Documente Academic
Documente Profesional
Documente Cultură
SEGMENTAL
BOX GIRDER
BRIDGE MANUAL
.
PUBLISHED BY
, APPENDIX....................................................................... 107
A.1 TENTATIVE DESIGN AND CONSTRUCTION SPECIFICATION FOR PRECAST
SEGMENTAL BOX GIRDER BRIDGES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107
A.2 SUMMARY OF PRECAST SEGMENTAL CONCRETE BRIDGES IN THE UNITED STATES
AND CANADA WITH CROSS SECTIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113
.
A.3 NOTATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116
A.4 REFERENCES.............................................................. 118
The majority of the technical material in this manual was developed under a contract
with the consulting firm of Bouvy, Van Der Vlugt & Van Der Niet/Segmental Technology
and Services (BVN/STS). H. H. Janssen prepared most of the BVN/STS material. The creep
and shrinkage data in Chapter 3 reflects the procedures in Comite Europeen du Beton/
Federation lnternationale de la Precontrainte bulletin dinformation No. 111 published in
October, 1975. Portions of Chapters 1, 2 .and 4 were adapted from the article by Jean
Muller of Enterprises Campenon Bernard, Ten Years Experience in Precast Segmental
Construction which was initially published in the January-February 1975 Journal of the
Prestressed Concrete Institute. Some of the material in Chapter 4 was taken from Recom-
mended Practice for Segmental Construction in Prestressed Concrete developed by the PCI
Committee on Segmental Construction and first published in the March-April 1975 Journal
of the Prestressed Concrete institute. The computer analysis for the effects of shear lag
presented in Chapter 3 was conducted by Professor Alex Scordelis of the University of
California at Berkeley. The prepublication drafts of the manual were reviewed by com-
mittees of the Prestressed Concrete Institute and the Post-Tensioning Institute. General
editorial work in development of the manual was by Clifford L. Freyermuth, Post-Tension-
ing Institute.
,
I
I
FOREWORD
In the period since the conclusion of World War II, prestressed concrete in various forms
I has emerged as a major factor in long span bridge construction. A number of prestressed
concrete box girder bridges with spans ranging to 700 ft. (210 m) have either been
completed or are underway in the U.S. and Canada. A prestressed concrete deck has been
selected for the Dames Point Bridge in Jacksonville, Florida. This cable-stayed bridge will
have spans of 650 ft., 1300 ft., and 650 ft. (200-400-200 m) for a total length of 2600 ft.
(800 m). The Pasco-Kennewick cable-stayed bridge in the State of Washington utilizing pre-
cast segmental construction will be completed in 1978 and has a main span of 981 ft. (299
I ml.
In the late 1940s, and in the 1950s, many innovative construction methods were devel-
oped in Europe for replacement of war damaged bridges. These construction methods pri-
marily related to the use of prestressed concrete. In particular, the cast-in-place cantilever
a
method of segmental bridge construction developed by the firm of Dyckerhoff & Widmann
in Germany opened the way to construction of concrete bridge spans in excess of 700 ft.
(210 m).
Beginning in the mid 1960s, the Freyssinet Organization developed technology in France
for the use of precast segmental box girder bridges. This technology subsequently spread to
countries throughout the world, including, in recent years, Canada and the United States.
As a contribution to the continuing evolution of prestressed concrete bridge construction,
the Prestressed Concrete Institute and the Post-Tensioning Institute are pleased to present
this joint publication on precast segmental box girder bridges.
!
CHAPTER 1 Zealand adopted the method. Many other
DEVELOPMENT OF PRECAST countries are today using the precast segmental
SEGMENTAL BRIDGE CONSTRUCTION techniques for various applications. The first
known application of precast segmental box girder
1.1 Introduction bridge construction in North America was a high-
way bridge over the Lievre River in Quebec. The
The earliest known application of precast seg-
Lievre River Bridge was built in 1967 and has a
mental bridge construction was a single span
main span of 260 ft. (79 m) with end spans of 130
county bridge in New York State built in 1952.
ft. (40 m). The Bear River bridge near Digby, Nova
The bridge girders were divided longitudinally into
Scotia, shown in Fig. 1.4 contains six interior spans
three precast segments which were cast end to end.
of 265 ft. (81 m) and end spans of 203 ft. (62 m).
After curing, the segments were transported to the
The Bear River bridge was opened to traffic in
job site where they were reassembled and post-
December 1972.
tensioned with cold joints.
The first U.S. precast segmental box girder
The development of long span prestressed con-
bridge was built near Corpus Christi, Texas and was
crete bridge construction techniques in Europe is
opened to traffic in 1973. The Corpus Christi
outlined in the Foreword. Of particular signifi-
bridge, shown in Fig. 1.5, has a central span of 200
cance was the development of cast-in-place canti-
ft. (61 m) and end spans of 100 ft. (30.5 m). Sub-
lever segmental construction in Germany by the
sequent to the Corpus Christi bridge, precast
firm of Dyckerhoff & Widmann, Inc. The technolo-
segmental bridges have been completed in Indiana
gy of cast-in-place segmental construction was
and Colorado, and a bridge of this type is now
adapted and extended for use with precast seg-
under construction in Illinois. A simple span pre-
ments in the Choisy-le-Roi Bridge over the Seine
cast segmental bridge has been constructed at the
River south of Paris in 1962. The Choisy-le-Roi
Pennsylvania State University test track as a re-
Bridge, designed and built by Enterprises
search project sponsored by the Federal Highway
Campenon Bernard, is shown in Fig. 1.1. Several
Administration and the Pennsylvania Department
other structures of the same type were built in due
of Transportation. Numerous precast segmental
course. At the same time, the techniques of pre-
bridges have been designed for other locations in
casting segments and placing them in the structure
the U.S. and Canada, and it is expected that this
were continually refined.
technique will be widely used in the years ahead.
A major innovation for construction of precast
segmental bridges was the launching gantry which
was used for the first time on the Oleron Viaduct,
shown in Fig. 1.2, which was built between 1964 1.2 Types of Precast Segmental Construction
and 1966. The Oleron Viaduct launching gantri/ Two main types of precast segmental bridge
is shown in Fig. 1.3. The launching gantry makes it construction have developed which may be differ-
possible to move segments over the completed part entiated by the use of either cast-in-place concrete
of the structure and place them in cantilever over or epoxy joints.
successive piers. Use of a launching gantry per- A number of precast segmental bridges have
mitted completion of the Oleron Viaduct at an been built using cast-in-place joints 3 to 4 in. (76
average of 900 linear feet (270 m) of finished deck to 102 mm) wide between segments. This procedure
per month. While the launahing gantry is a very eliminates the need for match-casting and reduces
useful means of erection in many cases, erection the dimensional precision required in casting the
can also be accomplished by use of cranes and segments, but it has major disadvantages including
other means as described in Section 4.3. the requirement of falsework to support the seg-
Experience with major precast segmental bridges ments while the cast-in-place joint cures, and sub-
in Europe allowed the refinement of the construc- stantial reduction in construction speed. On
tion process. Improvements were made in precast- balance, the use of cast-in-place joints is not gen-
ing methods and in the design of erection equip- erally attractive and for this reason this type of
ment to permit use of larger segments and longer joint will not be considered further in this manual.
spans, and which could accommodate horizontal The prevailing system of precast segmental
curvature in the roadway alignment. bridge construction uses an epoxy resin jointing
The technique of precast segmental construc- material. The thickness of the epoxy joint is on the
tion not only gained rapid acceptance in France order of l/32 in. (0.8 mm). The use of an epoxy
but spread to other countries. For example, the joint requires a perfect fit between the ends ot
Netherlands, Switzerland and later Brazil and New adjacent segments. This is achieved by casting each
1
\
St. Joseph River Benton Harbor, Michigan 408 98. 212,98 1 box 48-6% wide
l-205 Columbia River Bridge Oregon - Washington 10,000 620 max. multiple boxes
143total width
1 ft. = 0.3048 m
11
CHAPTER 2
CONSIDERATIONS FOR SEGMENT DESIGN
2.1 General
Much of the economy of precast segmental
bridges results from the standardization and indus-
trialization of the process of manufacturing the
segments. When design details permit repetition of
daily actions, one segment per day can be manufac-
tured from each form by a comparatively small
crew. To achieve this rate of production, it is im-
portant to avoid changes in the forms, to standard-
1 I1 I
Fig. 2.1 - Segment dimensions
ize the cage of mild steel reinforcement, and to use
a repetitive layout of the post-tensioning tendons.
. It is always necessary to thicken the bottom slab of w w
io-i -.o-
the segments near the pier. However, even this
minor variation in the details of the segments may
disturb somewhat the normal schedule of segment
production.
/ CAST-IN-PLACE JOINT
2.2 Principal Dimensions of Segments Fig. 2.2 - Superstructure with parallel segments and
cast-in-place joint
The principal segment dimensions are top slab
width W, construction depth D, width of
bottom slab B, web spacing Is, and segment only 25 percent of the deflection permitted in
length L. These dimensions are shown for a typ- steel structures in the U.S. Span/depth ratios for
ical segment in Fig. 2.1. end spans are usually somewhat lower than for in-
In the most simple case, the segment width W terior spans. The shallower depth structures require
is selected as equal to the width of the bridge. more high strength post-tensioning materials. Var-
When the bridge width exceeds about 40 ft. (12 iable depth structures become appropriate for
m), or when it is necessary to minimize segment spans in excess of 250 to 300 ft. (75 to 90 m). In
weight or size, the structure width can be divided this case, the span/depth ratios have normally been
into a multiple of the segment width as shown in selected as 18 to 20 at support and 40 to 50 at
Fig. 2.2. In this case, the transverse connection of midspan.
the top slabs may be accomplished by transverse When webs are vertical, the bottom slab width
post-tensioning which extends through all the B follows from the width W and the struc-
boxes and the cast-in-place joint(s). turally acceptable length of the cantilever as dis-
As an alternative to use of multiple boxes for cussed below. Sloping webs present no problem
structures wider than about 40 ft. (12 m), single when the box girder depth is constant, but do
boxes with multiple webs have been used for require significant form adjustments for produc-
widths up to about 70 ft. (21, m). For intermediate tion of variable depth segments due to the varia-
widths, single box sections may be used with inte- tion in bottom slab width. A narrow bottom slab
gral transverse floor beams under the roadway is desirable to reduce segment weight since the
slab (e.g., St-Andre de Cubzac Viaducts) or boxed bottom slab area is usually a factor for structural
cantilevers (e.g., Chillon Viaduct). These alterna- consideration only in the negative moment area
tives are illustrated in Fig. 2.3, which in addition, adjacent to piers.
shows the evolution of segment size and weight The segment length L has a pronounced effect
for a number of European bridges. on the economy of a bridge. The selection of the
The construction depth D is determined by segment length determines the total number of
the spans. Most European bridges have been built segments that must be produced and erected. Since
with span/depth ratios of 18 to 20. However, ratios the majority of the cost involved in production and
of 20 to 30 are considered feasible and structurally erection is fixed per unit and only a small share of
satisfactory. Deflection tests on the model of the the cost is variable, economy is achieved by using
Corpus Christi Bridge with a span/depth ratio of the smallest number of segments consistent with
25 resulted in a deflection of only L/3200 which is transportation requirements and the capacity of
BRIDGE CROSS SECTION SEGMENT MAXIMUM
AND MAX. SPAN (DIMENSIONS IN METERS) LENGTH SEGMENT WT.
(TONNES)
CHOISY-LE-ROI 2.50M 25
8.20 FT.
180
55MFT.
SEUDRE 3.30M 75
79 M 10.80 FT.
259 FT.
BLOIS 3.50M 75
91M 11.50 FT.
299 FT.
CHILLON 3.20M 80
104M 10.50 FT.
341 FT.
B3 SOUTH 2.50M-3.40M 50
50M 8.20 FT.-l 1.20 FT.
164 FT.
I
SAINT-CLOUD 41e 0 2.25M 130
106M n 7.40 FT.
348 FT. 1
+ 1 t
14
erection equipment. Since the cost of handling and 3. Local bending stresses due to wheel loads
erection increases with L, it is necessary to make applied directly over epoxy joints.
a study of the total in-place economy of various 4. Local anchorage bearing and splitting stresses
segment lengths to determine the most economical
for transverse post-tensioning (when used)
value. When segments must be transported over
require a minimum thickness of about 8% in.
highways, the weight and size limitations usually
(216 mm) for tendon forces ranging from 100
determine the value of L. to 120 kips (445 to 534 kN).
The spacing of webs s is normally determined
purely on structural criteria. In principle, any web In addition to the above structural considera-
spacing can be utilized if all pertinent structural tions, the top slab thickness must be adequate to
aspects are thoroughly investigated using, if necess- accommodate four layers of transverse and longitu-
more sophisticated structural dinal mild steel reinforcement, transverse and
ary, analysis
techniques. The need for such analysis is greatly longitudinal tendons, and minimum concrete cover
reduced when the web spacing is selected in such a of 2 in. (51 mm) on top and 1 in. (25 mm) on the
way that the ordinary beam theory can be applied bottom.
for longitudinal moments. The beam theory may The dimensions of haunches b, c and d
be used when the depth of the section is equal to in Fig. 2.1 are determined by the transverse bend-
or greater than l/30 of the span, and when the ing moments and by the space required for the
width W divided by the number of webs is not anchorages of the longitudinal post-tensioning
more than 7% percent of the span length. For sec- tendons (see Figs. 2.10 and 2.12). It is normally
tions such as shown in Figs. 2.1 and 2.2 the slab necessary to accommodate at least two layers of
cantilever C is about one-fourth WI. For box longitudinal tendons. A concrete depth of 14 in.
sections with more than two webs the slab canti- (356 mm) is required at anchorages of longitudi-
lever dimension should be selected to provide rea- nal strand tendons. A depth of 10 in. (254 mm)
sonable balance between cantilever and interior may suffice for bar tendons. Although it is
transverse moments. Use of these criteria for deter- essential to provide adequate space in the top slab
mining the number and spacing of webs also results and haunch thicknesses for the above considera-
in reasonable requirements for the depth of the top tions, it should also be kept in mind that the top
slab and the amount of transverse top slab rein- slab is the heaviest part of the box girder, and from
forcement. this standpoint it is desirable to keep those dimen-
Segment dimensions used on U.S. and Canadian sions as small as practical.
precast segmental bridges now completed or in The web thickness e is generally 14 in. (356
advanced stages of design are presented in Appen- mm) or more to provide room for the anchorage
dix Section A.2. hardware of 12-strand tendons which are a fre-
quently used tendon size. Minimum anchorage space
requirements for bar tendons is about 10 in. (254
mm). The 14 in. (356 mm) width may also be de-
sirable or necessary to accommodate the bursting
2.3 Detail Dimensions of Segments and splitting force from anchorages for 12.strand
The concrete dimensions of top slab, webs, bot- tendons. This thickness may be reduced when ten-
tom slab and haunches are determined by structur- dons are anchored in ribs or anchor blocks. Thick-
al considerations and by numerous practical factors nesses as small as 8 in. (203 mm) have been used
related to production of the segments. with strand tendons when webs were vertically pre-
The top slab thickness (a in Fig. 2.1) usually stressed. When shear forces near supports are re-
ranges from 7 to 10 in. (175 to 250 mm). It is duced by upward shear from the post-tensioning
necessary to consider the following structural tendons and segment depth is within the limits
described in Section 2.2., the shear stress require-
factors in selecting the top slab thickness:
ments for highway bridges are generally met when
1. Bending moments in the transverse direction the total width of webs amounts to 7 or 8 percent
caused by slab dead load, permanent loads of the bridge width. The principal tensile stresses
and live load. resulting from combination of vertical shear stresses
2. Compression zone requirements for longitu- and compressive stresses reach a maximum value at
dinal bending moments normally need be con- the intersection of the top slab and the web. Efforts
sidered in determining top slab thickness only should be made to keep these principal stresses
in structures with spans of 350 ft. (110 m) within allowable limits [see AASHTO Bridge
or more. Specifications,@ @@ion 1.6.6. (B)] , and to avoid
the use of additional reinforcement for this limits. The bottom slab thickening for this purpose
purpose. This requires the widening of the webs should be reduced to the minimum thickness re-
f as shown in Fig. 2.1. quired in the shortest distance possible to facili-
The web is a stiff element in the box section and tate manufacturing of the segments.
provides substantial moment restraint to the top The dimensions of the bottom slab haunches
slab, and consequently transverse moments at the (h and i in Fig. 2.1) have a major structural
junction of the web and top slab are high. In- task in the longitudinal negative moment area of
creased concrete thickness, obtained by widening transferring the change of force in the bottom slab
to the web f as shown in Fig. 2.1, reduces the to the webs. This function is illustrated in Fig. 2.4.
amount of reinforcement required. Particular The force differential AF is transferred by longitu-
attention should be given to lapping of reinforce- dinal shear, and is the highest in the negative
ment in this area to avoid discontinuity in areas of moment area. The bottom slab haunches also assist
high moment. in transmitting transverse bending moments
A different situation exists in positive and nega- between the bottom slab and the webs, and reduce
tive moment areas relative to the required bottom the amount of reinforcement required for this
slab thickness g. The structural significance of purpose.
the bottom slab in the positive moment area re-
lates only to the bottom slab contribution to the 2.4 Pier and Abutment Segments
section properties. As a result, the bottom slab Pier and abutment superstructure segments
thickness is usually reduced in positive moment differ from typical interior superstructure segments
areas to the minimum required to carry the slab in that they normally require a diaphragm to assist
dead load, and the space required for reinforce- the webs in distributing the high shear forces to
ment and concrete cover. Space for one layer of the bearings. As illustrated in Fig. 2.5, vertical and
tendons, mild steel reinforcement, and concrete transverse post-tensioning can be used to transfer
cover require a minimum bottom slab thickness of
the shear from the webs through the diaphragm to
about 7 in. (178 mm). In the negative moment
the bearings. The amount of post-tensioning
area, the bottom slab thickness is controlled by
utilized for this purpose is a function of the shear
high compressive stresses. Thickening of the bot-
forces in the webs. In addition to the post-tension-
tom slab near piers is nearly always required to
ing tendons, the pier and abutment segment dia-
keep the compressive stresses within the allowable
phragms are normally heavily reinforced with non-
prestressed reinforcement. The tendons extending
across the diaphragm in Fig. 2.5 must be tied into
F = total compressive the diaphragm with bonded reinforcement to resist
force in half of
bottom slab of
tendon splitting stresses at the corners of the open-
single box girder at ings. Precise analysis of diaphragm stresses requires
Section 1.
use of finite element or other similar analytical
techniques. However, an approximate analysis
based on force resolution is usually sufficient. As
shown in Fig. 2.5, it is essential that an opening be
maintained in both pier and abutment segment
F + AF = corresponding
compressive force at diaphragms sufficiently large to permit movement
Section 2. of men and equipment.
