Documente Academic
Documente Profesional
Documente Cultură
Netherlands Standards
General
ICS 23.040.10
July 2003
1
NEN 3650-1:2003
Apart from exceptions provided by the law, Although the utmost care has been taken with
nothing from this publication may be duplicated this publication, errors and omissions cannot
and/or published by means of photocopy, be entirely excluded. The Netherlands
microfilm, storage in computer files or Standardization Institute and/or the members
otherwise, which also applies to full or partial of the committees therefore accept no liability,
processing, without the written consent of the not even for direct or indirect damage,
Netherlands Standardization Institute. occurring due to or in relation with the
application of publications issued by the
Netherlands Standardization Institute.
The Netherlands Standardization Institute will,
with the exclusion of any other beneficiary,
collect payments owed by third parties for
duplication and/or act in and out of law, where
this authority is not transferred or falls by right
to the Reproduction Rights Foundation.
2
NEN 3650-1:2003
NEN 3650-1:2003
1
NEN 3650-1:2003
Contents Section 2
Forward............................................................................................................................................................ 4
8. Constructional Design..................................................................................................... 5
8.1 Pipeline Configuration..................................................................................................... 5
8.1.1 General.............................................................................................................................. 5
8.1.2 Route Definition............................................................................................................... 5
8.1.3. Aspects Related to the Choice of Pipeline Alignment..................................................5
8.1.4 Pipeline Depth Position................................................................................................... 6
8.1.5. Parallel Pipelines.............................................................................................................. 6
8.1.6 Channel Containing Cables and Pipes...........................................................................6
8.1.7 Pipe Sleeve....................................................................................................................... 6
8.1.8 Pigging Facilities.............................................................................................................. 7
8.1.9. Axially Rigid and Non-rigid Pipes...................................................................................7
8.1.9.1 General.............................................................................................................................. 7
8.1.9.2 Axially Rigid Connection................................................................................................. 7
8.1.9.3 Axially Non-rigid Connection.......................................................................................... 8
8.1.9.4 Compensator or Dismantling Joint Connection............................................................9
8.2 Pipeline Design.............................................................................................................. 10
8.2.1 General and Field of Application..................................................................................10
8.2.2 Basic Requirements for Pipeline Design.....................................................................10
8.2.3 Safety Level.................................................................................................................... 10
8.2.4 Maximum Limit State and Serviceability Limit State...................................................11
8.2.5. Calculation Method........................................................................................................... 11
8.2.6 Limitation of the Survey................................................................................................ 13
8.2.7 Loads.............................................................................................................................. 14
8.2.7.1 General............................................................................................................................ 14
8.2.7.2 Load Type Further Information ....................................................................................15
8.2.8 Load Combinations and Load Factors.........................................................................17
8.2.8.1 Load Combinations and Load Factors for Maximum Limit States............................17
8.2.8.2 Load Combinations and Load Factors for Serviceability Limit States......................18
8.2.9 Verification Procedure and Material Factors...............................................................18
8.2.10 Pipeline Outline and Classification in Sections to be Calculated .............................19
8.2.10.1 Outline......................................................................................................................... 19
8.2.10.2 Sections to be Calculated..........................................................................................19
8.2.11 Mutual Influencing of Pipelines and Related Structures............................................20
8.2.12 Specific Design Aspects................................................................................................21
8.2.12.1 Specific Design Aspects for Underground Sections...............................................21
8.2.12.2 Specific Design Aspects for Aboveground Sections...............................................21
8.3 Station Design................................................................................................................ 22
8.3.1 General............................................................................................................................ 22
8.3.2 Requirements................................................................................................................. 22
8.3.3 Components................................................................................................................... 23
8.2.4 Connection Between Pipeline and Station...................................................................24
2
NEN 3650-1:2003
3
NEN 3650-1:2003
Foreword
This standard is a revision of NEN 3650:1992. Besides steel pipe which was the hallmark of the 1992 publication, this
edition includes other pipeline materials.
The standard is divided into parts. The first part includes general requirements for pipeline systems. The parts that
follow include requirements specific to the pipeline material dealt with in that section, NEN 3650-2:2003 Steel, Draft
NEN 3650-3:2003 Synthetics, Draft NEN 3650-4:2003 Concrete, and Draft NEN 3650-5:2003 Cast Iron. The
standards series has been drawn up under the aegis of the Netherlands Standards Commission 310004 Transport
pipelines.
