units each rated at 323 MW gross output, with an oil-fired single re-heat boiler and tandem compound, two cylinder condensing steam turbines directly coupled to a hydrogen cooled generator. The design net available output is exported to WAPDAs national grid via the power stations 500kv switchyard. Both the plant configuration and the steam conditions represent conventional design based on proven technology
The Hub Power plant is one of the most efficient oil
fired thermal plant and can provide 10+% of countrys electricity demand. The plant is operated in such a way that it is available at a short notice during high demand period and can switch to flexible operations during low demand periods.
The Hub Power Station site has an ongoing
proactive approach to safety management. Stations commitment to safety procedures has already earned it with Royal Society for Prevention of Accidents (RoSPA) Gold Awards consecutively for the last many years.
Technical Details
The Plant
The Construction Contract was signed with a
construction consortium in July 1991, to provide engineering, procurement, construction and commissioning for a 1292 MW power plant on a lump-sum, turnkey basis. The construction consortium included:
Mitsui and Co. of Japan, consortium and
commercial leader; Ansaldo ENERGIA of Italy, technical coordinator and designer and supplier of the turbine generators; Ishikawajima-Harima Heavy Industries Co. Ltd of Japan, designer and supplier of the boilers, Campenon Bernard SGE SNC of France, the civil contractor.
The Plant consists of four generating units which
are each rated at 323 MW with an oil-fired single re-heat boiler and tandem compound, two cylinder condensing steam turbines directly connected to a hydrogen cooled generator. The net available output power of 1200 MW is exported to the Water and Power Development Authority (WAPDA) grid by means of the stations 5OOkV switchyard. Fuel is received by pipeline from Pakistan State Oil (PSO). Load tanker unloading facilities are also available.
The Plant design and engineering are based on
proven technology. It operates on the basis of a conventional steam cycle such that the steam produced by the boilers drives the turbine generator sets to make electricity. The thermodynamic characteristics of the units are as follows:
Steam pressure and temperature: 170 bar,
540OC; single re-heating up to 540OC; condensate and feedwater pre-heating, up to 250OC; turbine exhaust pressure: 0.087 bar (2.5 in Hg). This is somewhat higher than is normal because of the high average temperature of circulating water available at the plant site.
The plant, when operating at full load converts
energy in the residual fuel oil (RFO) at a thermal efficiency of approximately 38.9%.
Activities on the site began with soil investigations
in January 1993; two months later, work on site for temporary structures could begin and within eight months, work had started on the permanent structures. The first energisation of the GIS substation and start-up transformer took place in February 1996; the first unit was first operated at full load in June 1996.
The entire plant was fully commissioned on March
31, 1997.
The Condenser and Feed System
The condenser into which the steam from the LP
turbine is discharged is a closed vessel fitted with tubes through which sea water is circulated by the main circulating pumps. The outside of the cold tubes condenses the steam from the turbine back into feed water.
The condenser is a single-pass surface type, with
divided water-boxes to facilitate inspection and maintenance. The pressure in the condenser is 0.084 bar when the circulating water enters at a temperature of 33C.
The condensate and feed heating system includes
seven heating stages; the heating medium is based on the steam extracted from the turbine.
Four surface-type LP heaters are provided for
heating the condensate. These receive steam extracted from the LP section of the turbine. A direct-contact heater is provided to deaerate the feedwater and to be used as suction-tank for the feedwater pumps; this heater receives steam from the turbine IP section exhaust.
The boiler feed pump sets are provided to supply
about half of the feedwater needed by the boiler at full load and each pump set has a constant speed motor and booster pump, a hyraulic speed changer with step-up gear and a variable speed high pressure main feed pump.
Two surface type HP heaters are provided for the
heating of the feedwater. HP1 receives steam extracted from the IP section of the turbine whereas HP2 gets steam from the cold reheat line.
Cooling Water
The cooling water used in the condensers and for
the auxiliary plant is drawn from the Arabian Sea through submerged concrete inlet channel about 300m long to a siltation setting basin and than through an open inlet canal some 650m long to the circulating water pump house. The sea water flows from the circulating water intake through screens to remove debris and is pumped by the main sea water circulating pumps through the intake piping and valves to the condensers. The water is discharged through further piping and valves into a culvert and seal pit before flowing into the Hub River estuary through a 1,000m discharge canal.
The remainder of the auxiliary plant and systems
are cooled by a closed circuit water system, using demineralised water. Electrical System
There are four generators which develop a power
of 380 MVA each (power factor 0.85) and are of the windings direct cooling type.
The stator winding is cooled by the circulation of
deionised water which passes through the hollow conductor which forms part of the semi-coils. The rotor winding is cooled directly by hydrogen.
The generated power is despatched to WAPDAs
grid through two overhead 500 kV lines through a half-breaker scheme, SF insulated substation. There are also two start-up transformers. Station power supply and unit auxiliary power supply are provided to minimise any effects of equipment failure or maintenance on continuity of service.
The electrical auxiliary power system rests on
three major sub-systems:
AC power system DC power system AC emergency power system
The station transformers performs the start-up and
shut-down of the plant and supplies the common services boards.
The emergency ac source is ensured by emergency
diesel and 110V inverters, supplying the loads necessary for the safe shut-down of the power plant.
The Control System
A microprocessor control system (DCS) is used to
control and monitor the performance throughout the plant. A Bailey INFI90 DCS supports a decentralised hierarchical structure which allows for maximum mobility and flexibility to different plant locations. Thus control functions and data processing can be undertaken at the detailed plant area while at the same time retaining the ability to operate all control functions from the centre. It is sufficiently flexible to serve a wide range of requirements at loop and component level without any changes to hardware.
The DCS includes:
The process control unit
The data communication system The operator interface
A dedicated engineering workstation (EWS)
provides for fast off-line development of control strategies.
The automation system design operates on a
principle of high availability level.
The DCS which is in place ensures a safe, reliable,
available, economical and simple operation of the boiler turbine generator units, together with their associated auxiliary plants.
Auxiliary Plants
In addition to the main electricity production and
fuel storage facilities, the plant has auxiliary plant or sub-plant facilities which include: A desalination plant to convert sea water into feed, demineralised and potable water Water and waste water treatment plant RFO and lubricating oil processing plant Safety equipment A fire fighting system Hydrogen gas generation facilities An auxiliary boiler house
Arrangements for Despatch
Connections to the WAPDA Grid
Each generator is connected by a 21.5 kV/500 kV
step-up transformer to a gas insulated switchgear outdoor sbstation which in turn is connected to two overhead export lines designed by WAPDA and constructed by Saudi Cable of Saudi Arabia. Two station transformers suplied from the 500 kV substation provide power for start up of the Plant and for common services.