FUNDACION VIVE MEJOR

FORMATO NO. 9
UNIDAD EJECUTORA/COMITE TECNICO
FUNDACION VIVE MEJOR
PROYECTO:CONSTRUCCION PARQUE SANTA ROSA DE COPAN
FECHA: JUNIO DEL2017

I TERRACERIA
ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
1 EXCAVACION SUELO TIPO I CON RETROEXCAVADORA M3 D
2,000.00 64.51 L. 129,020.00
2 ACARREO DE MATERIAL CON VOLQUETA 5M3 Y CARGADORA M3 1,000.00 373.57 L. 373,570.00
TOTAL -TERRACERIA L. 502,590.00
II PORTAL DE ENTRADA
ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
3 TRAZADO Y MARCADO M.L. D44.25 15.36 L. 679.68
4 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 10.87 145.63 L. 1,583.00
5 RELLENO COMP. MATERIAL CERNIDO DEL SITIO M3 6.43 68.76 L. 442.13
6 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 5.55 373.57 L. 2,073.31
7 RELLENO COMPACTADO CON MATERIAL SELECTO M3 1.05 454.20 L. 476.91
8 ZAPATA CORRIDA 0.50, e=0.20 , 4 N3, N 3 @ 30 cms M.L. 18.85 388.40 L. 7,321.34
9 ZAPATA AISLADA Z-1 0.90X0.90X0.25 mts 5#3 a.s. UND 4.00 974.21 L. 3,896.84
10 ZAPATA AISLADA Z-2 1.90X0.60X0.25 mt 4#4 LONG. + 11#4 TRANSV. UND 1.00 1,578.16 L. 1,578.16
11 CONCRETO 76 KG/CM2 M3 0.11 1,275.55 L. 140.31
12 COLUMNA 30 X 30 4N4, N2 @ 20, CONCRETO 1:2:2 M.L. 4.20 1,230.56 L. 5,168.35
13 CASTILLO DE 0.15X0.15m, 4#3, #2@20cm, CONC 1:2:2 ML 27.36 380.26 L. 10,403.91
14 CASTILLO 15X10, 2#3 Y #2 @ 20,CONCRETO 1:2:2 ML 3.42 356.04 L. 1,217.66
15 CASTILLO Ca-3 15X25 cm 6#3 + #2 a 20 cm CONCRETO 1:2:2 ML 3.42 694.78 L. 2,376.15
16 CASTILLO Ca-4 15X(20+20)(10+10) cm 6#3 + #2 a 20 cm CONCRETO 1:2:2 ML 3.42 802.55 L. 2,744.72
17 CASTILLO Ca-5 15X(15+13)(10+10) cm 6#3 + #2 a 20 cm CONCRETO 1:2:2 ML 3.42 739.64 L. 2,529.57
18 COLUMNA METALICA TIPO H W6X20 L = 3.40 ml UND 4.00 4,500.00 L. 18,000.00
19 COLUMNA DE TUBO ESTRUCTURAL DE 8" L = 3.40 ml UND 2.00 4,000.00 L. 8,000.00
20 SOBRECIMIENTO DE BLOQUE 15 RELLENO CONC. M2 M2 7.92 752.12 L. 5,956.79
21 SOLERA INFERIOR 15X15cm,4#3, #2@20cm,CONC. 1:2:2 M.L. 18.85 393.42 L. 7,415.97
22 PARED DE BLOQUE SIMPLE DE 15cm M2 51.75 711.56 L. 36,823.23
23 REPELLO Y PULIDO DE PAREDES e=2 CM MORTERO DE 1:4 M2 113.98 122.08 L. 13,914.68
24 AZULEJO 20X20cm EN PARED (CON PASTA CEMENTO) M2 17.57 493.04 L. 8,662.71
25 SOLERA 15x25cm, 4#4,#2@20cm,CONC 1:2:2 ML 18.85 514.70 L. 9,702.10
26 SOLERA 10X15 2No.3 Y No.2 @ 20 CONCRETO 1:2:2 M.L. 18.85 364.88 L. 6,877.99
27 CARGADOR DE 10X15 2#3;#2 @ 0.20 CONCRETO 1:2:2 ML 1.80 253.52 L. 456.34
28 BATIENTE C/PESTAA 20x10cm,2#3,#2@20cm,CONC 1:2:2 M.L. 0.70 264.61 L. 185.23
29 LOSA DE CONCRETO e = 5 cm #3 a 30 cm, CANALETA 6" Y LAMINA ALUZINC M2 9.57 2,101.96 L. 20,115.76
30 IMPERMEABILIZACION ( APLICADA CON BROCHA) M2 7.02 250.00 L. 1,755.00
31 PISO CONCRETO, 7 CMS, #2@0.20, 1:2:3, CON COLORANT M2 7.02 689.08 L. 4,837.34
32 APLICACION DE SELLADOR EN PARED NUEVA M2 96.41 141.90 L. 13,680.58
33 PINTURA DE ACEITE M2 96.41 173.58 L. 16,734.85
34 PUERTA METALICA P-1,LAM TROQ 0.90X2.10m, CEB UND 1.00 5,500.00 L. 5,500.00
35 VENTANA CORREDIZA VIDRIO ALUMINIO NATURAL M2 0.36 3,500.00 L. 1,260.00
36 SERVICIO SANITARIO (INC. ACCESORIOS)(SUM/INST) UNID 1.00 7,299.52 L. 7,299.52
37 LAVAMANOS (INC. ACCESORIOS) (SUM/INST) UNID 1.00 4,905.20 L. 4,905.20
38 CANOPY UND 1.00 30,000.00 L. 30,000.00
39 ELEMENTO DE PORTAL CON ANCLAJE UND 1.00 65,446.50 L. 65,446.50
40 PORTON METALICO DE ACCESO DOBLE HOJA UND 1.00 25,000.00 L. 25,000.00
TOTAL - PORTAL DE ACCESO L. 355,161.81

