Sunteți pe pagina 1din 5

Close and Return

B.5.4 8th International Conference on Insulated Power Cables B.5.4

CHALLENGES AT THE PLANNING, DEVELOPMENT AND PERFORMANCE AT THE


275KV XLPE CABLE PROJECT IN THE CITY OF LIVERPOOL

Sebastian EBERT, Horst MEMMER, Andreas WEINLEIN, Gero SCHRDER, Sdkabel GmbH, Mannheim (Germany),
sebastian.ebert@suedkabel.com, horst.memmer@suedkabel.com, andreas.weinlein@suedkabel.com,
gero.schroeder@suedkabel.com

ABSTRACT The cable manufacturer has recommended the mixture of


the CBS to reach the required thermal resistivity values.
A 275 kV extra high voltage cable system has been The civil work company as part of the National Grid
designed, supplied, installed, commissioned and put in Alliance West has installed the CBS under the cable
operation between the substations Kirkby and Lister Drive
in Liverpool for National Grid, UK. This project was manufacturer l supervision.
demonstrating the successful performance of almost The cable route followed the main streets across the city
every implication in an EHV direct buried cable project of Liverpool Many other services, cables, gas pipes,
within big city metropolis. sewers has to be crossed or laid in parallel to the 275 kV
cables. For all these laying conditions rating calculations
have to be performed by the cable manufacturer. For
1. DESCRIPTION OF XLPE CABLE SYSTEM
some sections directional drilling with laying depths of up
A 275 kV extra high voltage cable, type 2XS(F)K2Y to 8 m (where necessary) and phase distances has to be
1x1600 RMS/190 160/275 kV system has been designed, increased up to 2 m in order to reach the required load.
supplied, installed, commissioned and put in operation The cable route has a total length of approx. 10.3 km,
between the substations Kirkby and Lister Drive in which means a total length of approx. 31 km XLPE cable
Liverpool for National Grid, UK. The cable route consisting quantity with a conductor size of 1600 mm (figure 3). The
of 15 single sections and 14 joint bays. conductor was designed in segmental construction
The cable is rated for a load of 1.600 A respectively consisting of oxidized wires to reduce the skin effect in
762 MVA. The cable arrangement is seen in figure 2 and order to increase the transmission capacity [9].
3. The cable is laid in CBS (Cement Bound Sand) with a The cable shows an insulation thickness of 25 mm and a
thermal resistivity of 1.05 Km/W (wet condition) and composite copper screen wire / lead sheath screen for
1.2 Km/W (dry condition). The standard laying depth of advanced mechanical strength. A HDPE outer jacket
the cables is 1200 mm and the phase distance center to provides the corrosion protection of the cable.
center is 400 mm.

Fig. 1: Cable ducted laying condition Fig. 3: Cable design


In order to reduce the sheath losses to a minimum, a cross
bonding system has been implemented. The link pillars, which
contain also the sheath voltage limiters (SVL) are installed
along the route at the joint bay positions above ground.