-DIAPHRAGM
BOTTOM SLAB
SECTION
SECTION AT PIER
Fig 2.4 - Longitudinal shear transfer by bottom slab to
web haunches Fig. 2.5 - Pier and abutment segments
16
dons with little interference with the erection
process. When tendons are anchored at the face of
a segment, a scaffold is normally used as shown in
Fig. 2.6 to facilitate installation and stressing of
tendons. With interior ribs, or web stiffeners,
these operations are accomplished from inside the
box. However, segments with interior ribs are
more difficult to manufacture, and selection of
segment details in a particular case requires con-
sideration of all aspects of manufacture, erec-
tion, and installation, stressing and grouting of
the tendons.
Continuity tendons are normally placed and
Fig. 2.6 - Use of scaffold for stressing of tendons stressed after the erection process and after the
closing of the castlin-place joints. Details for an-
erection. The anchorages for permanent longi- chorage of continuity tendons in the top slab over
tudinal tendons to be stressed during erection may the webs are presented in Fig. 2.8. This anchorage
be located either in the webs at the face of the detail has the disadvantage of allowing dirt, water
segment, or in special web stiffeners cast into the and extraneous material to enter the tendon ducts.
segment for the purpose of providing a location This may cause blockages and other problems.
for anchorage of permanent and temporary ten- Details for anchorage of continuity tendons in
dons that does not interfere with the erection the bottom slab are shown in Fig. 2.9. Continuity
process. Fig. 2.6 shows stressing of tendons with tendons may also be anchored in web stiffeners as
anchorages located in the web faces. Fig. 2.7 illustrated in Fig. 2.7. The stressing pockets for
shows details of a segment with an interior stif- anchors in the top slab should be kept as small
fening rib which provides a location for installa- as possible to minimize conflicts with mild steel
tion, stressing and anchorage of longitudinal ten- reinforcement or transverse post-tensioning ten-
(I) J O I N T
(2) W E B K E Y
(3) SLAB KEY FOR ALIGNMENT
(4) POSSIBLE WEB STIFFENER FOR
TENDON ANCHORAGE
(5) HOLES OR INSERTS FOR HANDLING
AND PROVISIONAL ASSEMBLY
(6) LONGITUDINAL DUCTS FOR
PRESTRESSING TENDONS
Fig. 2.7 - Details of segment with web stiffener() HORIZONTAL SECTION C-C
- A N C H O R A G E
SECTION A-A
L- SECTION B-B
/
Fig. 2.8 - Top slab anchorage block-out
a 4 - ##6 Hairpins I
Length 2-6 (0.8 m) - Typical for 12.strand tendon. Reinforcement requirement for other tendon sizes will vary.
#4 = 13 mm dia.
SECTION #6 = 19 mm dia.
4'.4" (VARIES)
(1.3 m)
----
----a
m-B-
----a
B--e
----a
20
PLAN Blockout to be filled
I
1
with mnrrrt+
-_. . . . --. .-.-..
;,;c,A, errin 9of
Bloc Lout heopeng Cut Bar.raftar rtressing
rfor g r o u t i n g \-- , __j /-as requared to fit blockout.
I
. :. .
. -.
Sepment Jt. /
Segment Jt./
SECTION A-A
Blockout in Blockout to be filled
with concrete l ftor
stressing of tendon
SECTION B-B
Fig. 2.10 - Stressing and coupler blockout details - Kishwaukee River Bridge
anchored at the same location at the segment
joints. In developing the tendon layout to comply
with the above requirements, the number of ten-
dons required is the design consideration of most
Importance.
Some practical suggestions relative to location
and detailing of tendon layouts aoae as follows:
1. Tendon spacing must be sufficient to permit
placement and vibration of concrete without
development of voids or honeycomb. A clear
distance of 1% in. (38 mm) is required be-
tween tendons during grouting to minimize
the possibility of grout transmission between
Fig. 2.11 - Temporary steel fittings attached to deck for
anchoring temporary prestressing bars adjacent ducts at the joints between seg-
ments. A typical layout of ducts meeting
In place of permanent vertical post-tensioning those requirements is presented in Fig. 2.12.
between pier segments and piers, post-tensioning 2. The bending radius of the tendons is deter-
may be employed temporarily to provide a mo- mined largely by the duct material. A semi-
ment connection during cantilever erection only. rigid duct of corrugated metal is preferable,
After erection has been completed and the con- and the minimum bending radius of such ducts
tinuity tendons have been placed and stressed, is about 15 ft. (4.6 m). Pre-bending requires
the temporary vertical post-tensioning at piers may an additional operation and complicates
be removed. This permits use of sliding bearings placement of the ducts. Sharp bends are un-
at piers in the finished structure to accommodate desirable from the standpoint of installing
volume changes due to temperature, shrinkage, and tendons, friction losses, and the high concen-
creep. trated forces resulting on the concrete.
3. A free passage of 5 in. (127 mm) minimum
width should be provided between tendons
located over the segment webs for proper
2.5.4 Layout of Post-Tensioning Tendons placement and vibration of concrete.
Unlike design of conventionally reinforced con- 4. Crossing of longitudinal tendons in the nar-
crete structural elements where a quantity of rein- row part of the web should be avoided.
forcement may be the final result of design calcu- 5. Tendon eccentricities should be made as large
lations, a practical tendon layout always requires as possible. Cantilever tendons can be spread
an iterative design process in which the designer laterally into the top slab and a second layer
and the detailer continuously exchange informa- of tendons can be accommodated in the top
tion. In the preliminary design stage, concrete slab haunches as shown in Fig. 2.12. Tendons
sections are assumed and bending moments and anchored in the first few segments remain
shear forces are calculated. Subsequently, an ini- within the web reinforcement because of
tial number and eccentricity of tendons required to bending radius limitations. This results in
counteract the bending stresses is determined along some loss of eccentricity. Midspan conti-
with the number and slope of tendons counter- nuity tendons are placed in the bottom slab.
acting shear forces. The preliminary design is com- 6. Cantilever strand tendons are anchored in
pleted by determination of the required mild the webs and top slab haunches, or on web
steel reinforcement. The preliminary design re- stiffeners. Cantilever bar tendons may be
sults must then be evaluated by the detailer on the anchored in the slab as shown in Fig. 2.10.
drawing board to see whether or not the prelimi- Shear tendons are anchored in webs. Con-
nary design assumptions can be achieved in prac- tinuity tendons are anchored as described in
tice. This is usually not the case on the first try, Section 2.5.2. The anchorage of continuity
and further iterations are then made. Detailing of tendons in the top slab combined with an-
post-tensioning tendons requires consideration of chorage of cantilever tendons in the webs
minimum radius of curvature, spacing require- provides a connection between the two
ments and avoidance of conflicts with mild steel overlapping tendon systems through con-
reinforcement. Further, because of formwork crete compression. In a layout where ten-
limitations, tendons are always located and dons are anchored in top and bottom slabs
the tendon anchors which may become an
important factor near the supports. Pre-
stressed stirrups may also be used to accom-
modate shear forces near supports.
8. Tendon lengths should be made as short as
possible. However, use of very short tendons
requires careful consideration of diffusion
of the prestress into the section and the pre-
stress losses due to seating of the anchorage.
Fig. 2.12 - Tendon spacing and 12-strand tendon anchor- From the structural viewpoint, the tendon
age details in top slab haunches layout may be in accordance with the bend-
ing moment diagram. However, the erection
procedure and the available anchorage loca-
tions usually require substantial adjustments
to the tendon layout resulting solely from
structural moment requirements.
27
With end span length on the order of 65 to 70
percent of the interior spans, a special segment
may be used at the abutment and one or two seg-
ments may be temporarily cantilevered out to
reach .the first balanced cantilever as shown in Fig.
3.3. (b).
When end spans are only 50 percent of the
length of interior spans, as in Fig. 3.3 (c), an up-
lift reaction has to be transferred to the abutment
during construction and in the completed struc-
ture. Abutment details that may be used to accom-
+SDmm plish this are shown in Fig. 3.3 (d). Here, the webs
I
i I
sp~~~&~~~.
1 1
28
the webs to transmit the uplift force and, at the To accommodate large movements and heavy
same time, to allow the deck to expand freely. loads, the use of more expensive pot type bearings
using neoprene to absorb rotation and a teflon
layer to permit volume changes may be appro-
3.2.3 Pier Details priate. Design information on these bearings is
available from suppliers.
Pier details should be developed with consider-
Heavy pier reactions during erection, or tem-
ation given to the need to provide stability to the
porary prestressing of the pier segment to the pier,
cantilevers during construction. Some details that
may require use of temporary bearing pads of steel
have been used to accomplish this are discussed
or concrete. Details of this type are shown in Sec-
and illustrated in Section 4.3.6.
tion 4.3.6 (see Figs. 4.20 and 4.21). The use of
four bearings at piers as shown in Fig. 4.21 sub-
stantially reduces the positive longitudinal live
3.2.4 Horizontal and Vertical Curvature
load moments in the superstructure, as illustrated
As noted in Chapter 1 and elsewhere, precast in Fig. 3.5.
segmental construction is readily adapted to nearly
any horizontal and vertical alignment by adjusting
the segment dimensions during casting. The Bear 3.3 Longitudinal Analysis
River Bridge, shown in Figs. 1.4 and 1 .lO, and the
Saint-Cloud Viaduct in France, shown in Fig. 3.4, 3.3.1 Erection Moments
are examples of bridges on curved alignment.
During erection, the moments over the piers
increase with the addition of each pair of segments,
as illustrated in Fig. 3.6. The additional moment
3.2.5 Bearing Details caused by adding segments No. 8 at each end of
Most European bridges have utilized laminated the cantilever is shown by the shaded area in Fig.
neoprene bearings. However, the European specifi- 3.6. These moments are resisted by post-tension-
cations for design of neoprene bearings are con- ing tendons in the top slab which may be anchored
siderably less restrictive than U.S. specifications. at the face of the segments or in build-outs inside
Fig. 3.5 - Comparison of superstructure live load moments with simple and double pier supports()
the box section. The use of build-outs makes it cast segmental bridges during erection are modi-
possible to place the segments and stress the ten- fied by thechange in statical system due to coupling
dons in two separate operations, but tends to com- cantilevers and the post-tensioning used to connect
plicate the process of manufacturing the segments. the cantilevers into a continuous structure. Subse-
The amount of post-tensioning required to main- quent to casting the closure joint and stressing
tain zero tensile stress in the top slab under the of the continuity tendons, the influence of con-
erection moments (including weight of any erec- crete creep modifies both the cantilever and con-
tion equipment) is readily calculated from the tinuity moments as will be illustrated in the fol-
simple formula: lowing sections.
Creep deformation of concrete is that part of
ME p We)
-=-+- the inelastic deformation not caused by shrinkage.
Zt A Zt Creep deformations occur as a result of the inelas-
tic response of concrete to long term loadings such
where M, = erection moment, in. lb. as dead load, post-tensioning forces, and perma-
Z, = section modulus with respect to nent displacements. Restraint of creep deforma-
top fibers, in.3 tions causes redistribution of moments. This hap-
P = post-tensioning force, lb.
pens, for example, when statical systems are
A = cross sectional area of pier seg-
changed by connecting a cantilever structure into
ment, ins2 a continuous structure. The effect of permanent
e = eccentricity of post-tensioning
deformations by external causes is reduced by
force, in.
creep. This occurs in the case of support settle-
The concrete area in the bottom slab at the pier ments.
must be sufficient to maintain compressive stresses The relationship between creep deformations
to the value allowed by the specifications. The and elastic deformations is linear. The ratio is
stress f,, is calculated as: called the creep factor 6. The following relation-
ship can be expressed for $ :
f,, = !$+;-F
b
31
A graph of (l-e-@t) vs. values of 4 is presented in
Fig. 3.9.
Using the relationships for (II and p:
(l-e+) = qLZ(l-e+t)
M, t qQ2
6 24
(Cl
32
Fig. 3.10 - Moment curves for cantilever system (I), fixed-end system (II), and cantilever system with later construction to
form fixed-end system (I I I)
3.3.2.2 The Effect of Creep on Moments due to Solving this equation as in Section 3.3.2.1:
Support Settlements X, = P (l-e+t)
Fig. 3.11 (a) illustrates a beam fixed at end A
and supported at end B. In Fig. 3.11 (b), the beam
is assumed to settle suddenly at B a distance 6.
The effect of this settlement is an additional mo-
ment at A which can be calculated as:
M = -PR
3El6
where P =-
P3
In Fig. 3.11 (c), the support has been removed at
B and the beam is loaded with a load equal to P.
The deflection resulting from the load P in the
time interval dt increases by 6d@,. In Fig. 3.11
(d), the support is again applied at B and the in-
crease of the deflection 6d@, resulting from the
load P is presumed to be eliminated by upward
displacement caused by an increase in the support
reaction in an amount of X,. The level of support
B does not change between Figs. 3.11 (b) and
3.11 (d). The increase in the support reaction
X, induces both elastic (by dX,) and creep (by
X,d@,) deformations. Since there is no further
deflection after Fig. 3.11 (b), the elastic and creep
deformations due to the reaction X, may be
equated to the creep deformation due to P. This (4 1%
gives the following expression: Fig. 3.11 - The effect of creep on moments due to support
(dX, + Xtd&) = Pd& settlements
33
The support reactions at B vary as follows: $J = 1.0, the value of e-d = 0.368, the final super-
Immediately after settlement the support at B structure moments due to the 1 in. settlement at
carries: R - P support 2 are as shown in Fig. 3.12 (c).
After the creep process, the support carries:
R- P+ P (l-et) = R- Pe$t
In a similar manner, the moments at A due to the 3.3.2.3 The Effect of Creep in Reducing Re-
settlement vary: straint Forces due to Shrinkage
Immediately after settlement: M = -PP
For this analysis, it is assumed that the shrink-
After the creep process: age at infinity, +,, develops with time at the same
M = -PQ + P (l-e-#t)Il rate as the creep factor. This assumption leads to
the equation:
M = -pQe-@t
The ultimate effect of creep on the reaction at
B and moment at A resulting from a support
settlement can be evaluated from the above form-
ulas by considering the value of e-4 for various where E,ht = shrinkage strain at time t
values of 4 as follows:
Esh = shrinkage strain at infinity
6 1 23 4 5 Development of the restraining force due to
e-4 0.368 0.135 0.05 0.018 0.007 0 shrinkage will be illustrated for the beam AB
It can be seen from the above that the effect of a shown in F/g. 3.13 (a) which is fixed against hori-
support settlement is reduced to zero by a large zontal movement at both ends. Due to shrinkage,
the beam shortens by:
value of $J~. As in the case of change in the statical
system, the creep redistributions have the tendency A sht = Esht Q
to approach the distribution belonging to the If the restraint to horizontal movement in the joint
system obtained after the change. at B is temporarily released, the beam would
To illustrate the application of the above, Fig. shorten due to shrinkage. Applying an axial force
3.12 (a) shows a three-span superstructure sub- S, to the beam at B as shown in Fig. 3.13 (b),
jected to a settlement of 1 in. at support 2. Fig. the beam elongates according to:
3.12 (b) shows the moment diagram resulting from
the 1 in. settlement at support 2. For a value of AS,=s,B
EA
t-F--Pi
1 ft. = 0.3048 m
1 k-ft. = 1.356 kN-m
1 k-ft.2 = 0.413 kN-mZ
(cl
f-I-#-
(b)
Fig. 3.12 - Superstructure moments due to support
settlement Fig. 3.13 - Restraint force resulting from shrinkage
34
time interval. This leads to the following expres- where 4 ct ,t,) = magnitude of the creep factor
sion: at time t for a concrete specimen
E,,, ad@,/@ = S,Qd@,fEA+dS,Q/EA loaded at time t,.
