Sunteți pe pagina 1din 24

C arhu a qu ero H y d r o e l e c t ri c Proje c t Proc. Instn Civ.

Engrs Wat., Marit.


&Energy, 1994,
Ing F. Rossinelli, Eudng G. P. &has, BScEng, PhD, FICE, and 106, Mar., l-24
D. G. Wardle, BScEng, ACGI, DipHE (Delft), MICE Energy Board
Paper 10143

I This Paper describes the project organiz- Background Ordinary Meeting


ation, technical definition studies, detailed 2. Peru (Fig. 1) is divided into three regions : 5.30 p.m., Tuesday,
design, construction and commissioning the more populated, arid, Pacific coastal strip 10 May 1994
of the Carhuaquero Hydroelectric Project. intersected by narrow fertile, irrigated valleys
The project was designed and built by an fed by river basins seasonally flushed with Written discussion
international consortium of companies heavy rainfall peaking in March (Table 1); the closes 24 May 1994
with international funding. It is situated generally cold, wet high Andes; and the vast,
within a zone of high seismic activity in hot and humid Amazonian rain forest extend-
the Peruvian Andes foothills at about ing into Colombia, Brazil and Bolivia.
1000 m above sea level. The Chancay River, 3. Recently, there has been a surge in
a steep mountain torrent with seasonal migration of the indigenous population from
flows that range from 5 m3/s to 1000 m3/s, the impoverished mountain regions to the
provides the power flows, up to 135 m3/s in major cities including Lima, Chiclayo and
the first (75 MW) phase. The topography is Arequipa. This has accentuated the demand for
rugged and the narrow Chancay valley new energy and infrastructure developments to
bears evidence of landslides. meet the aspirations of the migrants and to
During project definition, fundamental encourage incipient domestic industry.
alterations were made to the layout pro- 4. Electroperu was established in 1972 to
posed in the feasibility study-the basis operate and develop the public electricity
for the design and construction contracts. supply system with an installed capacity in
The dam was relocated further upstream, December 1986 of 2605 MW (Table 2). A grid
thereby substantially increasing the system at 220 kV, 60 Hz, links the centre to the F. Rossinelli,
Engineering
reservoir capacity. The headrace tunnel north of Peru (Fig. 1).
Maintenance Manager,
was changed from free surface to full flow, Operations Directorate,
with substitution of a headpond by a surge Electroperu SA
shaft, and the surface penstock was Feasibility study
replaced by a pressure shaft and tunnel. 5. The 75 MW Carhuaquero project was
The possibility of raising the ultimate identified in the 1960s within a multi-purpose
installed capacity from 75 MW to 125 MW development including Tinajones irrigation
was also identified. scheme. It is situated on the southern side of
Power flows pass through a large de- the Chancay River in the Andean foothills
sander, with an automatic flushing 82 km east of the coastal city of Chiclayo
system, to the nominally unlined headrace (population 500 000). With the oil crises of the
tunnel, which is 13 km long and 33-33 m 197Os, Electroperu embarked on a substantial
in diameter. This connects to the surge increase in hydroelectric generation. The plan
shaft, valve chamber and high pressure included the Carhuaquero project to provide
shaft and tunnel. The power station con- power for industrial development in Lam-
G. I? Sims,
tains three 25 MW, vertical axis Pelton bayeque department as well as to feed into the
Director and Chief
turbines, generating under 500 m head. grid. Electroperus investigation organization,
Civil Engineer,
Power is supplied to the national grid at INIE, prepared a feasibility study as the basis
EPD Consultants Ltd
the northern coastal city of Chiclayo for arranging the financing, design and con-
through 220 kV, 82 km long, transmission struction of the project. The feasibility work,
lines. conducted mainly as a desk study, was com-
pleted within 12 months.
6. The feasibility report envisaged a run-of-
Introduction river scheme (Fig. 2) incorporating the follow-
This paper describes the project organization, ing: a reservoir providing daily storage; an
technical definition studies and detailed design 18 m high concrete spillway dam combined
of the Carhuaquero Hydroelectric Project in with an intake and adjacent desander (Fig. 3);
Peru. From the feasibility study to completion a I3 km long free surface flow headrace tunnel
and commissioning, the project took 12 years to (Fig. 4) ending in an underground head-pond
execute, which, although undesirable, was not 8 m wide, 15 m high and 350 m long; a 1.9 m D. G. Wardle,
unusual for an underdeveloped country such as diameter surface steel pressure pipeline; and Associate Director
Peru with a variety of economic, climatic and a surface power-station containing three and Civil Engineering
physical problems. These and noteworthy 25 MW, horizontal axis Pelton turbine generator Consultant, EPD
aspects of the project are covered in the Paper. sets. Consultants Ltd
I
Contractual arrangements sultants (EPD), Skanska and ASEA (now ABB)
7. Tendering was based on the feasibility (Fig. 5). Both EPD and ASEA signed lump sum
study. Contracts for design, construction and contracts with provisions for escalation or
financing were awarded by Electroperu in May negotiated changes. Skanskas contract was on
1980 to an Anglo-Swedish consortium compris- a target cost/remeasured basis. A solidarity
ing Engineering and Power Development Con- agreement protected Electroperu from inter-

Piura

Chiclayo

75 MW
Hydra-electric
Project

I+
PACIFM: OCEAN

- Rivers
Scale of km
0 500 1000
I I ----I\
National boundaries

v v Central Northern Grid,


220 kV. 60 Hz

Fig. 1. Carhuaquero
location map
CARHUAQUERO
HYDROELECTRIC
PROJECT

Table 1. Chancay River mean monthlyflows at Carhuaquero (m3/s) (approximately 27years of monthly data)

