Plan Actual

Task Name Duration


Start Finish Start Finish
EFFECTIVE DATE 1 day Tue 8/12/14 Tue 8/12/14
ENGINEERING 1099 days Fri 8/29/14 Thu 8/31/17 Fri 8/29/14
Survey 98 days Fri 8/29/14 Thu 12/4/14 Fri 8/29/14 Thu 12/4/14
First Stage Drawing (Status NEN) 170 days Tue 7/7/15 Wed 12/23/15 Tue 7/7/15 Wed 12/23/15
Second Stage Drawing Revision Submission, Review and
Approval AA, BB (Status NEN) 213 days Tue 12/1/15 Thu 6/30/16 Tue 12/1/15 Thu 6/30/16
Third Stage Drawing Revision Submission, Review and
Approval AA+21, CC, DD, EE (Status NEN) 212 days Sat 10/1/16 Sun 4/30/17 Sat 10/1/16 Sun 4/30/17
Fourth Stage Drawing Revision Submission, Review and
Approval DDRS, DDS 184 days Wed 3/1/17 Thu 8/31/17 Wed 3/1/17
Shop Drawing and Material List (DD, EE) 61 days Thu 6/1/17 Mon 7/31/17 Thu 6/1/17
Shop Drawing and Material List (DDRS) 62 days Sat 7/1/17 Thu 8/31/17 Sat 7/1/17
Shop Drawing and Material List (DDS) 61 days Sun 7/2/17 Thu 8/31/17 Sun 7/2/17
Specification of Crossing 500kV Transmission Line 153 days Wed 3/1/17 Mon 7/31/17 Wed 3/1/17
Design of Tapping Tower of Existing 150kV Transmission
Line 139 days Sat 4/15/17 Thu 8/31/17 Sat 4/15/17
Loading Diagram & Calculation of Tower (DDRS) 78 days Mon 5/15/17 Mon 7/31/17 Mon 5/15/17
Tower Design and Calculation Sheet (DDRS) 78 days Mon 5/15/17 Mon 7/31/17 Mon 5/15/17

Tower Stress Diagram and Calculation Sheet (DDRS) 78 days Mon 5/15/17 Mon 7/31/17 Mon 5/15/17
Structural Drawings including clearance diagram
(Skeletons with dimension) (DDRS) 109 days Mon 5/15/17 Thu 8/31/17 Mon 5/15/17
Loading Diagram & Calculation of Tower (DDS) 92 days Thu 6/1/17 Thu 8/31/17 Thu 6/1/17

Tower Stress Diagram and Calculation Sheet (DDS) 92 days Thu 6/1/17 Thu 8/31/17 Thu 6/1/17
Tower Design and Calculation Sheet (DDS) 92 days Thu 6/1/17 Thu 8/31/17 Thu 6/1/17
Structural Drawings including clearance diagram
(Skeletons with dimension) (DDS) 92 days Thu 6/1/17 Thu 8/31/17 Thu 6/1/17

Outline Diagram of Each Type of Foundation (DDRS, DDS) 78 days Thu 6/15/17 Thu 8/31/17 Thu 6/15/17
Stub Setting Drawing (DDRS, DDS) 78 days Thu 6/15/17 Thu 8/31/17 Thu 6/15/17
Foundation Design and Calculation Sheet (DDRS) 78 days Thu 6/15/17 Thu 8/31/17 Thu 6/15/17
Foundation Design and Calculation Sheet (DDS) 78 days Thu 6/15/17 Thu 8/31/17 Thu 6/15/17

Structural Drawings of all types of foundations (DDRS) 78 days Thu 6/15/17 Thu 8/31/17 Thu 6/15/17