Fig. 2: Cable trench laying condition


Fig. 4: Pedestrian link pillar

Jicable11 19 23 June 2011, Versailles - France


Close and Return

B.5.4 8th International Conference on Insulated Power Cables B.5.4

The link pillars had to pass special internal arcing and The interface connection between the OSE top bolt and
short circuit current tests before National Grid approved the busbar (earthing spigot) had to be considered as well
the use of the link pillars in the city. The link pillar has during this project.
been designed as pedestrian model (figure 4).
Additionally as part of the 275 kV cable system design
The cross-bonding design is shown in figure 5. Each both, PD monitoring and a DTS monitoring system via
cable screen has been crossed bonded in each link pillar. fiber optic cables have been installed and commissioned.
The cable conductor has been transposed in each joint
bay entering area (bell mouth). For all activities on site method statements and risk
assessments had to be issued for approval prior to the
work commence.
Furthermore the cable manufacturer has developed a
special earthing design concept for each individual joint bay
in order to achieve a required maximum earthing resistance
of 5 , which has been measured at each joint bay after
installation before and after backfilling with CBS. The size
of each earthing system and the numbers of used earthing
rods with surrounding conductive material had to be
Fig. 5: Earthing design with cross bonding designed individually at each joint bay depend on the
thermal resistivity of the ground material (figure 14).
Six pieces of factory pre-tested and pre-assembled
275 kV compact outdoor plug-in sealing [6] ends were The joint type is three piece composite design, known
installed as outdoor terminations (figures 6, 7): from [3, 4, 5] which passed both, additional mechanical
load tests and water immersion tests of the corrosion
protection system according NGTS standards.

Fig. 8: Composite type joint VMEVCB 275

Fig. 6: Design of outdoor sealing end EHFVCS 275

Fig. 7: Installed doutdoor sealing ends Fig. 9: Joint bay

Jicable11 19 23 June 2011, Versailles - France


Close and Return

B.5.4 8th International Conference on Insulated Power Cables B.5.4

In total 14 joint bays had to be designed and installed with A general cable pulling schematic drawing is shown in
a number of 42 cross bonding joints and associated figure 11 which shows the position of drum stand, winch
equipment. During each installation of the EHV cable and main rollers. Ground loading tests had to be carried at
accessories hold points were implemented as an activity each joint by prior to drum offloading.
of quality assurance by the cable manufacturer and the
National Grid Alliance West.

2. COMPLEXITY OF INSTALLATION WORKS


As the route led straight through the city of Liverpool key
facts like traffic management, SHE management had to
be challenged during all stages of the project, which ran
through more than 2 years due to specific requirements of
the city council and the highway agency not to open too Fig. 11: Cable pulling overview
many trenches in one time because Liverpool was the Another main challenge were specific cable accessories
European capital of culture in 2008 and a lot of events installation methods in accordance with NSI 5 (working
took place at this time. under induced voltages and isolating working) due to
parallel working in different joint bays and at the sealing
Figure 8 shows a drum offloading as part of one delivery ends within the National Grid Substations. This caused a
within the city center of Liverpool at the main road combination of grounded and isolated way of working.
between the main Irish ferry port of Liverpool and the
motorway which is mainly used by all trailers for the heavy This work had to be carried out in accordance with the
transport through Great Britain. Each cable drum had a National Grid specification "Guidance Note 11 MAKING
weight up to 50 ton, a diameter of 4.5 m and a width of OR BREAKING DOWN SEALING ENDS ON HV CABLES
3.7 m. Also not negligible in terms of decisions for a "of UK BP / SE / NSI 5 CABLE SYSTEMS" (NSI 5
football town like Liverpool is to mention that roads like Working Procedure). Special Permits, risk assessments
this are the main roads on the way to the Liverpool and method statements had to be issued. Furthermore
football ground Anfield Road for supporters from outside special trainings were required for all involved engineers,
to watch their Liverpool Football Club. These effects the fitters and labours [8].
complexity of the necessary permanent project
management with many years experiences in this
business between all contractors at all times. That means
in details that route survey had to be carried prior to each
cable drum delivery in order to clarify details like the
required street furniture, ground load tests, police escort
services etc. Once all details are known permit
applications had to be forwarded to the authorities for their
approval. Furthermore method statements and risk
assessments had to be issued for approval. Once the
approval had been given to the contractors only appointed
qualified persons could be allowed to be involved in the
delivery process. As an escort vehicle was supervising the
transport from the factory in Germany to the port and from
the ship to the storage yard also the last stage between
the motorway in front of Liverpool up to the designated
offloading point had to be escorted by an escort car and
additionally by several police cars. Qualified persons had
to supervise the key points of the final delivery in order to
avoid local problems up to the road closures area.