Suyapa Andino CICH 2849


FUNDACION VIVE MEJOR

III GIMNACIO AL AIRE LIBRE


ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
41 TRAZADO Y MARCADO M.L. D52.00 15.36 L. 798.72
42 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 30.96 145.63 L. 4,508.70
43 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 38.70 373.57 L. 14,457.16
44 RELLENO DE MATERIAL SELECTO COMPACTADO C/COMPACTADORA DE PLATO M3 20.00 454.20 L. 9,084.00
45 CIMENTACION MAMPOSTERIA,CAMA ARENA e=5cm,MORT 1:5 M3 1.05 1,691.48 L. 1,776.05
46 PISO DE CONCRETO 1:2:2. REF.#2@30cms,e=8cms, A.S. M2 255.00 697.94 L. 177,974.70
47 JUNTA ASFALTICA EN PAVIMENTOS ML 50.00 350.00 L. 17,500.00
48 CONCRETO DE 210 KG/CM M3 4.80 1,760.26 L. 8,449.25
TOTAL - GIMNASIO AL AIRE LIBRE L. 234,548.59

IV JUEGOS INFANTILES
ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
49 TRAZADO Y MARCADO M.L. D
110.00 15.36 L. 1,689.60
50 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 32.23 145.63 L. 4,693.65
51 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 40.29 373.57 L. 15,051.14
52 RELLENO DE MATERIAL SELECTO COMPACTADO C/COMPACTADORA DE PLATO M3 32.23 454.20 L. 14,638.87
53 SUMINISTRO DE ARENA FINA M3 32.23 350.00 L. 11,280.50
TOTAL - JUEGOS INFANTILES CON ARENA L. 47,353.76

V MODULO DE COMIDAS (2)


ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
54 TRAZADO Y MARCADO M.L. D51.30 15.36 L. 787.97
55 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 22.96 145.63 L. 3,343.66
56 RELLENO COMP. MATERIAL CERNIDO DEL SITIO M3 14.60 68.76 L. 1,003.90
57 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 10.46 373.57 L. 3,907.54
58 RELLENO COMPACTADO CON MATERIAL SELECTO M3 4.64 454.20 L. 2,107.49
59 ZAPATA CORRIDA 0.50, e=0.20 , 4 N3, N 3 @ 30 cms M.L. 47.60 388.40 L. 18,487.84
60 SOBRECIMIENTO DE BLOQUE 15 RELLENO CONC. M2 M2 21.54 752.12 L. 16,200.66
61 SOLERA INFERIOR 15X15cm,4#3, #2@20cm,CONC. 1:2:2 M.L. 51.30 393.42 L. 20,182.45
62 CASTILLO DE 0.15X0.15m, 4#3, #2@20cm, CONC 1:2:2 ML 39.50 380.26 L. 15,020.27
63 CONCRETO DE 150 KG/CM M3 0.02 3,581.29 L. 71.63
64 ACERO DE REFUERZO GRADO 40 Fy=2800 Kg/cm2 KG 3.20 32.50 L. 104.00
65 CASTILLO 15X10, 2#3 Y #2 @ 20,CONCRETO 1:2:2 ML 28.30 356.04 L. 10,075.93
66 SOLERA 15X20cm, 4#3, #2@15cm, CONC. 1:2:2 ML 27.20 415.72 L. 11,307.58
67 PARED DE BLOQUE SIMPLE DE 15cm M2 66.16 711.56 L. 47,076.81
68 PARED DE BLOQUE SIMPLE DE 10 CM. M2 29.34 530.47 L. 15,563.99
69 REPELLO Y PULIDO DE PAREDES e=2 CM MORTERO DE 1:4 M2 149.06 122.08 L. 18,197.24
70 REPELLO DE PAREDES MORTERO 1:4 e= 2 CMS M2 9.46 122.08 L. 1,154.88
71 ENCHAPE DE PORCELANATO TEXTURA DE MADERA M2 9.46 522.89 L. 4,946.54
72 LOSA DE CONCRETO A=50CM, e=5CM, 5#3 LONG + #2@15CM TRANSV ML 10.50 1,102.88 L. 11,580.24
73 PISO CONCRETO, 7 CMS, #2@0.20, 1:2:3, CON COLORANT M2 30.90 689.08 L. 21,292.57
74 SOLERA 10X15 2#3, #2@15 CONCRETO 1:2:2 M.L. 10.50 346.40 L. 3,637.20
75 CORTINAS METALICAS ENROLLABLES GLB 2.00 16,560.00 L. 33,120.00
76 TECHO DE LAMINA URBAN COLOR ROJO Y TUBO ESTRUCTURAL M2 80.76 790.50 L. 63,840.78
77 FACIA DE DUROBLOK M2 9.60 637.32 L. 6,118.27
78 PUERTA P-1 0.72X0.85 mt UND 6.00 3,500.00 L. 21,000.00
79 LAVAPLATO ACERO INOXIDABLE 1.35X0.5 INC. PARED LAD UNID 6.00 7,057.96 L. 42,347.76
80 MUEBLE DE CONCRETO A=0.60, #3 @0.27 A/S ML 7.50 464.30 L. 3,482.25
81 AZULEJO 15X15cm EN PARED (CON PASTA CEMENTO) M2 21.60 470.00 L. 10,152.00
82 LAVAMANOS (INC. ACCESORIOS) (SUM/INST) UNID 2.00 4,905.20 L. 9,810.40
83 APLICACION DE SELLADOR EN PARED NUEVA M2 127.46 141.90 L. 18,086.57
84 PINTURA DE ACEITE M2 127.46 173.58 L. 22,124.51
TOTAL -2 MODULOS DE COMIDAS L. 456,132.94