Month Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec. Annual
Maximum 46.9 93.2 155.3 110.7 50.8 30.0 18.8 18.7 34.3 41.8 56.0 44.8
Mean 23.8 31.7 51.7 49.5 30.1 16.2 10.0 7.3 8.9 17.5 20.0 17.5 23.7
Minimum 5.3 94 18.7 14.2 10.2 5.6 5.1 4.0 3.0 3.8 4.9 5.3

consortium disputes. The contracts were in 25. Flows at Carhuaquero depend not only on
administered and the works supervised by the Chancay but also on water diverted from
Electroperu and its appointees. All documents, adjacent headwater catchments (Fig. 6), and
official discussions and meetings were in they are used for irrigation downstream. The 27
Spanish. years of monthly flow data (Table 1) include, in
8. Many subcontractors were also involved. the later years, the water diverted from the
For instance, EPD used local consultants and Chotano; the Llaucano diversion is planned for
experts in specialist fields including seis- future construction to boost irrigation flows.
mology, material analysis and hydraulic model The flow duration curve (Fig. 7) derived for the
testing. Skanska shared about 30% of its work feasibility study is based on monthly flow data
with local companies. The supply and erection (including the Chotano diversion) but, as only
of the turbines and the hydromechanical daily regulation would be available in Carhua-
equipment was provided by Kvaerner Brug of quero reservoir, EPD developed a slightly lower
Norway. Other suppliers included: curve on which to base energy calculations.
communications-Electrisk Bureau (Finland); The proposed 75 MW, three set station requires
desander flushing equipment-Bieri 19.5 m3/s maximum flow which is available for
(Switzerland); and transmission lines-Balfour 50% of the time.
Beatty Power (UK). Later, owing to Peruvian 12. A minimum daily flow of 3.9 m3/s is
credit difficulties, the supply and erection of available 95% of the time (the firm flow).
the transmission line was separated from the Flood flows (Fig. 8) were reviewed by reference
original contract and was completed by a to hourly peak flow data available from the
Peruvian-Argentine joint venture. nearby Tinajones irrigation scheme-
9. Since the tender documents had been 1000 m3/s is the 1000 year flood peak.
based on the feasibility study rather than on a 13. Sediment transport data given in the
fully developed tender stage design, the design feasibility study were based on the earlier
consultant, EPD, was required to produce, Tinajones studies for suspended load (average
within three months of the start of the contract, 600 me/l) and on theoretical calculations of
an Interim report to review the findings of the particle sizes and river discharges for bed load
feasibility study. This was followed by a (average 1150 mg/l). These figures are com-
Definitive report which, in Peruvian practice, parable with other Andean rivers.
corresponds broadly to tender design but
requires greater detail. The work required Geology
further site investigations and consideration of 14. The feasibility study geological work
alternatives, together with comprehensive comprised a desk study of earlier reports, while
designs, reports and specifications embracing more detailed information became available
civil, mechanical and electrical aspects. The
Definitive report was the means by which
Electroperu approved the project layout; it also
became the basis for construction design and Table 2. .??lectroperu installed capacity (1986)
detailing which proceeded concurrently.
Type of station Size of units Total capacity
Interim report
10. To minimize difficulties in the tight pro- >lOMW <lO MW MW %
gramme, EPD started work in April 1980,
before contract signature. Two factors helped : Number Total Number Total
most basic data were derived from the feasi- MW MW
bility study; for cost estimation purposes,
Hydroelectric 44 1900 147 39 1939 74
prices were already known from the draft con-
Thermal 80 475 503 191 666 26
tracts.
2605 100
Hydrology
11. The Chancay flows in a narrow, steep- Electrical energy generation = 700 kWh/inhabitant, Peru (cf. 5300 kWh/inhabitant,
sided valley with stream bed gradients up to 1 UK).
Dam and intake

:allendar-Hamilton

Dam, intake and


desander site
(feasibility study)

708 000 704ooo 696 000 public road 692 000

Scale of km
0 1 2 ?j 4 5
1 I I I I

A Indicates project triangulation points


Elevations in metres above mean saa level

Fig. 2. Project layout


Headrace tunnel
---_______-.-_._____

I nipe

from the results of core drilling as the project deemed prudent to classify the project within Fig. 3. Feasibility
proceeded. the most active zone in the Peruvian seismic Study: dam, intake
15. The rock in the project area, sum- risk map. Two earthquakes were defined: the and desander
marized in Table 3, is mainly Tertiary volcanic, design earthquake with an annual risk of 5% ;
consisting of a sequence of volcanic cones the maximum credible earthquake, as given in
buried by debris from later eruptions. The most Table 4.
common rock types encountered during tunnel- 19. Problems identified for later study
ling were strong coarse andesitic agglomerate included the following.
and andesite. A wide variety of agglomerates
(a) The dam and intake would be founded on
and tuffs also occur, whose composition
massive andesite on the right bank but on
includes rhyolite, dacite and trachyte. A bedded
increasing depths of alluvium towards the
series of weaker rocks occur within the typi-
left bank.
cally poorly bedded volcanics, comprising tuff,
siltstone, shale and limestone.
16. The bedrock has a gentle southerly dip.
Table 3. Major rock types
Multidirectional steeply dipping jointing and
fracturing is common. The tunnels are
Rock rype Density:
occasionally intersected by narrow shear and
kg/m3
fault zones, and by areas of brecciation and
disturbance.
17. In-situ rock stresses over the project immersion in
area have been influenced by unloading
attributable to recent rapid erosion of the
deeply incised river valleys. The region is tec-
tonically active, and the seismic data infer a Agglomerate 2520
roughly east-west orientation of major prin- Andesite 2410-2680
cipal stresses. l Limestone
Rhyolite Tuff 2460-2510
18. Following general seismic studies com-
Dacite Tuff 2560-2550
missioned from specialist consultants, it was
\
La Cartel
..^I,^., I I Tupala
VIllP A Playita Seca
valley

, 4 Puy;aJep \

Surge Elevation: m
Intake tunnel Shaft -1000
Reservoir normal /

h
maximum operating Desander
level 871-5 m Surface
A Free surface headrace tunnel ffeasibility study) - 900
r / Underground forebay pressure
pipeline
(feasibility
study)
- 800

I - 700
Valve
chamber
/I
4400 m 8700 m - 600
.-,4- Drill and blast tunnel
I-
TBM tunnel
600 m