Structural Drawings of all types of foundations (DDS) 78 days Thu 6/15/17 Thu 8/31/17 Thu 6/15/17
Design Drawings of forms and timbering of specified
structures (DDRS, DDS) 78 days Thu 6/15/17 Thu 8/31/17 Thu 6/15/17
PROCUREMENT 897 days Fri 1/15/16 Sat 6/30/18
Steel Tower Material 895 days Fri 1/15/16 Thu 6/28/18
Contract Agreement 1 day Fri 1/15/16 Fri 1/15/16
Stub Delivery AA6 2 days Mon 10/17/16 Tue 10/18/16 Mon 10/17/16 Mon 10/17/16
Stub Delivery AA6+21, BB6 2 days Mon 7/17/17 Tue 7/18/17 Mon 7/17/17
Stub Delivery CC6, DD6 2 days Fri 9/15/17 Sun 9/17/17
Stub Delivery DDRS6, EE6 2 days Tue 1/2/18 Thu 1/4/18
Stub Delivery DDS6 2 days Mon 3/19/18 Wed 3/21/18
Manufacturing (AA6) 60 days Tue 10/24/17 Sat 12/23/17
Manufacturing (BB6) 60 days Mon 12/18/17 Fri 2/16/18
Manufacturing (CC6) 60 days Fri 1/26/18 Tue 3/27/18
Manufacturing (DD6, DDRS6) 60 days Thu 2/22/18 Mon 4/23/18
Manufacturing (EE) 60 days Sun 12/31/17 Thu 3/1/18
Manufacturing (DDS) 60 days Sun 4/29/18 Thu 6/28/18
Conductor and GSW 135 days Thu 6/1/17 Fri 10/13/17
Insuance of Purchase Order 1 day Thu 6/1/17 Thu 6/1/17
Manufacturing 120 days Fri 6/9/17 Fri 10/6/17
FAT 3 days Tue 8/8/17 Thu 8/10/17
Conductor Delivery 7 days Sat 10/7/17 Fri 10/13/17
Insulator, Fitting and Others Accessories 140 days Sat 2/10/18 Sat 6/30/18
Insuance of Purchase Order 1 day Sat 2/10/18 Sun 2/11/18
Manufacturing & Import Process 120 days Sun 2/18/18 Mon 6/18/18
FAT 12 days Thu 4/19/18 Mon 4/30/18
Material Delivery 5 days Mon 6/25/18 Sat 6/30/18
CONSTRUCTION WORK 664 days Mon 8/15/16 Sat 6/9/18
Mobilization 4 days Mon 8/15/16 Fri 8/19/16
Foundation Work 654 days Thu 8/25/16 Sat 6/9/18
Bored Pile 584 days Thu 8/25/16 Sat 3/31/18
Tower #10 (AA6+3, 32piles, 6.9m) 16 days Thu 8/25/16 Fri 9/9/16 Thu 8/25/16 Fri 9/9/16
Tower #11 (AA6+6, 32piles, 10.1m) 18 days Fri 9/23/16 Mon 10/10/16 Fri 9/23/16 Mon 10/10/16
Tower #12 (AA6+0, 32piles, 8.5m) 24 days Tue 5/30/17 Thu 6/22/17 Thu 5/30/17 Fri 7/7/17
Tower #08 (AA6+6, 32piles, 7.5m) 24 days Sat 7/1/17 Mon 7/24/17
Tower #07 (BB6+3, 40piles, 9.1m) 20 days Tue 7/25/17 Sun 8/13/17
Tower #03 (BB6+6, 40piles, 8.1m) 20 days Mon 8/14/17 Sat 9/2/17
Tower #14 (BB6+3, 40piles, 5.5m) 20 days Sat 9/23/17 Thu 10/12/17
Tower #05 (CC6+0, Class 6) 20 days Fri 10/13/17 Wed 11/1/17
Tower #20A (CC6+6, Class 6) 20 days Thu 11/2/17 Tue 11/21/17
Tower #26 (DDRS6+3, Class 6) 20 days Wed 11/22/17 Mon 12/11/17
Tower #13 (EE6+6, Class 6) 20 days Sun 1/21/18 Fri 2/9/18
Tower #15 (DDS6+6, Class 6) 25 days Sat 2/10/18 Tue 3/6/18
Tower #16 (DDS6+6, Class 6) 25 days Wed 3/7/18 Sat 3/31/18
Tower #02 (BB6+9, 40piles, 6.7m) 20 days Sun 9/3/17 Fri 9/22/17
Tower #01 (BB6+0, 40piles, 10.7m) 20 days Mon 1/1/18 Sat 1/20/18
Tower #00 (DDRS6+0, Class 6) 20 days Tue 12/12/17 Sun 12/31/17
Tower #26 (DDRS6+3, Class 6) 42 days Fri 3/9/18 Thu 4/19/18
Tower #25 (AA6+6, Class 1) 30 days Mon 5/1/17 Tue 5/30/17 Mon 5/1/17 Tue 5/30/17
Tower #24 (CC6+3, Class 1) 38 days Mon 10/2/17 Wed 11/8/17
Tower #23 (DD6+3, Class 2) 42 days Thu 1/25/18 Wed 3/7/18
Tower #22 (AA6+0, Class 2) 30 days Tue 8/1/17 Wed 8/30/17
Tower #21 (BB6+3, Class 2) 38 days Fri 11/10/17 Sun 12/17/17
Tower #20A (CC6+6, Class 6) 36 days Tue 12/19/17 Tue 1/23/18
Tower #20 (EE6+6, Class 2) 42 days Fri 1/19/18 Thu 3/1/18
Tower #18 (DD6+6, Class 1) 42 days Sat 11/4/17 Fri 12/15/17