Fig. 12: Earthed working at the sealing ends


The cable manufacturer had to follow these guidelines as
almost the whole length of cable (approx. 10.3 km) was
already installed, the cable had entered the National Grid
substation which means that the cable is automatically
under the client rules. Due to time schedule restrictions a
parallel working was unavoidable. This means that a joint
installation and a sealing end installation were running in
Fig. 10: 50 t cable drum offloading liverpool city parallel. Both working groups had to be in constant
within main road closure & police escort communication for all working steps via radio. For an

Jicable11 19 23 June 2011, Versailles - France


Close and Return

B.5.4 8th International Conference on Insulated Power Cables B.5.4

earthed working method at the sealing ends, the wrapped around in order to avoid a contact with the
conductor and the screen had to be earthed at all times screen and the at this moment isolated conductor at the
(figure 12). For an isolated working procedure, a same time with the hands of the workers.
combination of at least 2 isolation barriers between man
and electrically conductive parts of the cable system or
installation scaffold had to be used (figure 13). The
scaffolding had to be earthed every 5 m.

Fig. 15: Isolating working in a joint bay for jointing of


EHV 275 kV XLPE cable joints
The difficulty of the working under these circumstances
was the combination of different working procedures
(mixture of earthed and isolated working at the sealing
ends and isolated working in the joint bay). It had to be
avoided that both working teams are working on the same
phase at the same time. Therefore a constant radio
communication was unavoidable. If the sealing end
installation team had to work on one phase, this phase
had to be earthed at the conductor and the screen by the
Fig. 13: Isolating working at the sealing ends sealing end installation team.
This means isolated mats (suitable for 20 - 25 kV), During this work the jointing team in the joint bay was not
isolated working boots (suitable for a insulation strength of allowed to work on this phase because they had to follow
7.5 kV per shoe) had to be worn. Alternatively isolated the isolating working procedure. If they had to work on
gloves could be worn but this would not allow a high one phase, the earthing connection at the sealing ends
standard working quality during the jointing due to had to be removed, so they were isolated from the
handling problems. For an isolating working insulating conductive parts of the cable system. The earthing
transformer had to be used in order to allow a galvanic connection at the sealing ends on the far end (other end
isolation between the generator and the working tool. of the cable circuit) had to be removed prior to all works
For the isolated jointing work in the joint bay isolated mats commence and the cable screen at the nearest joint bay
and boots had to be worn as well as a combination of at least was earthed in order to reduce the cable length and bring
2 isolation bareers between man and electrically conductive the earthing connection closer to the working place to
parts of the cable system or installation scaffolding. reduce the risk of induced voltages. The 275 kV cable
system was in fact not in operation at this time but due to
so many other services crossing the new installed 275 kV
cable circuits and due to so many parallel services a risk
of induced voltages from outside was present resulting in
all the precautions to allow an absolute safe working
process which is the aim of all working contractors.
This process has been designed and well planned by the
cable manufacturer together with all other project
contractors, which is mandatory. The design is the
Fig. 14: Isolating platform during jointing foundation for reducing risks for involved personnel.
For the using of chain hoists for lifting operations of joint Therefore, the cable manufacturer endorse the safety by
parts like the jointing body isolated gloves (suitable for a design concept. This system has been proofed by daily
insulation strength of 7.5 kV per glove) had to be used as briefings, talks, constant communication which each
the chain of the hoists are a conductive connection with other, issuing workable documents as risk assessments
the scaffolding beam on the the top. For reasons of and method statements which all parties had to
difficult practicability in terms of manual handling lifting understand and sign prior to the work commence.
slings were used between chains of chain hoists in order Every working step change had to be documented and
to avoid the using of isolated gloves at some stages of the signed which was controlled by the quality assurance
working process. Another difficulty was the connection of team in order to save the health of the workers against
the cable screen with the lead sheath of the cable. Once induced voltages and to comply with the client health and
this connection was made, an isolated tape had to be safety and working rules and requirements.