--00 -
9
@
A - A B - B c - c D-D
Power statron
Drill and blast Drill and blast Bored tunnel Bored tunnel, Concrete lined Steel lined
runner elevatron
tunnel, tunnel, full concrete lmrng pressure shan pressure tunnel
370.9 m
concrete Invert full concrete lining where necessary
where necessary

Tunnels and shafts have rock bolts and shotcrete lining where rock conditions dictate

Fig. 4. Longitudinal profile of project


I ELECTROPERU - Supervisor

r---------------- - - - - - - - - - - - - - ____________________----
I 1
I I
I Design Consultant: Civil Contractor: Electrical and Mechanical I
I I
I EPD SKANSKA Contractor: ASEA
I (Lump sum) (Target work, remeasured) (Lump sum) I
I I
I
L -----_ I - - - _ I ---- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - _ I
I t t
Local consultants Local contractors Turbines and hydromechanical
equipment
Kvaerner Brug

I
Local contractors

- - - - Scope of solidarity agreement


Fig. 5. Contractual
a organization

Fig. 6. Catchments above Carhuaquero

5. * .z;
I---- Continental drvide Scale of km
- Isohyets: mm/year
Op
Table 4. Seismic accelerations

Topography
20. Photogrammetric plots at 1 : 10 000
scale, provided by INIE, confirmed the levels
given in the feasibility study to sufficient accu-
racy for the Interim report. More detailed
surveys were made for access roads, bridge
sites, camps, the intake and power station. The
Fig. 7. Flow-duration (b) The impounded lake might undermine the reconnaissance of the Tupala valley (Fig. 2)
curves near vertical right bank. tunnel adit access road revealed steep terrain
( c ) The headrace tunnel line passed under with cross-slopes of 40 to vertical. The tri-
deep gulleys but, owing to the rugged angulation needed to link the intake area to the
terrain, drilling was uneconomical. power station was complicated by the narrow
(d) The pressure pipeline route crossed a con- valley and steep terrain. In order to obtain suf-
siderable depth of colluvium which provid- ficiently large, well-conditioned triangles, many
ed poor foundations. of the survey points had to be sited on adjacent
Fig. 8. Typical (e) The power station was founded on collu- hillsides at almost inaccessible locations over
Chancay River floods vium. 1000 m above the river.

Turbine g e n e r a t o r s
21. Based on modern design and experience,
Kvaerner Brug offered vertical axis, five-jet
pelton turbines rather than the two-jet, double
overhung, horizontal sets indicated in the feasi-
bility study. The advantages were a higher and
flatter efficiency curve over the whole range of
Date Peak flow: m% operation (Fig. 9), a simplified manifold
7( March 1983 784 arrangement, fewer inlet valves, easier disman-
April 1977 431 tling of the turbine runner, and a slightly lower
April 1973 385 setting giving increased head and reduced
spacing between sets. The changes gave
increased output worth about LJS$270 000 per
annum and capital cost savings of about US$2.2
million.
3
E
2 5t Electricity supply system
P
LL
22. The feasibility study viewed Carhua-
quero in relation to its immediate load zone of
Chiclayo and Pacasmayo but, as the northern
and Lima systems were to be linked, EPD reass-
essed the scheme within this wider context.
During high flows, surplus output from Carhua-
quero can supply the grid, thus saving fossil
31
fuel elsewhere; during low flows, a local energy
deficit can be supplied from the grid. Typical
daily load curves are shown in Fig. 10.
23. Of the alternative transmission schemes
considered in the feasibility study, a single
. circuit 220 kV line to Chiclayo was confirmed
as the most suitable. The security of a second
circuit was rejected on grounds of cost and the
high reactive power generated. The Carhua-
I(
24 6 12 18 24 6 12 18 24 6 12 quero line is provided with single pole auto-
Time reclosing, compatible with the existing grid.
Project layout studies
91-
24. The following three feasibility study
recommendations came under particular
review.
(a) The 75 MW installed capacity appeared :
unduly conservative in relation to the B Two jets, 450 rprn; horizontal
C Two jets, 514 rpm, horizontal
flow-duration curve.
(b) The free flow headrace tunnel, capacious 85 I I I I I I 1 I I I
underground head-pond and overflow 6 a IO 12 14 16 18 20 22 24 26
Output: M W
channels did not appear to compare well
with a full flow tunnel and surge shaft
which would save water, increase energy
and give better operation, particularly for required owing to the dry period firm Fig. 9. Turbine
peak lopping. power from Carhuaquero when used for efficiency curves
( c ) The steel, surface-mounted pressure pipe- peak-lopping purposes.
lines were reviewed on the basis that a ( c ) Net present value analysis was made to
concrete-lined, pressure shaft and tunnel obtain the equalizing discount rate for Car-
might be cheaper. huaquero against thermal generation, cal-
25. Installations of three, six and nine culated over a 40 year life.
25 MW sets were studied (using 20 m3/s, 31. Heavy fuel oil costs in 1980 (Table 8)
40 m3/s and 60 m3/s discharges). This showed when adjusted to July 1979 prices, indicated
that the optimum was five or six sets for exist- that US$135/t would be appropriate, leading to
ing flows, while with the later Llaucano diver- fuel costs of about 0.046 US$/kWh. In Peru in
sion, seven or eight sets would become 1980, electricity generation costs were about
worthwhile. Budgetary constraints influenced 0.09 US$/kWh but, because of subsidy, sales
Electroperu in deciding to limit Carhuaquero were at 0.03 US$/kWh. The conservative value
Stage 1 to three sets (75 MW) and Stage 2 to of 0.04 US$kWh was adopted for study pur-
five sets (125 MW). poses and applied to the average annual energy
26. The headrace study compared the pre- available (Table 9) to obtain the fuel benefits.
viously recommended free flow tunnel with a 32. Capital costs of typical fossil fuel fired
full flow alternative. Lined invert and fully generating plant in 1980 are shown in Table 10,
lined tunnels, with the necessary surge shaft, and US$llOO/kW installed was adopted for cal-
were considered. Costs are compared in Tables culation. The firm flow of 3.9 m3/s would Fig. 10. Typical daily
5 and 6. The lined-invert, full-flow tunnel was provide about 48 MW, giving a firm power load curves, Chiclayo
recommended, with full lining where necessary. benefit of US$52.8 million. area
27. The pressure pipeline was estimated to
be slightly cheaper than the shaft and tunnel.
The potential difficulty with anchor-block foun-
dations and the greater security against earth-
quake when underground meant that further 1
study was required for the definitive design.
28. The reservoir, dam, intake, desander
and surface power-station arrangements given
in the feasibility study were accepted subject to
review for the definitive design.

