Sunteți pe pagina 1din 1

PROGRESS REPORT

Client : - Report No : 16005-PLTF-PRO-003 Date 15 July 2016


Project : Oufitting Modul Period : 15 June 2016 ~ 15 July 2016 Scope Supply Manpower, Fabrication, Delivery & Erection
Job No : - Location Batam Yard
MARKING + FIT UP Visual Inspection Blasting & Total Total
ASSEMBLY REV. TOTAL FIT UP WELDING
NO DRAWING NO QTY UNIT WEIGHT CUTTING INSPECTION NDT/NDE Painting Progress Progress In
MARK DRAWING WEIGHT
15% 25% 5% 40% 5% 10% 100% Weight (Kg)
1 00784-ST-FBA-ESS-002-012 4PB-291 H 1 56.80 56.80 100% 100% 100% 100% 100% 100% 100% 56.80
2 00784-ST-FBA-ESS-002-012 4PB-292 H 1 38.00 38.00 100% 100% 100% 100% 100% 100% 100% 38.00
3 00784-ST-FBA-ESS-002-012 4PB-293 H 1 38.80 38.80 100% 100% 100% 100% 100% 100% 100% 38.80
4 00784-ST-FBA-ESS-002-012 4PB-294 H 1 38.80 38.80 100% 100% 100% 100% 100% 100% 100% 38.80
5 00784-ST-FBA-ESS-002-012 4RP-145 H 1 406.40 406.40 100% 100% 100% 100% 100% 100% 100% 406.40
6 00784-ST-FBA-ESS-002-012 4RP-146 H 1 121.20 121.20 100% 100% 100% 100% 100% 100% 100% 121.20
7 00784-ST-FBA-ESS-002-012 12DS-100 I 1 71.70 71.70 100% 100% 100% 100% 100% 100% 100% 71.70
8 00784-ST-FBA-ESS-002-012 12DS-101 I 1 50.00 50.00 100% 100% 100% 100% 100% 100% 100% 50.00
9 00784-ST-FBA-ESS-002-012 12PB-100 I 1 58.90 58.90 100% 100% 100% 100% 100% 100% 100% 58.90
10 00784-ST-FBA-ESS-002-012 12PB-101 I 1 105.80 105.80 100% 100% 100% 100% 100% 100% 100% 105.80
11 00784-ST-FBA-ESS-002-012 12PB-102 H 1 91.30 91.30 100% 100% 100% 100% 100% 100% 100% 91.30
12 00784-ST-FBA-ESS-002-012 12PB-103 I 1 20.00 20.00 100% 100% 100% 100% 100% 100% 100% 20.00
13 00784-ST-FBA-ESS-002-012 12PB-104 H 1 45.00 45.00 100% 100% 100% 100% 100% 100% 100% 45.00
14 00784-ST-FBA-ESS-002-012 12PB-105 I 1 99.20 99.20 100% 100% 100% 100% 100% 100% 100% 99.20
15 00784-ST-FBA-ESS-002-012 12PB-106 I 1 83.10 83.10 100% 100% 100% 100% 100% 100% 100% 83.10
16 00784-ST-FBA-ESS-002-012 12PB-107 I 1 36.10 36.10 100% 100% 100% 100% 100% 100% 100% 36.10
17 00784-ST-FBA-ESS-002-012 12PB-108 I 1 36.10 36.10 100% 100% 100% 100% 100% 100% 100% 36.10
18 00784-ST-FBA-ESS-002-012 12PB-109 I 1 102.00 102.00 100% 100% 100% 100% 100% 100% 100% 102.00
19 00784-ST-FBA-ESS-002-012 12PB-110 I 1 83.10 83.10 100% 100% 100% 100% 100% 100% 100% 83.10
20 00784-ST-FBA-ESS-002-012 12PB-113 H 1 28.50 28.50 100% 100% 100% 100% 100% 100% 100% 28.50
21 00784-ST-FBA-ESS-002-012 12PB-114 I 2 23.20 46.40 100% 100% 100% 100% 100% 100% 100% 46.40
22 00784-ST-FBA-ESS-002-012 12PB-115 I 1 21.60 21.60 100% 100% 100% 100% 100% 100% 100% 21.60
23 00784-ST-FBA-ESS-002-012 12PB-116 I 1 32.70 32.70 100% 100% 100% 100% 100% 100% 100% 32.70
24 00784-ST-FBA-ESS-002-012 12PB-123 I 1 78.60 78.60 100% 100% 100% 100% 100% 100% 100% 78.60
25 00784-ST-FBA-ESS-002-012 12PC-100 I 1 302.30 302.30 100% 100% 100% 100% 100% 100% 100% 302.30
26 00784-ST-FBA-ESS-002-012 12PC-101 I 1 279.70 279.70 100% 100% 100% 100% 100% 100% 100% 279.70
27 00784-ST-FBA-ESS-002-012 12PC-102 I 1 242.60 242.60 100% 100% 100% 100% 100% 100% 100% 242.60
28 00784-ST-FBA-ESS-002-012 12PC-103 I 1 301.90 301.90 100% 100% 100% 100% 100% 100% 100% 301.90
29 00784-ST-FBA-ESS-002-012 10PB-115 I 1 125.10 125.10 100% 100% 100% 100% 100% 100% 100% 125.10
30 00784-ST-FBA-ESS-002-012 12PB-124 I 1 107.50 107.50 100% 100% 100% 100% 100% 100% 100% 107.50
31 00784-ST-FBA-ESS-002-012 12PB-125 I 1 87.90 87.90 100% 100% 100% 100% 100% 100% 100% 87.90
32 00784-ST-FBA-ESS-002-012 12PB-126 I 1 99.00 99.00 100% 100% 100% 100% 100% 100% 100% 99.00
33 00784-ST-FBA-ESS-002-012 12PB-133 I 1 25.80 25.80 100% 100% 100% 100% 100% 100% 100% 25.80
34 00784-ST-FBA-ESS-002-012 12PB-134 I 1 22.50 22.50 100% 100% 100% 100% 100% 100% 100% 22.50
35 00784-ST-FBA-ESS-002-012 12PB-135 I 2 24.40 48.80 100% 100% 100% 100% 100% 100% 100% 48.80
3433.20 100% 3433.20

Prepared By Checked By Approved By

Engineering Production Project Engineer / QC / Production Manager Project Manager


Date : Date : Date :