Documente Academic
Documente Profesional
Documente Cultură
Piura
Chiclayo
75 MW
Hydra-electric
Project
I+
PACIFM: OCEAN
- Rivers
Scale of km
0 500 1000
I I ----I\
National boundaries
Fig. 1. Carhuaquero
location map
CARHUAQUERO
HYDROELECTRIC
PROJECT
Table 1. Chancay River mean monthlyflows at Carhuaquero (m3/s) (approximately 27years of monthly data)
Month Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec. Annual
Maximum 46.9 93.2 155.3 110.7 50.8 30.0 18.8 18.7 34.3 41.8 56.0 44.8
Mean 23.8 31.7 51.7 49.5 30.1 16.2 10.0 7.3 8.9 17.5 20.0 17.5 23.7
Minimum 5.3 94 18.7 14.2 10.2 5.6 5.1 4.0 3.0 3.8 4.9 5.3
consortium disputes. The contracts were in 25. Flows at Carhuaquero depend not only on
administered and the works supervised by the Chancay but also on water diverted from
Electroperu and its appointees. All documents, adjacent headwater catchments (Fig. 6), and
official discussions and meetings were in they are used for irrigation downstream. The 27
Spanish. years of monthly flow data (Table 1) include, in
8. Many subcontractors were also involved. the later years, the water diverted from the
For instance, EPD used local consultants and Chotano; the Llaucano diversion is planned for
experts in specialist fields including seis- future construction to boost irrigation flows.
mology, material analysis and hydraulic model The flow duration curve (Fig. 7) derived for the
testing. Skanska shared about 30% of its work feasibility study is based on monthly flow data
with local companies. The supply and erection (including the Chotano diversion) but, as only
of the turbines and the hydromechanical daily regulation would be available in Carhua-
equipment was provided by Kvaerner Brug of quero reservoir, EPD developed a slightly lower
Norway. Other suppliers included: curve on which to base energy calculations.
communications-Electrisk Bureau (Finland); The proposed 75 MW, three set station requires
desander flushing equipment-Bieri 19.5 m3/s maximum flow which is available for
(Switzerland); and transmission lines-Balfour 50% of the time.
Beatty Power (UK). Later, owing to Peruvian 12. A minimum daily flow of 3.9 m3/s is
credit difficulties, the supply and erection of available 95% of the time (the firm flow).
the transmission line was separated from the Flood flows (Fig. 8) were reviewed by reference
original contract and was completed by a to hourly peak flow data available from the
Peruvian-Argentine joint venture. nearby Tinajones irrigation scheme-
9. Since the tender documents had been 1000 m3/s is the 1000 year flood peak.
based on the feasibility study rather than on a 13. Sediment transport data given in the
fully developed tender stage design, the design feasibility study were based on the earlier
consultant, EPD, was required to produce, Tinajones studies for suspended load (average
within three months of the start of the contract, 600 me/l) and on theoretical calculations of
an Interim report to review the findings of the particle sizes and river discharges for bed load
feasibility study. This was followed by a (average 1150 mg/l). These figures are com-
Definitive report which, in Peruvian practice, parable with other Andean rivers.
corresponds broadly to tender design but
requires greater detail. The work required Geology
further site investigations and consideration of 14. The feasibility study geological work
alternatives, together with comprehensive comprised a desk study of earlier reports, while
designs, reports and specifications embracing more detailed information became available
civil, mechanical and electrical aspects. The
Definitive report was the means by which
Electroperu approved the project layout; it also
became the basis for construction design and Table 2. .??lectroperu installed capacity (1986)
detailing which proceeded concurrently.
Type of station Size of units Total capacity
Interim report
10. To minimize difficulties in the tight pro- >lOMW <lO MW MW %
gramme, EPD started work in April 1980,
before contract signature. Two factors helped : Number Total Number Total
most basic data were derived from the feasi- MW MW
bility study; for cost estimation purposes,
Hydroelectric 44 1900 147 39 1939 74
prices were already known from the draft con-
Thermal 80 475 503 191 666 26
tracts.