Construction programme
29. The feasibilty study construction period
of 54 months was reduced to 45 months in the
contracts. The most critical items were the
access roads and bridges, and the headrace
tunnel.

Scheme economics A Feaslbllity estimates for 1990


30. An economic assessment of the 75 MW
Stage 1 scheme was carried out as follows. B Curve C plus 20 MW Increase for
20 - cement works
(a) Costs (Table 7) were derived from contract C Actual load for northern system,
prices. north of Chimbote, 1990
(b) Benefits were the fossil fuel costs saved
with Carhuaquero operating, together with
0 t
4 0
I 1
12
I
16
I
20
J
24
the capital costs of the thermal plant not Hours of the day
Table 5. Capitalized head loss savings using full flow headrace tunnel*

-free surface tunnel

* Prices at July 1979; Cost of energy 0.04 US$/kWh; Discount rate 10%; Life 40 years.
For comparative purposes only, in this table the full flow tunnel has been assumed to be lined throughout.

Table 6. Capital costs of tunnels with forebay


07 surge shaft

-full flow tunnel,


lined invert

-full flow tunnel,


fully lined

Table 7. Estimated scheme costs (VS$ million) (base date July 1979)

Item Feasibility study Stage 1 scheme

Headrace tunnel hydraulics Free surface flow Full flow


Maximum discharge 21 m3/s 19.5 m3/s*

Civil engineering works 63.7 54.3t


Electrical and mechanical 52.2 52.9
engineering works

Totals 115.9 107.2

* Slightly smaller flow needed owing to reduced head losses.


t Includes lined invert tunnel.

Table 8. Heavy fuel oil costs in 1980

Location Fuel oil cost:


uswt

USA 110-120
Panama 150-152
Peru (for international sale) 149.5
Peru (for local sale) 76
33. Allowing for the timing of costs and Table 9. Average annual energy available
benefits, discounted cash flows were prepared
that considered energy benefits alone and with Scheme Maximum Average Annual energy available
firm power benefits added (Fig. 11). The equal- discharge : discharge:
m3/s m/s Fully lined Lined invert
ising discount rates obtained, 13% and 18%
respectively, were robust and confirmed project tunnel : tunnel:
GWh GWh
economic viability.
Feasibility study 21.0 16.8 516 -
Definitive design scheme
34. With the Interim report accepted, defini- Stage I scheme 19.5 15.4* 540t 540
tive design work proceeded. The urgent topics
for study were * The slight reduction from the feasibility study scheme is attributable to the use
of daily rather than monthly mean flows for the flow-duration curve; a further
(a) items on the critical path, namely accesses reduction is attributable to the lower required flow for the same power output.
and the headrace tunnel t The increase over the feasibility study scheme is attributable to reduced head
(b) consideration of the geological site investi- loss.
gation results
( c ) revision of the intake area layout.

Access to site Table 10. Capital costs of fossil fuel fired plant
35. A main road into the mountains (Fig. 2) in 1980
existed on the right bank of the Chancay. The
river valley is steep sided and the road is Station type Unit cost of
unpaved, narrow and tortuous; furthermore, installation:
the site was on the opposite bank. To provide US$jkW
temporary access to the intake area (Fig. 12), a
Callendar-Hamilton bridge was erected on Medium speed diesels 1000-1100
abutments consisting of massive boulders. Slow speed diesels 1400-1600
Coal fired steam plant 930
36. An old, left-bank road, partially
destroyed by landslides, was reopened to the
power-house area, and a second Callendar -
Hamilton bridge was provided nearby, founded
partly on the piers of a previous bridge. A tor- (f) that the reservoir volume was small,
tuous route up the steep hillside (Fig. 17) was thereby creating a possibility of rapid silt-
located to give a 10% gradient for the 400 m ation
climb to the head of the pressure pipeline and (g) that there was a danger that the reservoir
the bottom of the 30% gradient to the top of the water would destabilize the toe of the
surge shaft. 100 m high, vertical, right-bank hillside
37. A 9 km access road to a Tupala tunnel formed of alluvial material
adit was found impractical : not only would a (h) that it would be extremely difficult to
bridge have been needed over the river, but sec- arrange the main road diversion on the
tions of the road would have required extensive right bank.
ground stabilization works and the construc-
39. About 500 m upstream of this location,
tion of short tunnels, or overhanging half- the Chancay passed through a deep 2 m wide
tunnels, excavated in rock precipices. The high
gorge in solid rock. This site had been rejected Fig. 11. Economics of
cost of this road and the time needed for its by INIE because it had been feared that solu- Stage I scheme
construction resulted in reconsideration of the
tunnelling methods.