Suyapa Andino CICH 2849


FUNDACION VIVE MEJOR

VI MODULO SANITARIO
ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
85 TRAZADO Y MARCADO M.L. D44.62 15.36 L. 685.36
86 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 22.02 145.63 L. 3,206.77
87 RELLENO COMP. MATERIAL CERNIDO DEL SITIO M3 14.88 68.76 L. 1,023.15
88 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 8.92 373.57 L. 3,332.24
89 RELLENO COMPACTADO CON MATERIAL SELECTO M3 5.05 454.20 L. 2,293.71
90 ZAPATA CORRIDA 0.50, e=0.20 , 4 N3, N 3 @ 30 cms M.L. 44.62 388.40 L. 17,330.41
91 ZAPATA AISLADA 0.50X0.70X0.80, #3 @ 0.20 A/S UND 2.00 1,200.00 L. 2,400.00
92 SOBRECIMIENTO DE BLOQUE 15 RELLENO CONC. M2 M2 17.85 752.12 L. 13,425.34
93 SOLERA INFERIOR 15X15cm,4#3, #2@20cm,CONC. 1:2:2 M.L. 44.62 393.42 L. 17,554.40
94 CASTILLO DE 0.15X0.15m, 4#3, #2@20cm, CONC 1:2:2 ML 28.33 380.26 L. 10,772.77
95 CASTILLO 15X10, 2#3 Y #2 @ 20,CONCRETO 1:2:2 ML 17.65 356.04 L. 6,284.11
96 JAMBA 10X10, 2#3, #2@15, CONCRETO 1:2:2 ML 12.60 230.81 L. 2,908.21
97 CASTILLO DE 10X30 cm 3#3+#2@20 cm CONCRETO 1:2:2 ML 2.75 616.10 L. 1,694.28
98 CASTILLO DE 10X25 cm 3#3+#2@20 cm CONCRETO 1:2:2 ML 5.10 599.38 L. 3,056.84
99 CASTILLO 25X15cm, 4#3,#2@0.15m, CONCRETO 1:2:2 ML 2.70 698.75 L. 1,886.63
100 COLUMNA DE TUBO HG DE 4" LIVIAN0 L = 3.80 ml UND 2.00 2,500.00 L. 5,000.00
101 SOLERA 15X20cm, 4#3, #2@15cm, CONC. 1:2:2 ML 35.30 415.72 L. 14,674.92
102 SOLERA 10X10cm, 2#3, #2@20cm, CONC 1:2:2 ML 6.89 347.15 L. 2,391.86
103 PARED DE BLOQUE SIMPLE DE 15cm M2 83.23 711.56 L. 59,223.14
104 PARED DE BLOQUE SIMPLE DE 10 CM. M2 12.65 530.47 L. 6,710.45
105 REPELLO Y PULIDO DE PAREDES e=2 CM MORTERO DE 1:4 M2 88.16 122.08 L. 10,762.57
106 REPELLO DE PAREDES MORTERO 1:4 e= 2 CMS M2 113.45 122.08 L. 13,849.98
107 CERAMICA EN PARED DE 25X30 CM M2. 113.45 L. 0.00
108 PISO CONCRETO, 7 CMS, #2@0.20, 1:2:3, CON COLORANT M2 33.68 689.08 L. 23,208.21
109 LOUVER DE PLATINA DE 3/4"X1/4" @0.10 M2 31.32 L. 0.00
110 TECHO DE LAMINA URBAN COLOR ROJO Y TUBO ESTRUCTURAL M2 62.71 790.50 L. 49,572.26
111 PILETA DE ASEO H=0.45, A=0.50, L=0.65m UND 1.00 2,500.00 L. 2,500.00
112 MUEBLE DE CONCRETO A=0.60, #3 @0.27 A/S ML 4.00 464.30 L. 1,857.20
113 LAVAMANOS (INC. ACCESORIOS) (SUM/INST) UNID 4.00 4,905.20 L. 19,620.80
114 SERVICIO SANITARIO (INC. ACCESORIOS)(SUM/INST) UNID 4.00 7,299.52 L. 29,198.08
115 URINARIO DE PORCELANA (INC. ACCESOR.)(SUM/INST.) UNID 2.00 L. 0.00
116 PUERTA DE TABLERO DE MADERA DE COLOR 0.70X1.50 mt UND 4.00 5,000.00 L. 20,000.00
117 PUERTA DE TABLERO DE MADERA DE COLOR 1.00X1.50 mt UND 2.00 5,000.00 L. 10,000.00
118 PUERTA DE TABLERO DE MADERA DE COLOR 1.00X2.07 mt UND 1.00 6,500.00 L. 6,500.00
119 BARRA PARA DISCAPACITADOS UND 2.00 L. 0.00
120 RAMPA DE CONCRETO 1:3:5 C/PASAMANOS A=1.08m ML 4.30 L. 0.00
121 APLICACION DE SELLADOR EN PARED NUEVA M2 88.16 141.90 L. 12,509.90
122 PINTURA DE ACEITE M2 88.16 173.58 L. 15,302.81
TOTAL - MODULO SANITARIO L. 390,736.38

