Sunteți pe pagina 1din 15

Failure of Urea Strippers and Repair

Experience

During annual turnaround of our urea plant, cracks were noted in CS multilayers of
two strippers. An in-depth analysis is presented of the failures and corrective actions
taken to repair the strippers and prevent such failures in the future.

H.P. Pota, R.V. Nesari, S.K. Nayar, and C.B. T\imbde


Rashtriya Chemicals and Fertilizers Ltd., Thai, India

INTRODUCTION :
About 80% of total carbamate is
Rashtriya Chemicals & Fertilizers decomposed in stripper. The stripper
Ltd.,is the largest fertilizer producer is one of the most critical equipments
in India having a total capacity of 1.0 in the Snamprogetti Urea process.
Million MT of N., 0.12 Million MT of Simultaneous failure of two strippers
P2Oe and 0.045 Million MT of K2O. Thai gave most anxious moments to the
fertilizer complex of RCF, located Urea staff.Anal y ses of these failures
about 100 km. south of Bombay is one and timely corrective actions helped
of the biggest in Asia having 2 x to overcome this crisis.
1350 MTPD Ammonia plants designed
by Hal dor Topsoe, Denmark and 3 x STRIPPER-FUNCTION AND
1500 MTPD Urea plants designed by CONSTRUCTION :
Snamprogetti, Italy. These plants
were commissioned in 1984-85. In the Snamprogetti Urea
process,the stripper is basically a
Urea technology of Snamprogetti is high pressure decomposer, operating
based on the ammonia stripping at about 147 bar. It receives the
process. In this process, unconverted solution containing about 33% Urea,
carbamate is decomposed into ammonia 33% NH, and 13% CO2 as carbamate
and CO in the stripper operating at (NH4COONH2). In the stripper, the
almost the same pressure as that of solution is heated up with 22.6 bar
the Urea reactor by application of saturated steam as it flows down the
heat through steam and action by titanium tubes by forming a falling
excess ammonia fed into the reactor. film. The CO2 content of solution is

345
reduced to about 5.5% by the HISTORY OF FAILURES :
stripping action of excess ammonia as
it boils out of the solution. The stripper, being one of the most
critical high pressure items in the
Due to the corrosive nature of Urea plant, is checked every
carbamate solution, the tubes of the alternate year for thinning of the
stripper are of titanium material internal titanium tubes. During the
whereas the tube sheets and the annual shutdown in April 1991, while
dished ends are cladded with a checking the condition of the Unit-11
titanium lining. The stripper shell is (Stream-I) stripper, some insulation
fabricated with ASTM A-516 Gr.70 damage was noticed near the 1CNA
steel with a multilayered construction. nozzle (Fig.1). After removing the
There are 9 outer shells each of 14.9 insulation, it was observed that
mm in thickness and an inner shell of several cracks had developed in and
12 mm thickness. The inner shell is near the 1CNA nozzle and near a
lined with a 3 mm thick titanium portion of the lower channel around
liner. All the shell plates are welded the nozzle. Cracks were also found
to dished ends. These strippers were near the circumferential welding of
designed by Snamprogetti and the channel shell to the bottom head.
fabricated by Kobe Steel, Japan. The protective Zinc coating on the
These strippers were designed as outer surface of the stripper up to
reversible type to obtain a maximum bottom manhole portion was also
life from Ti tubes. missing. No such paint damage was
observed on the topside of the
THE BROAD SPECIFICATIONS OF stripper.
STRIPPER ARE :
The appearance of these cracks
Shell side Tube side only around the 1CNA nozzle on the
Pressure(bar) outer C.S.shell created a scare since
Operating 22.6 143.0 failure normally starts from inside in
Design 25.5 162.0 any equipment where process
conditions are severe and
Temperature(C) negligence/maloperationscan result in
Operating 220.0 Inlet 190.0 failures. The extent of the
Outlet 210.0 penetration of these cracks was also
unknown. Hence further
Design 230.0 225.0 investigations and analysis were
planned.
Tube OD x Thk x L
27 x 3.5 x 4500 mm Since Kobe Steel, Japan had
fabricated this stripper as per
No of tubes - 2966 Snamprogetti's approved drawings, it
Surface Area - 838.6 M2 was decided to call Kobe's technical
experts as well as Snamprogetti's
MATERIALS OF CONSTRUCTION : engineers for investigations.