Intake area layout


38. The feasibility study intake area layout (a) Energy and firm power benefits
80- 64 Energy value: 4 cents US/kWh
presented several difficulties, namely
z (b) Energy benefits
(a) that many major structures were close
0 Energy value: 4 cents US/kWh
together with little working space a4. - W
(b) that the dam was founded partially on rock 2
and partially on alluvium F
( c ) that it would be difficult to arrange the E
8
river diversion in the confines of the bed 2a O-
(d) that it would probably be difficult to
P I - : : - . - - : -
balance the flows between the desander
channels, owing to the curvature at the
-40
intake. 10 12 14 16 18 20
( e ) that the flood gully crossed the desander Discount rate: %
707 000

0 50 100

Fig. 12. Intake area layout


tion passages would form through a white joint graphs, surface photographs and site inspec-
infill material. Subsequent investigation proved tion. The steep river gradient and its shape
the rock to be mainly a grey, widely jointed, suggest a youthful stage of erosion, modified
fine to coarse, andesitic agglomerate with by successive down-cutting in response to
inclined bands of closely jointed, andesitic lava. regional uplifting.
The white joint infilling was either calcite or 44. The valley was blocked in recent times
zeolite. Unconfined compressive strength in by a substantial natural dam formed several
both materials was about 100 MPa. Per- kilometres downstream. The sediments depos-
meability was generally low except in some ited in the resulting lake blocked the original
shear zones. It was concluded that, with suit- river bed which ran to the left of the Andesite
able foundation treatment, this gorge would hill forming the left abutment of the dam.
provide a better dam site. Many other advan- 45. The valley slopes are being eroded by
tages accrued (Fig. 12). gullying on the higher slopes and by erosion on
the lower slopes, as evidenced by the pattern of
(a) The dam and intake, desander, tunnel truncated shoulders at river level. Upper parts
portal, access bridge and river diversion
of the slopes are steep and further small fail-
sites were all separately located, thus pro-
ures may occur. The lacustrine deposits of silt
viding better working spaces.
and clay blocking the earlier river bed have sta-
(b) The river diversion was simplified using a
bilized at a slope of about 45 where they are
diversion tunnel from upstream of the dam
protected by colluvium. Elsewhere, they stand
to the Cirato River, a downstream tributary
vertically up to 25 m high and are protected by
of the Chancay.
a sloping beach at the toe.
(4 The operating level of the reservoir would
46. The reservoir is small, and its effect on
be 20 m higher, thus increasing the head
the stability of the adjacent hillsides is not
and energy output.
expected to be severe; however, regular inspec-
(4 There was a better desander layout.
tions by qualified personnel have been recom-
(4 The box culvert could be arranged to
mended.
provide vehicle access to the headrace
tunnel for maintenance.
Dam and buried valley
(fi The flood gully could discharge over the
47. The dam (Fig. 13) is designed as an arch
box culvert.
(base width 7 m) spanning the narrow gorge. It
&I The reservoir provided 50% more live
was checked for normal, emergency and
storage and an eightfold increase in dead
extreme loads, the latter including the
storage.
maximum credible earthquake forces. It carries
@I Much of the toe of the right-bank hillside
the spillway of three 7 m wide by 9 m high
would be unaffected by reservoir water.
radial gates capable of passing 1000 m3/s at
The main road diversion could be effected
maximum flood level. At dam crest level the
by a new cutting, the old road providing gorge was widened to 31 m to accommodate the
access to the dam crest.
spillway. At lower levels, the gorge is concrete
40. The hydraulic functioning of the major lined and acts as the stilling basin with an
structures was modelled at the National outlet sill to retain a water cushion. The centre
Hydraulics Laboratory in Lima; the diversion gate discharges directly into the gorge, but
works, intake and dam were at 1 : 40 scale and flows from the two side gates are directed to
the desander at 1 : 20 scale. impinge against each other, thus providing
41. The diversion tunnel was designed for energy dissipation.
320 m3/s, a three-year flood, so the upstream 48. To avoid forming solution passageways
cofferdam was designed with a reinforced through soluble rock, the permeability in sheer
downstream slope in the expectation of over- fracture zones in the dam abutments was
topping. reduced by grouting.
49. The steep slopes rising above the dam
Reservoir area crest by about 30-50 m required terracing and
42. The unsurfaced Santa Cruz main road is rock stabilization measures.
on the right bank of the Chancay. About 2000 m 50. To the left of the present gorge and dam
upstream of the dam, the road is located at the site, a former river valley, about 20 m deeper
foot of a cliff on top of a concrete retaining wall than the present valley, has been infilled by
standing in the river bed. In view of the diffi- lacustrine deposits. This natural fill dam has
culty and cost of realigning the road, the level very flat slopes, so although seepage was
at this point was accepted as the control for the expected, it would not be to the extent that
maximum level in the reservoir. grouting was considered necessary. Also,
43. In view of the unstable nature of the natural fine sediment deposition in the
banks on both sides of the river, the geomor- reservoir over the project lifetime would further
phology of the reservoir was examined using reduce the permeability. Provision was made,
1 : 55 000 air photographs, oblique air photo- however, to add fill with reverse filter charac-
872 maximum Radial gate
flood level 7 m wide x 9 m h!gh

-. \, Original ground
\\ line
Plan Cross-section

Scale of m
0 10 20 30
L A - -
Upstream elevation

Fig. 13. Dam teristics on the downstream slope, in case than the spillway crest, and the left bank spill-
seepage should prove excessive or harmful. way gate will be left partly open whenever
there is adequate flow in the river. Annual
Intake, intake tunnel and desander flushing of the reservoir should also be possible
51. To aid in excluding sediments from the during high flow periods to reduce deposited
power flows, the intake (Fig. 14) is located close sediments. The intake location is a compromise
Fig. 14. Intake to the dam. It has an invert level 4 m higher between a solution that is the best hydrauli-