Q dm = magnitude of delayed elasticity
-dS,/EA at infinity
-d@,=
(Es,, /G3,/EA) = factor variable from zero to
bd(t--to)
Concrete Composition
Relative Humidity of Stiff Concrete Plastic Concrete Soft Concrete Thickness
Ambient Medium Slump l/2-314 Slump 1-2 Slump 3-6 Factor
(13-19mm) (25-51mm) (76-152mm)
P Cl P Cl P cl x
These factors are represented by PC, in Table 3.1 The variation of #f with time is shown in Fig.
@f- also depends on the theoretical thickness 3.16. The ordinate shows the factor of develop-
hth of the structural element in combination with ment of and the abscissa the time t, in days. In
the relative humidity of the atmosphere. These contrast to delayed elasticity, ed, the time scale
factors are represented by pc2. The value of #f, in Fig. 3.16 begins at the time the concrete is cast.
at infinity is the product of &, and Bc2 : Therefore, the influence of the age at loading, t,,
is obtained from the expression [flf(t)-~rct,b]. The
Of, =I&, x PC2
dependence of the rate of development of @Jr on
The theoretical thickness, hth, is evaluated from: the thickness of the member and the relative hu-
midity of the environment is indicated in Fig.
X2A,
hth = CC 3.16 by the different curves for various theoretical
thicknesses.
where X = theoretical thickness factor, taken As suggested by Fig. 3.7, loading of concrete
from Table 3.1 at an early age greatly increases the final flow fac-
A, = area of concrete section, cm2 tor, #f. In addition to age at loading, an adjustment
I-c = perimeter of concrete section in contact in creep effect calculations may be necessary when
with the atmosphere, cm a rapid hardening cement is used, or when the
After evaluating hth as above, the value of PC2 process of cement hydration is hampered because
can be taken from Fig. 3.15 and the value of of low temperatures. Such corrections may be
@f, can be calculated. made by calculating a theoretical age for the con-
crete by use of the formula:
a ; [T(,., + lo] At
t=
30
where t = theoretical age
a = 1 .O for ASTM cement Types I and I I
Q = 2.0 for ASTM cement Type II I
QI = 3.0 for cement having highly accel-
36
3.3.2.5 Example Creep Factor Calculations
To provide a numerical example of creep factor
calculations, a three-span example bridge will be
assumed which has 44 segments produced at a
rate of one segment per day over a period of nine
weeks. The average concrete thickness is 0.32 m
(12.6 in.). Slump of the concrete was 1% in. /38
mm). A three-week erection period starts four
weeks after production of the last segment. The
structure is made continuous by casting a midspan
splice one week after completion of segment
0.25 erection, and the bridge is erected over water.
The creep factor to be used for the moment
redistribution calculations is obtained as follows:
0
0 10 loo 1000 8000
Time t, days 1 cm = 0.39 in.
37
*
Section 3.3.2.1 are applied to actual bridge exam- Moment Calculations
erection and infinity, the bending moments in the Fig. 3.17 (b) - Effect of creep on dead load moments -
structure will be between the values calculated in Example 1
Steps 1 and 5.
Comparing the examples in Figs. 3.17,3.18, and
3.19 it is seen that the final dead load bending Construction Procedure
moments in the structure depend on the order in Structure weighs 5k/lin.
which the joints are closed in the structure. In ft. (73 kN/mj
a Step 1. - Erect cantilev-
these same figures, it is seen that the magnitude of ers over sup-
the moment redistribution due to creep also de- ports C and E.
F-G on false-
k. P P work,close j o i n t s
B and F and re- Figs. 3.20 and 3.21 illustrate that the effect of
move falsework creep on the moments resulting from continuity
i P P
Step 3. Concrete splice
at D post-tensioning depends on the construction se-
Fig. 3.17 (a) - Effect of creep on dead load moments - quence and the order in which the tendons are
Example 1 stressed.
I
38
Moment Calculations Moment Calculations
%4&f+-
obtained from dia-
grams 3 and 6 MF = -178 k-ft.
M = -12250-
M =+1471+ 48% = -12;736
O.! (2525) = 2228 k-ft.
1 k-ft. = 1.356 kNm k-ft. hlkf = +1429 k-ft.
MC = -12597 +
Elastic bending
2525 = -10072
moment distribu-
k-ft.
MD = -347 + 2525 tion continuous
= +2178 k-ft. bridge.
Difference be-
tween diagrams 5
Fig. 3.18 (b) - Effect of creep on dead load moments - and 6.
Example 2 Creep bending
moments, ob-
tained by multi-
plication of dia-
gram 7 with factor
Construction Procedure (1 -e@) (here
chosen to be 0.5)
Structure weighs 5kllin.
Dead load bending
ft. (73 kN/m)
moments at infin-
Step 1 - Erect cantilever ity obtained by
over support C. addition of dia-
Step 2 - Erect tailspan grams 5 and 8.
segment be-
AGC D E F G HI tween A and B Fig. 3.19 (b) - Effect of creep on dead load moments -
on falsework. Example 3
L
, 100li P, ll
4.0 P, n
1.0 P, ,g - concrete joint
at B Construction Procedure
r.,. - remove false-
work Prestressing force
. . ,.;.. .:. Step 3 - Erect cantilever F,=F2=1000k=F
P
over support E M = Fe assumed not to
A G C D
: : 1 - concrete joint rr*&mn II. rEWDOY F,- IL*DOW F, g vary with time
at D Eccentricity e = 3-0
1 Step 4 - Erect cantilever f (0.9 m)
h P P P 100
over support G. - Step 1 - Both halves of
: -concrete joint the structure
A1 at F.
100 ft. = 30.5 m erected
Step 5 - Erect tailspan
segment be-
tween H and I is stressed
1 k=4.448kN
on falsework
Step 2 - Midspan joint at
-concrete joint
C is concreted
at H. - midspan conti-
- remove false-
nuity prestress
work.
is stressed.
Fig. 3.19 (a) - Effect of creep on dead load moments - Fig. 3.20 (a) - Effect of creep on moments due to conti-
Example 3 nuity post-tensioning - Example 1
39
Moment Calculations Moment Calculations
Construction procedure
TENDON F,- TENOOH F>-
1 1 Prestressing force = F
d r I I d
(for simplicity assumed
10 ,70 30
100 I.0 100 constant over length and
Construction Procedure time)
100 ft. = 30.5 m Eccentricity = e
Prestressing force F, =
F2 = F
Eccentricity = e
M = Fe assumed not to
A a C D E F G vary with time
ISNDON F,.
Step 1 - Erect cantilever
over supports C
and E
I 1
P P - concrete mid- -2- Elastic distribu-
span joint at D ,o.m P. 0.335F. tion of bending
- stress contin- 2-F /i moments by pre-
k n i I
uity tendon Fg. stress if stressed in
o.*wJ 5%
Step 2 - Erect segments continuous bridge.
in tailspan be-
tween A and B
(F and G)
- stress continuity
tendons F t .
-4- Creep bending
moments due to
Fig. 3.21 (a) - Effect of creep on moments due to conti- cantilever prestress
o.ss0r.
nuity post-tensioning - Example 2 I obtained by multi-
I plication of dia-
l I gram 3 with factor
(l-e+), taken as
0.5.
40
3.3.3 Analysis for Superimposed Dead Load The longitudinal effects of temperature cause
and Live Load the total structure length to increase or decrease,
The main loadings on a precast segmental box and where there is a temperature difference be-
girder bridge, the dead load of the box girder tween the top slab and the remainder of the box
superstructure and the prestressing force exerted section, longitudinal bending moments and shears
by the post-tensioning tendons, were discussed in result. The change in overall length of structure
Section 3.3.2 with major emphasis given to mo- may be accommodated by expansion joints, ex-
ment redistribution resulting from creep. After pansion bearing details, and/or flexure of piers.
the structure has been erected and completely The effects of a temperature differential between
post-tensioned, the response of the superstructure top and bottom slabs is illustrated for simple span
to additional superimposed dead load and to live and continuous bridges.
load is considered in the same manner as for any For consideration of longitudinal temperature
continuous bridge. The response of the structure differential effects on a simply supported box
to these loads is elastic. The superimposed dead girder bridge, Fig. 3.23 (a) shows a structure where
load is subject to additional creep deformation, but the top slab temperature is increased At degrees
this deformation does not cause significant re- with respect to the bottom of the section. The
distribution of moments. normal expansion of the top slab is restrained
Consideration of the effects of live load on the by the webs and the remainder of the box sec-
transverse design moments and the use of trans- tion. For purposes of analysis, the deformation
verse post-tensioning in deck slabs is considered in of the box section may be considered to be pre-
Sections 3.4 and 3.5, respectively. vented by exerting external forces P at the centroid
of the top slab level as shown in Fig. 3.23 (a).
Concrete stresses in the top slab will be:
41
r
-t
f, = E&t
where E = modulus of elasticity of concrete
(Y = linear coefficient of
thermal expansion
p\p
(4)
+
-
-
(4
Fig. 3.23 - Analysis for temperature differential between top and bottom slabs
42
where: 2. The restraint moments M,, shown in Fig. 3.25
+ = tension (cl, required to rejoin the ends of the girders
- = compression over the supports are calculated.
6 = total area of section 3. The total temperature effects on the continuous
I = moment of inertia of section structure are obtained by adding the moments
Applying these equations to the cross section and stresses resulting from the calculations in 1
and section properties in Fig. 3.24 for a top slab and 2 above.
temperature increase of 18 F (10 C), with OL =
5.5 x 1 O6 in./in./OF (9.9 x lo6 m/m/C), and E =
4 x lo6 psi (27.6 x lo3 MPa) [SO00 psi (34.5
MPa) concrete], the stresses become:
f Cl = - 4000 x 5.5 x 1 O6 x 18 = -0.396 ksi I!,
(b)
(-2.73 MPa)
f c 2 = +0.396 x 1929.6/3614.4 = + 0.211 ksi
(+ 1.46 MPa)
fc3t= +0.396 x 1929.6 (18.5 - 4) x 18.5/
1142 x lo3 = + 0.180 ksi (+ 1.24 MPa)
MY UM,U
f c3b = -0.396 x 1929.6 (18.5 - 4) (48 - Fig. 3.25 - Procedure for analysis of a three span structure
for temperature differential stresses
18.5)/1142 x lo3 =-0.286 ksi
(-1.97 MPa)
Total top fiber stress: -0.396 + 0.211 + 0.180 = The calculation procedure for continuous super-
-0.005 ksi (-0.035 MPa) structures described above in general terms is ap-
Total bottom fiber stress: 0.211 - 0.286 = -0.075 plied in the following to the continuous bridge
ksi (-0.518 MPa) with five equal spans shown in Fig. 3.26 (a).
Proceeding with the first step in the analysis,
the superstructure is considered to be cut over
each support, and a constant equivalent thermal
moment, M, is applied over the full length of all
girders as shown in Fig. 3.26 (b). M causes equal
1 ft. = 0.3048 m
rotations at each girder and over the supports. In
1 in. = 25.4 mm order to rotate the girders back to the same slopes
at the supports, bending moments MI and M2
Fig. 3.24 - Superstructure cross section assumed for tem-
perature differential analysis must be applied resulting in the moment diagram
shown in Fig. 3.26 (c). The total slope at support
2 resulting from the constant temperature moment
From these calculations it is seen that a tempera-
M acting on simple spans l-2 and 2-3 may be cal-
ture increase in the top slab with respect to the re-
culated using moment-area or slope-deflection
mainder of the cross section causes very small
compressive stresses when the superstructure is techniques as:
simply supported. MP MQ MP
In the case of continuous superstructures, re- slope= -+-=-
2EI 2EI El
sistance to the rotation at the supports resulting
from temperature differentials between top and
By the same procedure, the slope due to MI and
bottom slabs generates additional moments and
M2 at support 2 is:
flexural stresses. For the three span structure
shown in Fig. 3.25 (a), the procedure for calcula-
M,n M,Q2M,11 M,a M,Q
tion of temperature moments and stresses is as - -
follows: 3EI +3EI+-=
6EI 3EI + 6EI
1. The continuous superstructure is considered to
be cut over the supports into three simply sup- Setting the slope due to the temperature moment
ported spans as illustrated in Fig. 3.25 lb). equal to the slope resulting from M, and M2
The temperature stresses and rotations at sup- provides the following:
ports can then be calculated for equivalent
thermal force and moment as for simple span 2M,Q M211 MI1
bridges as described above. zl+zEi-=El
43
L
shrinkage permitted by the specifications. Further,
A A A A I (a) the stress is less than 50 percent of the modulus
1 2 3 4 5 6 of rupture of the concrete so temperature stresses
would not be expected to cause cracking in the
superstructure.
The moments M, and M2 cause a change in sup-
, port reactions. For the above example the change
in reactions at supports 1, 2, and 3 will be respec-
I (b) tively +24M/1911, -3OM/19Q, and +6M/19P.
For spans 1, 2, and 3, respectively, and for II =
80 ft. (24.4 m) and M = P(c, - e) = E c@t (c, -
e) = 4 x lo6 x 144/1000x 5.5 x 10m6 x 18 x 13.4 x
(1.54 - 0.33) = 924 ft. kips (1253 kN-m). The
changes in support reactions are: +14.6 kips,
A A A A A
1 2 3 4 5 6 -18.2 kips, and +3.6 kips (+65.0, -80.9, +16.0
kN). The weight of the girder is 3.75 kips/ft.
(4 (54.7 kN/m) which provides dead load reactions
at supports 1, 2, and 3 of 119 kips, 339 kips, and
292 kips (525, 1503, 1294 kN). Therefore, the
change in dead load reactions due to the tempera-
Fig. 3.26 - Moments in a five-span continuous superstruc-
ture due to temperature differentials. ture differential is, for this structure, on the order
of 12 percent for the exterior support and 1.2 to
5.4 percent for interior supports.
M,Q + -=
5M$? -
MI1
6EI 6EI El
0.4
Solving these two equations simultaneously for MI
and M2 gives: (4
M, =gM
EM
Mz=,~
The total bending moment diagram is, therefore,
the sum of the diagrams in Figs. 3.27 (a) and 3.27
(b), as shown in Fig. 3.27 (c). The stresses due to
this moment diagram and the axial forces due to
+o 196
the temperature differential are calculated as fol-
lows for span 3-4: Fig. 3.27 - Moments and stresses in a five-span continuous
superstructure due to a temperature differential of 18OF
f,, = - 0.396 ksi (-2.73 MPa) (IOOC) between top and bottom slabs
f,, = +0.211 ksi (+1.46 MPa)
feat= +1/19 x 0.180 = +O.OlO ksi (+0.07
MPa)
f c3b =- l/19 x 0.286 = -0.015 ksi (-0.10 3.3.5 Shear Lag
MPa)
3.3.5.1 Computer Analysis of Shear Lag in Single-
The combined stresses for span 3-4 are shown in
Cell Box Girder Bridges
Fig. 3.27 (d). The compressive stress of 0.07 ksi
(0.52 MPa) calculated for the simple span case, Computer analyses of four single celled box
becomes a tensile stress of 0.195 ksi (1.35 MPa) girder bridges shown in Fig. 3.28 were performed
in the continuous case. While this is a significant to provide data on the magnitude of shear lag
stress, the magnitude is much less than the 25 to effects. The computer model assumed rigid dia-
40 percent stress increase for temperature and phragms at the pier and at abutments. The cross
44
STRUCTURE DEPTH D (1, SPAN L if,!
A 150
:: 150
E 150
0 100 ::
45
xb=Bottom Slab
Table 3.2 Summary of results for longitudinal force ratios for structures A and B
Structure A Structure B
L = 150 ft. D = 7.5 ft. L = 150 ft. D = 5.0 ft.