NEN 3650-1 has the status of a national standard. The section includes general guidelines from the earlier NEN
3650:1992 and NEN 3650:1998. Material-specific requirements are included in the relevant sections dealing with
those materials. Additions are made to general regulations whenever the use of materials other than steel makes this
necessary. Some standards have been withdrawn, as requirements have been adjusted from the standpoint of
technological progress, namely, with respect to the total life-cycle approach to external security (risk-control during
design, installment, maintenance and shut-down), design calculation and the relation to (European and international)
standards and directives. New attention is now being paid to the choice of route, articulated pipelines, offshore
pipelines and grooveless techniques. A probabilistic approach was applied to structural design, where assumptions
are made about various loadings (internal and external) and properties of materials. Via a model calculation, the
effects on the structure are determined, which must be compared with the minimal limit values and boundary
conditions. Backgrounds of the new calculation methods are covered in a supplement to NPR 3659:1996/A1:2003.
Appendices A,B,C,D,E,F and G are the components of which this standard consists. Appendixes H,I,J and K are
informational components of this standard.
Because the Figures in this standard are in large part adopted from the old standards, and the additions were made
outside NEN, the standards and editing rules for technical drawings have not been completely followed which can
be seen from the captions to the Figures. In the text part of the standard, however, correct standards were utilized.
Revision of Standard
NEN 3650-2 is divided into Sections. There is an annual review to determine whether or not the revision of one or
more Sections is necessary. The content of each Section is examined minimally once every 5 years. Proposals for
revision must be submitted in writing to NEN.
The purpose of the Standard-series is to obtain underground pipeline systems safe for people, the environment and
property, by making requirements for the design, installation, start-up and shut-down of pipeline operations that will
guarantee a durable, effective, and efficient system.
This demands safety regulations. Deviation from the (fixed) regulations of this standard is only possible, if it can be
shown that the same or higher level of safety will be otherwise attained.
Relative to the relevant EN standards for the pipeline-technical domain, this standard adds additional details for
conditions in the Netherlands.
The stipulations of this standard, including the adopted revisions according to NEN-EN 1594:2000 and ISO
13623:2000, are applicable to pipelines, in that this is also in compliance with the stipulations of NEN-EN 1594:2000
and ISO 13623:2000.
Use of Standard
The people applying the standard, must be familiar with the materials employed and be in possession of the relevant
expertise.
The designer, builder or user of the pipeline system is reminded that this standard is not a design specification nor a
handbook.
4
NEN 3650-1:2003
8. Constructional Design
8.1.1 General
The design, laying, operational management and temporary and/or final decommissioning of the
pipeline(s) should be taken into consideration when selecting the route. Future urban and industrial
developments near the route must be considered as well as ensuring that the number of adjustments,
rerouting or limitations continue to be kept at a minimum in the future.
The activities that must be performed before a route can be defined as definitive and before a pipeline
can be laid are given step by step. H.1 contains extensive descriptions of the activities.
The pipeline configuration must be designed in the chosen route strip in view of the risks involved and,
where possible, these must be limited. The following must be taken into consideration as well as other
issues:
5
NEN 3650-1:2003
The minimum required ground cover of 0.8 m should be increased in the following cases whereby ground
cover must be applied that has been adjusted to the circumstances:
- in areas where it may be expected that subsoiling, drainage or depth excavation will occur or
where provisions have been made for a pipeline system in order to improve drainage;
- at locations where ground excavations can be expected;
- in areas that may be liable to erosion;
- in situations where the pipeline may rise due to freezing;
- at locations where waterways cross in connection with the risk that damages may occur due to
ship anchors.
When the minimum ground cover of 0.8 m meets with important obstacles which makes it necessary to
protect the pipeline against external mechanical damage, the pipeline must be protected by a covering
construction.
The pipeline may have to meet certain requirements set by, among others, the owner of the ditch or the
water manager when the pipeline crosses a ditch or watercourse. The ground cover of sag pipes may be
increased with a supplement due to, for example, soil erosion and anchor risk as a consequence of
navigation after consulting with the manager involved (see also NEN 3651:2003).
Pipelines in a channel containing cables and pipes must be configured in consultation with and according
to the requirements of the manager of the channel containing cables and pipes. The channel is provided
with the necessary engineering structures to safeguard a separation of interests with other land use (for
example, water-retaining structures).
Pipelines in a channel containing cables and pipes have a smaller probability of failing than comparable
pipelines in the field as a result of the undertaken measures and the degree of management and
monitoring of the channel.