Intake gate - _
Access

Sectlon A-A

Scale of m
0 5 10
I I
tally but is expensive to construct, and a least- be foreseen, based on the feasibility layout. At
cost solution with poor hydraulics. the surge shaft end, the level could be any-
52. After it has passed the trash rack at the where below the lowest surge which could
intake-maximum velocity 0.4 m/s (0.7 m/s in occur under Stage 2 operation, provided that
Stage 2)-the power flow is accelerated to enter the gradient was not so steep as to cause diffi-
the intake tunnel and pass to the desander (Figs culties in construction or operation. This level
15 and 16) where it is decelerated to 0.2 m/s or was actually determined by the existence on the
less in the desander settlement channels. Thus, precipitous hillside of a small platform with
the majority of sediment particles of 0.2 mm adequate working space from which to con-
diameter or greater should deposit in the struct a tunnel portal.
correct location and not before. The sediment 56. The tunnel line was selected to give ade-
collected can be discharged periodically by the quate cover where it passed under the deep
opening of hydraulically activated gates set in valleys of La Cartel, Tupala and Playita Seca
the bottom of each channel. The system, manu- (Table 11). Initially, this was based on the 1 in
factured by the Bieri company, has been used 10 000 survey maps but was spot checked later
elsewhere in Peru for the heavily silt laden by trigonometric means when the project tri-
rivers of the Andes. The sand discharge chan- angulation was established.
nels, which are epoxy coated to resist erosion, 57. Although it had been normal Peruvian
discharge to the Chancay. practice to provide a full concrete lining for
53. The free surface flow intake tunnel and hydroelectric tunnels, Electroperu accepted the
the desander are, from a hydraulic point of recommendation to use a nominally unlined
view, part of the reservoir so that throughflow headrace tunnel (Fig. 4). The decision was
is determined by turbine demand without the based on three main criteria
need for regulating controls at the intake area.
The use of the deepest flow available minimizes (a) it promised a potential capital cost saving
the velocity through the desander, thus estimated at US$lO million
reducing the sediment load in the power flow, (b) the headrace tunnel construction time
and maximizes the head on the sets, thus gener- would be cut by several months
ating extra energy. ( c ) the overbreak could give important bene-
fits in reducing frictional losses.

Headrace tunnel 58. Tunnel support design was based on the


54. Since the feasibility study, fuel costs assessment of geotechnical parameters in situ,
had increased relative to construction costs; including the Q factor developed originally by
therefore, the optimum headrace tunnel dia- the Norwegian Geotechnical Institute.* The
meter increased. Also, the Tupala adit, application of this method was complicated
intended to provide two working faces, had because the designer did not have a site-based
been found to be impracticable, but the original tunnel engineer and because there was a sub-
drill and blast tunnel excavation method would stantial delay between the excavation of the
have taken too long when working from the two tunnel and the installation of the permanent
ends alone. Accordingly, Electroperu agreed to support. Consequently, the original support
the provision of a tunnel boring machine design became inappropriate. To overcome
(TBM), the first in Peru, for excavation of about this, the permanent support requirements for
two-thirds of the tunnel from the downstream the tunnel were redefined in the light of the
end. The replacement of the massive, under- following
ground head-pond by the much smaller surge
(a) the tunnel geological log
shaft was beneficial to the programme. The
TBM not only proceeded twice as fast as drill- (b) the assessment of & at frequent intervals
(c) the physical properties of the rock encoun-
and-blast methods but also gave a smoother
finish, thus minimizing friction losses in oper- tered
(d) the nature of the joint infill : i.e. expansive
ation.
55. Before tunnel construction could be or not
started, it was necessary to fix the tunnels line ( e ) the summary of construction progress
(f) the instrumentation data, including tunnel
and levels. The full flow configuration had
diameter and extensometer readings.
freed the tunnel level from absolute dependence
on the reservoir level, flow capacity, friction 59. The drill and blast tunnel has concrete
losses or head-pond level-the essential cri- invert lining to provide a suitable running
teria being that the soffit should always be surface for maintenance vehicles entering the
drowned at the intake and be below the hydrau- tunnel by way of the desander. A rock trap is
lic grade line, even under future flows. At the constructed at the downstream end of the
intake end, the dam location was still being tunnel. Man access is provided adjacent to the
investigated, so the level was set for the lowest control valve, and machines could enter the
upstream water level which could reasonably tunnel by removal of the valve itself.
0@1 0
Scale of m