Jicable11 19 23 June 2011, Versailles - France


Close and Return

B.5.4 8th International Conference on Insulated Power Cables B.5.4

All these steps were helping to reduce incidents and to REFERENCES


perform all works on the highest quality level.
[1] National Grid Transco Technical Specification TS
This project is demonstrating the successful management 2.5
of challenges comprising of almost every implications in a
EHV direct buried cable project within big city metropolis. [2] "Guidance Note 11 MAKING OR BREAKING
DOWN SEALING ENDS ON HV CABLES "of UK
BP / SE / NSI 5 CABLE SYSTEMS"
3. COMMISSIONING OF XLPE CABLE
SYSTEM [3] GUIDANCE NOTE 24/24a MAKING OR
BREAKING-DOWN SEALING ENDS ON H.V.
After successful installation a wide number of CABLES of UK BP/SE/NSI 5 CABLE
commissioning tests had to be carried out. The cable SYSTEMS
manufacturer had to perform SVL operating voltage tests,
[4] J. Kaumanns, E. Plieth, R. Plath, 2003, On-site
over sheath DC voltage withstand tests, insulating AC
AC testing and PD measurement of 345 kV /
voltage withstand test acc. to IEC 62067 with a voltage of
2500 mm2 XLPE cable systems for bulk power
210 kV at all phases and partial discharge tests at all
transmission, Jicable03, paper A8.4
accessories (figure 16). Further the cable manufacturer
performed a positive and zero sequence impedance [5] S. Sutton, R. Plath, G. Schrder, 2007, The St.
measurement, a verification of the cross-bonded sheath Johns Wood - Elstree experience testing a 20
system, a cable conductor resistance measurement, a km long 400kV XLPE-insulated cable system
measurement of the sheath system contact resistances after installation, Jicable07
and a measurement of the insulation resistance at all
installed 275 kV power cables. All tests have been passed [6] J. Kaumanns, G. Schrder, A. Weinlein, V.
successfully. Stroot, J. Lehnhuser: 400 KV XLPE-Insulated
cable systems with dry plug-in outdoor
terminations, Jicable07, paper A.1.2
[7] A. Weinlein, G. Schrder, S. Ebert, H. Geyer,
2011, On-site testing with compact a.c. test-
system at the first 500 kV XLPE cable project in
South America, Jicable11, paper C.4.1
[8] G. Schrder, "Working under induced voltage
conditions at installation of EHV cable systems",
S1-3.9, ICOLIM Conference 2004, Bucharest,
Romania.
[9] G. Schroeder, J. Kaumanns, R. Plath, Advanced
measurement of AC resistance on skin-effect
reduced large conductor power cables,
Jicable11, paper C.8.2

Fig. 16: On-site AC test set-up GLOSSARY


All tests had to be carried out during a short time outage
as the cable manufacturer had to replace an existing CBS Cement Bound Sand
oilfield cable system. This means that the cable EHV (Extra) High Voltage
manufacturer had to manage all replacement works SHE Safety Health Environment
without any gap, which had to be approved and confirmed NSI National Safety Instruction
by all involved parties including the city council before the XLPE Cross-Linked Polyethylene
fixed outage time had to be applied officially to the client SVL Sheath Voltage Limiters
for their final approval. AC Alternating Current
DC Direct Current
4. SUMMARY PD Partial Discharge(s)
DTS Distributed Temperature Sensing
A 10.3 km 275 kV XLPE cable circuit was installed in the OSE Outdoor Sealing End
heart of the city of Liverpool after passing all relevant
customer requirements (type registration).
The installation works has to handle several special
challenges during installation as limited space along the
route, limited time for work activities (route access), and
working under induced voltage conditions.
The 275 kV cable circuit was put in service in December
2009 after passing successfully all required
commissioning tests and has operated continuously
without any abnormalities since then.

Jicable11 19 23 June 2011, Versailles - France

S-ar putea să vă placă și