Sunteți pe pagina 1din 12

IMPROVING PROGRESSING CAVITY PUMP PERFORMANCE

THROUGH AUTOMATION AND SURVEILLANCE


K. A. Woolsey, SPE, KUDU Industries Inc. Copyright 2010, Society of Petroleum Engineers

kudupump.com
Abstract
To extend the run life of the pump while producing all be accurate and reliable, extending the run life while
available fluid is the goal of all PCP operators. The primary producing all available fluids.
challenge is to do so without starving the pump and
causing damage to the stator. The petroleum industry has Combining this automated technology at the well with
been searching for years to find a reliable way to control a web based system that feeds back real time data to a
progressing cavity pumps for pump-off. Several methods dedicated SCADA host allows PCP technical experts to
have been used, from monitoring torque to manual fluid diagnose problems, and operators to respond quickly to
levels. To date, none of these have been commercially changing well conditions.
successful. A method for controlling these wells has
been developed combining wedge meter flow technology This presentation discusses the advances in automation
and microprocessor control of both electric motors using and optimization of progressing cavity pumps. The method
variable frequency drives and hydraulic motors using will be explained and data will be presented of field study
proportional control valves. This method has proven to results showing actual well tests.

Introduction
The acceptance of progressing cavity pumps in the oil and controller has eliminated this concern, while producing
gas industry has grown throughout the world. One of the all the available fluid from the well bore without
major concerns has always been causing stator damage damaging the pump.
if the well is pumped off. The most common prevention is
to ensure that there is a substantial amount of fluid level With this automated technology and a web based
above the pump. Operators taking manual fluid level shots, SCADA system we were able to monitor several data
and adjusting pump speed has been the most widely used trends and discover additional control algorithms.
method to maintain a safe fluid level. With advancements Continued development of these algorithms
in fluid flow measurement and proven algorithms, the PCP is ongoing.

Pump off Control for


Progressing Cavity Pumps
Two main objectives were defined when the theory of the The second objective was to automatically optimize the
PCP Controller was first introduced. The first objective well. There are several problems associated with trying
was to reduce premature pump failure. The most common to maintain a safe fluid level with the use of manual
failure is stator damage due to pump off. Pump off is fluid level equipment. Fluid levels are only an indication
defined as a lack of fluid entry into the pump. This causes of how much fluid is over the pump at the time the fluid
a lack of lubrication to the stator resulting in extremely level is taken. There are a large number of misinterpreted
high temperatures being generated. The high temperature fluid levels due to surface and rod noise as well as foam.
ultimately burns the elastomer in the pump. The rubber Downhole anomalies such as high liner tops, bad dog legs,
surface of the stator becomes hard, brittle, and cracked. In or other non standard configurations will result in false
severe circumstances, the stator contour is completely torn fluid levels. It is extremely time consuming to shoot fluid
up producing rubber at surface. This may be caused by one, levels, adjust speed, allow the well to stabilize and shoot
or a combination of the following, problems; plugged pump the fluid level again. This manual process is often not a
intake, poor inflow, or production rates exceeding inflow. quick enough reaction to account for changes in inflow.

KUDU Industries Inc. Pg 2


By optimizing the well, we not only eliminate the fluid we are maintaining the lowest bottom hole pressure
level monitoring problems above, we also increase promoting the most fluid inflow. Second, by being able
overall production. This is accomplished in several to pump over capacity the system is able to make a quick
ways. First, by keeping the fluid at or near the pump recovery from downtime.