Shell - C.S.CASTM A-516 Gr.70) To assess the extent of the damage,


Tubes - Titanium (SB-338 Gr.3) all the insulation was removed to
Ferrules - 25/22/2 Cr/Ni/Mo carry out magnetic particle testing
Channels (MPT) of the total outer surface and
& tubesheets - C.S./Ti clad.(SB-265 dye penetrant test(DP test) of the
Gr.1). inside surface.
Design Code - ASM E Section VIII
Div.2 and TEMA-R.

346
Following were the observations of 1CNA nozzle area.
these tests:
6TH LAYER :
1. There was no defect detected in
the inner titanium lining. Cracks were observed in the bottom
portion initiating from the head
2. Extensive external multi-directional circumferential weld (Fig.5). A plate
cracks were observed around the of size 580 mm x 205 mm was gouged
1CNA nozzle (dummy inlet nozzle) and and removed from just above the
on the circumferential weld of the head circumferential weld.
head to channel shell (Fig.2).
CRACKS ON 1CNA NOZZLE :
3. One crack was also observed in
the circumferential seam weld of the In the 9th layer, minor cracks were
tube sheet to the channel shell. observed in the radial direction on
the 1CNA nozzle weld. The extent of
To check the extent of damage to these cracks on the 1CNA nozzle weld
the inner layers C.S. shell, crack kept increasing as the 7th layer was
affected plate portions of the approched. A large circumferential
respective layers were removed by crack approx. 300 mm long was
arc air gouging using 9 mm graphite observed in the 1CNA weld. The crack
electrodes and 500 amps direct was gouged to the depth of 55 mm
current with the following obser- from the 7th layer under the
vations : guidance of Kobe experts. After
grinding of the affected weld,
9TH LAYER (OUTER MOST LAYER) : a network of hairline cracks were
noticed in the 1CNA weld and parent
Crack affected plate of size 1380 metal.
mm x 1340 mm was removed from the
area around the 1CNA nozzle by CHECKING THE STRIPPERS OF OTHER
gouging. UNITS :

8TH LAYER : After noticing the condition of the


above mentioned stripper, it was
After removing the 9th layer plate decided to check the condition of the
portion, cracks were observed just stripper in two other streams. The
below the 9th layer cracks (Fig.3). shutdown was taken in Unit-21
Also a lot of corrosion deposits were (Stream II). The insulation cover
found near the cracks. Consequently, showed some decolouration. However,
a plate from the 8th layer of size after removing all the insulation, it
1000 mm x 840 mm was gouged and was noticed that the paint was still
removed from around the 1CNA intact around 1CNA nozzle and other
nozzle. areas. BY MPT, it was proved that
there was no crack on the outside
7TH LAYER : surface of the vessel.

On the 7th layer, cracks were In Unit-31, (Stream III) a colour


observed in a different location from change in the stripper insulation
the cracks observed in the 8th layer cover was observed around the
(Fig.4). Corrosion deposits were north side area of the 1CNA nozzle.
observed on the surface. After removing the insulation, cracks
were observed where the nozzle was
A plate of size 770 mm x 900 mm welded to the shell. One
was gouged and removed from the circumferential crack was observed