VII ANFITEATRO
ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
123 TRAZADO Y MARCADO M.L. D
185.10 15.36 L. 2,843.14
124 EXCAVACION MATERIAL TIPO III (ROCA, SUELTA) M3 27.63 L. 0.00
125 RELLENO COMP. MATERIAL CERNIDO DEL SITIO M3 15.61 68.76 L. 1,073.34
126 RELLENO COMPACTADO CON MATERIAL SELECTO M3 16.94 454.20 L. 7,694.15
127 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 15.03 373.57 L. 5,614.76
128 ZAPATA AISLADA Z-1 1.40X1.40X0.30 mt 10 #4 @ 10 cm a.s. UND 3.00 L. 0.00
129 CONCRETO 76 KG/CM2 M3 0.15 1,275.55 L. 191.33
130 COLUMNA 30 X 30, 8N6, N3 @ 0.2.CONC. 1:2:2 M.L. 9.90 L. 0.00
131 ZAPATA CORRIDA 0.50, e=0.20 , 4 N3, N 3 @ 30 cms M.L. 21.70 388.40 L. 8,428.28
132 SOBRE ELEVACION DE BLOQUE 8", REF. 1#3 @AGUJERO M2. 18.23 947.30 L. 17,269.28
133 SOLERA 20X20, 4No.3 Y No.2 @ 15cm, CONCRETO 1:2:2 M.L. 43.40 435.07 L. 18,882.04
134 CASTILLO 20X20 4 N3, N2@15CM, CONCRETO 1:2:2 ML 10.79 676.21 L. 7,296.31
135 CASTILLO DE 0.15X0.15m, 4#3, #2@20cm, CONC 1:2:2 ML 20.20 380.26 L. 7,681.25
136 PARED DE BLOQUE SIMPLE DE 15cm M2 25.63 711.56 L. 18,237.28
137 REPELLO Y PULIDO DE PAREDES e=2 CM MORTERO DE 1:4 M2 71.87 122.08 L. 8,773.89
138 APLICACION DE SELLADOR EN PARED NUEVA M2 71.87 141.90 L. 10,198.35
139 PINTURA ACRILICA PROPORCION 1:4 M2 71.87 L. 0.00
140 PISO CONCRETO, 7 CMS, #2@0.20, 1:2:3, CON COLORANT M2 16.12 689.08 L. 11,107.97
141 GRADAS DE MAMPOSTERIA HUELLA DE CONC. DIS. FHIS M.L 1.80 L. 0.00
142 REPELLO Y PULIDO DE PAREDES e=2 CM MORTERO DE 1:4 M2 0.90 122.08 .
143 SOLERA 15X20cm, 4#3, #2@15cm, CONC. 1:2:2 ML 63.10 415.72 L. 26,231.93
144 SOLERA 10X15 2#3, #2@15 CONCRETO 1:2:2 M.L. 63.10 346.40 L. 21,857.84
145 SOBRECIMIENTO DE BLOQUE SIMPLE M2 26.50 752.12 L. 19,931.18
146 TECHO LAMINA TIPO URBAN COLOR ROJO Y ESTRUCTURA METALICA ANFITEATRO M2 30.56 790.50 L. 24,157.68
TOTAL - ANFITEATRO L. 217,470.00