COMMENT: There is one pipeline channel in the Netherlands: Stichting buisleidingenstraat Zuidwest
Nederland from Pernis towards Antwerp.
8.1.7. Pipe Sleeve
6
NEN 3650-1:2003
- in other areas should the Pleistocene be approached and/or be drilled up to less than 2 m. This
also applies to Holocene sand embankments or swamps that have an open connection to the
Pleistocene.
- of liquid pipelines with storage basin dikes (see also NEN 3651:2003);
- of pipelines as a result of which corrosive substances are transported before the pipeline
material;
d) road crossing when pipe jacking of the pipeline itself is not possible;
The following requirements are made from the pipe sleeve (see also 9.6.2):
- the pipe sleeve must be suitable to absorb all external loads and the external design pressure of
the medium transporting pipeline in those cases in which this is specified in the design;
- the pipe sleeve must be put together in such a way that corrosion protection of the medium
transporting pipeline can be safeguarded;
- the pipe sleeve must be flexibly sealed at both ends to limit to a minimum the groundwater
circulation within the annular space and, thus, also the supply of oxygen.
It may have been determined from an operational system requirement viewpoint that transport pipelines
must be piggable. Aspects that help determine the construction and use of pigging facilities are:
8.1.9.1 General
Pipes are built using interconnected pipe elements. The connection method determines the behavior of
the pipeline concerning the axial rigidity, normal force and deformation.
A distinction is made between pipelines with axially rigid and non-rigid connections.
Axially rigid connections are connections where the pipe elements are connected to each other rigidly. A
continuous rigid pipeline is created applying this connection whereby the separate pipe elements are not
(or do not have to be) distinguished strength-technically. The connection must be able to resist the same
or a larger load as the pipe element itself.
COMMENT The following are examples of this type: straight joints (steel), flanged joints, screwed
pipe connections, mirror welding or electrowelded-on sockets (PE, glued (PVC, GVK) or laminated (GVK)
connections).
7
NEN 3650-1:2003
8
NEN 3650-1:2003
Applying compensators or dismantling joints may be a solution when expected (abrupt) settlement
differences or temperature differences produce more lateral or axial displacement than is admissible for
the connection structure of the pipe elements.
Bellow Compensators
Bellow compensators can be applied for different objectives. The axial compensator is connected to
compensate for the extensions or contraction of a pipeline (for example, as a consequence of
temperature changes). The tension-resistant compensator (constructed with a hinge over an axis or with
a universal joint) is suitable for allowing angles of rotation between pipe elements.
- the bellows undergoes direct and indirect (transferred via dismantling effect) soil and traffic load;
- the bellows waves fill up with the surrounding soil which means that the flexibility of the bellows is
reduced and the stress in the waves increase;
- the waves can internally act as sand and silt traps with the same effect, for example, with raw and
waste water pipelines;
- the bellows high-grade steel may be sensitive to stress corrosion and hydrogen brittleness;
When applying tension-resistant steel bellow compensators to include large discontinuous installation
subsidence differences in crossings (for example, sag pipe connections), it must be demonstrated that
these drawbacks have been resolved.
Rubber bellows can be applied to pipelines with a slight internal pressure. The bellows must be provided
with hinges (tension-resistant).
Dismantling Joint
Dismantling joints are usually constructed of construction steel and are provided with gland sleeve
connections with steel bearing segment rings for the relief of the rubber-sealing element; see Figure 7.
9
NEN 3650-1:2003
The (specific) structural strength calculation of the dismantling joint must be performed in consultation
with the supplier. The subsidence difference (discontinuous) that must be included amounts to:
z = L tan
where
is the maximum angle of rotation (for the usual value of = 4, z = 0.07 x L is used).
Tie rods are installed with tension-resistant dismantling joints that have to be secured during mounting
(for example, with a double nut). The tie rods are charged with a tensile force that equals the pressure
times the surface of the pipe sectional plane as a result of internal pressure.
COMMENT 1 This applies if there is a thrust effect near the dismantling joint (elbow or branch). If this is
not the case, axial force transfer is not required and, therefore, the tie rods are, in principle, unnecessary.
If both sides of the dismantling joint move in parallel to each other, an s clearance is required in the tie
rods before z occurs which equals:
COMMENT 2 This clearance could be included in advance of the tie rods by keeping the space free
between the safety device and the stop flange. It is, however, not necessary unless both the connecting
sections are completely axially fixed (for example, both have been poured in concrete foundations).