Development of Theory and


Control Algorithms
The primary control algorithm of the PCP Controller is the minute sampling period, the algorithm looks at the
production control algorithm. Its purpose is to optimize flow rate and determines if it satisfies the minimum
production of the well without causing pump off. The production increase requirement that was preset at
patented control algorithm varies the speed of the pump commissioning. For this purpose we will use 5%. If the
in steps while measuring the amount of fluid production production increase is greater than 5% the speed of the
from the pump. As long as sufficient fluid is available at pump will be increased a percentage of the previous
the pump intake to completely fill the pump cavities, a production increase while remaining within the minimum
linear relationship occurs between fluid production and and maximum speed change window and the hard set
pump speed. The special hunting algorithm continuously minimum speed change. This process is repeated until
looks for the most production. The controller continues the minimum production requirement is not met, or the
increasing the pump speed in user-defined steps, pump reaches the maximum speed allowed. At that
measures production rate at each step after the settling time the pump speed is reduced to a value between the
time, and establishes a speed/rate relationship. maximum and minimum speed decrease window that is
preset at commissioning. See Figure 1.
A description of the production control algorithm After the well is ramped down in speed the settling
is as follows: and sampling periods are again observed and the
The PCP Controller begins an operating cycle at a user- production still needs to meet the minimum production
defined startup speed. When the well is first started at requirement. There is a number of consecutive speed
the suggested start up speed, for example 150 rpm, the ramps allowed that are configured at commissioning
initial well state is the settling period. This is the period before the challenging algorithm is implemented. For
of time that the production from the well is allowed to this purpose we will use three. After the well is ramped
stabilize after any speed change. For our purpose we down in speed three consecutive times and the minimum
will use three minutes for the settling time. production requirement is not met, the pump is sped up
After the three minute settling time the controller goes the hard set minimum speed change, and the settling
into sampling period. This is the period of time that and sampling periods are again observed. If the minimum
the production from the well is measured and a flow production requirement is met then the pump continues to
rate is established. For our purpose we will also use be sped up and the production is tested. If the minimum
three minutes for the sampling time. The flow rate that production requirement is not met then the pump will be
is established is total fluid in barrels per day for that ramped down again and the process continues.
period. The pump is then sped up between the hard set
minimum speed change and the maximum allowable The PCP Controller also has secondary control algorithms
speed increase that is preset. The well is then placed that monitor the following:
back in the settling period again. A polished rod torque value either from the electric
After the three minute settling period and the three variable speed drive analog output, or hydraulic

KUDU Industries Inc. Pg 3


pressure from the hydraulic pump to the hydraulic violation occurs, the PCP Controller decreases motor
motor. This value is used to protect the rod string and speed by the value specified. At this state, the PCP
pumping equipment. Two violation settings are provided Controller operates in either a downtime or minimum
for torque with the option of programming the well running speed mode.
to either shut down or slow down when the limit is
exceeded. The torque limiting violation is used to limit All secondary control features slow the pump when one or
the rod torque. The current torque is compared to the more set point limit is violated. If the monitored variable
specified limit value to detect if the pump is beginning continues to be in an alarm condition when a programmed
to show evidence of stalling or fluid starvation that minimum speed is reached, the PCP Controller will stop
can cause friction between the stator and elastometer, the well to prevent damage to the pumping equipment.
thus increasing the torque. Torque is monitored every
second, and once it is violated, the PCP Controller will After proving the initial production control algorithm it
decrease the speed by the specified torque limiting became evident that the flow meter was a critical part
speed value, and continue reducing speed until the of the complete system. Although exact accuracy was
minimum operating speed is reached. In this state, not necessary, repeatability was critical. Many types of
the PCP Controller either operates in a downtime or meters were tested, however, the wedge meter proved
violation minimum running speed mode. The Critical to be the most reliable when measuring flow at the
Torque violation is used to either shut the well down or wellhead. Working in conjunction with the wedge meter
run in minimum speed when in a high torque situation. manufacturer many improvements were made and this
The current torque is compared to the specified limit device is now the meter of choice for most applications.
value. This is an instantaneous action that reduces the See figure 2.
speed to the minimum operating speed or shuts the
well off depending on the action selected. Combining this automated technology at the well with
A current flow rate value either via the wedge meter or a web based system that feeds back real time data to
another trusted flow measurement device. Two violation a dedicated SCADA host allows PCP technical experts
settings are provided for flow rate with the option of to diagnose problems, and operators to respond quickly
programming the well to either shut down, or slow to changing well conditions. See figures 3 & 4. Utilizing
down when the limits are exceeded. A low production statistical process control the SCADA host allows
fluid rate limit is specified defining the minimum operators to determine when changes in field conditions
amount of fluid production allowed. Production for occur. By monitoring the difference between the maximum
the current sampling period is compared to this value allowable working speed of the pump and the current
to detect a fluid starvation/dry pump condition. This speed we can immediately determine if the well is
feature also helps to detect (at the rate of one-minute optimized. Automatic reaction to changing field
resolution) if something is wrong with the production conditions prevents pump damage. See figure 5. This
transmitter. When a violation occurs, the PCP Controller has shown significant results in increased production,
decreases motor speed by the value specified. At this and pump run life, as well as a reduction in maintenance
state, the PCP Controller either operates in a downtime and down time, thus providing better cost/time
or minimum running speed mode. management for operations.
A low pump efficiency limit is specified defining the
minimum efficiency the pump is allowed to operate at. Continued improvement with customer input has driven
Production for the current sampling period is compared development of additional algorithms that make producing
to this value to detect low pump efficiency. When a wells with a high sand content much easier. See figure

KUDU Industries Inc. Pg 4


6. With additional equipment at surface, this technology amounts of sand without operator intervention. See
has successfully performed automated flushes of large figure 7.