347
from the 8 O'clock position to the 3 SOURCE OF AMMONIACAL SOLUTION
O'clock position. One of the cracks in (AMMONIUM CARBAMATE) :
the nozzle was found to be 112 mm
deep by Ultrasonic test (UT) In the stripper, the solution
measurement. containing urea, unconverted
carbamate and excess ammonia comes
FAILURE ANALYSIS : from the urea reactor. Before
entering the stripper, a butterfly
In order to investigate the causes control valve (HV-03) is installed just
of the failure, a thorough adjacent to the stripper solution inlet
investigation was carried out. NOT nozzle (1N) in order to control
examinations like Ultrasonic testing parameters in the reactor and
(UT), Magnetic Particle Testing (MPT), provide desired differential pressure
Radiography testing (RT) and Dye between the reactor and the stripper
Penetrant (DP) checks were carried (fig.SA & 8B). This line does not have
out by a third agency. Two samples any support between the reactor
of the plate were cut from the top and the stripper since the line is of
layer of the cracked zone of the comparatively short length. Because
strippers and sent for metallurgical of variations of the conditions of the
analysis. Chemical analysis indicated fluid flowing in the line, there used
that the plate material was as to be minor leakages in the upstream
specified. The material used for or down stream flange of the control
channel shell layers was normalised valve (HV-03). It is a normal practice
showing ferrite and pearlite struc- to put a source of low pressure
ture (Fig.6). Equiaxed structure was steam, near the leakage point to
seen on circumferential surfaces while avoid any urea/ammonium carbamate
banded structure was seen in cross deposition which may corrode the
section of shell layers. Cracks carbon steel material of the flanges.
followed the grain boundaries. However in Unit-11 and Unit-31, the
However, structural analysis indicated leakage sometimes was excessive. In
non-homogenity of the structure order to control gaseous emmissions
(Fig.7). of ammonia/carbamate, cold
condensate was put on the source of
From the metallurgical analysis, a leakage. The 1CNA nozzle is located
conclusion could be drawn that the just below the HV-03 control valve.
failure is intergranular, originating The condensate containing dissolved
from the welds due to corrosion by ammonia/carbamate, appeared to have
seepage of ammoniacal solution in seeped through the damaged
association with residual stresses in insulation portion which caused
the stripper channel layers. Also by soaking of the insulaton with
analysing the development of cracks ammon i cal/carbamate solution. While
in each layer, it was observed that checking the condition of the
all cracks were initiated from the insulation, it was noticed that there
exposed surface or from underneath was no aluminium foil on the outer
the cracks on the top adjacent layer. surface of the stripper and the
insulaton wool was in direct contact
This conclusion was also confirmed with the metal surface. It can be said
by another independent agency that the decolouration of the paint or
investigating the failure. Its surface corrosion was mainly because
conclusion was that the failure of attack by ammoniacal/carbamate
had taken place due to stress solution trapped in the insulation
corrosion cracking (SCC) caused by material.
ammonium carbamate solution and
residual stresses.

348
To analyse residual stresses which The Unit-11 stripper was sent for
could have caused the stress repair first. The details of repair
corrosion cracking (SCC), fabrication work carried out by L&T are :
details of the equipment were
checked. The stripper was fabricated RECTIFICATION/INVESTIGATION :
by Kobe Steel, Japan as per ASME
Section-VIII Div.2. There was no The investigation of the extent of
observed deviation from code. As the damage and the rectification work of
shell was fabricated in multilayers, the subject stripper was entrusted to
stress relieving of the circumferential Larsen & Toubro, Bombay, a renowned
weld between the channel and the Indian fabricator having expertise in
head was not required. Also, channel manufacturing vessels with exotic
and 1CNA nozzle welding stress materials.
reliveing was not necessary as per
code. So, the residual stresses caused A thorough investigation of the
during fabrication could not be equipment by non destructive
removed. It is felt that the attack of examinations and other tests could
ammoniacal carbamate solution on the only identify and segregate the
plate material along with residual components which required
stresses resulted in stress corrosion replacement and those which could be
cracking in this area. There are many reused.
other observations as given below
which support SCC failure in the For the bottom channel, the
stripper: internal titanium strips covering the
circumferential weld seams were
1) No cracks near the weld of the carefully removed by L & T.
shell plates were observed. This is Thereafter the weld between the
because these plates are welded multilayered channel shell and the
individually at three locations versus tubesheet was carefully cut ensuring
welding of all plates to the nozzle no damage to titanium parts. Gas
etc. This procedure does not create gouging of weidment was done up to
as much stresses as that of complete about 100 mm depth and arc air
welding (Fig.9). gouging for the balance thickness.
Purging of the titanium surfaces from
2) There were no cracks propagating inside of the channel with argon was
in the dished end regions which done during gouging of the outer
were heat treated. layers of the channel shell
3) No crack development has been A special arrangement for Argon
reported in monolayer strippers purging was made inside the channel
which are post heat treated. shell, near the circumferential seams
to keep the titanium surfaces cool
REPAIR OF STRIPPERS : which protected them from oxidation.
As an alternative, water cooling was
After discussing with Snamprogetti also tried to cool the titanium
and Kobe Steel, it was decided that surfaces. The weld between the
strippers in Unit-11 and Unit-31 channel shell and the hemispherical
should be taken out of service and head was also parted taking similar
the bottom channel be replaced. After precautions.
a lot of technical discussions with
Larsen & Toubro (L&T), Bombay, Carbon steel layers of the bottom
India, the job was given to them. channel shell were removed by
gouging/grinding without damaging
the inside Ti clad CS shell,

