2. Improvement Proposals:
Keeping in view the length of the project, the design parameters and likely facilities
to be provided in the project, the MSRDC had submitted the Estimate. It is proposed
to have rigid pavement for 2 lane carriageway including paved shoulders & 4 lane
carriageway for this project package. Based on Engineering Surveys, Investigations,
Traffic analysis and projections the following design standards have been adopted as
per Manual of specifications and standards for 2-laning of Highways with paved
shoulder (IRC:SP:73-2015)published by IRC.
Sr.
Item Standards for Plain / Rolling Terraig
No
2.50% (Bituminous)
(i) Carriageway & Paved Shoulder
2.0% (Rigid)
5. Scope of work:
Broadly the Scope of work is defined as under
A. Main carriageway -
(i) Crust Composition (Rigid Pavement) (Length=30.125 km)
Design Life-30 years
(Length - 1.275 to 31.400 km)
a. GSB 150 mm thick
b. DLC - 150 mm
c. PQC - 300 mm thick (M-40)
B. Junction Improvements -
Major Junctions - 1 Nos.
o Major junction @ km 13+000
Minor Junction - 43 Nos.
C. Culverts
Pipe culverts - 68 Nos.
- Reconstruction - 32 Nos.
- Widening - 36 Nos.
- Retained - Nil
- Abandoned - Nil
- New Construction - Nil
Slab/ Box Culverts - 9 Nos.
- Widening & Rehabilitation - Nil
- New Construction - Nil
- Reconstruction - 9
D. Bridges
Major Bridges - Nil
- Reconstruction - Nil
- Retained - Nil
F. ROB - Nil
H. Traffic Control Devices, Road Safety Work and Road Furniture as per provision of
manual have also been taken.
I. Miscellaneous Work -
The provision of slope and shoulder protection, high embankment protection, utility ducts,
RCC cover drains with footpath in built up section have also been taken.
J. Project Facilities -
The provision of project facilities in accordance to requirement of manual such as
(i) Road Boundary, km and 200 m stones
(ii) Street lighting in habitation and structure approaches.
(iii) Bus Shelters (9 x 2 Nos).
S. AMOUNT AMOUNT
ITEM OF WORKS
No. (Rs.) (Cr.)
1 ROAD WORKS
i BILL No. 1 - SITE CLEARANCE AND DISMANTLING 14050257.03 1.41
BILL No. 2 - EARTH WORK, EROSION CONTROL AND
ii 108047057.32 10.80
DRAINAGE
BILL No. 3 - SUB-BASES, BASES (NON- BITUMINOUS) AND
iii 145967362.99 14.60
SHOULDERS
iv BILL No. 4 - BITUMINOUS PAVEMENT 8896300.00 0.89
V BILL No. 5 - CEMENT CONCRETE ROAD 852583424.65 85.26
vi BILL No. 6 - NEW JERSEY TYPE MEDIAN 60212764.44 6.02
vii BILL No. 7 - C.C. DRAIN 206721561.37 20.67
viii BILL No. 8 - PAVER BLOCK 164036005.00 16.40
BILL No. 9 - TRAFFIC SIGNS, ROAD MARKINGS AND OTHER
ix 129088061.67 12.91
APPURTENANCES
BILL No.10 - JUNCTION IMPROVEMENT & APPROCHES
x 112554877.68 11.26
IMPROVEMENT
xi BILL No.11 - PLANTATION (HORTICULTURE) WORK 7809400.25 0.78
xii BILL No.12 - PROTECTION WORK 103970347.80 10.40
xiii BILL No.13- BUS SHELTER 4599344.00 0.46
AMOUNT - I 1918536764.20 191.85
2 CD-STRUCTURES - BIIL No. 11
i RECONSTRUCTION OF CULVERT 52,754,760.25 5.28
ii WIDENING OF CULVERT 11,733,348.00 1.17
iv RECONSTRUCTION OF MINOR BRIDGE 71,570,138.90 7.16
v WIDENING & REPAIR OF MINOR BRIDGE 79,503,916.30 7.95
AMOUNT - II 215,562,163.45 21.56
(A) COST OF CIVIL WORKS (SUB TOTAL) BASE COST 2,134,098,927.65 213.41
MODIFICATIONS & DEVIATION , IF ANY
SUB TOTAL FOR CIVIL WORKS (A) 2,134,098,928 213.41
COST PER KM FOR CIVIL WORKS 70,841,458 7.08
***