2605 100
Hydrology
11. The Chancay flows in a narrow, steep- Electrical energy generation = 700 kWh/inhabitant, Peru (cf. 5300 kWh/inhabitant,
sided valley with stream bed gradients up to 1 UK).
Dam and intake
:allendar-Hamilton
Scale of km
0 1 2 ?j 4 5
1 I I I I
I nipe
from the results of core drilling as the project deemed prudent to classify the project within Fig. 3. Feasibility
proceeded. the most active zone in the Peruvian seismic Study: dam, intake
15. The rock in the project area, sum- risk map. Two earthquakes were defined: the and desander
marized in Table 3, is mainly Tertiary volcanic, design earthquake with an annual risk of 5% ;
consisting of a sequence of volcanic cones the maximum credible earthquake, as given in
buried by debris from later eruptions. The most Table 4.
common rock types encountered during tunnel- 19. Problems identified for later study
ling were strong coarse andesitic agglomerate included the following.
and andesite. A wide variety of agglomerates
(a) The dam and intake would be founded on
and tuffs also occur, whose composition
massive andesite on the right bank but on
includes rhyolite, dacite and trachyte. A bedded
increasing depths of alluvium towards the
series of weaker rocks occur within the typi-
left bank.
cally poorly bedded volcanics, comprising tuff,
siltstone, shale and limestone.
16. The bedrock has a gentle southerly dip.
Table 3. Major rock types
Multidirectional steeply dipping jointing and
fracturing is common. The tunnels are
Rock rype Density:
occasionally intersected by narrow shear and
kg/m3
fault zones, and by areas of brecciation and
disturbance.
17. In-situ rock stresses over the project immersion in
area have been influenced by unloading
attributable to recent rapid erosion of the
deeply incised river valleys. The region is tec-
tonically active, and the seismic data infer a Agglomerate 2520
roughly east-west orientation of major prin- Andesite 2410-2680
cipal stresses. l Limestone
Rhyolite Tuff 2460-2510
18. Following general seismic studies com-
Dacite Tuff 2560-2550
missioned from specialist consultants, it was
\
La Cartel
..^I,^., I I Tupala
VIllP A Playita Seca
valley
, 4 Puy;aJep \
Surge Elevation: m
Intake tunnel Shaft -1000
Reservoir normal /
h
maximum operating Desander
level 871-5 m Surface
A Free surface headrace tunnel ffeasibility study) - 900
r / Underground forebay pressure
pipeline
(feasibility
study)
- 800
I - 700
Valve
chamber
/I
4400 m 8700 m - 600
.-,4- Drill and blast tunnel
I-
TBM tunnel
600 m
--00 -
9
@
A - A B - B c - c D-D
Power statron
Drill and blast Drill and blast Bored tunnel Bored tunnel, Concrete lined Steel lined
runner elevatron
tunnel, tunnel, full concrete lmrng pressure shan pressure tunnel
370.9 m
concrete Invert full concrete lining where necessary
where necessary
Tunnels and shafts have rock bolts and shotcrete lining where rock conditions dictate
r---------------- - - - - - - - - - - - - - ____________________----
I 1
I I
I Design Consultant: Civil Contractor: Electrical and Mechanical I
I I
I EPD SKANSKA Contractor: ASEA
I (Lump sum) (Target work, remeasured) (Lump sum) I
I I
I
L -----_ I - - - _ I ---- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - _ I
I t t
Local consultants Local contractors Turbines and hydromechanical
equipment
Kvaerner Brug
I
Local contractors
5. * .z;
I---- Continental drvide Scale of km
- Isohyets: mm/year
Op
Table 4. Seismic accelerations
Topography
20. Photogrammetric plots at 1 : 10 000
scale, provided by INIE, confirmed the levels
given in the feasibility study to sufficient accu-
racy for the Interim report. More detailed
surveys were made for access roads, bridge
sites, camps, the intake and power station. The
Fig. 7. Flow-duration (b) The impounded lake might undermine the reconnaissance of the Tupala valley (Fig. 2)
curves near vertical right bank. tunnel adit access road revealed steep terrain
( c ) The headrace tunnel line passed under with cross-slopes of 40 to vertical. The tri-
deep gulleys but, owing to the rugged angulation needed to link the intake area to the
terrain, drilling was uneconomical. power station was complicated by the narrow
(d) The pressure pipeline route crossed a con- valley and steep terrain. In order to obtain suf-
siderable depth of colluvium which provid- ficiently large, well-conditioned triangles, many
ed poor foundations. of the survey points had to be sited on adjacent
Fig. 8. Typical (e) The power station was founded on collu- hillsides at almost inaccessible locations over
Chancay River floods vium. 1000 m above the river.
