Documente Academic
Documente Profesional
Documente Cultură
2014
Contents
1. Operation Report............................................................................... 2
1.1 Executive Statistic ........................................................................................ 2
1.2 Operation Summary ..................................................................................... 2
2. Maintenance Report .......................................................................... 3
1) Mechanical Maintenance ...............................................................................................................3
2) I&C Maintenance ..........................................................................................................................8
3) Electrical Maintenance ..................................................................................................................9
1
1. Operation Report
1.1 Executive Statistic
During 2014 the facility had been operating on combined cycle mode. Almost of
operation was on fuel oil 81.93% FO and 18.07% NG (Based on exported energy
percentage).
The Facility exported 1,491,194.125 MWh, wherein the utilization factor was
45.63% with 9,487.36 kJ/kWh heat rate comparing with 9,782.58 kJ/kWh
guaranteed heat rate.
The Facility outage were 242,071.837 MWh. The weighted availability was
92.593% comparing with 92.01% planned availability for this year in accordance
with 2014 O&M plan submitted (ref: AQPP-KOSPO-QSO-14-0031).
Detailed Operation events are shown in the tables and charts included in the
attachment #1. These are classified according generation unit number CTG11,
CTG12, STG and the facility with consideration that some items are common that
couldnt be connected with a certain unit such as natural gas consumption.
2
2. Maintenance Report
1) Mechanical Maintenance
During the year 2014, Mechanical Section performed mainly the following tasks:
a) Major Activities:
a) CTG11 HGPI was performed during (July 28, 2014 ~ August 25, 2014);
The following items were performed on the CTG#11 and auxiliaries:
3
1. Replace the Turbine blades 1st &2nd stage.
2. Replace the Turbine vanes 1st &2nd stage.
3. Sandblasting and NDT for turbine blades and vanes last stage.
4. Cleaning and NDT for turbine blades and vanes 3rd stage.
5. Made sandblasting and welding and repair for the mixing chamber and
Flame tube.
6. Made cleaning and inspection for the fuel oil and fuel gas burners
(diffusion and premix nozzles).
7. Change the defected ceramic tiles.
8. Made inspection and leaking test for the fuel oil and fuel gas ball cock
valves.
9. Made inspection and repair for the fuel oil and fuel gas control valves.
10. Made inspection for the inlet guide vanes and compressor 1st stage.
11. Replace all coalescer filter of Air intake system (1004EA).
12. Cleaning all Air intake pre-filters.
13. Made inspection for lube oil pumps.
14. Change the lube oil and jacking oil and mist eliminator filters.
15. Clean the heat exchanger of the lube oil and generator system.
4
g) STG lube oil pumps (A,B,C) were dismantled and inspected (bearings
were replaced by new, bearing gasket and casing gasket were replaced,
shaft and impeller and wearing rings inspected, suction strainer of the
pumps cleaned, check valves inspected).
h) Lube oil filters: New filters changed.
i) Jacking oil filters: New filters changed.
j) Oil vapor fan: gasket of the fan was changed by new.
k) Lube oil: four drums add to the lube oil system.
l) STG Hydraulic oil skid (change all the hydraulic oil: 3 drum, change
suction filters and discharge filters).
m) Condensate drains system (made inspection for the drain pumps A&B,
condensates drain pot welding point NDT check).
n) All STG drain valves and warming valves were inspected.
5
g) Flow control valves (FCV) (HP drum FCVs 100%, 30% and CPH outlet,
LP drum FCVs (dismantle and check inside, Inspected internals parts and
replace the defective parts).
h) HP Drum (Open HP manholes, check inside and clean it )
i) LP Drum (Open manholes and check inside , Repaired weak points by
welding and grinding )
j) Dearetor Drum (Open manhole and check inside, Repaired metals trays
(baffle) made modification to reduce flow at metals trays).
k) Perform hydraulic test for HP, LP drums and systems.