349
so that it could be reclaimed in clad shell was continuously monitored
usable condition. CS layers of the during various stages of fabrication
channel were initially gouged to avoid decolouration and/or
longitudinally, till reaching the excessive temperatures to ensure that
second layer and thereafter were no oxidation of the titanium surfaces
machined. took place.
L & T fabricated the substitute Ail weld seams including those on
carbon steel channel shell by the titanium liners were examined by
mul ti w all technique. Monowall liquid penetrant testing (PT) to look
construction was not considered to for defects, prior to starting welding
avoid a longer procurement time. The operations for rectification.
multiwall channel shell could be
fabricated using readily available The tubesheet and hemispherical
materials. head were examined for the presence
of cracks, using NOT methods such as
Nozzle 1CN was removed by Liquid penetrant testing (PT)
machining/grinding with utmost ,Magnetic particle testing (MPT) and
caution to avoid damaging titanium Ultrosonic testing(UT).
portion.
Various NOT checks were also done
As the CS portion of nozzle 1CNA during fabrication on the complete
was found unusable, a new forged CS equipment including strict quality
neck was procured on urgent basis control on the repair work. This was
and the same was welded to the new done to enable certifying
multiwall channel. acceptability of the components. Some
* of them are given below.
After machining the ID of the new
multiwall channel shell (manufactured - PT examination of all exisiting welds
by shrink fitting 6 shell courses of from outside and on the titanium
28+18+22+30+30+30 mm), the same was liners from inside.
shrink fitted on the reclaimed Ti clad
CS lined shell. This was done after - RT of longitudinal seams of each
taking a skim cut on the outer shell course of multiwall channel.
diameter of the CS portion of the
reclaimed Ti clad CS lined shell. Grooves were made on the
separating lines of the shrink fitted
The leak detecting tubes (weep shell courses of the multiwail channel
holes) were also reclaimed by and filled by welding and PT/MT
carefully removing the outer coupling examined.
and grinding off the weld between
the leak tube and the Ti clad liner. - PWHT (post weld heat treatment) of
channel shell after shrink fitting all
Extreme care had to be taken for shell courses concentrically and after
repair/rectification work to avoid welding CS forging for nozzle 1CNA
damage to the exchanger components on to the same was carried out. PWHT
having titanium materials. Titanium is not a mandatory requirement from
components were handled avoiding code point of view. Yet L & T carried
iron contamination by covering them out the same to remove any residual
with plastic sheets/brown papers and stresses caused during fabrication.
by avoiding exposure to dusty
atmospheric conditions. - PT/MT examinations of weld edges
on tubesheet, hemispherical head
The titanium surface of the inner and channel shell. (The weld edges

350
had to be weld built up at a few threaded titanium liner, dry ice was
spots and re-prepared for butt used to shrink the iiner.This was
welding). required prior to unscrewing the
liner since it was badly jammed. The
- UT examination of a 100 mm wide threading on the reclaimed titanium
band at the edge of hemi- spherical liner of nozzle 1CNA was found
head to detect defects if any. damaged. The repair was done by
weld buildup and subsequent
- UT examination of CS nozzle neck reth read ing.
to multiwall channel shell welding.
iii) In order to ensure matching with
After completion of the the existing pipe lines, it was
circumferential seams between the necessary to maintain the original
multiwall channel shell and the dimensions, specifically for nozzle
tubesheet/hemisperical head, locations and projections. This
titanium insert plates were fitted.The necessitated limiting the reduction in
fitting required high skill and a lot height of the tubesheet hub to 6 to
of precautions to ensure that no gaps 8 mm while parting the same from the
remained underneath. This was existing channel by removing the
required to ensure that welds existing weld metal including heat
connecting titanium cover strips did affected zone.
not fail under channel side pressure.
All titanium welds were visually Rectification of the hemispherical
inspected to detect decolouration and head and the subsequent machining
PT examined to ensure freedom from for preparing the weld edge resulted
defects. in a marginal reduction in the length.
To match this, the same additional
- All tube to tubesheet welds were length was provided on the multiwail
subjected to a helium leak detection channel.
test by filling and pressurising
helium on the shell side. Also, weld buildup had to be
carried out on the CS portion of the
Titanium cover strips were inner Ti clad CS shell on both ends
pneumatically and helium leak (Fig.10).
tested before hydrotesting. A Helium
leak test was also repeated after Extreme precautions had to be
hydrotesting. taken during the weld build up to
avoid damage to the titanium
- Equipment was finally subjected to cladding. Titanium cladding was
hydrotesting on both the shell side stripped off upto about 35 mm away
and tube side at pressures of 34.7 from the edges to enable the CS weld
bar and 221.9 bar respectively. bui I tup on the CS portion to increase
the length. Arrangement/monitoring
- Rectification also required a number was done to ensure that the
of special operations to be carried temperature of the titanium surface
out, some of which are listed below : did not increase above 200C. The
stripped off portion of titanium was
i) Cutting of special threads on CS made up using extra wide titanium
forgings for nozzle neck 1CNA was insert strips and cover strips.
required. This was done to match the
threads on the reclaimed titanium - Fabrication of the multiwall channel
liner. involved shrink fitting of the shell
courses with strict control on gaps
ii) In order to dismantle the between the different layers.