Turbine g e n e r a t o r s
21. Based on modern design and experience,
Kvaerner Brug offered vertical axis, five-jet
pelton turbines rather than the two-jet, double
overhung, horizontal sets indicated in the feasi-
bility study. The advantages were a higher and
flatter efficiency curve over the whole range of
Date Peak flow: m% operation (Fig. 9), a simplified manifold
7( March 1983 784 arrangement, fewer inlet valves, easier disman-
April 1977 431 tling of the turbine runner, and a slightly lower
April 1973 385 setting giving increased head and reduced
spacing between sets. The changes gave
increased output worth about LJS$270 000 per
annum and capital cost savings of about US$2.2
million.
3
E
2 5t Electricity supply system
P
LL
22. The feasibility study viewed Carhua-
quero in relation to its immediate load zone of
Chiclayo and Pacasmayo but, as the northern
and Lima systems were to be linked, EPD reass-
essed the scheme within this wider context.
During high flows, surplus output from Carhua-
quero can supply the grid, thus saving fossil
31
fuel elsewhere; during low flows, a local energy
deficit can be supplied from the grid. Typical
daily load curves are shown in Fig. 10.
23. Of the alternative transmission schemes
considered in the feasibility study, a single
. circuit 220 kV line to Chiclayo was confirmed
as the most suitable. The security of a second
circuit was rejected on grounds of cost and the
high reactive power generated. The Carhua-
I(
24 6 12 18 24 6 12 18 24 6 12 quero line is provided with single pole auto-
Time reclosing, compatible with the existing grid.
Project layout studies
91-
24. The following three feasibility study
recommendations came under particular
review.
(a) The 75 MW installed capacity appeared :
unduly conservative in relation to the B Two jets, 450 rprn; horizontal
C Two jets, 514 rpm, horizontal
flow-duration curve.
(b) The free flow headrace tunnel, capacious 85 I I I I I I 1 I I I
underground head-pond and overflow 6 a IO 12 14 16 18 20 22 24 26
Output: M W
channels did not appear to compare well
with a full flow tunnel and surge shaft
which would save water, increase energy
and give better operation, particularly for required owing to the dry period firm Fig. 9. Turbine
peak lopping. power from Carhuaquero when used for efficiency curves
( c ) The steel, surface-mounted pressure pipe- peak-lopping purposes.
lines were reviewed on the basis that a ( c ) Net present value analysis was made to
concrete-lined, pressure shaft and tunnel obtain the equalizing discount rate for Car-
might be cheaper. huaquero against thermal generation, cal-
25. Installations of three, six and nine culated over a 40 year life.
25 MW sets were studied (using 20 m3/s, 31. Heavy fuel oil costs in 1980 (Table 8)
40 m3/s and 60 m3/s discharges). This showed when adjusted to July 1979 prices, indicated
that the optimum was five or six sets for exist- that US$135/t would be appropriate, leading to
ing flows, while with the later Llaucano diver- fuel costs of about 0.046 US$/kWh. In Peru in
sion, seven or eight sets would become 1980, electricity generation costs were about
worthwhile. Budgetary constraints influenced 0.09 US$/kWh but, because of subsidy, sales
Electroperu in deciding to limit Carhuaquero were at 0.03 US$/kWh. The conservative value
Stage 1 to three sets (75 MW) and Stage 2 to of 0.04 US$kWh was adopted for study pur-
five sets (125 MW). poses and applied to the average annual energy
26. The headrace study compared the pre- available (Table 9) to obtain the fuel benefits.
viously recommended free flow tunnel with a 32. Capital costs of typical fossil fuel fired
full flow alternative. Lined invert and fully generating plant in 1980 are shown in Table 10,
lined tunnels, with the necessary surge shaft, and US$llOO/kW installed was adopted for cal-
were considered. Costs are compared in Tables culation. The firm flow of 3.9 m3/s would Fig. 10. Typical daily
5 and 6. The lined-invert, full-flow tunnel was provide about 48 MW, giving a firm power load curves, Chiclayo
recommended, with full lining where necessary. benefit of US$52.8 million. area
27. The pressure pipeline was estimated to
be slightly cheaper than the shaft and tunnel.