do

Fig. 15. Desander: plan

Fig. 16. Desander: sections

Sand discharge
channel

Section A-A

Slide
Slide

Normal maximum Minimum water

Sand discharge
channel

Section B-B
Scale of m
0
L--!L21
Pressure waterways Table 11. Rock cover to headrace tunnel*
60. The Interim study left unresolved
whether or not to adopt a surface pressure pipe- Low cover point Static Vertical Horizontal
line or a pressure shaft and tunnel (Fig. 17). (distance from head : cover : cover :
Geological investigations (Fig. 18) revealed that upstream portal) m m m
there was a deep zone of rock weathering
around the central part of the pipeline route La Cartel (5.3 km) 61 100 300
Tupala (9.4 km) 89 60 2300
and that the lower part of the steep slope was Playita Seca (11.5 km) 105 156 300
covered with colluvial material up to 20 m deep.
Accordingly, the pipeline would present diffi- * Maximum vertical cover about 1000 m (3.4 km from the upstream portal).
cult anchor block foundation conditions and
would require expensive drainage provisions.
By contrast, the horizontal pressure tunnel
would be excavated in a massive agglomerate,
with excellent tunnelling conditions. The pres- 64. Access to the pressure shaft is by means
sure shaft would pass mostly through a varied of an inspection cage lowered by winch through
sequence of tuffs and lavas but with a zone of a hatch provided at the upper bend within the
mudstones and shales towards the top. The valve chamber (Fig. 4). Access to the pressure
shaft and tunnel could be entirely steel lined or, tunnel is through manholes in the pressure
where possible, concrete lining could be pipes within the power station.
adopted. With optimized diameters, the capital
costs and head losses of the three options were
calculated (Table 12), whereupon the partly
Power station area
steel-lined pressure shaft and tunnel were
65. No major change was made to the power
recommended. The relative novelty of the pro-
station area plan (Fig. 19) except to provide for
posed solution was unacceptable initially and
the future extension to five sets. The discharge
Electroperu ordered work to proceed on the canal joins the Chancay by way of a standard
surface pipeline. During clearance for the pipe-
USBR energy dissipator downstream of a
line route, trial pits were excavated and, at the
natural rock sill, thus lowering the set centre-
middle anchor block location, the colluvium
line and maximizing the head on the station.
was not considered a suitable foundation. An
When the river flows exceed 580 m3/s (1 in 25
independent review panel established by
year case), the Pelton buckets are drowned and
Electroperu endorsed the recommendation to
the station has to close down temporarily.
construct a partially steel-lined pressure shaft
66. The power station is founded on well-
and tunnel. compacted and dense alluvium containing boul-
61. Perhaps the most important decision in
ders up to 2 m in diameter and reaches 20 m
respect of the shaft and tunnel arrangement is
depth overlying rock. To handle seismic condi-
the extent of the steel tunnel liner. A liner is tions more easily, the power station (Fig. 19) is
needed wherever the internal water pressure
divided structurally into separate blocks where
exceeds the confining stresses in the surround.
there are significant changes in the cross-
ing rock mass. Apart from the obvious dis-
section or foundation depth.
advantage of uncontrolled loss of water, the
67. The design of the distributor (Fig. 19)
additional forces exerted on the surfaces of
was dominated by the need to allow for relative
joints could affect adversely the stability of the
underground works or the adjacent hillside. movement between the power station, on allu-
vium, and the pressure tunnel lining, in solid
The approach adopted was that of measuring
the minor in-situ principal stress, and if this rock. Finite-element analysis was used to
adjust the distributor geometry to permit
exceeded the pressure in the tunnel by an ade-
12 mm relative movement in any direction and
quate margin, no steel lining was needed.
62. No satisfactory method exists for taking
account of residual tectonic stress in the calcu-
lation of the in-situ stress, hence it was mea-
sured directly. A CSIRO hollow intrusion cell
was used in an over-coring technique. The Table 12. Pressure pipeline or pressure shaft and tunnel alternatives
measured in-situ principal stresses ranged from
23 & 7 MPa to 6 k 1.5 MPa. Alternative Comparative Head
63. Measured bearings and dips were con- cost: losses :*
sistent with the topography. The calculated US$ million m
lithostatic overburden pressure is 9 MPa, sug- 6.99 8.92
Surface pressure pipeline
gesting that the in-situ stress field is influenced Pressure shaft and tunnel-fully steel lined 13.83 6.83
by tectonic movement, perhaps associated with Pressure shaft and tunnel -partly steel lined 6.56 6.73
the active subduction nearby of the Nazca Plate
beneath the South American Plate. * At maximum discharge for three set (75 MW) station.
to calculate the forces on the power station which is a cheaper solution than would have
resulting from seismic activity. been possible for the surface pipeline route.
68. Extensive slope protection measures
were needed on the steep hillside above the Transmission line route
power station. Drainage from the area is carried 69. The power-station substation is about
in gullies on either side of the power station, 1000 m downstream on the opposite bank of the

ZV transmission Iirie/(l
Pressure
/ tunnel \ ,iv., \

Power
station
3xmv

Scale of m
0 200 400 600 600 1000
1 I I I I I

Fig. 17. Power


Station area
Surge shaft

LWZl Andesitic agglomerates/tuffs esl Calcareous mudstone and shale


Fig. 18. Pressure
cz] Rhyolitic tuft @JJ Porphyritic lavas
shaft and tunnel:
geological section

Chancay (Fig. 17), the closest level space of suf- from both the dam and the tunnels was not
ficient size. Each unit generator transformer used as aggregate because it was generally not
steps up from 10 kV to 220 kV, with an individ- sufficiently strong.
ual circuit to the substation. 73. Most reinforcement bars were obtained
70. The 82 km single circuit 220 kV trans- locally, but 25 mm diameter reinforcement had
mission line route from Carhuaquero to the Chi- to be transported over 2000 km from a steel mill
clayo substation, where it joins the grid, was near Arequipa.
selected by a reconnaissance and tacheometric 74. Specialist materials from overseas,
survey. It passes over irregular terrain until it usually procured from Europe, included con-
reaches the cultivated lands on the outskirts of crete admixtures, geotextiles and waterproofing
Chiclayo. Many of the towers were located on elements. Imported materials, including all the
high points to enable the spans to be increased, construction machinery and the permanent
the maximum span being about 880 m. Many of plant, were landed at the port of Paita, about
these high points were found to be ancient look- 280 km from the project. Explosives were
out sites of pre-Colombian civilizations. The obtained locally, and ANFO was used for the
line also had to cross an area containing many drill and blast tunnels.
large unexcavated burial mounds. The authori-
ties declared these as areas of special archae- Roads, camps, water supply and drainage
ological interest, and about 190 tower 75. As the site was in a remote area, exten-
foundations had to be carefully investigated by sive new infrastructure was required, which
archaeologists before permission was granted took about one year to develop. Several tempo-
to construct the line. rary camps and offices were constructed
catering for up to 200 staff and their families,
and about 1500 technicians and workers. The
Construction and commissioning
permanent staff are housed in Chiclayo. The
Sources of construction materials project roads, constructed of roller-compacted
71. Ordinary Portland cement was obtained fill with gravel surfacing, required a pro-
locally from Pacasmayo, 180 km from the gramme of continuous maintenance to regrade
project. Sulphate resisting cement, for use in the running surface, reduce dust and repair
the underground works, and natural pozzolana occasional flood damage. Where required,
(volcanic ash), for use in pressure grouting, gravity retaining walls, incorporating Cyclo-
came from works near Lima (840 km away). pean concrete in accordance with a local design,
72. The river Chancay provided a readily were used.
available source of boulders and river sand for 76. Water for both potable and construction
concrete aggregates. The rock spoil excavated use was abstracted from the Chancay and
treated by a plant of modular design, using pumped about 5 km to the camps, using galva-
back-flushing filters. During the wet season, nized steel pipes placed directly on the ground
when sediment concentrations were very high, which avoided the cost of excavating trenches
filter wells near the river were also used in the hard ground.
together with a large settling lagoon to help 77. Storm water, collected around struc-
remove the sediment. The treated water was tures, project facilities and along roads, dis-

0
,....5O
Scale of m Section A-A

\\ : : ;