Dist. X Ratio of N, Ratio of N,
from MUPDI 3/Beam Analysis MUPDI 3/Beam Analysis
Load Support
Case Ft. Remark a b C d a b C d
1 56.25 MAX+M 1.04 1.05 1.04 1.06 1.04 1.07 1.04 1.06
75 MIDSPAN 1.04 1.07 1.05 1.07 '1.04 1.07 1.05 1.07
Dead 144 1.07 1.08 1.07 1.08 1.08 1.11 1.09 1.10
Load 146 1.11 1.12 1.11 1.10 1.13 1.16 1.13 1.15
148 1.33 1.32 1.37 1.34 1.35 1.37 1.40 1.39
150 MAX-M 1.41 1.44 1.51 1.50 1.44 1.46 1.52 1.50
2 75 MIDSPAN 0.84 1.02 0.78 1.02 0.92 1.02 0.91 1.02
135 1.02 2.14 1.03 2.11 1.01 0.61 1.02 0.59
Pre- 144 1.07 1.51 1.03 1.55 1.06 3.46 1.06 3.63
Stress 146 1.05 1.49 1.06 1.54 1.05 3.00 1.06 3.00
148 1.07 1.42 1.09 1.45 1.06 2.36 1.08 2.39
150 MAX-M 1.09 1.37 1.12 1.41 1.07 1.96 1.10 2.07
3 75 MIDSPAN 1.20 1.17 1.17 1.17 1.12 1.13 1.11 1.13
87 PT.LOAD 1.33 1.38 1.47 1.40 1.33 1.33 1.36 1.35
2 Lanes 144 1.25 1.28 1.26 1.28 1.23 1.25 1.26 1.25
LL+l 146 1.35 1.32 1.32 1.28 1.32 1.33 1.32 1.31
for 148 1.58 1.49 1.63 1.63 1.63 1.58 1.70 1.61
-M 150 MAX-M 1.75 1.69 1.91 1.80 1.81 1.66 1.91 1.74
4 60 PT.LOAD 1.12 1.21 1.21 1.22 1.15 1.18 1.20 1.18
75 MIDSPAN 1.07 1.07 1.08 1.09 1.04 1.07 1.05 1.07
2 Lanes 144 1.14 1.17 1.08 1.20 1.18 1.26 1.22 1.21
LL+1 146 1.25 1.31 1.23 1.31 1.33 1.32 1.35 1.29
for 148 1.56 1.60 1.60 1.26 1.64 1.60 1.09 1.19
+M 150 MAX-M 1.70 1.65 1.76 1.81 1.75 1.68 1.78 1.77
5 75 MIDSPAN 1.10 1.06 1.09 1.07 1.03 1.07 1.04 1.07
87 PT.LOAD 1.11 1.13 1.20 1.13 1.13 1.13 1.14 1.13
4 Lanes 144 1.09 1.07 1.07 1.08 1.10 1.09 1.10 1.10
LL+I 146 1.15 1.11 1.13 1.08 1.14 1.16 1.14 1.14
for 148 1.29 1.32 1.31 1.35 1.35 1.36 1.39 1.37
-M 150 MAX-M 1.40 1.43 1.50 1.48 1.45 1.44 1.52 1.47
6 60 PT.LOAD 1.00 1.07 1.07 1.08 1.04 1.07 1.08 1.07
75 MIDSPAN 1.03 1.02 1.04 1.03 1.00 1.03 1.00 1.04
4 Lanes 144 1 .oo 1 .oo 0.96 1.03 1.05 1.13 1.08 1.08
LL+I 146 1.06 1.12 1.08 1.13 1.17 1.16 1.18 1.13
for 148 1.28 1.37 1.30 1.37 1.36 1.38 1.39 1.42
+M 150 MAX-M 1.35 1.41 1.41 1.50 1.41 1.46 1.43 1.50
1 ft.= 0.3048m
46
~b=Bot+om Slab
Table 3.3 Summary of results for longitudinal force ratios for structures C and D
Structure C Structure D
L=300ft.D=15ft. L=3OOft.D=lOft.
1 112.5 MAX+M 0.99 1.01 1.00 1.02 0.99 1.01 0.99 1.01
150 MIDSPAN 0.99 1.02 0.99 1.02 0.99 1.01 1 .oo 1.01
Dead 294 1.02 1.02 1.02 1.02 1.04 1.04 1.04 1.04
Load 296 1.08 1.12 1.11 1.13 1.10 1.13 1.12 1.13
298 MAX-M 1.13 1.19 1.17 1.22 1.14 1.20 1.18 1.21
300 1.13 1.20 1.18 1.23 1.13 1.20 1.17 1.21
2 150 MIDSPAN 0.85 1.00 0.77 1.01 0.96 1.00 0.95 1.00
270 0.99 1.09 0.99 1.11 0.99 1.33 0.99 1.27
Pre- 294 1 .oo 1.08 1.00 1.09 1.00 1.22 1.00 1.23
Stress 296 1.00 1.10 1.01 1.10 1 .oo 1.17 1.01 1.18
298 1.02 1.11 1.03 1.10 1.01 1.12 1.03 1.13
300 MAX-M 1.02 1.11 1.04 1.09 1.01 1.10 1.03 1.09
3 150 MIDSPAN 1 .oo 1.04 1 .oo 1.03 1.00 1.02 1.03 1.00
174 PT.LOAD 1.08 1.10 1.09 1.12 1.05 1.11 1.09 1.09
2 Lanes 294 1.12 1.11 1.14 1.11 1.09 1.12 1.10 1.11
LL+I 296 1.22 1.22 1.24 1.25 1.18 1.17 1.19 1.19
for 298 1.29 1.30 1.34 1.32 1.26 1.22 1.29 1.25
-M 300 MAX-M 1.17 1.31 1.38 1.37 1.25 1.21 1.29 1.23
4 120 PT.LOAD 1.04 1.05 1.11 1.04 1.02 1.04 1.05 1.04
150 MIDSPAN 1 .oo 1 .oo 1 .oo 1.02 1.00 1.02 1.00 1.00
2 Lanes 294 1.08 1.10 1.10 1.08 1.11 1.09 1.09 1.09
LL+I 296 1.15 1.24 1.18 1.27 1.20 1.17 1.20 1.18
for 298 1.21 1.32 1.30 1.36 1.27 1.21 1.27 1.23
+M 300 MAX-M 1.29 1.29 1.39 1.33 1.26 1.20 1.32 1.26
5 150 MIDSPAN 1.00 1.02 0.98 1.02 1.00 1.01 1.01 1.00
174 PT.LOAD 1.00 1.02 1.00 1.04 1.00 1.04 1.01 1.03
4 Lanes 294 1.04 1.02 1.05 1.02 1.02 1.05 1.04 1.04
LL+I 296 1.09 1.12 1.12 1.13 1.08 1.10 1.09 1.11
for 298 1.14 1.19 1.18 1.19 1.13 1.13 1.15 1.16
-M 300 MAX-M 1.07 1.21 1.20 1.23 , 1.11 1.12 1.14 1.14
6 120 PT.LOAD 1.00 1.01 1.04 1.00 1 .oo 1.01 1.01 1.00
150 MIDSPAN 1.00 1.00 0.99 1.01 0.99 1.02 0.99 1.00
L
4 Lanes 294 1 .oo 1.03 1.03 1.00 1.05 1.03 1.03 1.03
LL+I 296 1.04 1.14 1.07 1.15 1.10 1.10 1.10 1.10
for 298 1.07 1.20 1.15 1.23 1.14 1.13 1.15 1.15
+M 300 MAX-M 1.14 1.19 1.22 1.20 1.13 1.13 1.17 1.16
1 ft. = 0.3048m
47
seen that the latter are considerably lower indi-
cating that an increase in span results in a de-
crease in force ratio. This is logical since it is
generally recognized that shear lag is inverse-
ly proportional to the span length to plate
width ratio.
48
eters chosen for the computer analyses were in-
tentionally selected to provide an upper bound to
the magnitude of the shear lag effect that could
be expected in a bridge. The shear lag effect from
the prestressing counteracts the shear lag due to
dead load and live load. In this regard, the model
3 985
used in the above computer analysis, which con-
siders the bridge post-tensioned by continuous ten-
Fig. 3.34 - Ultimate moment curves vs. capacity for a three-span segment of a precast segmental bridgeC2)
50
(4
U.4
+RI
t 7
Fig. 3.36 - Non-symmetrical loading and reaction assumption for transverse analysis
51
3.4 Transverse Analysis 0 t
3.4.1 General
Transverse moments, shear and axial forces in
box girders are analyzed taking into consideration A
I B
the longitudinal geometry, torsional properties,
4
and transverse geometry of the box girder. Inter-
P P
mediate diaphrams are generally not required, and
the design method presented in the following sec- -47
Id
tions does not include consideration of them.
3.4.2 Principles
In Fig. 3.35 (a), loading 2P per unit length is
assumed to be constant over the length of a simply
supported box girder with section ABCD. Con-
sider the corners of the box girder supported as
shown in Fig. 3.35 (b). The analysis reduces then
to simple case of a frame. This analysis is carried
out and transverse moments, shear and axial
forces are calculated. Also the support reactions
R,, Ra, Ra, and R4 are evaluated.
Non-symmetrical loading as indicated in Fig.
3.36 (a) would cause bearing forces or support
reactions as shown : fb)
R, > R, and R4 = -Rg Fig. 3.37 - Transverse analysis for symmetrical loading
52
W
(bl
(Cl
Substituting the value of 7 from above: Since the box girder is relatively stiff in the
transverse direction, the response of the structure
Tr, = T3f - Pb2dz
21 to upward and downward forces -P and +P is to
balance transversely. This results in transverse
The transverse axial force diagram caused by cen- moments M, and horizontal and vertical shear
tral loading of 2P is as indicated in Fig. 3.38 (4. forces S,., and S, as shown in Fig. 3.39 (b). There
The shortening or elongation of the individual are also horizontal and vertical displacements h
members due to axial loads sets up transverse mo- and v.
ments which can usually be neglected. These displacements h and v cannot occur with-
out the resistance of the top slab and bottom slab
(h) and webs (v) in the longitudinal direction.
Deflection v of web AD will cause longitudinal
3.4.4 Antisymmetrical Loading
bending stresses, compression -T at D and tension
Antisymmetrical loading of the box girder as +T at A. Because of compatability of strains,
shown in Fig. 3.39 (a) affects the structure in the equal stresses +T occur in the top slab CD due to
following ways: horizontal displacement h as shown in Fig. 3.39
1. In the transverse direction, transverse bending (c). This illustrates that, as a result of transverse
and torsional shear are induced. deformations, bending moments and shear forces
2. In the longitudinal direction, moments and are set up in the longitudinal direction of the box
shear forces are set up acting in the planes girder. The longitudinal forces act in the planes of
of the bottom slab and top slab. the slabs and webs and, as a result, part of the ex-
53
3.4.5 Evaluation of the Contributions of Trans-
tI
calculated as follows:
Mt
to zTd=-
2VH
t, = t,V
fh = t, H
where t, = torsional unit shear force
= torsional shear stress
M: = torsional moment per unit length of
box girder
t, and t,, = rate of change of torsional shear
force in the web and slab, respec- Fig. 3.41 - Equilibrium of horizontal and vertical forces
under antisymmetrical loading
tively.
54
The relations of S, and S,, and t, and tIh fol-
low from the geometry of the box girder:
S;
--Z S;=M,
f)-
fh t,
-z-z to
H V
IO t/m
tim
INote: 10 tonnes 0
force in the c.g.1.
mctnc wonl =
170 =p 9.8 x ,w Nmtcml
f!q 1 an tbs SI sysom. Thir
looom analyar II I the
_ 570 c.g.*. syrtsml
d = web thickness Fig. 3.43 - Example transverse analysis box girder section
d, = slab thickness
P = rotation of corner
L = unit length
L = span length V tc
EdV3 Ed, H3
v=crT,L4 12 and h = OLT,, L4 -
/ I 12
- 3 . 4 2
4 +
P
1
892 (cl Support Forces, t/m 1.08
f
Fig. 3.45 - Moments, axial forces, and support forces for example transverse analysis
FE l-T-[ + p-j +
1m2 1 ID8 I5 15 L LB2
f
Substituting these values of h and v in the above 3.92 - 0.95 = 2.97 t/m (2010 Ib./ft.)
equation: at bottom
1
check: 2.97 - 0.95 = 2.02 = t, + T,
S x 1.72
= 1.99 + 0.03
o.33 =
5
384
x
404 -
12 x T, 12 x T,
o.3x5.73x1 .7 +0.3x5.7x1.73 1
S = 177.17[$ +G]
= 5.45 T, + 61.3 T,
1 t/m = 0.678 k/ft.
From vertical equilibrium:
Fig. 3.47 - Transverse axial forces for example transverse
3.92 = t, + T, + 2 S, analysis, t/m
57
2.581
227
58
.
59
Mid span Support
cross-section cross-section
- 7.78
1 ft. = 0.3048 m
1 in. = 25.4 mm
1 ft.-k/ft. = 0.45 t-m/m
Transverse bending moment in ft-kips/ft
1 psi = 0.0069 MPa
for temperature difference T, - Ti = 27F (15C)
Corresponding Point 1 1 2 2
Edge Stresses Span 5564 *220 +485 + 68
(psi) Support ?483 f 84 +446 +446
Fig. 3.51 - Transverse moments and stresses due to a temperature difference of 27OF between the outer and inner surfaces of a
box girder()
60
3 A high level of assurance is provided against t o see if the combined prestressed and nonpre-
the development of longitudinal cracking in stressed reinforcement in the transverse direction
the deck slab. This provides a more durable is sufficient to meet the load factor requirements.
deck with minimal potential maintenance If not, the amount of either the prestressed or
costs. nonprestressed reinforcement should be increased
as required.
4 In the area of top slab anchorages, such as
Tendon profiles for transverse deck slab rein-
illustrated in Fig. 2.8, transverse compres-
forcement may vary depending on the type of ten-
sion is helpful in counteracting tensile stresses
don material and on other design and construction
in the slab which result from concentrated
requirements. Tendon geometry used for the Kish-
anchorage forces.
waukee River Bridge is shown in Figs. 3.52 and
5 For wide segments, the use of transverse 3.53. Fig. 3.52 illustrates the use of bar tendons,
post-tensioning in the deck slabs usually and Fig. 3.53 the geometry proposed in the design
results in reduced overall structure cost. drawings. The placement of the bar tendons in
the center of the slab was selected in this case to
Transversely post-tensioned deck slabs also nor- provide a means of support for the longitudinal
mally have transverse and longitudinal nonpre- tendons. While this increased the required amount
stressed reinforcement in the top and bottom of of transverse post-tensioning by about 30 percent,
the slab. This contributes to the flexural capacity this increase in cost was offset by reduction in
of the slab in ultimate strength calculations and labor requirements for placement of the longitud-
provides the necessary flexural capacity to permit inal tendons. The tendon profile shown in Fig.
removal of the section from the forms and handl- 3.53 was selected to more closely approximate
ing prior to stressing of the transverse tendons. the moment diagram.
The transverse post-tensioning is proportioned to One additional factor that must be considered
limit the tensile stresses in the deck slabs to the when transverse post-tensioning of the deck slab
design values. Subsequently, the slab is checked is used is the effect of the transverse elastic short-
E Sor Qirder
(Symm.)
Fig. 3.53 - Transverse tendon geometry from design drawings, Kishwaukee River Bridge, Illinois
ening of the deck slab in generating Wditional 3.6 Analysis and Correction of Deformations
transverse moments and stresses. The lateral bend-
ing of the webs sets up fixed end moments that
3.6.1 General
must be distributed throughout the transverse
frame. An analysis of this effect on a cross sec- The development of segmental construction has
tion of a post-tensioned box girder bridge cast-in- made it economical to build slender concrete
place on falsework is shown in Fig. 3.54. bridges with long spans. As a result, the magnitude
For wide sections, such as this, relatively high of the deformations and deflections may be in-
tensile stresses are generated by the slab short- creased to such an extent that they require more
ening. Even in narrower sections that might be attention and usually need adjustment during con-
expected in a precast segmental bridge, this effect struction. The amount of deformation is further
may be substantial and should be considered in increased by erection of a structure in free can-
the design. These stresses become highest near piers tilever. The deformations require correction of the
where th& transverse frame elements are thickest. geometry of a structure during segment fabrica-
A design check should be made to assure that tion which can only be based on an effective pre-
stresses resulting from transverse post-tensioning diction of the deformations.
of the deck slab, in conjunction with the transverse Erection of a typical span in a multispan bridge
temperature stresses discussed in Section 3.4.7, usually starts at a pier by placing segments alter-
dre not sufficiently high to cause cracking at nately on both sides in free cantilever until mid-
the bottom exterior corner as illustrated in Fig. span is reached. The newly erected cantilever is
3 . 55. () The magnitude of these stresses and the then connected to the completed part of the struc-
potential for crack development are minimized ture by casting the midspan splice. This procedure
by use bf the thinnest possible concrete sections is repeated for each additional span, however, with
consistent with strength requirements and with different resulting deformations since these depend
segment design recommendations presented in on the statical system in which the addition takes
Chapter 2. place. Obviously, this statical system changes
62
13.12 13.12' 13.12' 13.12' 13.12'
V, = 67.197 lb//f V, = 67,197 lb//f
j-$m3--
.-. -. ~j+&~--
- - - -
2' I
t I I
Midspan cross-section
Fig. 3.54 - Transverse bending moments due to normal force component of post-tensioning in deck slab2)
63
3.6.2.1 Phase A - Free Cantilever This time is also needed for the determination of
Loading conditions are: the contribution of creep to the deformations.
Steel relaxation varies significantly for different
1. Elastic deflection due to self weight.
post-tensioning materials (wire, strand or bar),
2. Elastic deflection due to initial cantilever
and low relaxation materials are available (relax-
prestress.
ation losses for low relaxation strand are in the
3. Creep deformation of 1 and 2 for the dura-
range of 25 percent of the values in Fig. 3.56 (a)).
tion of this phase.