351
This necessitated controlling the after the welding. They were then
circumferences of the fabricated allowed to cool to room temperature.
individual shell courses within about The weld repaired portion and a
0.5 mm and a highly skilled operation band of about 100 mm width from
of shrink fitting. dished end edge were PT and UT
examined after 24 hours to detect
- In order to salvage the titanium delayed cracking. Subsequently, the
leak tubes (weepholes), cutting of the repaired areas were also RT examined.
CS layers of existing channel was All precautions were taken to ensure
done in four/five sectors. Also, in that no damage occured to the
order to compensate for the reduction titanium surfaces during weld repair/
in length of the weephole tubes, the build up by employing argon
depth of the counter bore on the purging, monitoring of colour,
channel shell had to be increased. temperatures, etc.

- In order to carry out investigations - After separating the inner Ti clad


on site, a number of deep scoop ings shell a few cracks were noticed on
were done by gouging circumferential the CS* portion. These were ground
seams of the channel to head out and the areas were weld built up
including the adjoining base metal. with due precautions ensuring no
The sizes of the scooped out areas damage occured to titanium surfaces.
ranged between 125 mm to 150 mm
long, 35 mm to 50 mm wide and 40 mm - Titanium surfaces were thoroughly
to 90 mm deep. One spot was cleaned and subjected to Ferroxyl
scooped out near the tubesheet to test to ensure freedom from iron
channel shell joint while 8 spots were contamination.
scooped out near the hemispherical
head to channel joint (Fig. 11). UREA STRIPPER UNIT-31 :

To repair the above scooped out With the experiences of the Unit-11
areas which possesed linear cracks as stripper failure, the Unit-31 stripper
revealed on subsequent inspection job was started. On
investigations^ specially developed removing insulation from the bottom
technique was adopted. Existing weld channel shell, visual cracks were
metal and heat affected zones were observed near the 1CNA dummy inlet
removed completely and verified by nozzle. The crack location was identi-
an etching test. The linear defects cal to that in Unit-11, but the cracks
were removed by grinding and were of less severe nature.
cleared by PT examination. The
scooped out areas/grooves were built CRACKS LOCATION :
up using special electrodes of
specific sizes. Controlled preheat and i) 1 CNA dummy inlet nozzle to
interpass temperatures were applied. channel shell weld.
An Initial layer was deposited using
3.2 mm dia. electrodes and ii) Outermost (9th) layer of the
subsequent layers with 4 mm dia. muitilayered channel shell.
electrodes.
iii) 1CNA dummy inlet nozzle body.
In order to make up the
dimensions, weld deposition was also INVESTIGATIONS :
done on the weld edge of the
hemisherical head. Weld repaired/built Ultrasonic testing of the 1CNA
up areas were post heated at 200 to nozzle body was done to determine
250 C for four hours immediately the crack depth. The depth of five