Suyapa Andino CICH 2849


FUNDACION VIVE MEJOR

VIII BARRACA MILITAR


ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
147 TRAZADO Y MARCADO M.L. D32.13 15.36 L. 493.52
148 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 12.66 145.63 L. 1,843.68
149 RELLENO COMP. MATERIAL CERNIDO DEL SITIO M3 3.62 68.76 L. 248.91
150 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 11.31 373.57 L. 4,225.08
151 RELLENO COMPACTADO CON MATERIAL SELECTO M3 3.19 454.20 L. 1,448.90
152 ZAPATA CORRIDA 0.50, e=0.20 , 4 N3, N 3 @ 30 cms M.L. 24.60 388.40 L. 9,554.64
153 SOBRECIMIENTO DE BLOQUE 15 RELLENO CONC. M2 M2 13.49 752.12 L. 10,146.10
154 SOLERA INFERIOR 15X15cm,4#3, #2@20cm,CONC. 1:2:2 M.L. 64.25 393.42 L. 25,277.24
155 CASTILLO DE 0.15X0.15m, 4#3, #2@20cm, CONC 1:2:2 ML 28.45 380.26 L. 10,818.40
156 CASTILLO 15X10, 2#3 Y #2 @ 20,CONCRETO 1:2:2 ML 31.20 356.04 L. 11,108.45
157 CASTILLO 20X15 4#3, #2@20 CONCRETO 1:2:2 M.L. 2.40 440.16 L. 1,056.38
158 SOLERA 15X20cm, 4#3, #2@15cm, CONC. 1:2:2 ML 32.13 415.72 L. 13,357.08
159 CARGADOR DE 10X15 2#3;#2 @ 0.15 CONCRETO 1:2:2 M.L. 5.30 253.52 L. 1,343.66
160 BATIENTE C/PESTAA 20x10cm,2#3,#2@20cm,CONC 1:2:2 M.L. 3.30 264.61 L. 873.21
161 PARED DE BLOQUE SIMPLE DE 15cm M2 52.47 711.56 L. 37,335.55
162 PARED DE BLOQUE SIMPLE DE 10 CM. M2 12.44 530.47 L. 6,599.05
163 REPELLO Y PULIDO DE PAREDES e=2 CM MORTERO DE 1:4 M2 117.43 122.08 L. 14,335.85
164 CERAMICA EN PARED DE 25X30 CM M2. 12.41 L. 0.00
165 PISO CONCRETO, 7 CMS, #2@0.20, 1:2:3, CON COLORANT M2 23.34 689.08 L. 16,083.13
166 FIRME DE CONCRETO DE 5 cm DE ESPESOR M2 0.98 L. 0.00
167 TECHO CANALET.2"X4", ALUZINC ESMALTADA CAL.26 M2. 27.88 L. 0.00
168 LAVAMANOS (INC. ACCESORIOS) (SUM/INST) UNID 1.00 4,905.20 L. 4,905.20
169 SERVICIO SANITARIO (INC. ACCESORIOS)(SUM/INST) UNID 1.00 7,299.52 L. 7,299.52
170 DUCHA (INC. BORDILLO REPE. Y PUL.)(SUM/INST) UNID 1.00 L. 0.00
171 PUERTA DE TABLERO DE MADERA DE COLOR 1.00X2.07 mt UND 1.00 L. 0.00
172 PUERTA TERMOF.0.80X2.10m CONTRAM. MADERA UNID. 1.00 L. 0.00
173 VENTANA DE ALUMINIO, CELOSIA DE VIDRIO NEVADO M2 3.90 L. 0.00
174 RAMPA DE CONCRETO 1:3:5 C/PASAMANOS A=1.08m ML 2.00 L. 0.00
175 APLICACION DE SELLADOR EN PARED NUEVA M2 117.43 141.90 L. 16,663.32
176 PINTURA DE ACEITE M2 117.43 173.58 L. 20,383.50
TOTAL BARRACA MILITAR L. 215,400.35
IX AREA DE ZUMBA
ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
177 TRAZADO Y MARCADO M.L. D23.50 15.36 L. 360.96
178 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 23.50 145.63 L. 3,422.31
179 RELLENO COMPACTADO CON MATERIAL SELECTO M3 22.24 454.20 L. 10,101.41
180 PISO DE CONCRETO 1:2:2 CON #2@30 CM EN A.S. E=10 CM M2 30.80 L. 0.00
181 BORDILLO DE CONCRETO 15X15 CMS ML. 23.50 274.70 L. 6,455.45
TOTAL ZUMBA/DOJO L. 20,340.12