For this reason, use of relaxation curves for the
The deflected shape of the completed cantilever is specific material to be used is recommended.
easily calculated. Elastic deflections due to self Although creep starts from erection of the first
weight and prestress are calculated assuming a segment onwards, without the use of a computer
Youngs modulus of elasticity: it is not practical to calculate total creep deforma-
tion as the sum of the effects of each successive
E = 33 w32 fi
step. A reasonable approximation is obtained when
where f, = cylinder strength of concrete in the completed cantilever is considered to creep
psi at the time of erection during a time interval which starts when the can-
w = unit weight of concrete in lb. per cu. ft. tilever is halfway complete and ends when a con-
E may be assumed constant for precast segments nection with the completed structure is made.
after the segment age reaches 28 days. This time interval is different for each canti-
The prestressing force used for the calculation is lever arm as illustrated by Fig. 3.57.
the total of initial tendon forces reduced only Creep deformations are obtained by multiplica-
by friction losses and part of the steel relaxation tion of the elastic deformations by a creep factor.
loss. The relaxation loss is evaluated from a relaxa- The creep factor used here is
tion-time curve based on test results by the steel
supplier, or from typical relaxation curves such as 4 '2'1 = @d, fld(tZpt, ) + @f,
[~f,,-~ftJ for part a
given in Figs. 3.56 (a) and 3.56 (b), and an esti-
mate of the time the cantilever is in phase A. 4 t4t2 = #d, (3d(t4-2) + @fee[oft4 -aft,] for part b
30 50
TIME-HOURS
YEARS
64
I
TIME IN HOURS
Fig. 3.56 (b) - Relaxation loss curves for 150 K 1% in. diameter bars (1030 MPa - 32 mm@)
rckx.ed at t2 -closed at t4
65
2. Elastic and creep deformation by prestress
losses.
3. Creep deformations by self weight, cantilever
prestress and continuity prestress.
Determination of the elastic deformation by
lb) superimposed dead load (weight of topping, curbs,
railings, etc.) needs no further comment. The
creep deformation is obtained by multiplication
of the elastic value by @ct, -t,), with t, being the
time of application of the dead load.
For the amount of deformation by prestress
losses, a simplification is made. The total amount
of the losses caused by creep, shrinkage and re-
laxation is reduced by the part of the relaxation
(dJ loss deducted in phase A. All other losses are con-
I sidered to take place in the final system. This
negative prestressing force F again causes elastic
and creep deformation and is written, therefore, in
a simplified form as:
Fig. 3.58 - Superstructure deformations in phase 8 The determination of the creep deformations
by self weight and prestressing in the completed
structure is based on the solution presented in
Section 3.3. Evaluation of the creep deformations
in this phase can be restricted to those occurring
system. With reference to Fig. 3.57, the creep fac- in the final system. The creep effects of the inter-
tor to be used is: mediate phases B,B are then neglected; the
error is small, since the most important contri-
# (t4t2) = @d, fld(t,yt2) + @f, [oft,- fq
bution, the creep of the forward cantilever arm,
has been taken into account. After a few spans
The total deformation is shown in Fig. 3.58 (d)
have been completed, the statical system during
indicating a rotation over pier C, bringing down the construction closely resembles the final com-
forward cantilever arm. Also, this rotation in- pleted structure.
creases by creep while the structure is in phase B.
Addition of a new span, Fig. 3.58 (e), again causes
secondary moments which will affect span BC as
well, Fig. 3.58 (f), and so will the connection of 3.6.3 Alignment
each successive span. For this reason, it is easier
The need for correction of deformations should
to calculate the deformation due to secondary
be investigated for all precast segmental bridges.
moments after summation of all contributing
The use of match-cast joints makes alignment cor-
moment diagrams. The rotation of each forward
rections during construction awkward and un-
arm, however, must be determined just before
desirable. In the casting yard, corrections are al-
closure of the next span.
ways minor and are easily accommodated by the
casting equipment. Adjustments of alignment can
be made during construction by use of stainless
steel shims in the joints. The following procedure
3.6.2.3 Phase C - Final Continuous System
of alignment correction for a bridge with several
Deformations in this phase consist of: equal spans illustrates the principles. Corrections
1. Elastic and creep deformation by superim- consist of those resulting from deformation, ro-
posed dead load. tations, and superimposed curvatures.
66
3.6.3.1 Correction of Deformations
The correction curve of each cantilever arm
equals the deformation curve but with opposite
sign. Typical deflection curves are shown in Fig.
3.59. The theoretical curve is approached by ,.
straight lines one or more segments long. The
*
difference between a curve and approximating
straight lines obtained in this way is not visible
provided the angular changes are kept below 0.001 Fig. 3.60 - Cantilever rotations due to continuity post-
tensioning
radians as shown.
As indicated in Section 3.6.2.2, the deforma-
tion of the forward cantilever arm will be differ-
ent from the backward arm, because of different
creep behavior and the rotation caused by con-
tinuity prestress. Although it is possible to make
additional corrections during casting for forward
and backward cantilever arms, it proves simpler
to make such corrections by counter rotations.
correction /
67
\ Fig. 3.66 - Summation of geometry corrections
Fig. 3.63 - Example alignment calculations
68
3.7.2 Sources of Computer Programs
Detailed information on computer program
services may be obtained from the following:
,
CHAPTER 4 of the casting of the joints during erection and less
on the accuracy of the segments. Curvature and
FABRICATION, TRANSPORTATION
twisting of the structure may be obtained within
AND ERECTION OF PRECAST SEGMENTS
the joint.
The principle of the match-cast joint is that the
4.1 Fabrication of Precast Segments 4,
connecting surfaces fit each other very accurately,
so that only a thin layer of filling material is
4.1 .l General Considerations needed in the joint. Each segment is cast against
During design of a segmental structure, consider- its neighbor. The sharpness of line of the assembled
ation should be given to the formwork necessary construction depends mainly on the accuracy of
to achieve economy and to obtain efficiency in the manufacture of the segments.
production. It is generally preferable to use as few
units as possible, consistent with economic ship-
ping and erection. 4.1.2 Methods of Casting
In the case of girder segments, economy and Segments to be erected with wide joints may be
speed of production may be increased by: cast separately. Match-cast joint members are cast
1. Keeping the length of the segments equal and by the long-line or short-line method.
keeping them straight, even for curved struc-
tures.
2. Proportioning the segments or parts of them, 4.1.2.1 The Long-Line Method
such as keys and web stiffeners, in such a way
Principle-All of the segments are cast, in their
that easy stripping of the forms is possible. correct relative position, on a long line. One or
3. Maintaining a constant web thickness in the more formwork units move along this line. The
longitudinal direction. formwork units are guided by a pre-adjusted soffit.
4. Maintaining a constant thickness of the top An example of this method is shown in Figs. 4.1
flange in the longitudinal direction. through 4.3
5. Keeping the dimensions of the connection Advantages-A long line is easy to set up and to
between webs and the top flange constant. maintain control over the production of the
6. Bevelling corners to facilitate casting. segments. After stripping the forms it is not
7. Avoiding interruptions of the surfaces of webs necessary to take away the segments immediately.
and flanges caused by protruding parts for Disadvantages-Substantial space may be re-
anchorages, inserts, etc. quired for the long line. The minimum length is
8. Using a repetitive pattern, if practical, for normally slightly more than half the length of the
tendon and anchorage locations. longest span of the structure. It must be con-
9. Minimizing the number of diaphragms and structed on a firm foundation which will not
stiffeners. settle or deflect under the weight of the segments.
10. Avoiding dowels which have to pass through In case the structure is curved, the long line must
the forms. be designed to accomodate the curvature. Because
11. Minimizing the number of blockouts. the forms are mobile, equipment for casting,
Variation of the cross section of girder segments is curing, etc., has to move from place to place.
generally limited to changing the depth and width
of the webs and the thickness of the bottom
flange. Curves in the vertical and horizontal direc- 4.1.2.2 The Short-Line Method
tion and twisting of the structure are easily ac-
Principle-The segments are cast at the same
commodated.
place in stationary forms and against a neighboring
Segmental construction is distinguished by the
element. After casting, the neighboring element is
type of joint between elements. The following
taken away and the last element is shifted to the
types have been used:
place of the neighboring element, clearing the
1. Wide (broad) joints (this type of joint is not space to cast the next element. A horizontal cast-
considered in the design procedures presented ing operation is illustrated in Figs. 4.4 through 4.6.
in this manual). Segments intended to be used horizontally may
2: Match-cast joints. also be cast vertically. A photograph of a short-
The precision of line of segments assembled line form is presented in Fig. 4.7.
with wide joints depends mainly on the accuracy Advantages-The space needed for the short-
71
R n
Formwork
\ Soffit
Fig. 4.1 - Cross section of formwork using long-line method(14)
/Outside Fotmwork
Inside Formwork
ELEVATION
1 I
PLAN
Fig. 4.2 - Start of casting (long-line method)(14)
ELEVATION
PLAN
Fig. 4.3 - After casting several segments (long-line method)(4)
72
AFTER STRIPPING 0 L D DURING CASTING
; FORMWORK ,
=+#t+# f# - C A R R I A G E
-
hJRNBUCKLES
73
Fly. 4 7 Shott line form used for Purls Belt Brdges)
line method is small in comparison to the long- be flexible in order to accomr%date slight dif-
line method, approxim&tefy ttiree times the length ferences of dimensions with the previously cast
of a segment. The entire process is centralized. segment. They must be designed in such a way
Horizontal and vertieaf c-urves and twisting of that the.. necessary adjustments ior the desired
the structure are obtained by adjusting the po- camber, curvature and twisting can be achieved
sitionof the neighboring segment. accurately and easily.
Special consideration must be given to those
Disadvantages-To obtain the desired structural
parts of the forms that have to change in dimen-
configuration, the neighboring segments must be
sions. To facilitate alignment or adjustment, spec-
accurately positioned.
ial equipment such as wedges, screws, or hydraulic
jacks should be provided. Anchorages of the
tendons and inserts must be designed in such a
4.1.3 Formwork way that their position is rigid during casting.
Formwork must be designed to safely support Fittings must not interfere with stripping of the
all loads that might be applied without. undesired forms. If accelerated steam curing using tempera-
deformations or settlements. Soil stabilizat$n OP ture in excess of approximately 160 F (71 C) is
the foundation may be required, or the forr&ork~ foreseen, the .influences of the deformations of the
may be designed so thaf adjustments can be made + . forms, caused- .: by 1 heating and cooling, must be
to compensate for settlement. -* consid&e$ig prder to avoid development of cracks
Since prodUction of, segments is based onreusing in the -concrete. External vibrato& must be
the forms as much aspossible,.the formwork must_ attached at locations that will achieve maximum
be sturdy and s$%ai attention must be giLen to consolidation and permit easy exchange during
construction details. Forms must also be easy to the casting operations. Internal vibration may
handle. Paste leakage through formwork joints also be required.
must be prevented. This can normally be achieved Holes for prestressing tendons may be formed by:
by using a flexible sealing material. Special atten- 1. Rubber hoses which are pulled out after harden-
tion must be given to the junction of tendon ing of the concrete.
sheathing with the forms. The forms may need to 2. Sheathing which remains after hardening of the
concrete. Flexible sheathing made out of spirally characteristics of concrete required by the design
wound metal is usually stiffened from the inside may vary somewhat depending on whether the
by means of dummy cables, rubber or plastic segments are cast in the field or in a plant. The
hoses, etc., during the casting operation. results will be affected by curing temperature
3. Rigid sheathing with smooth or corrugated walls and type of curing. Liquid or steam curing or
may be ,used that will not deform significantly electric heat curing may be used.
under the pressure of wet vibrated concrete and A sufficient number of trial mixes must be made
for which there is no danger of perforation. to assure uniformity of strength and modulus of
4. Movable mandrels. elasticity at all significant load stages. Careful
Holes must be accurately positioned, particu- selection of aggregates, cement, gdmixtures and
larly when a large number of holes is required. water will improve strength and modulus of elas-
Horizontal and vertical tolerance for tendon ticity and will also reduce shrinkage and creep.
holes within the segment should not exceed +% Soft aggregates and poor sands must be avoided.
in. (13 mm) from the theoretical location. Ten- Creep and shrinkage data for the aggregates and/or
don ducts shall be match-cast in alignment at concrete mixes should be available or should be
segment faces. determined by tests.
Formwork that produces typical box girder Corrosive admixtures such as calcium chloride
segments within the following tolerances is con- may not be used. Water-reducing admixtures and
sidered good workmanship. also air-entraining admixtures which improve
concrete resistance to environmental effects such
Width of web. . . . . . . . . . . . . . +3/8 in. (10 mm)
as deicing salts and freeze and thaw actions are
Depth of bottom slab. . . ~~t00in.(13mmt00)
highly desirable. However, their use must be
Depth of top slab . . . . . . . . . . . &l/4 in. (6 mm)
rigidly controlled in order not to increase undesir-
Overall depth of segment. . . . . . *l/4 in. (6 mm)
able variations in strength and modulus of elastic-
Overall width of segment. . . . . . *l/4 in. (6 mm)
ity of concrete. The cement, fine aggregate, coarse
Length of match-cast segment. . +_ l/4 in. (6 mm)
aggregate, water and admixture should be com-
Diaphragm dimensions . . . . . . ?1/2 in. (13 mm)
bined to produce a homogeneous concrete mix-
Grade of roadway and soffit . . . .+1/8 in (3 mm)
ture of a quality that will conform to the mini-
Depending upon the detail at bridge piers, the
mum field test and structural design requirements.
tolerances for the soffit of a pier segment may need
Care is necessary in proportioning concrete mixes
to be limited to *l/16 in. (1.6 mm). The tolerance
to ensure that they meet specified criteria. Reliable
of a segment should be determined immediately
data on the potential of the mix in terms of
after removing the forms. If specified tolerances
strength gain and creep and shrinkage performance
are exceeded, acceptance or rejection should be
should be developed for the basis of improved
based on the effect of the over-tolerance on final
design parameters. Proper vibration should be used
alignment and on whether the effect can be cor-
to afford use of lowest slump concrete and to
rected in later segments. In match-cast construc-
allow for the optimum consolidation of the con-
tion, a perfect fit is established between segments.
crete.
Limits for smoothness and out-of-squareness of
the joint should be established.
75
joints surface area. 4.3 Methods of Erection7*20)
For match-cast joints, the surface, including
formed keys, should be even and smooth, to avoid 4.3.1 Cranes
point contact and surface crushing or chipping
Mobile cranes moving on land or floating on
off of edges during post-tensioning. Holes or
barges are commonly used where access is available
sheathing for tendons must be located very pre-
as illustrated in Fig. 4.8. Occasionally, a portal
cisely when producing segments joined by post-
crane straddling the deck has been used with
tensioning. Care is required to prevent leakage or
tracks installed on temporary trestles on either
penetration of joint-filling materials into the
side of the bridge. The capacities of cranes readily
duct, blocking passage of the tendons.
available in the United States and Canada makes
this method of erection more attractive than it is
in Europe.
4.1.6 Bearing Areas
Bearing areas at reactions should be even, with- 4.3.2 Winch and Beam
out ridges, grooves, honeycomb, etc., to assure In this method, illustrated in Fig. 4.9, a lifting
uniform distribution of bearing forces. It may be device attached to an already completed part of
desirable to place bearing elements like pads or the deck raises the segments which have been
steel plates in the forms before casting. Other- brought to the bridge site by land carrier or barge.
wise, cement mortar or epoxy may be required The segments are lifted into place by winches
on contact surfaces. carried at deck level on a short cantilever mechan-
ism anchored on the bridge. In the first applica-
tions of this type of erection in Europe, the seg-
ment over the pier had to be placed independently
4.2 Handling and Transportation of Precast (either cast-in-place or handled by a separate
Segments 4, mobile crane). Recently, this drawback has been
overcome. Now the precast pier segment may be
Segments should be handled carefully in a
placed on the pier with the same basic equipment
manner that limits stresses to values compatible
cantilevered temporarily from a tower attached
with the strength and age of the concrete. It should
to the pier.
be verified that the segment weights are less than
the capacity of the lifting equipment. Highway and
site transportation may produce dynamic stresses
4.3.3 Launching Gantry
which may be considered by use of an impact
coefficient. Special care of cantilever projections is In this method, a special machine travels along
often needed to prevent cracking. Location of lift- the completed spans and maintains the work flow
ing hooks and inserts should be determined care- at the deck level. The crane gantry, which was
fully to avoid excessive stresses in the segment first used for the Oleron Viaduct, has contributed
during handling, and they should have a safety significantly to the development of precast seg-
factor of 1.75 to 2.00 when all loads and stresses mental construction. The principle behind seg-
have been considered. Storage of units at the site mental erection using the crane gantry system is
should be arranged to minimize damage, deflec- shown in Fig. 4.10. An essential component in
tion, twist, and discoloration of the units. Stock- the system is a truss girder which has a length some-
piling should be limited to avoid excessive direct what greater than the maximum bridge span. The
or eccentric forces. Special precautions may be system consists essentially of:
required to avoid settlement of foundations made 1. A main truss where the bottom chords act as
to support the stored segments. Inserts, anchorages rolling tracks.
and other imbedded items may need to be pro- 2. Three-leg frames which may or may not be fixed
tected from corrosion and from penetration of to the main truss. The rear and center frames
water or snow during cold weather. In cases where allow the segments to pass through them longi-
extensive transportation of segments is required, tudinally.
it is recommended that a segment should not be 3. A trolley which can travel along the girder and
erected before it is certain that the subsequent is capable of longitudinal, transverse, and
segment has been safely transported. vertical movement as well as horizontal rotations.