Tower #17 (EE6+9, Class 2) 42 days Sun 1/21/18 Sat 3/3/18
Tower #16 (DDS6+6, Class 6) 50 days Sat 4/21/18 Sat 6/9/18
Tower #15 (DDS6+6, Class 6) 50 days Thu 4/5/18 Thu 5/24/18
Tower #14 (BB6+3, Class 6) 32 days Sun 12/17/17 Wed 1/17/18
Tower #13 (EE6+6, Class 6) 42 days Tue 4/17/18 Mon 5/28/18
Tower #12 (AA6+0, Class 6) 30 days Sat 7/1/17 Sun 7/30/17
Tower #11 (AA6+6, Class 6) 30 days Sun 11/6/16 Mon 12/5/16
Tower #10 (AA6+3, Class 6) 17 days Wed 10/19/16 Fri 11/4/16
Tower #09 (AA6+21, Class 2) 30 days Tue 8/1/17 Wed 8/30/17
Tower #08 (AA6+6, Class 6) 30 days Fri 9/1/17 Sat 9/30/17
Tower #07 (BB6+3, Class 6) 32 days Mon 10/2/17 Thu 11/2/17
Tower #06 (AA6-3, Class 2) 30 days Fri 9/1/17 Sat 9/30/17
Tower #05 (CC6+0, Class 6) 38 days Wed 12/13/17 Fri 1/19/18
Tower #04 (AA6+9, Class 2) 30 days Fri 9/1/17 Sat 9/30/17
Tower #03 (BB6+6, Class 6) 38 days Mon 10/2/17 Wed 11/8/17
Tower #02 (BB6+9, Class 6) 32 days Fri 11/10/17 Mon 12/11/17
Tower #01 (BB6+0, Class 6) 32 days Sat 3/3/18 Tue 4/3/18
Tower #00 (DDRS6+0, Class 6) 42 days Mon 3/5/18 Sun 4/15/18
Test Concrete Plan 671 days Thu 8/25/16 Tue 6/26/18
Erection Work 212 days Sun 1/7/18 Mon 8/6/18
Tower #26 (DDRS6+3) 21 days Thu 5/31/18 Thu 6/21/18
Tower #25 (AA6+6) 12 days Sat 1/20/18 Thu 2/1/18
Tower #24 (CC6+3) 14 days Tue 3/13/18 Tue 3/27/18
Tower #23 (DD6+3) 22 days Tue 5/8/18 Wed 5/30/18
Tower #22 (AA6+0) 12 days Fri 2/2/18 Wed 2/14/18
Tower #21 (BB6+3) 12 days Wed 3/28/18 Mon 4/9/18
Tower #20A (CC6+6) 14 days Mon 4/23/18 Mon 5/7/18
Tower #20 (EE6+6) 22 days Fri 6/22/18 Fri 7/13/18
Tower #18 (DD6+6) 21 days Wed 5/9/18 Wed 5/30/18
Tower #17 (EE6+9) 22 days Fri 7/13/18 Fri 8/3/18
Tower #16 (DDS6+6) 25 days Fri 7/13/18 Mon 8/6/18
Tower #15 (DDS6+6) 25 days Fri 7/13/18 Mon 8/6/18
Tower #14 (BB6+3) 12 days Tue 4/10/18 Sun 4/22/18
Tower #13 (EE6+6) 22 days Fri 6/22/18 Fri 7/13/18
Tower #12 (AA6+0) 12 days Mon 2/5/18 Sat 2/17/18
Tower #11 (AA6+6) 12 days Sun 1/7/18 Fri 1/19/18
Tower #10 (AA6+3) 12 days Wed 1/10/18 Mon 1/22/18
Tower #09 (AA6+21) 12 days Tue 1/23/18 Sun 2/4/18
Tower #08 (AA6+6) 12 days Thu 2/15/18 Tue 2/27/18
Tower #07 (BB6+3) 12 days Fri 3/16/18 Wed 3/28/18
Tower #06 (AA6-3) 12 days Sun 2/18/18 Fri 3/2/18
Tower #05 (CC6+0) 14 days Wed 4/11/18 Wed 4/25/18
Tower #04 (AA6+9) 12 days Wed 2/28/18 Mon 3/12/18
Tower #03 (BB6+6) 12 days Sat 3/3/18 Thu 3/15/18
Tower #02 (BB6+9) 12 days Thu 3/29/18 Tue 4/10/18
Tower #01 (BB6+0) 12 days Thu 4/26/18 Tue 5/8/18
Tower #00 (DDRS6+0) 21 days Thu 5/31/18 Thu 6/21/18
STRINGING AND SAGGING 78 days Mon 7/30/18 Mon 10/15/18
Insulator Installation T#00 - T#14 8 days Mon 7/30/18 Mon 8/6/18
Insulator Installation T#26 - T#17 8 days Tue 8/7/18 Tue 8/14/18
Insulator Installation T#15 - T#16 2 days Wed 8/15/18 Thu 8/16/18
Stringing of Conductor and GSW T#00 - T#15 28 days Fri 8/17/18 Thu 9/13/18
Stringing of Conductor and GSW T#26 - T#16 28 days Fri 9/14/18 Thu 10/11/18
Stringing of Conductor and GSW T#15 - T#16 4 days Fri 10/12/18 Mon 10/15/18
Stringing of Conductor and GSW T#00 - Switchyard 2 days Fri 10/12/18 Sat 10/13/18
COMMISSIONING 20 days Tue 10/16/18 Sun 11/4/18
CERTIFICATION 20 days Mon 11/5/18 Sat 11/24/18
MODIFICATION & CONNECTION TO EXISTING TL 14 days Tue 10/16/18 Mon 10/29/18
TIE-IN & PLANT ENERGIZATION 1 day Mon 1/7/19 Mon 1/7/19