Do
Doall
allthe
thejobs
jobsget
getdone
doneon
ontime?
time?
Answer: Last-Come First-Served Schedule
Jobs (in order Processing Due Date Flow Time
of arrival) Time (days) (days hence) (days) No,
No,Jobs
JobsBB
D 1 4 1 and
andAAare
are
C 3 6 4 going
goingtotobe
be
B 7 10 11 late
late
A 4 5 15
12
Comparison of Priority Rules
FCFS 15 11 5
SOT 15 7 2
13
Job Sequencing: Johnsons Rule
Suppose
Supposeyou
youhave
havethe
thefollowing
followingfive
fivejobs
jobswith
withtime
time
requirements
requirementsin
intwo
twostages
stagesof
ofproduction.
production. What
Whatis isthe
the
job
jobsequence
sequenceusing
usingJohnsons
JohnsonsRule?
Rule?
Time in Hours
Jobs Stage 1 Stage 2
A 1.50 1.25
B 2.00 3.00
C 2.50 2.00
D 1.00 2.00
14
Job Sequencing: Johnsons Rule
First, select the job with the
Time in Hours
smallest time in either stage.
Jobs Stage 1 Stage 2
That is Job D with the smallest A 1.50 1.25
time in the first stage. Place that B 2.00 3.00
job as early as possible in the C 2.50 2.00
unfilled job sequence below. D 1.00 2.00
Drop D out, select the next smallest time (Job A), and place it 4th in the job
sequence.
Drop A out, select the next smallest time. There is a tie in two stages for
two different jobs. In this case, place the job with the smallest time in the
first stage as early as possible in the unfilled job sequence.
Then place the job with the smallest time in the second stage as late as
possible in the unfilled sequence.
Job Sequence 1 2 3 4
Job Assigned D B C A 15
Shop-Floor Control:Major Functions
16
4. Providing actual output data for capacity
control purposes
Work
Input Output
Center
18
Principles of Work Center
Scheduling
1. There is a direct equivalence between work
flow and cash flow
2. The effectiveness of any job shop should be
measured by speed of flow through the shop
3. Schedule jobs as a string, with process steps
back-to-back
4. A job once started should not be interrupted
19
5. Speed of flow is most efficiently achieved by
focusing on bottleneck work centers and jobs
21
Personnel Scheduling in Services
22
Capacity and Scheduling
Finite loading (Here, the jobs are assigned by comparing the required hours for
each operation with the available hours in each work center for the period
specified by the schedule)
Forward scheduling (It starts the schedule as soon as the job requirement are
known. It is usually designed to produce a schedule that can be accomplished even
if it means not meeting the due date. In many cases forward scheduling causes a
buildup WIP inventory)