Fig. 4.8 - Segment erection by crane, Corpus Christi Bridge, Texas
3. Finally, the segment placing trolley is used as a
launching cradle with the help of an auxiliary
tower bearing on the newly placed pier seg-
ment. The gantry is then transferred to its initial
position one span further thus allowing the seg-
ment placing cycle to repeat itself [Fig. 4.10
(c)l .
For structures combining vertical and horizon-
tal curvatures, including variable superelevation,
the launching gantry can be designed to follow
the geometry of the bridge while maintaining
operational stability and segment placing capa-
bility. In the last few years, several important
Fig. 4.9 - Winch and beam erection, St. Andre de Cubzac technical improvements have been made in gantry
Bridge, France() design. These advancements are exemplified
starting at the Chillon Viaduct in Switzerland,
and later at the Saint-Cloud Bridge where 143-
ton (130 t) segments were easily placed in a 337
ft. (102 m) span with a 1090 ft. (332 m) radius
of curvature (see Figs. 3.4 and 4.11). It should be
noted that, on certain structures, a somewhat
different approach is used in designing the launch-
ing gantry system (see Fig. 4.12). The total length
of the truss girder is now slightly greater than
twice the maximum span length. In this system,
all three gantry supports rest directly over a pier.
Although the investment cost is higher in this
system than in the original concept, this type of
52.00
f ~~
54.00 gantry has several advantages:
I
106.00
t 1. The completed deck carries no gantry reactions.
2. Stability against unsymmetrical loading due to
unbalanced cantilever erection may be pro-
vided by the gantry.
3. The pier segment may be placed and adjusted
during the normal placing cycle for the preced-
i 106.00 ing cantilever spans.
t
4. Construction time may be further reduced if
Fig. 4.10 - Operational stages of a launching gantry (first two placing trolleys are used.
type)()
In this advanced system, segments may be
moved in place over the completed bridge or
beneath the bridge. This procedure was used on the
large Rio-Niteroi Bridge where all segments were
To complete a full construction cycle for a typical
floated on pontoons and lifted into place by four
span, the gantry assumes three successive positions:
540 ft. (164 m) long launching gantries weighing
1 . For placing typical segments in cantilever, the 400 tons (363 t) each (see Fig. 4.13). A similar
center leg rests directly over a pier while the approach was also used for the 83 South Via-
rear leg is seated towards the end of the pre- ducts near Paris.
viously completed deck cantilever [Fig. 4.10
(a)].
2. For placing the segment over the adjacent pier,
the girder is moved along the completed deck 4.3.4 Progressive Placing
until the ceder leg reaches the end of the can- The latest development of precast segmental
tilever. The front leg rests on a temporary cor- construction embodies the concept of progressive
bel fixed to the pier while the pier segment is placing. This approach actually comes directly
placed and adjusted into position [Fig. 4.10 (b)l . from cantilever design. Here, segments are placed
Fig. 4.11 - Launching gantry, St. Cloud Bridge, Parist7)
at each pier. 7
When the-deck reaches one pier, permanent
bearings are installed and construction proceeds
to the next span. Some noteworthy advantages
of the method are:
SEGMENT WEIGHTS: 60 TO 40 t
4.3.6.2 Moment Resisting Piers
- ?.tAX. STATICAL REACTION IN SUPPORT: ,060 , Moment resisting piers are designed to with-
stand the unbalanced moments during construc-
tion while temporary vertical prestress rods make a
rigid connection between the deck and the pier
cap. The Corpus Christi Bridge shown in Fig. 4.19
PROVISIONAL SUP utilized moment resisting piers.
When the ratio between span lengths and pier
height allows it, the rigid connection and the
corresponding frame action may be maintained
1 t = 1.1 ton
1 m = 3.28 ft. permanently between the deck and piers. This
frame action is also achieved by use of twin neo-
Fig. 4.16 - Stability during construction() prene bearings which allow for deck expansion.
-- --
Fig. 4.19,- Moment resisting piers, Corpus Christi Bridge, TexaO
Fig. 4.21 - Twin neoprene bearings in final structure(2)
a3
CHAPTER 5
DESIGN EXAMPLE,
NORTH VERNON BRIDGE, INDIANA
5.1 General
1 m = 3.28 ft.
The North Vernon Bridge over the Muscatatuck
Fig. 5.1 - Span arrangement
River in Indiana was built parallel to an existing
reinforced concrete arch bridge with the purpose
of doubling the capacity of the existing roadway.
The spans were therefore fixed to meet those of
the arch, as indicated in Fig. 5.1. Cost estimates
for widening the bridge with another arch proved
too expensive and led to consideration of both
steel and concrete alternatives. The presence of a
precast concrete plant in the vicinity of the bridge
site, and the feasibility of segment erection by
mobile crane made it possible that even this small
SPAN SUPPORT
structure with a total deck area of only 8855 sq. I
ft. (823 m*) could be built competitively using
JOINT NUMBERS
precast segmental construction.
a-AREA A (M2)
b-DISTANCE CG TO TOP
C, (Ml 1.002 1.066 1.122 1.151
c-MOMENT OF INERTIAI (MO) 4.0239 4.423 4.750 4.908
d-MOMENT OF RESIST 4.0151 4.1482 4.2328 4.268
5.2 Structure Dimensions 2,
Zb
lM3)
lM3) 2.3115 2.6378 2.9306 3.0824
e-KERNEL BEAM Kt IM) 0.555 0.608 0.705 0.74
The total bridge length of 381 ft. (116.04 m) Kb (Ml 0.956 0.938 0.925
f-THICKNESS BOTTOM D 041 0.252 0.302 0.33
is made up of 2 end cross girders of 5 ft. 3 in. (1.6
m), 44 segments of 8 ft. 0 in. (2.44 m) length, 2
Fig. 5.3 - Cross section dimensions and segment properties
pier segments of 9 ft. 0 in. (2.74 m) length, and a
cast-in-place splice of 5 ft. 3 in. (1.6 m). The span
and segment dimensions are shown in Fig. 5.2. for all segments except for the two segments lo-
In consideration of the length of the main span, cated on either side of the two pier segments. In
the depth of the box girder was selected as 9 ft. these segments, the bottom slab thickness was
0 in. (2.745 m). The resulting span/depth ratio of increased from 8 in. (0.20 m) to 13 in. (0.33 m)
21 .l is well within the economical limits. The box in order to reduce the compressive stress in the
girder dimensions and section properties are pre- bottom fibers resulting from the negative support
sented in Fig. 5.3. These dimensions are constant moments.
,
I
I2 3 4 5 6 7 6 9 IO II 12 13 1st l5 I6 I7 I6 I9 20 21 22 23 24 25 26
29.8 I 29.01
*
1 m = 3.28 ft.
Fig. 5.2 - Segment dimensions and joint numbers
85
5.3 Order of Erection 5.4 Post-Tensioning Details
The erection sequence for the structure is i n Except as noted below, the post-tensioning is
three steps as indicated in Fig. 5.4. carried out by tendons consisting of twelve % in.
Step 1: The segmental cantilevers are erected diameter 270 k strands (13 mm $I, 1862 MPa)
from each pier. with an ultimate force of 495 kips (2202 kN).
Step 2: The precast end cross girders a r e All tendons are stressed initially to 70 percent of
erected. their ultimate force. The effective force level in
Step 3: The midspan splice is cast-in-place. the example design calculations at time of pre-
stressing is reduced to allow for anchor seating and
friction losses. The final tendon forces after losses
are 60 percent of ultimate or lower. ,
I
I
a P B
The post-tensioning tendons are arranged in
groups as follows:
Group 1: Cantilever post-tensioning consists of
II STEP I
26 tendons, 13 in each web (See Fig.
5.5).
Group 2: Tail span continuity post-tensioning
consists of 2 tendons, one in each web
u,v,
S T E P 2
(See Fig. 5.6).
Group 3a: Center span continuity post-tensioning
consists of 8 tendons, 4 in each web,
> S T E P 3
located in the bottom slab at midspan
and anchored in the top slab (See Fig.
Fig. 5.4 - Erection sequence 5.7).
GROUP I
I
T
251
Fig. 5.7 - Center span continuity tendons: Bottom slab (Group 3a)
Top slab (Group 3b)
86
CANTILEVER TENDONS CENTER SPAN CONTINUITY -TENDONS
GROUP 3b
87
Step 4: Addition of permanent loads. Stress con- In all cases, provision must be made to accom-
trol. modate additional temporary erection loads on
Step 5: Addition of variable loads. Stress control. the structure, and stress and stability checks must
Step 6: Influence of time. be made for the structure under these loadings.
Step 6a: Dead load moment redistribution due to Such erection loads can be intentional (for exam-
concrete creep. Stress control. ple, movement of a launching girder over the struc-
Step 6b: Post-tensioning moment redistribution ture), or unintentional (storage of post-tensioning
due to concrete creep. Stress control. tendons or a large group of visitors on the struc-
Step 6c: Prestress losses. Stress control. ture). Consideration of erection loads has been
Step 7: Final stress control omitted in the presentation of this design exam-
Step 8: Transverse section analysis. ple for simplicity.
Other calculations required to complete the
design are made by procedures common to con-
ventional post-tensional box girder bridges or con-
NOTE:
ventional reinforced concrete design and are not
presented here. These calculations relate to the All of the following design example diagrams and
following: dimensions are in c.g.s. metric units
1. Calculation of end cross girder and pier segment Dimensions = meters (3.28083 ft)
reinforcement. Forces = metric tonnes (2204.62 lb)
2. Support forces and bearing requirements. Bending moments = tonnes x meters (7232.98 ft. I b.)
3. Road joint movements. Stress = tonnes/sq. meter (1.422 psi)
4. Principal shear stresses at service load. The relationship to SI metric units is:
5. Ultimate moments, safety to failure. Force: 1 t = 9.8 kN = 2204.62 lb.
6. Ultimate shear, safety to failure. (1 lb. = 4.448 Newtons)
7. Substructure loading during erection. Moment: 1 t-m = 9.8 kN-m = 7232.98 ft.-lb.
8. Temporary prestressing of segments during (1 ft.-lb. = 1.356 kN-m)
erection. Stress: 1 t/m2 = 9.8 kPa = 1.422 Ib./in.2
9. Reinforcement of keys. (1 Ib./in.2 = 6.895 kilopascals)
88
5.6.1 Step 1. Free Cantilever Plus Initial Can- force diagram by the section modu-
tilever Group 1 Post-Tensioning lus of the bottom fiber and dividing
by the section area F/A x Zb. This
In Step 1, stresses are calculated for loading due
is the bottom fiber moment due to
to the dead load of the free cantilever box girder
the axial compression from post-
section and the Group 1 cantilever post-tensioning.
tensioning (t-m).
The post-tensioning is shown in Fig. 5.5 and con-
sists of 13 tendons in each web. A check is made
for unbalance during erection. The calculations are
JOINT NUMBERS
made as follows: (See Fig. 5.2)
89
Diagram 11 Check top fiber moments (indirect-
(Fig. 5.11) ly checking stresses). Moment dia-
gram (a) is obtained by adding dia-
grams 8 and 9 from Fig. 5.10.
This is the top fiber moment due to
the combination of bending and
axial force resulting from post-
I I
tensioning. Diagram c + a is diagram
a reduced by the dead load moment
diagram (diagram 5 in Fig. 5.10).
The top fiber compressive stress
control limits are indicated by the
f, x Z, diagram. Allowable com-
pressive stress at this stage is 2150
t/m2. In this case 2150 x 1.422 =
3057 psi or approximately 0.55 x
5500 = 3025 psi.
Diagram 12 Check bottom fiber moments (indi-
rectly checking stresses). Moment
diagram b is obtained by adding
diagrams 8 and 10 from Fig. 5.10.
This is the bottom fiber moment 12
90
5.6.2 Step 2. Completion of Tail Span Plus Add diagrams 3 and 5 to obtain
Continuity Group 2 Post-Tensioning 6b. This is the combined axial
(expressed as a moment) and
The completion of the tail span is achieved by
bending moment effect of the post-
addition of the end span cross girders and installa-
tensioning on the bottom fiber
tion of the Group 2 post-tensioning shown in Fig.
(t-m).
5.6. This post-tensioning consists of one tendon in
each web. For analytical purposes, the changes
with respect to Step 1 are:
1. End cross girder is added 2 3 4 5 6 7 8 8 1 0
cross girder.
Diagram 2 Determine force diagram of Group
2 post-tensioning tendons and the
tendon eccentricities.
Diagram3 Determine the bending moment dia-
4
gram due to Group 2 tendons.
The structure is simply supported
and the bending moment equals the
force multiplied by the eccentricity.
Diagram 4 The tendon force diagram multi- 5
plied by the top section modulus,
Z,, and divided by the section
area, A, expresses the axial com-
pression due to post-tensioning in 6a
terms of a top fiber moment (t-m).
Diagram 5 The tendon force diagram multi-
plied by the bottom section mod-
ulus, Zb, and divided by the section
area, A, expresses the axial com-
pression due to post-tensioning in
terms of a bottom fiber moment
(t-m). -172
Diagram 6 Add diagrams 3 and 4 to obtain 6 b
diagram 6a. This is the combined
axial (expressed as a moment)
and bending moment effect of the
post-tensioning on the top fiber Fig. 5.12 - Completion of tail span plus continuity group
(t-m). 2 post-tensioning
91
See diagrams of Fig. 5.13 with numbers corres-
ponding to those below, and diagrams from previ-
ous figures as noted.
Diagram 7 Add bending moment diagrams due
to box girder dead load from Steps
7
1 and 2 (diagram 5 from Fig. 5.10
plus diagram 1 from Fig. 5.12)
92
5.6.3 Step 3. Completion of Center Span account for the effect of the axial
At this stage, the cast-in-place midspan splice is force.
completed and continuity post-tensioning in Diagram 5 Add diagrams 2e and 3 to obtain
Groups 3a and 3b is placed and stressed. Group 3a diagram 5a which is the total
post-tensioning consists of four tendons in each effect of the post-tensioning with
web which are located in the bottom slab at mid- respect to the top fiber, expressed
span. Group 3b post-tensioning consists of four 6- as a moment.
strand top slab tendons. Both Group 3a and Group Add diagrams 2e and 4 to obtain
3b post-tensioning are shown in Fig. 5.7. diagram 5b which is the total
The calculation procedure illustrated in Fig. effect of the post-tensioning with
5.14 for this step is as follows: respect to the bottom fiber, ex-
pressed as a moment.
Diagram 1 Calculate the bending moment dia-
gram due to the additional weight 456!69
93
Top and bottom fiber stresses are checked in 5.6.4 Step 4. Addition of Superimposed Dead
Fig. 5.15 in terms of moments as follows: Loads
At this stage the effect of permanent superim-
Diagram 6 Check top fiber moment by addi- imposed dead loads due to addition of curbs,
tion of diagrams 1 and 5a of Step railings and toppings is considered. Permanent
3 to diagram 9 of Step 2. The mo- superimposed loads are treated separately from live
ments (and stresses) are satisfac- loads because permanent loads cause creep defor-
tory in all locations. mations of the structure. The amount of the super-
imposed dead load is 1.525 t/m (1.03 kip/ft.).
Diagram 7 Check bottom fiber moment by ad-
With reference to Fig. 5.16, the calculation pro-
dition of diagrams 1 and 5b of Step
cedure is as follows:
3 to diagram 11 of Step 2. Again
the moments are well within the Diagram 1 Calculate bending moments due to
allowable values throughout the superimposed loads.
length of the structure. Diagram 2 Check top fiber moments by add-
ing diagram 1 above to diagram 6
of Step 3. All top fiber moments
6
are within the allowable.
Diagram 3 Check bottom fiber moments by
adding diagram 1 above to diagram
7 of Step 3. All bottom fiber mo-
ments are within the allowable.
94
5.6.5 Step. 5. Application of Live Load and Diagram 4 Check top fiber moments with
Temperature Load (Fig. 5.19) respect to allowable by combining
diagram 2 of Step 4 (Fig. 5.16)
The live load on the structure is HS20-44.
with 3a and 3b of Step 5. All
The temperature loading consists of a 10 C
(18O F) temperature rise of the top slab with moments within the allowable.
respect to the webs and the bottom slab for maxi- Diagram 5 Check bottom fiber moments with
mum temperature effects and a 5O C (go F) tem- respect to allowable by combining
perature decrease of the top slab with respect to diagram 3 of Step 4 (Fig. 5.16)
the webs and bottom slab for minimum tempera- with diagrams 3a and 3b of Step 5.
ture effects. With the area of the top slab 1.988 All moments within the allowable.
m* (21.39 ft.*) and modulus of elasticity 3.5 x
lo6 t/m* (5 x lo6 psi), the force developed by a
1OoC temperature differential with a thermal co-
efficient, CY, of 0.00001 m/m/C (5.56 x 1O-6
in./in./OF) is 695.8 t (1534 kips). The eccentricity
of this force with respect to the neutral axis is
0.926m (3.04 ft.). The temperature differential
analysis procedure is presented in Section 3.3.4.
