1.0 Purpose
This method statement covers the casting of blinding concrete described in
Section 03300 of the contract specification.
2.0 Scope
This method statement defines the responsibilities and describes the procedure
to be implemented during casting of blinding concrete for Parcels 601, 602, 603,
225, 805 and 800 series to conform to the approved shop drawings, contract
specification and other related standards.
3.0 Responsibilities
3.1 The Site Engineer shall be responsible for the implementation of the work
in accordance with this method statement and their responsibilities shall
be, but not limited, to the following:
3.1.1 Preparation of work schedule and casting drawing/plan.
3.1.2 Booking and ordering of only approved concrete mix and
preparation of required tools and equipment.
3.1.3 Designating skilled workers.
3.1.4 Supervising the work to ensure the work is performed properly in
accordance with this method statement and related specification of
the contract document.
3.2 The surveyor shall be responsible for setting out areas and levels for the
blinding concrete and survey check during casting.
3.3 The Site Engineer and Quality Control Engineer shall continuously monitor
all activities related to the work if implemented in accordance with this
method statement.
4.0 Materials
4.1 Concrete shall be ordered from approved concrete suppliers and concrete
PAGE : 1 of 2
METHOD STATEMENT
BLINDING CONCRETE CASTING
ACADEMIC SUPPORT FACILITIES
SABAH AL-SALEM UNIVERSITY CITY, KUWAIT
UNIVERSITY
CONTRACT NO.: KU/KUCP/C1010/13-14
DOCUMENT NO. : CSCEC-C1010-MS-09, REVISION : 01
shall be:
4.1.1 K180 SRC for parcels 601, 602, 603, 225, 805
4.1.2 K250 SRC - for parcels 800 series
6.0 Methodology
6.1 Guide lines and levels as per approved shop drawings shall be provided
by the surveyor.
6.2 Formworks shall be installed to comply with the guideline and levels.
6.3 Concrete pumps shall be located as per casting plan.
6.4 Upon arrival of concrete at site, it shall be checked for temperature and
slump and composite samples shall be taken as per clause 3.19 of
Section III-2/03300 of the contract specification.
6.5 Concrete shall be monitored and programmed such as no interruption on
arrival of concrete truck mixers at site will be encountered.
6.6 Concrete shall be casted continuously to avoid cold joints.
6.7 Casted concrete shall be leveled as per the required elevation and level
shall be regularly checked by the surveyor.
PAGE : 2 of 2
METHOD STATEMENT
BLINDING CONCRETE CASTING
ACADEMIC SUPPORT FACILITIES
SABAH AL-SALEM UNIVERSITY CITY, KUWAIT
UNIVERSITY
CONTRACT NO.: KU/KUCP/C1010/13-14
DOCUMENT NO. : CSCEC-C1010-MS-09, REVISION : 01
8.0 The Site Engineer in coordination with the Safety Officer, shall be ensuring
compliance with project HSE Plan during the implementation of this work which
shall include, but not limited to the following:
8.1 Provision and proper use of safety paraphernalia.
8.2 Maintaining cleanliness at work areas.
PAGE : 3 of 2