The potential difficulty with anchor-block foun-
dations and the greater security against earth-
quake when underground meant that further 1
study was required for the definitive design.
28. The reservoir, dam, intake, desander
and surface power-station arrangements given
in the feasibility study were accepted subject to
review for the definitive design.
Construction programme
29. The feasibilty study construction period
of 54 months was reduced to 45 months in the
contracts. The most critical items were the
access roads and bridges, and the headrace
tunnel.
* Prices at July 1979; Cost of energy 0.04 US$/kWh; Discount rate 10%; Life 40 years.
For comparative purposes only, in this table the full flow tunnel has been assumed to be lined throughout.
Table 7. Estimated scheme costs (VS$ million) (base date July 1979)
USA 110-120
Panama 150-152
Peru (for international sale) 149.5
Peru (for local sale) 76
33. Allowing for the timing of costs and Table 9. Average annual energy available
benefits, discounted cash flows were prepared
that considered energy benefits alone and with Scheme Maximum Average Annual energy available
firm power benefits added (Fig. 11). The equal- discharge : discharge:
m3/s m/s Fully lined Lined invert
ising discount rates obtained, 13% and 18%
respectively, were robust and confirmed project tunnel : tunnel:
GWh GWh
economic viability.
Feasibility study 21.0 16.8 516 -
Definitive design scheme
34. With the Interim report accepted, defini- Stage I scheme 19.5 15.4* 540t 540
tive design work proceeded. The urgent topics
for study were * The slight reduction from the feasibility study scheme is attributable to the use
of daily rather than monthly mean flows for the flow-duration curve; a further
(a) items on the critical path, namely accesses reduction is attributable to the lower required flow for the same power output.
and the headrace tunnel t The increase over the feasibility study scheme is attributable to reduced head
(b) consideration of the geological site investi- loss.
gation results
( c ) revision of the intake area layout.
Access to site Table 10. Capital costs of fossil fuel fired plant
35. A main road into the mountains (Fig. 2) in 1980
existed on the right bank of the Chancay. The
river valley is steep sided and the road is Station type Unit cost of
unpaved, narrow and tortuous; furthermore, installation:
the site was on the opposite bank. To provide US$jkW
temporary access to the intake area (Fig. 12), a
Callendar-Hamilton bridge was erected on Medium speed diesels 1000-1100
abutments consisting of massive boulders. Slow speed diesels 1400-1600
Coal fired steam plant 930
36. An old, left-bank road, partially
destroyed by landslides, was reopened to the
power-house area, and a second Callendar -
Hamilton bridge was provided nearby, founded
partly on the piers of a previous bridge. A tor- (f) that the reservoir volume was small,
tuous route up the steep hillside (Fig. 17) was thereby creating a possibility of rapid silt-
located to give a 10% gradient for the 400 m ation
climb to the head of the pressure pipeline and (g) that there was a danger that the reservoir
the bottom of the 30% gradient to the top of the water would destabilize the toe of the
surge shaft. 100 m high, vertical, right-bank hillside
37. A 9 km access road to a Tupala tunnel formed of alluvial material
adit was found impractical : not only would a (h) that it would be extremely difficult to
bridge have been needed over the river, but sec- arrange the main road diversion on the
tions of the road would have required extensive right bank.
ground stabilization works and the construc-
39. About 500 m upstream of this location,
tion of short tunnels, or overhanging half- the Chancay passed through a deep 2 m wide
tunnels, excavated in rock precipices. The high
gorge in solid rock. This site had been rejected Fig. 11. Economics of
cost of this road and the time needed for its by INIE because it had been feared that solu- Stage I scheme
construction resulted in reconsideration of the
tunnelling methods.