The temperature stresses calculated are converted
to equivalent bending moments. As illustrated by
Figs. 5.17, 5.18 and 5.19, the calculation proce-
dure is as follows:
Diagram 1 Calculate live load positive mo-
(Fig. 5.17) ments (diagram la) and negative
moments (diagram 1 b).
Diagram 2 Calculate maximum bottom fiber
(Fig. 5.17) temperature moments (2a) and
minimum bottom fiber temperature 2b
tively).
Diagram 3 Combine diagrams 1 and 2 to pro-
(Fig. 5.18) vide:
3a. Maximum live load moment
plus maximum temperature mo-
ment bottom fiber.
3b. Minimum live load moment and
minimum temperature moment top Fig. 5.17 - Step 5. Application of live load and tempera-
fiber. ture load
95
3 b
Fig. 5.18 - Step 5 continued. Maximum live load plus Fig. 5.19 - Step 5 continued. Check top fiber and bottom
maximum temperature moments on bottom fiber and top fiber moments
fiber
96
5.6.6 Step 6. Influence of Time Diagram 5 Diagram 3 is multiolied bv the IOW
With passage of time, the moments in the struc- value of the creep factor Ci - e*2 )
ture are modified due to creep effects on box gird- to provide a low estimate of the
er dead load moments and post-tensioning mo- box girder dead load m o m e n t
ments, and by the effect of prestress losses. These redistribution.
three effects will be considered separately in the
following calculations. Step 6a will consider the
redistribution of box girder dead load moments 60
due to creep, Step 6b will cover the redistribution
of the post-tensioning moments due to creep, and
Step 6c will consider the effect of prestress losses.
In all of these calculations, high and low values
of the creep factors will be assumed as follows:
f#l, = 1.41 #* = 1.05
(1 -e-@I) =0.76 (1 -ee-@2) =0.65
97
5.6.6.2 Step 6b. Post-Tensioning Moment Redis- Diagram 12 Combine diagrams 5 and 10 to ob-
tribution Due to Creep tain a low value of the total redis-
Diagram 1 The effects of cantilever post- tribution of post-tensioning mo-
(Fig. 5.21) tensioning (Group 1) on the contin- ments due to creep.
uous structure.
Diagram 2 The cantilever post-tensioning mo-
ments at the end of erection (dia- 6 b
gram 8 from Step 1, Fig. 5.10).
Diagram 3 The difference between diagrams 1
and 2 above.
Diagram 4 Multiply diagram 3 by the high
value of the creep factor (1 - e*l ),
giving a high estimate of the canti-
lever post-tensioning (Group 1)
2
moment redistribution due to creep.
Diagram 5 Multiply diagram 3 by the low
value of the creep factor (1 - e-#2 )
giving a low estimate of the canti-
lever post-tensioning (Group 1)
moment redistribution due to creep.
Diagram 6 Determine the effect of Group 2
continuity post-tensioning on the
continuous structure. 3
Diagram 7 The effect of Group 2 post-tension-
ing during construction (diagram 3, 4
Fig. 5.12).
Diagram 8 The difference between diagrams 6 5
and 7, above.
Diagram 9 Multiply diagram 8 by the high
6+21
value of the creep factor ( 1 -
e-@l 1, giving a high estimate of
the Group 2 post-tensioning mo- 7
t 21
ment redistribution due to creep.
Diagram 10 Multiply diagram 8 by the low value 6
98
5.6.6.3 Step 6c. Effect of Prestress Losses Diagram 8 Group 2 continuity post-tensioning
(Fig. 5.23) bending moments in continuous
Prestress losses due to friction, elastic shorten-
ing, shrinkage and creep have been calculated as system multiplied by loss per-
14 percent of initial forces or 18.610 t/m* (26,460 centage.
Diagram 9 Group 1 cantilever post-tensioning
psi).
bending moments in continuous
Diagram 2 Group 1 post-tensioning tendon
system multiplied by loss per-
(Fig. 5.22) force diagram multiplied by pre-
centage.
stress loss percentage. Group 3 continuity post-tensioning
Diagram 10
Diagram 3 Group 2 post-tensioning tendon bending moments in continuous
force diagram multiplied by pre-
system multiplied by loss per-
stress loss percentage. centage.
Diagram 4 Group 3 post-tensioning tendon
Diagram 11 Diagrams 8, 9 and 10 added to-
force diagram multiplied by pre- gether.
stress loss percentage. Diagram 11 added to diagram 6 to
Diagram 12
Diagram 5 Diagrams 2,3 and 4 added together. obtain total equivalent top fiber
Diagram 6 Diagram 5 multipled by 2, and bending moments due to losses.
divided by the section area, A. This Diagram 13 Diagram 11 added to diagram 7 to
is the prestress force loss effect on obtain total equivalent bottom fiber
the top fiber expressed as a mo- bending moments due to losses.
ment.
Diagram 7 Diagram 5 multiplied by 2, and di-
vided by the section area, A. This
is the prestress force loss effect on 162021222324252627
g a
0 a
II -a
-41
12
I
6
-30
13
+tD
99
5.6.7 Step 7. Final Stress Control
100
p
101
,325 t/m
2 3
4 IO 4
-QLlOl I
\
0 0
102
9
1 / I9 p g! /
1
-0.024 t on24
I
1-o.co2 1 SECTION 5;
I
ISECTION
~SECTION 2
I
Fig. 5.28 - Influence lines for vehicle Fig. 5.29 - influence lines for vehicle, continued
103
Fig. 5.30 - Transverse moments and axial forces due to Fig. 5.31 - Transverse moments and axial forces due to
uniformly distributed live load vehicular loading
104
CABLES.
309
i
411
, II
319 @ 6 / i
3194 @ 6
, / -- -- J
1 ft. = 0.3048 m
T- ---fi l\,.
f 7+ I 1 in. = 25.4 m m
, 4 1 3 Cal IO1
t
Note:
I
bar size is indicated by the first digit of bar numbers
Fig. 5.32 - Transverse reinforcement details
A. APPENDIX Elastic analysis and beam theory may be used in
the design of precast segmental box girder struc-
A.1 Tentative Design and Construction Specifica- tures. For box girders of unusual proportions,
tions for Precast Segmental Box Girder Bridges. methods of analysis which consider shear lag*
%The PCI Bridge Committee prepared tentative shall be used to determine stresses in the cross
design and construction specifications and accom- section due to longitudinal bending.
panying commentary in 1975 in the form of a pro- (B) Design of Superstructure
posed addition to the AASHTO Standard Specifi- (1) Flexure
cations for Highway Bridges. They were presented
The transverse design of precast segments for
to the AASHTO Committee on Bridges and Struc-
flexure shall consider the segment as a rigid box
tures for evaluation, and then were published by
frame. Top slabs shall be analyzed as variable depth
the Prestressed Concrete Institute (PC1 JOURNAL,
sections considering the fillets between the top
July-August 1975) to develop comments and dis-
and webs. Wheel loads shall be positioned to pro-
cussion.
vide maximum moments, and elastic analysis shall
The PCI Bridge Committee evaluated the com-
be used to determine the effective longitudinal
ments received relative to the 1975 tentative speci-
distribution of wheel loads for each load location
fications as well as new information on design and
(see Article 1.2.8). Transverse post-tensioning of
construction of precast segmental box girder
top slabs is generally recommended.
birdges, and prepared the following version of the
In the analysis of precast segmental box girder
design and construction specifications for con-
bridges, no tension shall be permitted at the top of
sideration by the AASHTO Subcommittee on
any joint between segments during any stage of
Bridges at its 1977 Regional Meetings. The speci-
erection or service loading. The allowable stresses
fication proposals as presented in this section rep-
at the bottom of the joint shall be as specified in
resent the recommendations of the PCI Bridge
Article 1.6.6 (B) (2).
Committee, and may be modified prior to final
adoption as AASHTO Standard Specifications for (2) Shear
Highway Bridges. (a) Reinforced keys shall be provided in segment
The specification proposals are presented here in webs to transfer erection shear. Possible reverse
a format utilizing section numbers compatible with shearing stresses in the shear keys shall be
the 1973 AASHTO Standard Specifications for investigated, particularly in segments near a
Highway Bridges. Specifically, new sections of the pier. At time of erection, the shear stress car-
1973 AASHTO Specifications are proposed as ried by the shear key shall not exceed 2c
follows:
(b) Design of web reinforcement for precast
segmental box girder bridges shall be in ac-
cordance with the provisions of Article 1.6.13.
1.6.25 Precast Segmental Box Girders
2.4.33 (L) Precast Segment Manufacture and (3) Torsion
Erection In the design of the cross section, consideration
2.4.33 (M) Epoxy Bonding Agents for Pre- shall be given to the increase in web shear resulting
cast Segmental Box Girders from eccentric loading or geometry of structure.
2.4.33 (N) Inspection of Precast Segmental (4) Deflections
Box Girder Jointing Procedures
Deflection calculations shall consider dead load,
2.4.33 (0) Epoxy Bonding Agent Tests
live load, prestressing, erection loads, concrete
creep and shrinkage, and steel relaxation.
Deflections shall be calculated prior to manu-
1.6.25 Precast Segmental Box Girders facture of segments, based on the anticipated pro-
(A) General duction and erection schedules. Calculated deflec-
Except as otherwise noted in this section, the tions shall be used as a guide against which erected
provisions of Section 6 - Prestressed Concrete deflection measurements are checked.
shall apply to the analysis and design of precast
segmental box girder bridges. Deck slabs without
transverse post-tensioning shall be designed under
the applicable provisions of Section 5 - Concrete Defined as non-uniform distribution of bending stress over the
Design. cross section.
106
(5) Details (C) Design of Substructure
(a) Epoxy bonding agents for match-cast joints In addition to the usual substructure design con-
shall be thermosetting 100 percent solid siderations, unbalanced cantilever moments due to
compositions that do not contain solvent or segment weights and erection loads shall be ac-
any non-reactive organic ingredient except for commodated in pier design or with auxiliary struts.
pigments required for coloring. Epoxy bond- Erection equipment which can eliminate these un-
ing agents shall be of two components, a balanced moments may be used.
resin and a hardener. The two components
shall be distinctly pigmented, so that mixing
COMMENTARY
produces a third color similar to the concrete
in the segments to be joined, and shall be
1.6.25 Precast Segmental Box Girders
packaged in pre-proportioned, labeled, ready-
to-use containers. (A) General
Epoxy bonding agents shall be formulated to Material strengths and allowable stresses need be
provide application temperature ranges which no different from other prestressed concrete
will permit erection of match-cast segments at bridges; therefore, current limits in Standard Speci-
substrate temperatures from 40F (5C) to fications for Highway Bridges should apply. How-
115F (46C). If two surfaces to be bonded ever, higher strength concrete has advantages and
have different substrate temperatures, the should be used when available. Higher strength
adhesive applicable at the lower temperature concrete has more durability, not only because of
shall be used. the mix design but also because of the greater
If a project would require or benefit from quality control required to produce it.
erection at concrete substrate temperatures Precast segmental box girders may be designed
lower than 4OF, the temperature of the by beam theory with consideration of shear lag.
concrete to a depth of approximately 3 in. Shear lag need only be investigated for segments
(76 mm) should be elevated to at least 40F to wider than 40 ft. (12m) used on 150 ft. (46m)
insure effective wetting of the surface by the spans or less, because of the shallow depth.
epoxy compound and adequate curing of the
(B) Design of Superstructure
epoxy compound in a reasonable length of
time. An artificial environment will have to be Influence surfaces for design of constant and
provided to accomplish this elevation in variable depth deck slabs have been published
temperature and should be created by an (see References 5 and 6, page 109).
enclosure heated by circulating warm air or
by radiant heaters. In any event, localized The following limitations are recommended:
heating shall be avoided and the heat shall be 1. When beam theory is used, single cell boxes
provided in a manner that prevents surface should be no more than 40 ft. (12m) wide, includ-
temperatures greater than 11OF (43C) during ing cantilevers. For bridges wider than 40 ft.,
the epoxy hardening period. Direct flame jett- multiple box cross sections or multiple cell boxes
ing of concrete surfaces shall be prohibited. are usually used. Single cell boxes of width greater
Epoxy bonding agents shall be insensitive to than 40 ft. can be used if carefully analyzed for
damp conditions during application and, after shear lag to determine the portion of cross section
curing, shall exhibit high bonding strength capable of handling longitudinal moment.
to cured concrete, good water resistivity, low 2. For maximum economy, the span-to-depth
creep characteristics and tensile strength ratio for constant depth structures should be 18
greater than the concrete. In addition, the to 20. However, span-to-depth ratios of 20 to 30
epoxy bonding agents shall function as a have been used when required for clearances or
lubricant during the joining of the match-cast esthetics. The shallower depths require the use of
segments being joined, and as a durable, more high strength post-tensioning steel which may
watertight bond at the joint. See Article 2.4.33 cause congested cross sections. Variable depth
(M) for epoxy bonding agent specifications. structures usually have span-to-depth ratios of 18
to 20 at the supports and 40 to 50 at midspan.
(b) Articles 1.6.24 (C) and 1.6.24 (F) relating to
flange thickness and diaphragms shall not 3. Width-to-depth ratios should also be consid-
apply to precast segmental box girders. ered. A shallow box girder that is too wide begins
107
to behave as a slab. No criteria have been estab- 4. Maisel, V. I., and Roll, F., Methods of Analysis
lished, but when the width-todepth ratio is greater and Design of Concrete Boxbeams with Side
than six, considering the total width of the section Cantilevers, Technical Report No. 42.494,
including slab cantilevers, it is recommended that Cement and Concrete Association, 52 Grosvenor
the designers use multiple cell boxes or carefully Gardens, London, SWlW OAQ, November, 1974.
analyze the cross section. 5. Pucher, Adolph, Influence Surfaces of Elastic
4. Proper fillets should be used in the cross sec- Plates, 4th Edition, 1973 (English), Springer
tion to allow stress transfer around the box per- - Verlag New York, Inc.
imeter and to provide ample room for the large
6. Homberg, Helmut, Double Webbed Slabs,
number of tendons.
(Dalles Nervurees Platten Mit Zwei Stegen),
5. Diaphragms should be considered. These are 1974 (English), Springer - Verlag New York,
usually required only at piers, abutments, and ex- Inc.
pansion joints.
6. The thickened bottom slab in pier segments,
when required for stresses, should taper down or 2.4.33 Prestressed Concrete
step down to the minimum midspan segment bot-
tom slab thickness in as short a distance as is prac- (L) Precast Segment Manufacture and Erection
tical. (1) Manufacture of segments
7. Web thicknesses should be chosen for pro- Each segment shall be match-cast with its ad-
duction ease. If post-tensioning anchorages are jacent segments to ensure proper fit during erec-
located in the webs, web thickness may be gov- tion. As the segments are match-cast they must be
erned by the anchorage requirements. precisely aligned to achieve the final structure
8. Permanent access holes into the box section geometry. During the alignment, adjustments to
should be limited in size to the minimum func- compensate for deflections are made.
tional dimension and should be located near points All tendon ducts are placed during production.
of minimum stress. The conduit to enclose grouted, post-tensioned
tendons shall be mortar tight, made of galvanized,
(C) Design of Substructure
ferrous metal, and may be either rigid with a
Unbalanced cantilever moments occur during smooth inner wall, capable of being curved to the
erection only and are usually greater in magnitude proper configuration, or a flexible, interlocking
than service load moments. Wind loads in combi- type. Couplers for either type shall also provide a
nation with erection loads could develop critical mortar tight connection. Rigid conduit may be
stresses and, thus, wind loads should be consid- fabricated with either welded or interlocking
ered in accordance with Article 1.2.22. seams. Galvanizing of welded seams for rigid con-
duit or of conduit couplers will not be required.
During placing and finishing of concrete in a seg-
Selected References ment, inflatable hoses capable of exerting suffi-
cient pressure on the inside walls shall be placed
The following selected references provide some internally in all conduits and shall extend a mini-
useful guidelines in the design and construction of mum of 2 ft. (0.6m) into the conduit in the pre-
precast prestressed segmental box girder bridges: viously cast segment. Either type of conduit shall
1. PCI Committee on Segmental Construction, be capable of withstanding all forces due to con-
Recommended Practice for Segmental Con- struction operations without damage. Other types
struction in Prestressed Concrete, PCI JOUR- of conduit and/or internal protection systems are
NAL, V. 20, No. 2, March-April 1975, pp. 22- permitted subject to the approval of the Engineer.
41. (2) Erection of Segments
2. Muller, Jean, Ten Years of Experience in Pre- Segments are usually erected by the cantilever
cast Segmental Construction, PCI JOURNAL, method from each pier without falsework, al-
V. 20, No. 1, January-February 1975, pp. 28-61. though temporary supports may be used. With
3. Swann, R. A., A Feature Survey of Concrete the approval of the Engineer, other systems of
Box Spine-Beam Bridges, Cement and Concrete erection may be considered.