352
radial cracks (going transverse in the weld. As stress relieving was
through the nozzle to the channel not possible after welding, all the
shell weld) was determined as shown weld beads were peened using a
in Fig.12. The UT indicated a depth pneumatic blunt chisel. Magnetic
of 112 mm in the crack No.2 (2nd Particle Inspection was carried out in
from left) and 40 to 45 mm depth as order to check for any delayed
detailed in Fig. 13. cracking after completing all the
welding jobs. No indications of cracks
REPAIR JOB AT SITE : were observed.
Bharat Heavy Plates and Vessels, TESTING :
the only company manufacturing the
multilayered vessels in India,were After completing the job, the
called for carrying out the stripper was hydraulically tested at
specialised repair job on site. The a pressure of 161.9 bar (Operating
job was carried out as per the repair pressure 142.2 bar) for one hour. No
procedures given by Kobe Steel. leakage was observed. The MPI was
carried out again after hydraulic
The outermost 9th layer plate of testing. No crack indications were
size 800 mm x 650 mm covering the observed.
cracked area in the plate was taken
out by gouging (Refer to Fig.12). The ACOUSTIC EMISSION MONITORING OF
cracks in the nozzle body were also UNIT-31 STRIPPER :
gouged. Cracks at location Nos.1,3,4,&
5 (Ref.Fig.13) disappeared after An acoustic Emission Technique
gouging up to 40 mm depth in the (AET) was used to monitor on-line the
nozzle body. The cracks at location status of repaired cracks.
No.2 remained even after gouging
upto a depth of 80 mm. The cracks EXPERIMENTALS :
in the 8th layer and subsequent
layers of the channel shell were I- channel Ounegan/Endevco make
gouged till the cracks disappeared. 3000 series AE equipment was utilised
The radial crack No.2 (Ref.Fig.13) in for recording the AE signals. Two
the nozzle to channel shell weld joint PZT sensors of 175 KHZ frequency
was left beyond 80 mm depth, since (resonant type) along with
crack removal by gouging could preamplifiers of 40 dB fixed gain and
affect the integrity of the titanium with a band pass filter were used to
liner inside. record the signals. Three rods were
welded onto the outer most layer
All the cracks were welded with around the nozzle to act as
E-7018-1 electrodes.dried between waveguides. The AE system has a
200-250 C. Proper pre-heating fixed voltage threshold of 1 volt.
(100-150 C) and post heating Threfore,the total gain values for
(100-150'C) with 1 hr. soaking time both the channels were selected at 78
for the nozzle weld were strictly dB to cut off the background noise
followed. For p re-heating and post (including flow induced noise).
heating, special LPG burners were
used. All the cracks in the nozzle In absence of any baseline data
weld, nozzle body and multilayered and in order to classify the AE
channel shell wrapper plates were sources, it was decided to compare
welded in proper sequence. During the event/count rate for signals
welding, Magnetic Particle Inspection recorded after 1 month with the first
was carried out at every stage to measurements as the locations of
check for any propagation of cracks possible AE sources were known.

353
Otherwise, with a 2 channel system, it As can be seen in Figs. 14 & 15, the
would have been very difficult to event rate has increased substantially
locate the sources in a cylindrical in 25 days under constant pressure.
vessel. For example on Oct.18, 1991, a total of
354 events were recorded during 16
The AE signals were recorded on hours compared to a total of 312
October 18,1991 and November 12,1991. events on November 12, 1991 recorded
The parameters like pressure, during 8 hours (i.e.half of the
temperature etc. were the same. Also previous recording period).
the gain and threshold settings of AE Therefore, the AE source (i.e. crack
unit were the same as during the propagation in all probability) is
first measurement. critically active. If the source is
critically active, it is indicative of
RESULTS AND DISCUSSION : questionable structural integrity and
should be evaluated by other NOT
The process parameters during the Methods.
AE recording are given in Table-1.
Parameters which can affect AE The experimental evidence clearly
behavior of material are pressure and indicates that the source of AE is
to some extent temperature. They critically active which means that the
remained fairly constant during the cracks have propagated. This was
recording period. also confirmed by UT. Additionally,
the substantial increase in event
TABLE -1 rate may be concluded as rapid
deterioration in structure with time.
SPECIFICATION OF UREA-31 STRIPPER However, it is not possible to
calculate the crack propagation
velocity on the basis of available
1. Vessel Material Carbon Steel data.
2. Inner Lining Titanium CONCLUSIONS :

3. Op. top Temp. 196'C It can be concluded that the


failures of two strippers were due
4. Op. bottom Temp. 206 'C to stress corrosion cracking as a
result of seepage of ammoniacal
5. Operating Pressure 141.3 bar solution through the damaged
insulation in combination with
Cumulative events vs.time plots for residual stresses in layers of the
recordings on Oct. 18,1991 and shell.
November 12,1991 are shown in Figs.
14 & 15 respectively. As per the The failure could have been avoided
standard recommended practice, a if :
source is considered active if its
event/count continues to increase 1) The butterfly control valve HV03,
with increasing or constant was located away from the stripper.
stimulation. A source is considered to
be critically active if the derivative 2) No cold condensate was used on
of event/count with respect to the leaky flanges.
stimulus continuously increases with
increasing stimulation or with time 3) Insulation was covered after
under constant stimulus (Fig.16). wrapping aluminium foil on the shell
position all around.