X CERCO FRONTAL 2
ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
182 TRAZADO Y MARCADO M.L. D11.05 15.36 L. 169.73
183 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 4.42 145.63 L. 643.68
184 RELLENO COMP. MATERIAL CERNIDO DEL SITIO M3 2.16 68.76 L. 148.52
185 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 2.83 373.57 L. 1,057.20
186 ZAPATA CORRIDA 0.50, e=0.20 , 4 N3, N 3 @ 30 cms M.L. 11.05 388.40 L. 4,291.82
187 SOBRECIMIENTO BLOQ. 6",RELLENO, 1#3@20 y 1#3@1 HIL M2 4.53 1,058.28 L. 4,794.01
188 SOLERA 15 X 15 4 N3, N3 @ 15 CONCRETO 1:2:2 M.L. 11.05 393.42 L. 4,347.29
189 CASTILLO 15X15cm, 4#3, #3@0.20cm,CONC 1:2:2 ML 13.76 380.26 L. 5,232.38
190 PARED BLOQ. 15cm,1#3 @60CM HORIZONTAL,MORTERO 1:4 M2 30.73 728.95 L. 22,400.63
191 SOLERA 10X15 2No.3 Y No.2 @ 20 CONCRETO 1:2:2 M.L. 11.05 364.88 L. 4,031.92
192 REPELLO Y PULIDO DE PAREDES e=2 CM MORTERO DE 1:4 M2 63.65 122.08 L. 7,770.39
193 APLICACION DE SELLADOR EN PARED NUEVA M2 63.65 141.90 L. 9,031.94
194 PINTURA DE ACEITE M2 63.65 173.58 L. 11,048.37
TOTAL - CERCO 2 FRONTAL L. 74,967.89

Suyapa Andino CICH 2849


FUNDACION VIVE MEJOR

XI CERCO FRONTAL 1
ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
195 TRAZADO Y MARCADO M.L. D29.38 15.36 L. 451.28
196 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 11.16 145.63 L. 1,625.23
197 RELLENO COMP. MATERIAL CERNIDO DEL SITIO M3 5.76 68.76 L. 396.06
198 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 6.75 373.57 L. 2,521.60
199 ZAPATA CORRIDA 0.50, e=0.20 , 4 N3, N 3 @ 30 cms M.L. 29.38 388.40 L. 11,411.19
200 SOBRECIMIENTO BLOQ. 6",RELLENO, 1#3@20 y 1#3@1 HIL M2 12.04 1,058.28 L. 12,741.69
201 SOLERA 15 X 15 4 N3, N3 @ 15 CONCRETO 1:2:2 M.L. 29.38 393.42 L. 11,558.68
202 CASTILLO 15X15cm, 4#3, #3@0.20cm,CONC 1:2:2 ML 5.56 380.26 L. 2,114.25
203 PARED BLOQ. 15cm,1#3 @60CM HORIZONTAL,MORTERO 1:4 M2 22.92 728.95 L. 16,707.53
204 BATIENTE DE 10X15 2 #3, #2@ 15 CONCR. 1:2:2 M.L. 29.38 240.00 L. 7,051.20
205 REPELLO Y PULIDO DE PAREDES e=2 CM MORTERO DE 1:4 M2 45.84 122.08 L. 5,596.15
206 APLICACION DE SELLADOR EN PARED NUEVA M2 45.84 141.90 L. 6,504.70
207 PINTURA DE ACEITE M2 45.84 173.58 L. 7,956.91
208 CERCA METALICA DE TUBO ESTRUCTURAL DE 2"X2" Y 1"X2" M2 51.80 L. 0.00
209 SIMBOLO ELEMENTO EN CERCA METALICA UND 6.00 L. 0.00
TOTAL - CERCO 1 FRONTAL L. 86,636.46

XII AREAS ADOQUINADAS


ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
210 TRAZADO Y MARCADO M.L. D
720.00 15.36 L. 11,059.20
211 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 227.25 145.63 L. 33,094.42
212 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 75.74 373.57 L. 28,294.19
213 RELLENO COMPACTADO CON MATERIAL SELECTO M3 151.51 454.20 L. 68,815.84
214 BORDILLO DE CONCRETO 15X15 CMS ML. 720.00 274.70 L. 197,784.00
215 ADOQUINADO 3000 PSI M2 720.00 725.09 L. 522,064.80
216 VIBRADO DE ADOQUIN CON COMPACTADORA DE PLATO M2 720.00 L. 0.00
TOTAL ADOQUINADO L. 861,112.45