0 50 100
11 11 11 1 I
Scale of m

Plan

Fig. 19. Power


station
charged to gullies by way of open stone-pitched 150 mm. Compared with the drill and blast
channels connected to buried corrugated steel drive, the TBM caused virtually no damage to
pipes at road crossings. Concrete fords were the rock, as strikingly demonstrated at the
used where streams and gullies intersected the breakthrough point (Fig. 21).
roads. It was recognized that these drainage
facilities would require regular maintenance.
Sewage was treated by aeration and settlement El NiGo
before discharge to the Chancay. 82. In the early months of 1983, the nor-
78. There were no telephone lines to the mally dry coast of northern Peru suffered
project site so a radio link was used between several weeks of torrential rainfall. This was
the site and Chiclayo. associated with an unusually deep penetration
of the warm Pacific ocean current, El Nifio, into
Tunnel boring machine the normally cold waters on the western sea-
79. A 3.8 m diameter Atlas Copco Jarva board. An analysis of historical rainfall data
TBM was selected. The machine was about suggested a 50 year return period for this
150 m long and was assembled at the headrace event. Areas of northern Peru were devastated
tunnel downstream portal area (Fig. 20). by the heavy rainfall. Project installations
80. The generally dry and hard rock condi- under construction were damaged, including
tions did not require either a protective hood or the powerhouse which was partly buried under
facilities for bolting or shotcreting close to the a mud slide. Roads were destroyed and the
face, and there was no requirement for advance camps were cut off for several weeks. The
probing and grouting. The machines single upstream cofferdam was overtopped but the
disk cutters were designed to drive in rock with dam was sufficiently advanced not to suffer
an unconfined compressive strength of about major damage. A smaller cofferdam was con-
30-300 MPa. The cutters applied a load of structed later to complete the dam. Based on
about 100 kN. Tunnel spoil ranged in size these experiences, drainage and slope protec-
between 0.1 mm and 50 mm. The TBM drove tion measures were considerably strengthened.
8 km of tunnel at an average advance rate
of 94 m/week; this compared with the 5 km Delays during construction
driven by drill and blast at an average rate of 83. The preliminary construction works
41 m/week. The TBM recorded maximum began in 1980, and by the end of 1981, most of
penetration rates of 718 m/month and 65 m in the project infrastructure was in place. Excava-
one 24 hour day. tions for the permanent excavations also began
81. The TBM met the drill and blast tunnel in 1981; the headrace tunnel drives were started
at chainage 4.4 km (Fig. 4) with an accuracy of in February (upstream) and April (downstream)

Fig. 20. Tunnel


boring machine
Fig. 21. Junction of
TBM tunnel with drill
and blast tunnel

1981. Construction activity peaked during 1982 short sections of extra rockbolting and shot-
when up to 1000 workers were employed at site. Crete and the treatment of a few isolated clay
84. Unfortunately, the works had to be filled joints. The concrete linings in the pres-
halted in early 1983 as a result of a shortage of sure tunnel and shaft were found to be in good
funds to cover the extra construction costs condition. The tunnels and shafts were then
arising from necessary layout changes and the refilled to permit the electromechanical plant to
devastation caused by the El Nifio floods, The be commissioned.
works remained effectively paralysed until 86. The filled reservoir was satisfactory
1986, although some sporadic construction apart from the need to relocate short sections of
work and general maintenance were effected the public road away from the reservoir sides
during this period, including completion of the where some sloughing was observed. The spill-
remaining 1.4 km of headrace tunnel. Full pro- way gates were opened to simulate an extreme
duction did not recommence until late 1987. flood condition and the stilling basin was found
The project was completed by the end of 1988, to work efficiently, as predicted by the hydrau-
apart from some finishing works and the trans- lic model tests. The observed seepage through
mission line which were completed in 1990. The the infilled, buried valley to the left of the
effective construction period was about five dam was within the predicted limits, with the
years during a total contract period of just over flows and piezometric levels stabilizing as
10 years. expected.

Commissioning Dewatering and inspection after one years


85. Commissioning of the works in 1990 operation
was supervised directly by Electroperu and 87. The scheme was dewatered for inspec-
started with an experimental filling of the tion in August 1991, after one years operation,
reservoir (Fig. 22), tunnels and shafts. As a chiefly because of the design of the nominally
safety precaution, the tunnels and shafts were unlined headrace tunnel. Emptying the tunnels
filled over a two-week period. Initially, the total and shafts took four days, and first access to
leakage from the tunnels was about 100 l/s, but the upstream end of the headrace tunnel was
this reduced to about half within a month. available on the second day.
Small seepage into the head of the drainage 88. In general, all structures and plant were
tunnel soon dried up. The tunnels and shafts in very good working condition and no major
were then dewatered equally slowly and structural instability was observed. The effect
inspected in detail. Minor remedial works were of sand erosion on the runner buckets and spear
required in the headrace tunnel, comprising nozzles could be seen but was slight, and repair
Fig. 22. Carhuaquero
dam and intake from
the reservoir

Fig. 23. Desander,


looking downstream
is likely to be less frequent than previously Acknowledgements
anticipated. The desander (Fig. 23) is fulfilling 90. The Authors thank both Electroperu for
its function and, in comparison with other permission to publish this Paper, and Mr P. G.
schemes in Peru, the Carhuaquero experience is Davies, formerly EPD liaison engineer on site,
considered encouraging. for the preparation of valuable background
89. For minor scaling of rock or shotcrete material.
linings in the headrace tunnel, the rock trap
(Fig. 4) had proved entirely adequate. However, References
1. PRICE JONES A. and SIMS G. P. Measurement of in
a small rockfall, about 30 m3, did take place, situ stresses for a hydroelectric scheme in Peru.
seemingly as a result of the dewatering itself. ISRM Symp. on Design and Performance of
The whole tunnel has now withstood as severe Underground Excavations, Cambridge, 3-6 Sept.
a test as it is ever likely to get, with the result 1984. British Geotechnical Society, London, 1984.
that after repairs have been effected, no further 2. B A R T O N N., L I E N R. and L U N D E J. Engineering clas-
dewatering should be needed for at least five sification of rock masses for the design of tunnel
years. support. Rock mechanics, 1974,6, No. 4,189-236.

S-ar putea să vă placă și