Association, 52 Grosvenor Gardens, London Match-cast segments shall be erected using
SW1 W OAQ, 1972. epoxied joints. Pressure shall be provided on the
108
joint by means of post-tensioning. The pressure surface dry (no visible water).
shall be as uniform as possible with a minimum of Instructions furnished by the supplier for the
30 psi (0.21 MPa) at any point. safe storage, mixing and handling of the epoxy
Deflections of cantilevers shall be measured as bonding agent shall be followed. The epoxy shall
erection progresses and compared with computed be thoroughly mixed until it is of uniform color.
deflections. Any deviation from the required align- Use of a proper sized mechanical mixer operating
ment shall be corrected by either modifying the at no more than 600 RPM will be required. Con-
segment geometry during the casting operation or tents of damaged or previously opened containers
by inserting stainless steel screen wire shims in the shall not be used. Mixing shall not start until the
epoxy joints during erection. The maximum thick- segment is prepared for installation. Application of
ness of shims at any joint shall be l/16 in. (1.6mm). the mixed epoxy bonding agent shall be according
Provision shall be made to permit alignment ad- to the manufacturers instructions using trowel,
justments of a completed cantilevered portion of rubber glove or brush on one or both surfaces to
the box girder before the midspan splice connect- be joined. The coating shall be smooth and uni-
ing adjacent cantilevers is constructed. form and shall cover the entire surface with a mini-
(3) Grouting mum thickness of l/16 in. (1.6mm) applied on
both surfaces or l/8 in. (3.2mm) if applied on one
Grouting of the ducts shall be done in accord-
surface. Epoxy should not be placed within 3/8 in.
ance with Article 2.4.33 (I). Under normal condi-
(9.5mm) of prestressing ducts to minimize flow
tions, grouting shall be accomplished within 20
into the ducts. A discernible bead line must be ob-
calendar days following installation of tendons.
served on all exposed contact areas after tempo-
For delays beyond 20 days, tendons shall be pro-
rary post-tensioning. Erection operations shall be
tected with a water soluble oil or approved equal
coordinated and conducted so as to complete the
protective agent.
operations of applying the epoxy bonding agent
Protection of the tendon ducts against splitting
to the segments, erection, assembling, and tem-
from freezing of water in ducts must be provided
porary post-tensioning of the newly joined segment
until cement grout can be used. Use of some other
within 70 percent of the open time period of the
type grout should be considered when erecting in
bonding agent.
these low temperatures.
The epoxy material shall be applied to all sur-
(M) Epoxy Bonding Agents for Precast Segmental faces to be joined within the first half of the gel
Box Girders time, as shown on the containers. The segments
All epoxy bonding agents shall meet the require- shall be joined within 45 minutes after applica-
ments of Article 1.6.25 (B) (5) (a). Two-part tion of the first epoxy material placed and a mini-
epoxy bonding agents shall be supplied to the erec- mum average temporary prestress of 50 psi (0.35
tion site in sealed containers, pre-proportioned MPa) over the cross section should be applied with-
in the proper reacting ratio, ready for combining in 70 percent of the open time of the epoxy mater-
and through mixing in accordance with the manu- ial. At no point of the cross section shall the tem-
facturers instructions. All containers shall be porary prestress be less than 30 psi (0.21 MPa).
properly labeled to designate the resin component The joint shall be checked immediately after
and the hardener component as well as the tem- erection to verify uniform joint width and proper
perature range for its application. The substrate fit. Excess epoxy from the joint shall be removed
temperature range of 40F to 115F (5C to 46C) where accessible. All tendon ducts shall be swabbed
may be divided into either two or three applica- immediately after stressing, while the epoxy is
tion ranges for bonding agents. Such ranges shall still in the non-gelled condition, to remove or
overlap each other by at least 6F (3C). smooth out any epoxy in the conduit and to seal
Surfaces to which the epoxy material is to be any pockets or air bubble holes that have formed
applied shall be free from oil, laitance, form re- at the joint.
lease agent, or any other material that would pre- If the jointing is not completed within 70 per-
vent the material from bonding to the concrete cent of the open time, the operation shall be ter-
surface. All laitance and other contaminants shall minated and the epoxy bonding agent shall be
be removed by light sandblasting or by high pres- completely removed from the surfaces. The sur-
sure water blasting with a minimum pressure of faces must be prepared again and fresh epoxy shall
5000 psi (35 MPa). Wet surfaces should be dried be applied to the surface before resuming jointing
before applying epoxy bonding agents. The sur- operations.
face should be at least the equivalent of saturated As general instructions cannot cover all situa-
109
tions, specific recommendations and instructions Specification: 30 minutes minimum on one
shall be obtained in each case from the Engineer quart (0.95Q) and one gallon (3.79Q) quantities
in charge. at the maximum temperature of the designated
Epoxy bonding agents shall be tested to deter- application temperature range. (Note: gel time is
mine their workability, gel time, open time, bond not to be confused with open time specified in
and compression strength, shear, and working tem- Test 3).
perature range. See Article 2.4.33 (0) for test Test 3 - Open Time of Bonding Agent
methods and recommended specification limits.
This test measures workability of the epoxy
The frequency of the tests shall be stated in the
bonding agent for the erection and post-tensioning
Special Provisions of the Contract.
operations. As tested here, open time is defined as
The Contractor shall furnish the Engineer sam-
the minimum allowable period of elapsed time
ples of the material for testing, and a certification
from the application of the mixed epoxy bonding
from a reputable independent laboratory indicating
agent to the precast segments until the two seg-
that the material has passed the required tests.
ments have been assembled together and tempo-
(N) Inspection of Precast Segmental Box Girder rarily post-tensioned.
Jointing Procedures Testing Method: Open time is determined using
In addition to the material acceptance tests, test specimens as detailed in the Tensile Bending
which should be initially performed by a neutral Test (Test 4). The epoxy bonding agent, at the
testing laboratory and then checked by the owners highest specified application temperature, is mixed
organization, the owners inspector should make together and applied as instructed in Test 4 to the
regular checks of the epoxy jointing procedures. concrete prisms which shall also be at the highest
Data such as weather, ambient temperature, con- specified application temperature. The adhesive
crete surface temperature, adhesive batch number, coated prisms shall be maintained for 60 minutes
and the jointing time should be noted. The inspec- at the highest specified application temperature
tor should frequently sample and record data such with the adhesive coated surface or surfaces ex-
as the observed gel time of the epoxy bonding posed and uncovered before joining together.
agent, the surface conditions of the segments The assembled prisms are then cured and tested as
being joined, the adequacy of coverage of the ad- instructed in Test 4.
hesive, the amount of material being squeezed Specification: The epoxy bonding agent is ac-
from the joints, and the approximate open time of ceptable for the specified application temperature
the epoxy. An approximate determination of the only when essentially total fracturing of concrete
open time can be noted from behavior of lap joint paste and aggregate occurs with no evidence of
samples spread on small cement-asbestos boards. adhesive failure.
(0) Epoxy Bonding Agent Tests Construction situations may sometimes require
application of the epoxy bonding agent to the
Test 1 - Sag Flow of Mixed Epoxy Bonding Agent precast section prior to erecting, positioning and
This test measures the application workability of assembling. This operation may require epoxy
the bonding agent. bonding agents having prolonged open time. In
Testing Method: ASTM D 2730 for the desig- general, where the erection conditions are such
nated temperature range. that the sections to be bonded are prepositioned
Specification: Mixed epoxy bonding agent must prior to epoxy application, the epoxy bonding
not sag flow at l/8 in. (3.2mm) minimum thick- agent shall have a minimum open time of 60 min-
ness at the designated minimum and maximum utes within the temperature range specified for
application temperature range for the class of its application.
bonding agents used.
Test 4 - Three Point Tensile Bending Test
Test 2 - Gel Time of Mixed Epoxy Bonding Agent This test, performed on a pair of concrete
Gel time is determined on samples mixed as prisms bonded together with epoxy bonding agent,
specified in the testing,method. It provides a guide determines the bonding strength between the
for the period of time the mixed bonding agent bonding agent and concrete. The bonded concrete
remains workable in the mixing container and dur- prisms are compared to a reference test beam of
ing which it must be applied to the match-cast jo concrete 6x6~18 in. (150x150x460mm).
joint surfaces. Testing Method: 6x6x9 in. (150xl50x230mm)
Testing Method: ASTM D 2471 (except that concrete prisms of 6000 psi (41 MPa) compressive
one quart and one gallon quantities shall be tested). strength at 28 days shall be sandblasted on one 6x6
110
in. side to remove mold release agent, laitance, tion temperature range.
etc., and submerged in clean water at the lower Testing Method: ASTM D 648.
temperature of the specified application tempera- Specification: A minimum deflection tempera-
ture range for 72 hours. Immediately on removing ture of 122F (5OC) at fiber stress loading of 264
the concrete prisms from the water, the sand- psi (1.8 MPa) is required on test specimens cured
blasted surfaces shall be air dried for one hour at 7 days at 77F (25C).
the same temperature and 50 percent RH and each Test 7 - Compression and Shear Strength of
shall be coated with approximately a l/16 in. (1.6
Cured Epoxy Bonding Agent
mm) layer of the mixed bonding agent. The adhe-
sive coated faces of two prisms shall then be placed This test is a measure of the compressive strength
together and held with a clamping force normal to and shear strength of the epoxy bonding agent
the bonded interface of 50 psi (0.35 MPa). The as- compared to the concrete to which it bonds. The
sembly shall then be wrapped in a damp cloth slant cylinder specimen with the epoxy bonding
which is kept wet during the curing period of agent is compared to a reference test cylinder of
24 hours at the lower temperature of the specified concrete only.
application temperature range. Testing Method: A test specimen of concrete
After 24 hours curing at the lower temperature is prepared in a standard 6x12 in. (15Ox300mm)
of the application temperature range specified for cylinder mold to have a height at midpoint of 6 in.
the epoxy bonding agent, the bonded specimen and an upper surface with a 30-degree slope from
shall be unwrapped, removed from the clamping the vertical. The upper and lower portions of the
assembly and immediately tested. The test shall specimen with the slant surfaces may be formed
be conducted using the standard ASTM C78 test through the use of an elliptical insert or by sawing
for flexural strength with third point loading and a full sized 6x12 in. cylinder. If desired, 3x6 in.
the standard MR unit. At the same time the two (75xl50mm) or 4x8 in. (lOOx200mm) specimens
prisms are preapred and cured, a companion test may be used. After the specimens have been moist
beam shall be prepared of the same concrete, cured for 14 days, the slant surfaces shall be pre-
cured for the same period and tested following pared by light sandblasting, stoning or acid etching,
ASTM C78. then washing and drying the surfaces, and finally
Specification: The epoxy bonding agent is ac- coating one of the surfaces with a 10 mil (0.25mm)
ceptable if the load on the prisms at failure is thickness of the epoxy bonding agent under test.
greater than 90% of the load on the reference test The specimens shall then be pressed together
beam at failure. and held in position for 24 hours. The assembly
shall then be wrapped in a damp cloth which shall
Test 5 - Compression Strength of Cured Epoxy be kept wet during an additional curing period of
Bonding Agent 24 hours at the minimum temperature of the
This test measures the compressive strength of designated application temperature range. The
the epoxy bonding agent. specimen shall then be tested at 77F (25C) follow-
Testing Method: ASTM D 695. ing ASTM C 39 procedures. At the same time as
Specification: Compressive strength at 77F the slant cylinder spcimens are made and cured, a
(25C) shall be 2000 psi (14 MPa) minimum after companion standard test cylinder of the same con-
24 hours cure at the minimum temperature of the crete shall be made, cured for the same period,
designated application temperature range and 6000 and tested following ASTM C 39.
psi (41 MPa) at 48 hours. Specification: The epoxy bonding agent is ac-
Test 6 - Temperature Deflection of Epoxy Bond- ceptable for the designated application tempera-
ture range if the load on the slant cylinder speci-
ing Agent
ment is greater than 90 percent of the load on the
This test determines the temperature at which companion cylinder. The bond strength on the
an arbitrary deflection occurs under arbitrary slant surface (shear), determined by dividing the
testing conditions in the cured epoxy bonding specimen test load by the area of the elliptical slant
agent. It is a screening test to establish perform- surface, shall be at least 3000 psi (21 MPa) at 48
ance of the bonding agent throughout the erec- hours.
111
A.2 Summary of Precast Segmental Concrete
Bridges in the United States and Canada With
Cross Sections
Note: for metric dimensions
1 ft. = 0.3048 m
1 in. = 25.4 mm
v-0
l- 1
J
23'.5"
c 4
1'.ll'%" 3,-o" l'e 2'-(1 6'-6"
-. I- -I " .
Fig. A.2.2 Bear River Bridge, Nova Scotia Fig. A.2.5 North Vernon, Indiana
End Spans: 203 feet 9 inches Over Muscatatuck River
Interior Spans: 265 feet Spans: 95 feet - 190 feet - 95 feet
Bridge Length: 1997.50 feet Bridge Length: 380 feet
Segment Length: 14 feet 2 inches Segment Length: 8 feet
112
Fig. A.26 Kishwaukee River Bridge, Illinois , -9 lo.0
4,-O SPLICE
Fig. A.2.8 Turkey Run, Indiana Fig. A.2.11 Scottdale Bridge, Michigan
Bridge Length: 322 feet Bridge Length: 407 feet
Spans: 180 feet - 180 feet Spans: 97 feet - 206.5 feet - 97 feet
Segment Length: 8 feet Segment Length: 8 feet
113
Fig. A.2.15 Akron Bridge, Ohio
Westbound: 3660 feet
Eastbound: 3646 feet
Spans: Variable 100 to 290 feet
Segment Length: 6,7 and 8 feet
Fig. A.2.12 Illinois River, Illinois
Eastbound: 3329.5 feet
Westbound: 3203.5 feet
Approach Spans: 175 feet - 230 feet
Main Spans: 390 feet - 550 feet - 390 feet
Segment Length: 10 feet
l-3-1,4 ,4.11,16
114
A.3 Notation c, = distance from centroid to top fiber
A = cross sectional area of segment c,, = distance from centroid to bottom fiber
d = web thickness
A = area of top slab
A, = area of concrete section d, = slab thickness
= d = thickness of top and bottom slab (Fig.
E 28-day modulus of elasticity of concrete
Fi = initial prestressing force 3.38)
e = eccentricity of post-tensioning force
Ff = final prestressing force
= base of natural logrithms = 2.718. . .
H = horizontal distance center to center of
;I, = 28-day compressive strength of concrete
webs
I = moment of inertia test cylinders
L = span length f, = concrete stress
L = unit length along span f cb = bottom fiber compressive stress
h = horizontal displacement
M, = transverse moments
Mcr = creep moment resulting from change of h th = theoretical thickness of structural element
statical system with respect to relative humidity
II = cantilever length (Fig. 3.8)
ME = erection moment
= uniformly distributed load (Fig. 3.8)
M, = moment due to loads before change of q
t = theoretical age
statical system (Fig. 3.10)
t = theoretical time after casting (days)
MI, = moment due to same loads, considered to
produce M,, applied to changed statical t, = theoretical age of concrete at time of
system (Fig. 3.10) loading (days)
M, = moment at time t t, = rate of change of torsional shear force in
M, = torsional moment per unit length of box top and bottom slabs
girder t, = rate of change of torsional shear force in
N, = ratio of longitudinal forces obtained from webs
computer analysis to forces obtained from t, = time of completion of the structure
elementary beam theory t, = time of application of the dead load
= V = vertical displacement
P post-tensioning force
P = load causing deflection 6 (Fig. 3.11) w = unit weight of concrete
= Z = vertical dimension from centerline of box
P loading per unit length (Fig. 3.35)
R = reaction before settlement (Fig. 3.11) section to centerline of slab
R = support reactions (Fig. 3.36) AS, = member elongation due to shrinkage re-
Sh = horizontal shear force in transverse analysis straint force, St
s, = E,h EA, elastic shrinkage restraint force A f,ht 8, member shortening due to shrink-
sht =
115
= factor variable from zero to unity indi- a = stress
fld(t-t,)
cating the variation of #d with time 7 = maximum shear stress in bottom slab
rClfW - Brct,, = factor variable from zero to unity [Fig. 3.38(a)]
indicating the variation of $f with 7 = torsional shear stress
time 4 = ecr/ee, creep factor, also = @d + @f
6 = elastic deflection (Fig. 3.8) @t = E,,/E~ at time t
EC, = creep strain @d = creep due to delayed elasticity or re-
E, = elastic strain coverable creep on removal of load
Esh = shrinkage strain at infinity Of = creep due to flow, not recoverable
Esht = shrinkage strain at time t ~kt,) = magnitude of the creep factor at time t for
x = factor used in determining the theore- a concrete specimen loaded at time t,
tical thickness hth (Table 3.1) @d, = magnitude of delayed elasticity at
P = perimeter of concrete section in contact infinity
with the atmosphere @f, = magnitude of flow at infinity
116