0 50 100
-. \, Original ground
\\ line
Plan Cross-section
Scale of m
0 10 20 30
L A - -
Upstream elevation
Fig. 13. Dam teristics on the downstream slope, in case than the spillway crest, and the left bank spill-
seepage should prove excessive or harmful. way gate will be left partly open whenever
there is adequate flow in the river. Annual
Intake, intake tunnel and desander flushing of the reservoir should also be possible
51. To aid in excluding sediments from the during high flow periods to reduce deposited
power flows, the intake (Fig. 14) is located close sediments. The intake location is a compromise
Fig. 14. Intake to the dam. It has an invert level 4 m higher between a solution that is the best hydrauli-
Intake gate - _
Access
Sectlon A-A
Scale of m
0 5 10
I I
tally but is expensive to construct, and a least- be foreseen, based on the feasibility layout. At
cost solution with poor hydraulics. the surge shaft end, the level could be any-
52. After it has passed the trash rack at the where below the lowest surge which could
intake-maximum velocity 0.4 m/s (0.7 m/s in occur under Stage 2 operation, provided that
Stage 2)-the power flow is accelerated to enter the gradient was not so steep as to cause diffi-
the intake tunnel and pass to the desander (Figs culties in construction or operation. This level
15 and 16) where it is decelerated to 0.2 m/s or was actually determined by the existence on the
less in the desander settlement channels. Thus, precipitous hillside of a small platform with
the majority of sediment particles of 0.2 mm adequate working space from which to con-
diameter or greater should deposit in the struct a tunnel portal.
correct location and not before. The sediment 56. The tunnel line was selected to give ade-
collected can be discharged periodically by the quate cover where it passed under the deep
opening of hydraulically activated gates set in valleys of La Cartel, Tupala and Playita Seca
the bottom of each channel. The system, manu- (Table 11). Initially, this was based on the 1 in
factured by the Bieri company, has been used 10 000 survey maps but was spot checked later
elsewhere in Peru for the heavily silt laden by trigonometric means when the project tri-
rivers of the Andes. The sand discharge chan- angulation was established.
nels, which are epoxy coated to resist erosion, 57. Although it had been normal Peruvian
discharge to the Chancay. practice to provide a full concrete lining for
53. The free surface flow intake tunnel and hydroelectric tunnels, Electroperu accepted the
the desander are, from a hydraulic point of recommendation to use a nominally unlined
view, part of the reservoir so that throughflow headrace tunnel (Fig. 4). The decision was
is determined by turbine demand without the based on three main criteria
need for regulating controls at the intake area.
The use of the deepest flow available minimizes (a) it promised a potential capital cost saving
the velocity through the desander, thus estimated at US$lO million
reducing the sediment load in the power flow, (b) the headrace tunnel construction time
and maximizes the head on the sets, thus gener- would be cut by several months
ating extra energy. ( c ) the overbreak could give important bene-
fits in reducing frictional losses.
do
Sand discharge
channel
Section A-A
Slide
Slide
Sand discharge
channel
Section B-B
Scale of m
0
L--!L21
Pressure waterways Table 11. Rock cover to headrace tunnel*
60. The Interim study left unresolved
whether or not to adopt a surface pressure pipe- Low cover point Static Vertical Horizontal
line or a pressure shaft and tunnel (Fig. 17). (distance from head : cover : cover :
Geological investigations (Fig. 18) revealed that upstream portal) m m m
there was a deep zone of rock weathering
around the central part of the pipeline route La Cartel (5.3 km) 61 100 300
Tupala (9.4 km) 89 60 2300
and that the lower part of the steep slope was Playita Seca (11.5 km) 105 156 300
covered with colluvial material up to 20 m deep.
Accordingly, the pipeline would present diffi- * Maximum vertical cover about 1000 m (3.4 km from the upstream portal).
cult anchor block foundation conditions and
would require expensive drainage provisions.
