Sunteți pe pagina 1din 4

Republic of the Philippines

COMMISSION ON AUDIT
Office of the Team Leader
Construction Industry Authority of the Philippines
5-F 369 Executive Bldg., Sen. Gil J. Puyat Avenue, Makati City

Ref. AOM No. 2017-06


Date: May 25, 2017

AUDITORS REJOINDER ON MANAGEMENTS RESPONSE


TO AUDIT OBSERVATION MEMORANDUM

ENGR. LEILANI DL DEL PRADO


Acting Executive Director
Construction Industry Authority of the Philippines

Attention : MR. RUFINO H. TIVIDAD


Chief, AFMD / Chairman, Bids and Awards Committee

MS. EDNA S. DOMINGO


OIC, Accounting Services

We acknowledge receipt of your response dated May 15, 2017 re: reply to the AOM No.
2017-06 dated May 2, 2017 (procurement of one (1) unit brand new car). However, please find
hereunder the audit team's rejoinder:

Management Comment /
Observations Auditors Rejoinder
Actions taken
Contract and its supporting We (management) were unable to It is understood that all of the
documents were not submitted obtain some of the documents documents pertaining to the
to the Audit Team within five from the other party, considering procurement process (e.g. from
working days after perfection the circumstances at that time. Invitation to Bid up to the
thereof which is not in accord Nonetheless for purpose of issuance Purchase Order) are
with COA Circular No. 2009-001 record, the Purchase Order and already in the possession of the
dated February 12, 2009. some supporting documents were management, particularly the
endorsed to COA for perusal on BAC Secretariat, hence, there
February 20, 2017. should have been no hindrance in
the submission of the required
documents to COA on time
which should be on or before
January 3, 2017, considering that
the PO was issued on December
29, 2017.

Failure to post Performance The bidders were informed that We consider the justification of
Security in the particular procurement the management and acknow-
process, the winning bidder shall ledge the receipt of the
only be given one (1) day to Performance Bond issued by
deliver the vehicle as the day Western Guaranty Corporation
Management Comment /
Observations Auditors Rejoinder
Actions taken
following the opening of the bids on May 10, 2017, which was
is the last working day of 2016. posted by the winning bidder,
x x x. Nevertheless, the Broadway Motor Sales
Performance Security for the Corporation (BMSC), five (5)
subject vehicle is attached hereto months after the issuance of the
as annex A to form an integral P.O.
part hereof.
It is the position of the Audit
Team, however, that in the
succeeding procurement, the
agency should strictly follow the
provisions stated in the Revised
IRR of RA 9184, particularly
Section 39.1, which requires the
posting of a performance security
prior to the signing of the
contract.

Absence of Warranty Security Upon the delivery of the subject The Audit Team opined that the
vehicle, it was already protected New Vehicle Warranty issued by
under a New Vehicle Warranty the car manufacturer is not a
issued by Nissan Philippines Inc. sufficient compliance with the
x x x. provision of the Revised IRR of
RA 9184.

Section 62.1 of the Revised IRR


of RA 9184 provides that:

x x x.

The obligation for the warranty


shall be covered by either
retention money in an amount
equivalent to at least one percent
(1%) of every progress payment,
or a special bank guarantee
equivalent to at least one percent
(1%) of the total contract price.
The said amounts shall only be
released after the lapse of the
warranty period x x x. (under-
scoring ours)

Hence, the Audit Team reiterates


the submission of warranty
security (either retention money
or special bank guarantee) as
provided by the aforesaid
provision of the procurement law.

It is informed that during the time


Management Comment /
Observations Auditors Rejoinder
Actions taken
Failure to notify the COA of the Due to time constraints and the of the supposed delivery of the
delivery of the motor vehicle need to utilize the budget procured sedan, COA personnel
allocated for vehicles under the were available to conduct such
re-aligned 2016 Budget, the inspection. However, the
vehicle was delivered around management failed to inform the
four olock in the afternoon of Audit Team on the actual time
December 29, 2016. At that time, of the delivery of the said motor
there was no COA personnel vehicle. Moreover, per
available. Nonetheless, during clarification from the Supply
the bidding process, the Officer, since the subject vehicle
representative of COA and was delivered at the time that
Private Sector (Philexport) were office hours was about to close,
aware of the December 29, 2017 he only assumed that the COA
date of delivery. personnel were no longer
available to witness/inspect the
delivery.

It should also be pointed out that


the management did not furnish
the Audit Team with the
documents relative to the said
delivery (e.g. sales invoice,
delivery receipt) even after the
days following the delivery.

It was noted that during the


opening of bids on December 28,
2016, BAC stated that the
supposed delivery of the sedan
shall be on the next day, only if
and when the lone bidder will
pass the post-qualification. The
Audit Team at that time was not
sure whether or not the lone
bidder will pass the post-
qualification and therefore,
deliver the vehicle on the next
day.

Thus, the Audit Team is firm in


its conclusion that the
management failed to notify the
COA of the delivery of the
procured sedan within 24 hours
from such acceptance as required
by Section 6.06 of COA Circular
No. 95-006 dated May 18, 1995.

The Audit Team acknowledge the


Delayed insurance of the vehicle The management admitted to the submission of the GSIS
delay in the submission of the Insurance Policy for the subject
insurance policy by the seller, as vehicle. Henceforth, ensure that
these were all processed during newly procured vehicle shall be
Management Comment /
Observations Auditors Rejoinder
Actions taken
the year end, as such, even GSIS properly insured with the GSIS
personnel have mostly been on prior to its acceptance.
leave. x x x. The GSIS Insurance
Policy for vehicle with Policy
No. MV-PC-GSISHO-0131880
was issued January 25, 2017.
Well taken.
Form used to issue the PPE not The management shall abide with
the prescribed form the observation.

Notwithstanding this rejoinder, the audit team still recommends for the submission of the
Warranty Security in compliance with Section 62.1 of the Revised IRR of RA 9184.

YOLANDA P. JUAN
State Auditor III
OIC, Audit Team Leader

MA. LOURDES C. CENTENO


State Auditor V
Supervising Auditor, DTI Audit Group

S-ar putea să vă placă și