XIII SISTEMAS DE AGUAS NEGRAS


ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
217 TRAZADO Y MARCADO M.L. D
105.96 15.36 L. 1,627.55
218 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 21.19 145.63 L. 3,085.90
219 RELLENO COMP. MATERIAL CERNIDO DEL SITIO M3 16.95 68.76 L. 1,165.48
220 ACARREO DE MATERIAL (DESPERDICIO) M3 4.24 117.30 L. 497.35
221 SUMINISTRO DE TUBERIA PVC DE 4" RD-41 M.L. 43.48 115.24 L. 5,010.64
222 SUMINISTRO DE TUBERIA PVC DE 2" RD-41 M.L. 62.48 46.09 L. 2,879.70
223 INSTALACION DE TUBERIA PVC DE 4" M.L. 43.48 26.15 L. 1,137.00
224 INSTALACION DE TUBERIA PVC DE 2" M.L. 62.48 24.65 L. 1,540.13
225 CAJA DE REGISTRO 0.80X0.80X0.85m UND 7.00 3,116.98 L. 21,818.86
TOTAL SISTEMA DE AGUAS NEGRAS L. 38,762.61

XIV SISTEMA DE AGUA POTABLE


ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
226 TRAZADO Y MARCADO M.L. D44.92 15.36 L. 689.97
227 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 6.74 145.63 L. 981.55
228 RELLENO COMP. MATERIAL CERNIDO DEL SITIO M3 4.04 68.76 L. 277.79
229 RELLENO COMPACT. CON MATERIAL DEL SITIO M3 2.70 454.20 L. 1,226.34
230 SUMINISTRO DE TUBERIA PVC DE 1" RD-26 M.L. 18.52 15.00 L. 277.80
231 SUMINISTRO DE TUBERIA PVC DE 3/4" RD-26 M.L. 15.95 11.67 L. 186.08
232 SUMINISTRO DE TUBERIA PVC DE 1/2" RD-13.5 M.L. 10.45 8.33 L. 87.08
233 INSTALACION DE TUBERIA PVC 1" M.L. 18.52 70.00 L. 1,296.40
234 INSTALACION DE TUBERIA PVC 3/4" M.L. 15.95 61.00 L. 972.95
235 INSTALACION DE TUBERIA PVC " M.L. 10.45 51.00 L. 532.95
236 CAJA DE CONEXION DOMICILIARIA UNID 4.00 2,000.00 L. 8,000.00
237 VALVULA COMPUERTA DE 1" PARA HG(SUM/INST) UNID 1.00 500.00 L. 500.00
238 VALVULA COMPUERTA DE 3/4" PARA HG(SUM/INST) UNID 3.00 450.00 L. 1,350.00
TOTAL SISTEMA DE AGUA POTABLE L. 16,378.91

Suyapa Andino CICH 2849


FUNDACION VIVE MEJOR

XV TRAMPAS DE GRASAS (2)


ITEM ACTIVIDAD UNID CANTIDA PRECIO TOTAL
239 TRAZADO Y MARCADO M.L. D 9.60 15.36 L. 147.46
240 EXCAVACION MATERIAL TIPO I (MATERIAL COMUN) M3 3.08 145.63 L. 448.54
241 ACARREO DE MATERIAL CON VOQUETA 5M3 Y CARGADORA M3 3.86 373.57 L. 1,441.98
242 LOSA CONCRETO e=8 CMS N3 a/c 20 CMS a/s M2 2.88 L. 0.00
243 CASTILLO 15X15, 3 No.3 Y No.2 @ 20,CONCRETO 1:2:2 M.L. 6.72 380.26 L. 2,555.35
244 PARED DE BLOQUE SIMPLE DE 15cm M2 6.80 711.56 L. 4,838.61
245 SOLERA 10X15 2No.3 Y No.2 @ 20 CONCRETO 1:2:2 M.L. 1.80 364.88 L. 656.78
246 REPELLO 1:4 e=2 CM Y AFINADO M2 15.20 122.08 L. 1,855.62
247 CONCRETO DE 210 KG/CM M3 0.32 1,760.26 L. 563.28
248 ACERO DE REFUERZO GRADO 40 Fy=2800 Kg/cm2 KG 21.78 L. 0.00
TOTAL 2 TRAMPAS DE GRASA L. 12,507.62

XVI SISTEMA ELECTRICO


310 SUM/INST transformador 75 KVA. Unidad 1.00 L. 0.00
311 SUM/INST medidor principal con base. Unidad 2.00 L. 0.00
312 SUM/INST Centro de Carga "PE". Unidad 1.00 L. 0.00
313 SUM/INST Centro de Carga "PTH". Unidad 1.00 L. 0.00
314 Suminsitro e onstalacin de Centro de Carga "PL1". Unidad 1.00 L. 0.00
315 SUM/INST Centro de Carga "PL2". Unidad 1.00 L. 0.00
316 SUM/INST Centro de Carga "PL3". Unidad 1.00 L. 0.00
317 SUM/INST Centro de Carga "PL4". Unidad 1.00 L. 0.00
318 SUM/INST Centro de Carga "PL5". Unidad 1.00 L. 0.00
319 SUM/INST Centro de Carga "PL6". Unidad 1.00 L. 0.00
320 SUM/INST medidores restaurantes con base. Unidad 6.00 L. 0.00
321 SUM/INST aterrizaje general. Unidad 1.00 L. 0.00

SUM/INST luminarias generales en poste, equivalente a T2M DSX1 MAST ARM LED,
322 4000K, 131W, 220V, de Lithonia Lighting. Unidad 25.00 L. 0.00
323 SUM/INST postes de 5"x5"x25 para luminarias generales. Unidad 20.00 L. 0.00
Suministro e instalacin de canalizacin y cableado iluminacin general. Utilizando
canalizacin PVC CED40 "3/4, y cableado 2x10 + 1x14 AWG THHN. Dejando cajas de
registro de 0.6x0.6x0.6m segn descritos en planos. Incluye zanjeado y compactado.