354
4) Insulation was covered with
aluminium sheets with no leakage on to c mcLuBCD wrr -rattsaupr or TWW +
joints.

5) Stress relieving of the


circumferencial joint between the
shell channel and head and also
between the shell and nozzles was
uc*K percent/G
carried out. TUBE. Mrt. Tt

After the repaired strippers in


Unit-11 and Unit-31 were installed
with the above precautions, they
were inspected during a recent
annual shutdown. The repaired
surface was in good condition.

ACKNOWLEDGEMENT :

The authors wish to acknowledge


with gratitude the support and
encouragement given by the UMI otTKTM* nts-tun- 7?
Management of Rashtriya Chemicals nuet
and Fertilizers Ltd. for the S//S "
presentation of this paper.

DISCUSSION
Diagram 1
G.R. Prescott, Consultant: You showed a detail of
the leak detecting tube, and if I heard you correctly
you said it was welded to the titanium liner. Is that
correct?
Nayar: Yes.
Prescott: How does it detect leaks in that case? the titanium clad layer near the weld of the filler
Nayar: I will try to explain the leak detection with plate (Diagram le). A cover plate is welded to the
the help of a slide (see sketch below). There are titanium clad layer, covering the welds of the filler
nine layers of carbon steel clad with 12 mm carbon plate and the leak detecting tube. In this cover plate
steel and 3 mm titanium inner layer (see Diagram 1 groover are machined (Diagram Id) to carry any
below). The clad plate joints are welded after leakage of the cover plate welds to the leak detect-
removing the titanium layer in the vicinity of the ing tube. The process fluid will not come into con-
welds (Diagram la). The weld is covered by a tact with the carbon steel plates.
filler plate welded to the titanium liner (Diagram
Ib). The titanium leak detecting tube is welded to

355
H.P.Pota S.K. Nayer

R.V. Nesari C.B. Tfcmbde

Figure 1. Urea stripper.


Figure 2. Developed view of cracked area
near nozzle 1CNA.

356
Figure 6. Optical micrograph showing a
typical equiaxed ferrite (white)
and peariite (black) structure on
Figure 3. Crack In 8th layer plate. both inner and outer surfaces of
the samples (200x).

760

4 r . .* "v*L. : I \. _'. .

210

Figure 4. Crack In 7th layer plate.

'eouseo afro loo


TMS *OP f f

risiets IH M.P.J.
\1Ctt
CHUCKS

$70

200X

Figure 7a and b. The cross section of the


layers show banded ferrlte-
pearlite structure.
Figure 5. Crack In 6th layer plate.

357
CMAUMfL SMSIL CC-!

25 mm

Figure 10. Detail of weld buildup carried out


on reclaimed inner titanium clad
c.s. layer to make up the length.
A 1401. O* WO
S |M(.*MI"B
Cl IS lx * S"
80
ezuiiiiW"*
C31ISI.X1SWXSOO

O I8*IX47W80D

Figure 8a. R-1 to E-1 original line.

Figure 11. Scooped out areas on channel


shell to hemi head joint; cracks
seen in scooped out area.
/-

Figure 8b. R-1 to E-1 modified line.


55 , 5 5 , 5 5

TUBE
swetr

tO K

Figure 9. Weld seam of channel shell.


Figure 12. 31 E-1: 8th layer plate crack detail.
358
CITAClr
KO.
IN weio IN NOZZLE
MOT

t 42/45 il

2 M2/H3 \\Z to
3 4Z 17

4 &5 20 300
S 4&/*t l7/>8

2*0

<
.4

I uo
3

to

t A * 10
TIME (HOURS) -

Figure 15. Cumulative events vs. time for


test carried out on Nov. 12,1991.

Figure 13. Max. depth of crack found in u.t.

a I-
ACTIVE)

t'4

(INACTIVE)

STIMULUS

TIME (HOURS) -
Figure 16. Classification of AE sources.

Figure 14. Cumulative events vs. time for


test carried out on Oct. 18,1991.

359

S-ar putea să vă placă și