The lengthening (tensile pretensioning) that can generate expansion as a result of internal pressure over
the angle in the tie rods, is a smaller order of magnitude than the abovementioned clearance s, is,
moreover, opposed as a result of the surrounding soil (thrust absorption) and can be ignored.
This paragraph deals with the general provisions for the strength-technical design of land pipelines (straight pipe,
elbows, connections and branch pipes). A distinction is made between underground (buried or trenchless
installations) pipelines and aboveground (usually only local supporting) pipelines.
Specific provisions for offshore pipelines are dealt with in chapter 11.
Landfall pipelines must be dealt with as would land pipelines. As well as the crossing with the water-
retaining structure (specific land pipeline), there is an overlap with offshore pipelines for the section in the
shallow water just before the coast. The laying method used for the section has an important role in the
design of the pipelines. Knowledge of land and offshore pipelines must be combined for this issue.
Pipelines must be designed and constructed in such a way that the probability of exceeding a limit state is
acceptably low for the anticipated duration of use.
Measures must be taken when it is reasonable and possible to limit any potential damage to the pipeline
by avoiding, undoing and/or reducing hazards that threaten the pipeline and/or it should be designed in
such a way that the related hazards can be resisted appropriately (see also Table 2).
10
NEN 3650-1:2003
The required safety level is determined by the consequences in case of pipeline failure. A more serious
consequence demands a lower level of risk of failure. A pipeline that is designed, laid and managed
based on the requirements of this standard complies with the required risk of failure level which is
achieved through a combination of (a) external measures, (b) strength-technical design requirements and
(c) installation requirements .
The contribution of the strength-technical design is further specified in 8.2, especially, the loads and load
combinations to be taken into account, the load factors to be applied, the calculations to be performed,
the strength functions to be used and the tests to be performed.
Differentiations in strength-technical pipeline design are achieved by the following among other elements:
- the quality of the piping design. This not only refers to the strength and the deformation capacity
but also the possibilities of achieving correct installation, avoiding potentially dangerous
situations, building in resilience, making inspections possible during implementation and
operation, etc.;
- the size of the load factors to be applied and the load combinations to be assessed. The size is
partly determined by the pipeline position (pipeline in the field, pipeline in crossings with important
water management projects, area class in relation to, for example, natural gas transport);
- the volume and quality of the calculations to be performed to determine the response of the
piping under the expected loads;
- the reliability of the strength functions based on which the results of the calculations must be
tested;
- the requirements for the pipeline materials to be applied (such as for steel: strength and
toughness of the parent material and welds, admissible geometry deviations such as wall
thickness differences, out-of-roundness, welding imperfections, etc.);
Refer to NEN 3650-2 and Draft NEN 3650-3,-4 and 5 for further details on the above where the load
factors and load combinations which are to be taken into account are given per material, pipeline type and
position.
A limit state is a state where the set performance requirements are no longer complied with according to
ISO 2394:1998. A distinction is made between maximum limit states and serviceability limit states:
- maximum limit states are limit states in which the collapse or other forms of structure failure occur
or the maximum strength is exceeded (for example, the tearing open of the piping and leakage of
substances which cause unacceptable damage);
- serviceability limit states are limit states in which the set requirements are not complied with any
longer in relation to the correct operation of the structure (for example, presenting too much out-
of-roundness, the occurrence of annoying vibrations or noise, leakage of substances that do not
cause unacceptable damages).
Limit states and related strength functions are included in the sections which refer to each type of used
material.
11
NEN 3650-1:2003
Calculation values for the loads (so-called calculation loads) are used for the calculation. These are
obtained by multiplying the representative loads with the related load factors. Next, relevant load
combinations are determined.
Calculation values for material characteristics are obtained by dividing the typical values for the
characteristics by the corresponding material factors.
COMMENT When the load, settlement, strain limit and tensile strength quantities and such are
mentioned in this standard, the calculation value for the quantity involved is referred to unless otherwise
stated.
The effects of these load combinations on the construction are determined through calculations, such as
section forces, deformations of the piping, stresses, strains and any varieties thereof. Finally, it must be
shown that no limit state has been reached. The effects must be tested in relation to the relevant strength
functions for this purpose. See also 8.2.8 and 8.2.9.
COMMENT The strength functions may involve material characteristics but may also relate to a
calculation formula that describes the course of a certain failure mechanism (for example, implosion or
buckling).
