1.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m (GIGANTOGRAFIA) u 1.00 348.63 348.63
2 BOCATOMA 3,010.29
02.03.02 CONCRETO CICLOPEO f'c=140 kg/cm2 + 70 % PG. PISO BOCATOMA m3 1.54 103.96 160.10
03.02.03 REFINE Y NIVELACION EN TERRENO NORMAL PARA ZANJAS m 1,000.00 0.36 360
03.02.04 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO m3 40.00 5.59 223.6
03.03.01 TUBERIA PVC SAP C-10 DE 2", INSTALACION m 1,000.00 6.14 6140
04.07.01 TAPA METALICA SANITARIA DE 0.60M x 0.60M e=1/8" u 1.00 175.3 175.3
05.03.01 CONCRETO f'c=140 kg/cm2 + 30% PM PARA CIMIENTO m3 12.86 188.64 2425.9104
05.09.01 TAPA METALICA SANITARIA DE 0.70M x 0.70M e=1/8" u 1.00 195.3 195.3
05.09.02 ESCALERA TIPO GATO F G 3/4" SEGUN DISEO u 1.00 190.2 190.2
06.03.01 CONCRETO f'c=140 kg/cm2 + 30% PM PARA CIMIENTO m3 5.11 188.64 963.9504
06.09.01 TAPA METALICA SANITARIA DE 0.70M x 0.70M e=1/8" u 1.00 195.3 195.3
06.09.02 ESCALERA TIPO GATO F G 3/4" SEGUN DISEO u 1.00 190.2 190.2
07.08.01 TAPA METALICA SANITARIA DE 0.60M x 0.60M e=1/8" u 5.00 175.3 876.5
07.08.02 TAPA METALICA SANITARIA DE 0.40M x 0.40M e=1/8" u 5.00 75.3 376.5
08.02.03 REFINE Y NIVELACION ZANJA TERRENO NORMAL PARA TUBERIA 3/4"-2" m 3,145.81 0.38 1195.4078
08.02.04 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO m3 94.37 5.59 527.5283
08.03.01 TUBERIA PVC SAP C-10 DE 2", INSTALACION m 21.40 6.14 131.396
08.03.02 TUBERIA PVC SAP C-10 DE 1 1/2", INSTALACION m 796.70 5.48 4365.916
9 HIDRANTES 8,569.78
9.05 TAPA METALICA SANITARIA DE 0.30M x 0.40M e=1/8" u 36.00 55.3 1990.8
10 VALVULAS 1,961.17
10.05 TAPA METALICA SANITARIA DE 0.30M x 0.40M e=1/8" u 13.00 55.3 718.9
11 CAPACITACION 2,725.00
11.05 Capacitacin uso y manejo de riego por Aspersion, operacin y mantenimiento de infraestructura hidrulica glb 1.00 525 525
SUB TOTAL
TOTAL PRESUPUESTO
Item Descripcin Und. Metrado Precio S/. Parcial S/.
01 OBRAS PROVISIONALES 348.63
1.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m (GIGANTOGRAFIA) u 1.00 348.63 348.63
2 BOCATOMA 3,010.29
02.03.02 CONCRETO CICLOPEO f'c=140 kg/cm2 + 70 % PG. PISO BOCATOMA m3 1.54 103.96 160.10
03.02.03 REFINE Y NIVELACION EN TERRENO NORMAL PARA ZANJAS m 1,000.00 0.36 360
03.02.04 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO m3 40.00 5.59 223.6
03.03.01 TUBERIA PVC SAP C-10 DE 2", INSTALACION m 1,000.00 6.14 6140
04.07.01 TAPA METALICA SANITARIA DE 0.60M x 0.60M e=1/8" u 1.00 175.3 175.3
05.03.01 CONCRETO f'c=140 kg/cm2 + 30% PM PARA CIMIENTO m3 12.86 188.64 2425.9104
05.09.01 TAPA METALICA SANITARIA DE 0.70M x 0.70M e=1/8" u 1.00 195.3 195.3
05.09.02 ESCALERA TIPO GATO F G 3/4" SEGUN DISEO u 1.00 190.2 190.2
06.03.01 CONCRETO f'c=140 kg/cm2 + 30% PM PARA CIMIENTO m3 5.11 188.64 963.9504
06.09.01 TAPA METALICA SANITARIA DE 0.70M x 0.70M e=1/8" u 1.00 195.3 195.3
06.09.02 ESCALERA TIPO GATO F G 3/4" SEGUN DISEO u 1.00 190.2 190.2
07.08.01 TAPA METALICA SANITARIA DE 0.60M x 0.60M e=1/8" u 5.00 175.3 876.5
07.08.02 TAPA METALICA SANITARIA DE 0.40M x 0.40M e=1/8" u 5.00 75.3 376.5
08.02.03 REFINE Y NIVELACION ZANJA TERRENO NORMAL PARA TUBERIA 3/4"-2" m 3,145.81 0.38 1195.4078
08.02.04 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO m3 94.37 5.59 527.5283
08.03.01 TUBERIA PVC SAP C-10 DE 2", INSTALACION m 21.40 6.14 131.396
08.03.02 TUBERIA PVC SAP C-10 DE 1 1/2", INSTALACION m 796.70 5.48 4365.916
9 HIDRANTES 8,569.78
9.05 TAPA METALICA SANITARIA DE 0.30M x 0.40M e=1/8" u 36.00 55.3 1990.8
10 VALVULAS 1,961.17
10.05 TAPA METALICA SANITARIA DE 0.30M x 0.40M e=1/8" u 13.00 55.3 718.9
11 CAPACITACION 2,725.00
11.05 Capacitacin uso y manejo de riego por Aspersion, operacin y mantenimiento de infraestructura hidrulica glb 1.00 525 525
SUB TOTAL
TOTAL PRESUPUESTO