MANPOWER PLANNING Project Schedule

Basic Design
Project Name : HEAVY OIL PRODUCTION FACILITY EPCC: Pre-Award
AT UMM NIQA EPCC: Detail Engineering
EPCC: Procurement
Revision: 00 (Effective: 07/23/17) EPCC: Construction
EPCC: Painting
Phase: I
EPCC: Errection
Duration: 8 WEEKS
Initial Acceptance

Dur. WEEKS
Item Designation Reqd 1 2 3 4 5 6 7 8 9 10 11 12 13 14
(Mth) 12 hours per day Working
1 Project Engineer 2 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
2 Fitter 2 2.00 2.00 2.00 2.00 2.00 2.00 2.00 1.00
3 Welder 2 2.00 2.00 2.00 2.00 2.00 2.00 2.00 1.00
4 Cutter 2 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
5 Grinder 2 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
6 Helper 2 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00
7 Rigger 2 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9
10

Total 10.0 10.0 10.0 10.0 10.0 10.0 10.0 8.0 0.0 0.0 0.0 0.0 0.0 0.0