By contrast, the horizontal pressure tunnel
would be excavated in a massive agglomerate,
with excellent tunnelling conditions. The pres- 64. Access to the pressure shaft is by means
sure shaft would pass mostly through a varied of an inspection cage lowered by winch through
sequence of tuffs and lavas but with a zone of a hatch provided at the upper bend within the
mudstones and shales towards the top. The valve chamber (Fig. 4). Access to the pressure
shaft and tunnel could be entirely steel lined or, tunnel is through manholes in the pressure
where possible, concrete lining could be pipes within the power station.
adopted. With optimized diameters, the capital
costs and head losses of the three options were
calculated (Table 12), whereupon the partly
Power station area
steel-lined pressure shaft and tunnel were
65. No major change was made to the power
recommended. The relative novelty of the pro-
station area plan (Fig. 19) except to provide for
posed solution was unacceptable initially and
the future extension to five sets. The discharge
Electroperu ordered work to proceed on the canal joins the Chancay by way of a standard
surface pipeline. During clearance for the pipe-
USBR energy dissipator downstream of a
line route, trial pits were excavated and, at the
natural rock sill, thus lowering the set centre-
middle anchor block location, the colluvium
line and maximizing the head on the station.
was not considered a suitable foundation. An
When the river flows exceed 580 m3/s (1 in 25
independent review panel established by
year case), the Pelton buckets are drowned and
Electroperu endorsed the recommendation to
the station has to close down temporarily.
construct a partially steel-lined pressure shaft
66. The power station is founded on well-
and tunnel. compacted and dense alluvium containing boul-
61. Perhaps the most important decision in
ders up to 2 m in diameter and reaches 20 m
respect of the shaft and tunnel arrangement is
depth overlying rock. To handle seismic condi-
the extent of the steel tunnel liner. A liner is tions more easily, the power station (Fig. 19) is
needed wherever the internal water pressure
divided structurally into separate blocks where
exceeds the confining stresses in the surround.
there are significant changes in the cross-
ing rock mass. Apart from the obvious dis-
section or foundation depth.
advantage of uncontrolled loss of water, the
67. The design of the distributor (Fig. 19)
additional forces exerted on the surfaces of
was dominated by the need to allow for relative
joints could affect adversely the stability of the
underground works or the adjacent hillside. movement between the power station, on allu-
vium, and the pressure tunnel lining, in solid
The approach adopted was that of measuring
the minor in-situ principal stress, and if this rock. Finite-element analysis was used to
adjust the distributor geometry to permit
exceeded the pressure in the tunnel by an ade-
12 mm relative movement in any direction and
quate margin, no steel lining was needed.
62. No satisfactory method exists for taking
account of residual tectonic stress in the calcu-
lation of the in-situ stress, hence it was mea-
sured directly. A CSIRO hollow intrusion cell
was used in an over-coring technique. The Table 12. Pressure pipeline or pressure shaft and tunnel alternatives
measured in-situ principal stresses ranged from
23 & 7 MPa to 6 k 1.5 MPa. Alternative Comparative Head
63. Measured bearings and dips were con- cost: losses :*
sistent with the topography. The calculated US$ million m
lithostatic overburden pressure is 9 MPa, sug- 6.99 8.92
Surface pressure pipeline
gesting that the in-situ stress field is influenced Pressure shaft and tunnel-fully steel lined 13.83 6.83
by tectonic movement, perhaps associated with Pressure shaft and tunnel -partly steel lined 6.56 6.73
the active subduction nearby of the Nazca Plate
beneath the South American Plate. * At maximum discharge for three set (75 MW) station.
to calculate the forces on the power station which is a cheaper solution than would have
resulting from seismic activity. been possible for the surface pipeline route.