324 m.l. 1,076.00 L. 0.00


Suministro e instalacin de canalizacin y cableado de acometida para panel "PTH".
Utilizando canalizacin PVC CED40 3/4", y cableado 4x10 AWG THHN. Incluye zanjeado y
compactado.

325 m.l. 120.00 L. 0.00


Suministro e instalacin de canalizacin y cableado de acometida para panel "PL1".
Utilizando canalizacin PVC CED40 1", y cableado 3x08 + 1x10 AWG THHN. Incluye
zanjeado y compactado.
326 m.l. 40.00 L. 0.00
Suministro e instalacin de canalizacin y cableado de acometida para panel "PL2".
Utilizando canalizacin PVC CED40 1", y cableado 3x08 + 1x10 AWG THHN. Incluye
327 zanjeado y compactado. m.l. 40.00 L. 0.00
Suministro e instalacin de canalizacin y cableado de acometida para panel "PL3".
Utilizando canalizacin PVC CED40 1", y cableado 3x08 + 1x10 AWG THHN. Incluye
zanjeado y compactado.
328 m.l. 40.00 L. 0.00
Suministro e instalacin de canalizacin y cableado de acometida para panel "PL4".
Utilizando canalizacin PVC CED40 1", y cableado 3x08 + 1x10 AWG THHN. Incluye
zanjeado y compactado.
329 m.l. 40.00 L. 0.00
Suministro e instalacin de canalizacin y cableado de acometida para panel "PL5".
Utilizando canalizacin PVC CED40 1", y cableado 3x08 + 1x10 AWG THHN. Incluye
zanjeado y compactado.
330 m.l. 40.00 L. 0.00
Suministro e instalacin de canalizacin y cableado de acometida para panel "PL6".
Utilizando canalizacin PVC CED40 1", y cableado 3x08 + 1x10 AWG THHN. Incluye
zanjeado y compactado.

331 m.l. 40.00 L. 0.00

SUM/INST canalizacin y cableado de circuitos de iluminacin de mdulos, restaurantes,


332 anfiteatro y entrada. Utilizando canalizacin EMT 1/2", y cableado 2x12 + 1x14 AWG THHN. m.l. 153.00 L. 0.00

SUM/INST canalizacin y cableado de circuitos de tomacorrientes 110V de mdulos,


restaurantes, anfiteatro y entrada. Utilizando canalizacin EMT 1/2", y cableado 2x12 + 1x14
333 AWG THHN. m.l. 108.00 L. 0.00

SUM/INST canalizacin y cableado de circuitos de tomacorrientes 220V de mdulos,


restaurantes, anfiteatro y entrada. Utilizando canalizacin EMT 1/2", y cableado 4x12 AWG
334 THHN. m.l. 50.00 L. 0.00

Suyapa Andino CICH 2849


FUNDACION VIVE MEJOR

SUM/INST luminarias fluorescente 2x32W, equivalente a DM 2 32 MVOLT GEB10IS, de


335 Lithonia Lighting. Unidad 13.00 L. 0.00
Suministro e instalacin de luminarias de pared anti-vandlica con bombillo fluorescente
336 compacto de 13W. Unidad 12.00 L. 0.00

337 SUM/INST luminarias tipo rosseta superficial con bombillo fluorescente compacto de 11W. Unidad 2.00 L. 0.00
338 SUM/INST luminarias de emergencia similiar a la ELM de Lithonia Lighting. Unidad 3.00 L. 0.00
339 SUM/INST luminarias de pared similar a HLED-930/N de Tecno Light. Unidad 6.00 L. 0.00

340 SUM/INST luminaria tipo reflector LED 50W, 3000K, 4000LM, 120V, con apertura de 120. Unidad 4.00 L. 0.00
341 SUM/INST interruptores sencillos 120V 15AMP con placa. Unidad 13.00 L. 0.00
342 SUM/INST interruptores dobles 120V 15AMP con placa. unidad 8.00 L. 0.00
343 SUM/INST tomacorrientes dobles 120V con placa. unidad 35.00 L. 0.00
Suministro e instalacin de cableado de acometida principal de transformador hacia panel
general 2x1/0 + 1x02 AWG THHN.
344 m.l. 40.00 L. 0.00
TOTAL INSTALACIONES ELECTRICAS L. 0.00
TOTAL DE OBRA A OFERTAR = L. 3530,099.88