7
2) I&C Maintenance
During the year 2014, I&C Section performed mainly the following tasks:
a) Major Activities
[1] Main gas valve (ESDV) pneumatic connections were modified to ensure
redundant operation of the solenoids
[2] CTG's #HGPI : I&C team performed all required maintenance for HGPI
including:
a) Calibrating all process transmitters and switches and control valves
b) Dismantling all needed instrumentation from control valves and
equipment, and installing again after mechanical maintenance was finished
c) Disconnect wiring from combustion chambers mainly to facilitate
mechanical maintenance, and connecting again.
[3] STG inspection:
a) I&C team performed the needed maintenance on STG and its related
equipment
b) Removed needed instrumentation from STG and its main equipment
c) Installed again STG monitoring Instrumentation and control valves insts
after mechanical work
d) Calibrated control valves, to ensure consistent operation
8
c) Preventive Maintenance Activity.
Preventive maintenance actions were done completely according to I&C section
Schedules and procedures.
The preventive activities are included in attachment #2 (I&C Maintenance
Preventive Activities).
3) Electrical Maintenance
During 2014 Electrical team Perform facility comprehensive maintenance (HGPI)
for CTG, STG and HRSG,
a) Major Activities
[1] Generator
Electrical team made full inspection and test for Generator and GCB as:
a) Inspect Stator insulation paper and wedges situation.
b) Insulation resistance test for Stator and rotor.
c) Inspect slip ring situation and Excitation brushes holder situation.
d) Inspect Generator Star point and NGR.
e) Generator bearing inspection (PT and UT).
[2] Transformer :
We made full inspection and test for GSUT and SAT as follow:
a) Inspect transformer Bushing situation.
b) Actual test for Transformer mechanical protection and test all tripping
signal with NEPCO.
c) Inspect OLTC and its mechanism.
d) Inspect the transformer cooling system (Fans and pumps).
e) Inspect the GSUT and SAT CTs.
[3] GCB :
We made full inspection and test for GCB as follow:
a) Functional test for GCB mechanism.
b) Inspect VTs and CTs in GCB and Generator.
c) Inspect SF6 chamber in GCB.
9
d) Check flexible Joint for GCB and Generator.
[4] PCC :
We made full inspection and test for PCC as follow:
a) Inspect the PCC SWGR ACB
b) Inspect PCC Load breaker mechanism
c) Inspect SFC system (Thyrestor, internal mechanism ,controller and
transformer)
d) Inspect SFC system (Thyrestor, internal mechanism , controller and
transformer
e) Inspect Protection panel and Synchro. Panel and its relay and CTs
f) Inspect Battery charger and Battery bank and Battery charger.
[5] MOVs :
We made full inspection for HRSG and STG MOVs and CTG combustion
chamber MOVs as follow:
a) Inspect control card and Adjustment switches.
b) Inspect MOV motor situation.
c) Full calibration for all STG and HRSG MOVs.
b) Electrical Modification.
10
[3] HRSG #11 ,12 diverter damper LCP :
Diverter damper LCP its located in body of HRSG which have strong
vibration which could damage electrical equipment, so move the panel to be in
ground grid
3. HSE Report
a) HSE Inspection
The site has been surveyed and the check list was prepared as the attachment #3
(Attachment #3 HSE Inspection Checklist)
b) Environment Inspection
The site has been surveyed and the check list was prepared as the attachment #3
(Attachment #3 Environment Inspection Checklist).
11
4. Administration Report
4.1 Document Status
The following table shows the status of official letters received from QEPC and
submitted by KOSPO to QEPC.
Document Statistics
Received Unattended
Division
(Total Yearly) (Total Yearly)
P&E 35 1
Electrical 1 0
Mechanical 8 0
I&C 6 2
Chemical 0 0
HSE 3 1
Admin 10 0
5. Plans of 2015
5.1 Operation and maintenance plan for year 2015. (Attachment 12)
12
<Attachments>
[1] Operational Detailed Report.
[2] Attachment # 2 Corrective & Predictive maintenance and improvement Actions.
[3] HSE Annual Environmental report.
[4] Emergency Plan during Rainy and Snow.
[5] Organizational Chart.
[6] Employee in & out list for 2014.
[7] Budget Execution Statement for 2013
[8] Procurement Status.
[9] Facility Inventory Spare Part for 2014.
[10] Document Status in Details.
[11] Operation and maintenance plan for year 2015.
13