The calculation includes the following detailed steps; see also the flow chart in Figure 8.
d) Under certain conditions it is admissible to utilize a simplified calculation whereby usually only the
internal pressure is taken into account. Such a simplified calculation has been elaborated further
in NEN 3650-2-2003.
e) Determining the load combinations, loads and related load factors that should be taken into
account as well as determining the limit states to be tested. Every section of a pipeline system
must be examined for the influences of the loads given in 8.2.7. Based on this, the loads and load
combinations that are relevant to that section must be determined. The calculation loads are
assumed for the calculation. Section 8.2.8 provides information on the load factors to be applied.
f) The calculation of displacements, deformations, force and moment distribution and reactions.
This calculation depends on the uncoiled length of the pipeline configuration and, where it is
required, the time relation. The trajectory and the size of the forces (normal force, shear force,
bending moment, torque moment, ground loads and bearing reactions), the deformations
(bending deformation and normal force deformation) and the (relative) displacements and
deflections must be determined for the relevant combinations of loads. This applies to both the
pipeline and also to the effects the pipeline has on its environment (soil and support, fixed point
and conductivity structures, etc.).
g) Calculation of the quantities to be tested such as section forces, section capacities, stresses,
strains and variations therein.
12
NEN 3650-1:2003
The positive and negative values of the stresses and strains that can occur in the wall of the
pipeline system sections must be determined and, where necessary, also the course of the
amplitudes and frequencies of stress and/or strain variations.
As a stress increase occurs in the pipeline elements as a consequence of geometry, it must be
taken into consideration (for example, for elbows in rigid pipelines). Quantities that are not
relevant or quantities in relation to which there is no doubt about the subordinated and/or
favorably active character, do not have to be included in the calculations.
h) Determination of the limit values from the strength functions, taking material factors into
consideration that relate to the relevant limit states. These are material-specific and are further
described in the material section concerned.
i) Testing
The section forces, sectional deformations, stresses, strains and other values obtained through
the calculation loads may not exceed the limit values.
13
NEN 3650-1:2003
14
NEN 3650-1:2003
- a simplified calculation is permitted (specified in Figure 8 to the right). This calculation, however,
is material-dependent and applies under specific preconditions. See the relevant material section
in this standard;
- there are results available from a previously performed survey of an identical or comparable
pipeline system and the loads that apply to these results are also comparable and/or higher;
- there is no doubt about the subordinated and/or non-relevant or contrary (favorably working)
character thereof in relation to certain loads.
8.2.7 Loads
8.2.7.1 General
Load means all physical processes that lead to deformations and/or stresses and/or displacements of the
piping in the pipeline material.
An inventory of permanent and incidental loads that may operate on the pipeline system is required for
the pipeline system design.
The survey should include both the laying phase and the operational phase.
COMMENT Loads that occur in the laying phase can have a permanent character and can, therefore,
remain during the operational phase; for example, the application of pretension.
The size of every load should be checked for both phases. The loads thus obtained or the combinations
thereof form the basis for the design of the pipeline with regard to strength, deformations and stability.
The following load types and/or reasons, respectively, must be considered in the design if applicable:
A short explanation is given in 8.2.7.2 regarding the load types. Refer to 11.4.2.3 for specific load types or
reasons for the load for offshore pipelines.
Annex C offers methods that can be utilized to determine the size of the loads.
COMMENT The typical load can be utilized as a representative value whereby a distinction can be
made based on:
- variable loads; for which usually the used typical load is that which is expected to be reached no
more than once during the life cycle;
- permanent loads; for which usually the average value is utilized as the typical load unless the
load concerned shows a relatively high variation coefficient. The utilized load, in such cases, for
which the probability of the value being exceeded is less than 5%.
15
NEN 3650-1:2003
Pressure
- the maximum and minimum negative pressure and excess pressure (maximum operational
pressure, design pressure), respectively. The negative pressure has to be increased with any
(hydrostatic) existing external excess pressure;
- pressure impulses in the media as a consequence of opening and closing the valves and/or
starting or stopping the pumps, compressors and such (incidental pressure increase), cavitation
after pipe burst;
- pressure variations during business operation (in relation to limit state fatigue).
The determination method for the force of these loads is specified in C.2.
Temperature
All thermal loads (these are loads that occur as a result of a hampered and/or hindered thermal
deformation of the pipeline) must be utilized in the survey.