68. Extensive slope protection measures
were needed on the steep hillside above the Transmission line route
power station. Drainage from the area is carried 69. The power-station substation is about
in gullies on either side of the power station, 1000 m downstream on the opposite bank of the
ZV transmission Iirie/(l
Pressure
/ tunnel \ ,iv., \
Power
station
3xmv
Scale of m
0 200 400 600 600 1000
1 I I I I I
Chancay (Fig. 17), the closest level space of suf- from both the dam and the tunnels was not
ficient size. Each unit generator transformer used as aggregate because it was generally not
steps up from 10 kV to 220 kV, with an individ- sufficiently strong.
ual circuit to the substation. 73. Most reinforcement bars were obtained
70. The 82 km single circuit 220 kV trans- locally, but 25 mm diameter reinforcement had
mission line route from Carhuaquero to the Chi- to be transported over 2000 km from a steel mill
clayo substation, where it joins the grid, was near Arequipa.
selected by a reconnaissance and tacheometric 74. Specialist materials from overseas,
survey. It passes over irregular terrain until it usually procured from Europe, included con-
reaches the cultivated lands on the outskirts of crete admixtures, geotextiles and waterproofing
Chiclayo. Many of the towers were located on elements. Imported materials, including all the
high points to enable the spans to be increased, construction machinery and the permanent
the maximum span being about 880 m. Many of plant, were landed at the port of Paita, about
these high points were found to be ancient look- 280 km from the project. Explosives were
out sites of pre-Colombian civilizations. The obtained locally, and ANFO was used for the
line also had to cross an area containing many drill and blast tunnels.
large unexcavated burial mounds. The authori-
ties declared these as areas of special archae- Roads, camps, water supply and drainage
ological interest, and about 190 tower 75. As the site was in a remote area, exten-
foundations had to be carefully investigated by sive new infrastructure was required, which
archaeologists before permission was granted took about one year to develop. Several tempo-
to construct the line. rary camps and offices were constructed
catering for up to 200 staff and their families,
and about 1500 technicians and workers. The
Construction and commissioning
permanent staff are housed in Chiclayo. The
Sources of construction materials project roads, constructed of roller-compacted
71. Ordinary Portland cement was obtained fill with gravel surfacing, required a pro-
locally from Pacasmayo, 180 km from the gramme of continuous maintenance to regrade
project. Sulphate resisting cement, for use in the running surface, reduce dust and repair
the underground works, and natural pozzolana occasional flood damage. Where required,
(volcanic ash), for use in pressure grouting, gravity retaining walls, incorporating Cyclo-
came from works near Lima (840 km away). pean concrete in accordance with a local design,
72. The river Chancay provided a readily were used.
available source of boulders and river sand for 76. Water for both potable and construction
concrete aggregates. The rock spoil excavated use was abstracted from the Chancay and
treated by a plant of modular design, using pumped about 5 km to the camps, using galva-
back-flushing filters. During the wet season, nized steel pipes placed directly on the ground
when sediment concentrations were very high, which avoided the cost of excavating trenches
filter wells near the river were also used in the hard ground.
together with a large settling lagoon to help 77. Storm water, collected around struc-
remove the sediment. The treated water was tures, project facilities and along roads, dis-
0
,....5O
Scale of m Section A-A
\\ : : ;
0 50 100
11 11 11 1 I
Scale of m
Plan
1981. Construction activity peaked during 1982 short sections of extra rockbolting and shot-
when up to 1000 workers were employed at site. Crete and the treatment of a few isolated clay
84. Unfortunately, the works had to be filled joints. The concrete linings in the pres-
halted in early 1983 as a result of a shortage of sure tunnel and shaft were found to be in good
funds to cover the extra construction costs condition. The tunnels and shafts were then
arising from necessary layout changes and the refilled to permit the electromechanical plant to
devastation caused by the El Nifio floods, The be commissioned.
works remained effectively paralysed until 86. The filled reservoir was satisfactory
1986, although some sporadic construction apart from the need to relocate short sections of
work and general maintenance were effected the public road away from the reservoir sides
during this period, including completion of the where some sloughing was observed. The spill-
remaining 1.4 km of headrace tunnel. Full pro- way gates were opened to simulate an extreme
duction did not recommence until late 1987. flood condition and the stilling basin was found
The project was completed by the end of 1988, to work efficiently, as predicted by the hydrau-
apart from some finishing works and the trans- lic model tests. The observed seepage through
mission line which were completed in 1990. The the infilled, buried valley to the left of the
effective construction period was about five dam was within the predicted limits, with the
years during a total contract period of just over flows and piezometric levels stabilizing as
10 years. expected.