Field Study Results and Historical Data


1. A 15 well pilot project started in January 2007 included control on the proportional valve without adding heat to
the host SCADA system and the PCP VFD Combo unit the system. See graph 3.
complete with wedge flow meters. The results showed 3. A single well pilot started in Dec 2009 was chosen by
an increased average oil production from 120 m3/day, the producer because they were unable to keep the well
to 145 m3/day. An unexpected benefit of increased running. Before optimizing the well the concentration
average gas production from 19 to 23 dec/day was also was on producing the sand that was preventing the
noticed. This showed an estimated payout in 120 days. well from running. Once this was achieved we were
See sample well from this project on graphs 1 & 2. able to increase fluid production. By bringing the well
2. A single well pilot started July 2008 was chosen due on slowly, limiting the maximum speed over four stages
to its extreme production difficulties For the first six the sand was cleaned up to a very manageable level and
months prior to the installation of the PCP controller, the revenue for the well was increased from $ 0/day to
this Bakken zone well had four pump changes due $7,798/day with an oil gain of 19.4 m3/day. See table 1.
to sand and inflow issues. The well produced a total 4. A single well pilot started in Sept 2009 was chosen due
of 2711 m3 with an operational cost of $198,000.00. to the short run life of the pumps. Prior to installing the
On July 1st, 2008 Kudu installed a 300TP1200 pump PCP controller the pumps were being replaced every
and added the hydraulic PCP controller with wedge 3 to 4 months. A new pump was installed at the same
flow meter. For the next six months the well produced time the PCP controller was installed. This pump has
19,779 m3 with no work overs. The pump ran for 14 been producing since Sept 2009 and the most recent
months before it needed to be changed out due to wear test showed a pump efficiency of 74% with an oil gain
and tear from abrasion. The hydraulic control system of 1.84 m3/day, increasing oil revenue by an average of
expertly maintained speed changes using PID loop $925.00/day. See graph 4.

KUDU Industries Inc. Pg 5


GRAPH 1: Example 1 Results

GRAPH 2: Example 1 Results


KUDU Industries Inc. Pg 6
GRAPH 3: Example 2 Results

TABLE 1 Example 3 Results

Nov 26-Dec 26/09 Dec 27-Mar 15/10 Mar 16-Apr 15/10 Apr 15-May 15/10 May 16-June 15/10
Pre-controller #1 Post-controller #1 Post-controller #2 Post-controller #3 Post controller #4
Hrs On 744 741 744 744 744
m3 Oil/Day 0.00 0.99 1.29 10.19 19.40
m Sand/Day
3
0.000 0.006 0.000 0.000 0.000
m H2O/Day
3
48.97 38.45 108.95 139.40 144.30
m3 Oil/Day 0.00 0.99 1.29 10.19 19.40
$/Day $ 0.00 $ 398.11 $ 517.41 $ 4,097.81 $ 7,798.80
$/Month $ 0.00 $ 12,341.40 $ 16,039.80 $ 127,032.00 $ 241,762.80

KUDU Industries Inc. Pg 7


GRAPH 4: Example 4 Results


Conclusion
The PCP controller has proven to be a successful and and exceeds the goals and expectations of maximized
viable well manager for progressing cavity pumps, production, minimized downtime, reduced equipment
in meeting the objectives originally set forth. Overall failures, and extended equipment run life. By eliminating
productivity has been increased for the well and for the the need to continuously monitor fluid levels and manually
entire field by increasing daily fluid production, recovering adjust pump speed, operators are able to concentrate on
more quickly from downtime, and enhancing cost and time other tasks. Secondary control features allow protection
management for operations. The PCP controller meets from over pressure, high torque, and sand plugging.

Acknowledgements
I would like to express my gratitude to Lufkin Automation information and equipment used in this paper, as well as
and Theta Oilfield Services Inc. for their product IHS for the Accumap production and well data provided.

KUDU Industries Inc. Pg 8


FIGURE 1: Minute by Minute Production, Speed, and Torque Trends

FIGURE 2: Wedge

FIGURE 3: XSPOC Group Status Screen

KUDU Industries Inc. Pg 9


FIGURE 4: Well Status Screen

FIGURE 5: Minute by minute production and speed trend showing automatic reaction to
increased flow line pressure.

KUDU Industries Inc. Pg 10


FIGURE 6: 7 Day trend data showing automated sand handling

FIGURE 7: Trend data showing automated flush technology

KUDU Industries Inc. Pg 11


+1 403 279 5838
kudupump.com

S-ar putea să vă placă și