KARNATAKA NEERAVRI NIGAM LIMITED BALIS

KARNATAKA NEERAVARI NIGAM LIMITED


BHIMA LIFT IRRIGATION SCHEME

Err:502
BALUNDAGI LIFT MAIN CANAL

Item SL. QUANTIT RATE AMOUN


DESCRIPTION OF WORK UNIT
No NO. Y Rs. Ps T Rs.
1 2 3 4 5 6
1 Excavation in all kinds of soil including boulders upto 0.60 m dia.
(0.113 cum) for foundations of canal cross drainage and other
appurtenant structures and placing excavated stuff neatly in
specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50m and initial lift upto 1.5m. (SR
Item No.1, page 54 of WRD, for year 2003-04)

a) Lift 0.00 m to 1.50 m cum 18.000 45.00 810/-

2
Providing and laying insitu vibrated M-15 (28 days cube
compressive strength not less than 15 N/sqmm ) grade cement
concrete using 20 mm downsize approved, clean, hard, graded
aggregates for sub-structure/ super structure works including cost
of all materials, machinery, labour, formwork, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with all leads and lifts. (Cement content: 270
kg/cum) (SR Item No.15, page 56 of WRD, for year 2003-04)

Cum 46.400 2576.00 119526/-

3 Providing and laying reinforced concrete pipe NP3-600mm dia for


culverts including pointing ends, and fixing collars with cement
mortar 1:2 including cost of all materials, labour, curing complete
as per specifications.Specifications. No. KSRB 1000, 2300 MORT
& H Specification No. 1000/2300 Rmt 40.00 1656.00 66240/-

4
Providing semi-pervious/ pervious casing embankment with soil
from approved borrow areas in layers of 25 to 30 cm before
compaction including cost of all materials, machinery, labour, all
operations such as excavation, sortingout, transporting, spreading
in layer of specified thickness, breaking clods, sectioning,
watering, compacting to density control of not less than 95 percent
or as stipulated by power roller etc., complete with initial lead upto
1 km and all lifts.(SR Item No.8, page 39 of WRD, for year 2003-
04)
cum 68.000 123.82 8420/-

TOTAL 194996/-

#VALUE! TOTAL 195000/-

______________________________________________________________________________________________
Secon Private Ltd., Bangalore-66 CAUSE WAY @ Ch: 26+940KM OF BALUNDAGI LIFT MAIN CANAL
________________________________________________________________________________________________
KARNATAKA NEERAVRI NIGAM LIMITED BALIS
KARNATAKA NEERAVARI NIGAM LIMITED
BHIMA LIFT IRRIGATION SCHEME

DETAILED ESTIMATE FOR CONSTRUCTION OF CAUSEWAY AT CH: 26+940 KM


BALUNDAGI LIFT MAIN CANAL

Item SL. UNI


DESCRIPTION OF WORK No. L B D QUANTITY
No No. T

1 2 3 4 5 6 7 8
1 Excavation in all kinds of soil including boulders upto 0.60 m dia.
(0.113 cum) for foundations of canal cross drainage and other
appurtenant structures and placing excavated stuff neatly in
specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50m and initial lift upto 1.5m. (SR
Item No.1, page 54 of WRD, for year 2003-04)
a) Lift 0.00 m to 1.50 m Cum
i) For Causeway 1 7.880 5.000 0.335 13.199
ii) For Cutoff walls 2 7.880 0.300 1.000 4.728
Total 17.927
Say 18.000

2
Providing and laying insitu vibrated M - 15 (28 days cube
compressive strength not less than 15N/Sqmm )grade cement
concrete using 20mm downsize approved, clean,hard, graded
aggregates for sub-structure/super structure works including
cost of all materials, machinery, labour, formwork , scaffolding,
cleaning, batching, mixing, placing in position levelling, vibrating,
finishing, curing, etc.,complete with initial lead upto 50m and all
lifts (Cement Content : 270Kg/cum)
cum
I) For Pipe 1 7.880 5.000 1.545 60.873
Deduct for Pipe 8 4.500 0.465 -16.740
Deduct for collars 8 0.500 0.636 -2.544
II)Cutoff walls 2 7.880 0.300 1.000 4.728
Total 46.317
Say 46.400
3 Providing ,hauling & laying NP3 RCC hume pipes in position
carefully & jointing with 1 : 2 and curing etc.,complete (including
cost of pipes) above 450mm dia and upto 600mm dia . Rmt
ii) For Causeway 16 2.500 - - 40.000
Total 40.000
Say 40.000

4 Providing semi - pervious/pervious casing embankment using


soil from approved dump area in layers of 25-30 cm before
compaction including cost of all materials , labour ,machinery ,
all operations such as re-excavation, sorting-out, transporting
,spreading in layer of specified thickness ,breaking clods
,sectioning ,watering ,compacting each layer to density control of
not less than 95 percent or as stipulated by power roller
etc.,complete with lead upto 1Km and all lifts cum
i) S.R -U/S 1 17.130 5.000 1.142/2 48.906
ii) S.R -D/S 1 10.680 5.000 0.712/2 19.010
Total 67.917
Say 68.000

______________________________________________________________________________________________
Secon Private Ltd., Bangalore-66 CAUSE WAY @ Ch: 26+940KM OF BALUNDAGI LIFT MAIN CANAL
________________________________________________________________________________________________
KARNATAKA NEERAVRI NIGAM LIMITED BALIS
ATAKA NEERAVARI NIGAM LIMITED
HIMA LIFT IRRIGATION SCHEME

R CONSTRUCTION OF CAUSEWAY AT CH: 26+940 KM


BALUNDAGI LIFT MAIN CANAL

REMARKS

______________________________________________________________________________________________
Secon Private Ltd., Bangalore-66 CAUSE WAY @ Ch: 26+940KM OF BALUNDAGI LIFT MAIN CANAL