Waterfront Structures
Power Plant
Basement Construction

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Function: Effective retaining wall system easy to handle, transport &
installation in sea / waterway.
Types of retaining structures in Waterfront Structures:
1) Ship Berthing Area
2) Key Wall
3) Breakwater
4) Slipway

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Ship Berthing Area: Where ship stops for loading / unloading
operation
Overview of wharf:

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Ship Berthing Area: Where ship stops for loading / unloading operation
Design Consideration:
Bollard load

Example of
bollard structure

Bollard load tie ship

Bollard load tie ship

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Ship Berthing Area: Where ship stops for loading / unloading operation
Design Consideration:
Container area additional load on top of wall

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Ship Berthing Area: Where ship stops for loading / unloading operation
Design Consideration:
Ship Impact Fender to allow transmission of ship impact load to
the back of wall

Example of fender
Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Ship Berthing Area: Where ship stops for loading / unloading operation
Design Consideration:
Installation in sea conditions appropriate machinery, platform & guiding frame.
Additional impact force to retaining wall during hydraulic filling operation.

Required
platform level
Sea level Sea level

Impact force to wall during


hydraulic filling operation
Original ground level

Required dredge level


Retaining Wall

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Ship Berthing Area: Where ship stops for loading / unloading operation
Design Consideration:
Bollard load: Depends on the terminal capacity to cater for type / size of ship, bollard
loading (to tie ship) can be 50 ton at spacing 30m c/c. This will affect the design
requirement of anchorage force anchor wall at the back. Typically bollard can be
collapsible or anchored into capping beam.
Container area: Depends on the staging height of container, the surcharge loading at wall
area is much higher than assumed for normal construction vehicle load. Typically container
area surcharge can be 30kPa 50 kPa depends on the loading / unloading activity.
Ship Impact: As ship is coming to berth at this area, high impact loads (depends of size of
ship, velocity of ship coming) will transfer to fender. Then depends on how the impact force
is transferred to capping beam of retaining wall and dissipate to the back of wall.
Consider hydraulic filling operation that might cause additional impact load to retaining
wall.

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Ship Berthing Area: Where ship stops for loading / unloading operation
Design Requirements:
Serviceability: Less strict control on the deflection
requirement where more than 100mm deflection is
allowed.
Retaining wall service life is long term, > 50 years.
Thus sheet piling protection by permanent coating,
catholic protection, sacrificial / additional steel
thickness for corrosion.

Consider toe scouring effects in


retaining design final dredging
depth + scouring depth, softening
zone at passive side of wall.

Permanent coating of sheet piling will


delay corrosion of section at least 20 years
Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Ship Berthing Area: Where ship stops for loading / unloading operation

Design Requirements:
Sea water level affecting detailing of capping beam, tie back Consider tie back
system (to suit design requirement & underwater installation) & system at corner
construction sequence (to optimized dredging operation). area.
Installation in rough sea conditions guided frame, suitable
machinery (vibro machine with right frequency to suit soil condition +
drop hammer).
Pre-boring requirement (depth & location) for hard soil conditions.

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Key Wall: Retaining wall for platform of harbour / jetty terminal
Overview of key wall:

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Key Wall: Retaining wall for platform of
harbour / jetty terminal
Design Considerations:
Wall height is normally very high , 10
20m with one or more tie back
anchorage
Reduce load on high
retaining wall, transfer top
portion loading to piling

Practical use of relieving platform to


reduce top portion surcharge and soil load
to retaining wall by transfer down to
bearing piles.
Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Key Wall: Retaining wall for platform of harbour / jetty terminal
Design Considerations:
Additional loads of wave impact.
Thus requirement for retaining
wall to form continuous & rigid
barrier is important. All the
connection must be ensure for
long term functionality.

Sheet Piling support vertical deck loads Concrete deck


Consider connecting retaining
wall to decks, thus sheet piling
can be designed to take part of
Concrete deck supported by
vertical loads. sheet piling & concrete piles

Concrete Piles
Sheet piling Concrete pile

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Key Wall: Retaining wall for platform of harbour / jetty terminal
Design Requirements:
Retaining wall service life is long term, > 50 years. Thus sheet piling protection by
permanent coating, catholic protection, sacrificial / additional steel thickness for
corrosion.
Consider toe scouring effects in retaining design final dredging depth +
scouring depth, softening zone at passive side of wall.

Scouring at
Thickness Reduced
toe of wall
Zone by Corrosion.
Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Key Wall: Retaining wall for platform of harbour / jetty terminal
Design Requirements:
Sea water level tie back system (to suit design requirement & underwater
installation) & construction sequence.
Pre-boring requirement (depth & location) for hard soil conditions.

Guide frame to suit site conditions

Batter concrete piles as anchor


elimination installation of tie
rod in sea conditions
Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Breakwater: To stop / reduce sea wave impact
Overview of breakwater structure:

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Breakwater: To stop / reduce sea wave impact
Design Considerations:
Wall height is normally high, > 10m and tie back double wall.
Additional high loads for wave impact. Thus requirement for retaining wall
to form continuous & rigid barrier is important. All the connection must be
ensure for long term functionality.
Normally site conditions extending from shoreline will encounter loose
sandy soil beneath.

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Breakwater: To stop / reduce sea wave impact
Design Requirement:
Retaining wall service life is long term, > 50 years. Thus sheet piling protection by
permanent coating, catholic protection, sacrificial / additional steel thickness for
corrosion. Additional requirement for large splashing zone area than other
waterfront structures.

Considering loss
of steel at Max
Moment location

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Breakwater: To stop / reduce sea wave impact
Design Requirement:
Construction sequence might need free standing
sheet piling to withstand wave impact before tie
back can be realized.
Installation in rough sea conditions guided frame,
suitable machinery (vibro machine with right
frequency to suit soil condition + drop hammer).
Consider toe scouring effects in retaining design
final dredging depth + scouring depth, softening zone
at passive side of wall.
Water pumping is required. Thus consider water
tightness of sheet piling, wider section will have less
opening of interlocks.

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Slipway: Area for ship to be transported inland for maintenance
Overview of slipway structure:

Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Slipway: Area for ship to be transported inland for maintenance
Design Considerations:
Retaining wall to Very high straddle wheel loads (to carry ship to inland)
take additional of 500 ton.
sloping revetment
weight.
Straddle to
carry ship
Workshop

Anchor
Slipway Tie Sheet
Back Pile Wall

Unloading ship Main Sheet


for maintenance Pile Wall
Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone
wish to apply this information shall satisfy themselves of its validity relatives to the applicable conditions. All the technical data in this document is liable to change without notice.
Application of Sheet Piling Waterfront Structures
Slipway: Area for ship to be transported inland for maintenance

Design Requirement:
Retaining wall service life is long term, > 50 years. Thus sheet piling protection by
permanent coating, catholic protection, sacrificial / additional steel thickness for
corrosion.
Consider toe scouring effects in retaining design final dredging depth +
scouring depth, softening zone at passive side of wall.

Decrease in thickness as a result of


corrosion in the sea water
Recommendations of the Committee
for Waterfront Structures Harbours
and Waterways EAU 1996, 7th
edition.
Unauthorized reproduction and distribution prohibited. The information contained in this document is for general information purposed only. No warranty is expressed or implied. Anyone