FLOW CHART LIFTING DESIGN BY CRANE

START

DATA OF LOAD: SITE CONDITION:


ROW MATERIAL
DIMENSION & SURFACE &
AND DELIVERY
WEIGHT FOUNDATION

REFERENCE:
RIGGING BOOK + EQUIPMENT MANUAL +
RIGGING STANDARD + WELDING PROCEDURE

TYPE OF CRANE

SAFETY
FACTOR
ANALYSIS

SOLO CRANE DUO CRANE DUO CRANE BY TILING

RIGGING STUDY &


LIFTING STUDY BY
CRANE

RISK
RISK
ANALYSIS

SAFE

RISK
GROUND BEARING
PRESSURE AND
REACTION

TYPE OF CRANE
FOUNDATION

COST OVER
ANALYSIS

AGREE

LIFTING PLAN &


STANDAR
OPERATIONAL
PROCEDURE

PURCHASING ORDER
CUTTING PLAN MAN POWER PLAN
& DELIVERY ORDER

MECHANICAL WORKS
CIVIL WORKS
ELECTRICAL WORKS

POOR
QUALITY
CONTROL

GOOD

LIFTING

CONTROL

REPORT

FINISH
.
START

DATA MATERIAL:
DIMENSION & WEIGHT

REFERENCE:
RIGGING BOOK + EQUIPMENT MANUAL +
RIGGING STANDARD

TYPE OF
LIFTING

MONO CRANE TAILING SYSTEM SPECIAL EQUPMENT

RIGGING STUDY &


LIFTING STUDY

RISK RISK
ANALYSIS

SAFE

COST OVER
ANALYSIS

AGREE

LIFTING PLAN

ACTION

CONTROL

REPORT

FINISH
.
START

DATA OF LOAD: SITE CONDITION:


ROW MATERIAL
DIMENSION & SURFACE &
AND DELIVERY
WEIGHT FOUNDATION

REFERENCE:
RIGGING BOOK + EQUIPMENT MANUAL +
RIGGING STANDARD + WELDING PROCEDURE

DRAFT OF GANTRY

ANALYSIS

STRESS ANALYSIS FRAME ANALYSIS GROUND BEARING

RIGGING STUDY &


LIFTING STUDY BY
GANTRY

RISK RISK
ANALYSIS

SAFE

COST OVER
ANALYSIS

AGREE

LIFTING PLAN &


STANDAR
OPERATIONAL
PROCEDURE

PURCHASING ORDER
CUTTING PLAN MAN POWER PLAN
& DELIVERY ORDER

MECHANICAL WORKS
CIVIL WORKS
ELECTRICAL WORKS

QUALITY POOR
CONTROL

GOOD

LIFTING

CONTROL

REPORT

FINISH

.
START START

DATA MATERIAL: DATA OF LOAD: SITE CONDITION:


ROW MATERIAL
DIMENSION & SURFACE &
DIMENSION & WEIGHT AND DELIVERY
WEIGHT FOUNDATION

REFERENCE: REFERENCE:
RIGGING BOOK + EQUIPMENT MANUAL + RIGGING BOOK + EQUIPMENT MANUAL +
RIGGING STANDARD RIGGING STANDARD + WELDING PROCEDURE

DRAFT OF GANTRY
TYPE OF
LIFTING

ANALYSIS
MONO CRANE TAILING SYSTEM SPECIAL EQUPMENT

STRESS ANALYSIS FRAME ANALYSIS GROUND BEARING


RIGGING STUDY &
LIFTING STUDY

RIGGING STUDY &


LIFTING STUDY BY
RISK RISK GANTRY
ANALYSIS

SAFE RISK RISK


ANALYSIS

COST OVER
ANALYSIS SAFE

AGREE COST OVER


ANALYSIS

LIFTING PLAN AGREE

LIFTING PLAN &


STANDAR
OPERATIONAL
ACTION
PROCEDURE

CONTROL
PURCHASING ORDER
CUTTING PLAN MAN POWER PLAN
& DELIVERY ORDER

REPORT
MECHANICAL WORKS
CIVIL WORKS
ELECTRICAL WORKS
FINISH
.
QUALITY POOR
CONTROL

GOOD

LIFTING

CONTROL

REPORT

FINISH
.