COMMENT Thermal deformation can occur due to temperature variations of both the media and the
environment. Thermal load can occur as a result of uneven heating or cooling of the pipeline (for
example, because of the sun or wind) or as a result of a layered movement of warm and cold media. In
special cases: loads as a result of a considerable temperature gradient on the wall.
Heating as a result of sun radiation can lead to a significant pressure increase (for example, between two
closed valves) in an aboveground closed section that has been filled with liquid.
The determination method for the force of the load due to temperature is described in C.3.
Ground Load
The following should be taken into account when designing pipeline systems:
- load due to directly and indirectly transferred ground loads (neutral ground load up to a maximum
of the passive ground load);
- load as a result of uneven vertical and/or horizontal displacement of the pipeline and/or uneven
vertical and/or horizontal displacement of the subsoil;
- reaction forces of the soil as a result of loads on and shape-changing of the pipeline and
displacement in relation to the surrounding soil (lateral vertical under and above, lateral
horizontal, axial friction reaction and tangential friction reaction), respectively;
- load due to ground formations as a result of the vibratory extraction of sheetpile walls.
Ground loads that can occur when laying pipelines as a result of, for example, earth fill or one-sided
ground load due to excavations must be utilized when designing the pipeline.
16
NEN 3650-1:2003
The designer must also take any load on the pipeline into account due to nearby foundations of hydraulic-
engineering works, structures or buildings.
The determination method for the force of the ground load is described in C.4.
Traffic Load
The traffic load that occurs during the laying phase or operational phase must be included in the design.
The determination method for the force of the traffic load is described in C.5.
The weight of the pipeline, sheathing and everything attached to the pipeline as well as the weight of the
media to be transported or the test media must be utilized in the investigation (the appendages and other
equipment belonging to the pipeline must be calculated as the pipeline's own weight).
Especially with aboveground pipelines the weight of snow or ice on the pipelines must be considered for
the survey.
Underground pipelines may be forced up from under the groundwater level when in soft ground types (for
example, peat or mild clay) or when the trench backfill liquefies. Ground anchors or reinforcements of the
pipeline can be used to prevent the above.
The determination method for the force of these loads is described in C.6.
Both the reactions that are exercised on the pipeline by the support points (spring-based or rigid) and by
connected structures (tanks, barrels, pumps, bridges, safety valves, platforms) must be taken into
account for the survey.
Special attention should be given to displacement or rotation of support points or connected structures.
Vibrations as a result of the media (compressor or pump) or as a result of the environment (machines, but
also wind, waves or currents) can create pipeline loads. This must be investigated during the design
phase. The determination method for the force of the load due to vibrations is described in F.2.2.4. Refer
also to Appendix J of NEN-EN 1594:2000.
Bearing loads of pipes during transport and storage demand necessary attention; especially in relation to
thin-walled pipes and their stacking height, clear span and bearing saddles or blocking.
Different load situations can occur when the pipeline is laid which must be investigated, such as:
17
NEN 3650-1:2003
- loads in relation to thrust boring, drag sag pipes and horizontal directional drilling.
External incidental loads are usually similar to an impulse load. Impulse loads are, for example, created
by:
- loads due to excavation, pile driving, foundation and cone penetration works, drilling operations,
subsoiling, mechanical draining, seismic surveys, etc. (see also Appendix K of NEN-EN
1594:2000);
- falling objects;
- mining activities and earthquakes (see also Appendix C and Appendix F, respectively, of NEN-EN
1594:2000);
- landslides or movements of ground deposits, etc., as a result of processing due to heavy rainfall.
Use can be made of data from available literature for determining incidental external loads. Generally,
these loads are not involved in the normal strength calculation of the pipeline but the safety of the pipeline
against these types of loads are investigated separately in a risk assessment and the pipeline is provided
with additional risk limiting provisions if required.
8.2.8.1 Load Combinations and Load Factors for Maximum Limit States
Pipelines and related parts, such as, fittings and supports or attachments, must be able to withstand
unfavorable combinations of loads that may occur simultaneously with sufficient reliability, provided that:
- the extreme value of a changing load does not have to be combined with the extreme values of
other changing loads or with special loads;
- a special load does not have to be combined with extreme values of changing loads or with other
special loads.
Q = g x Grep + qi x Q1irep + qi x t x Qirep
12
where:
Grep is the representative value for the permanent load such as the equilibrium of the pipeline and the
weight of the ground cover;
18
NEN 3650-1:2003
is the reduction factor dependent on the anticipated duration of use (often it is taken to be 1);
Q1rep is the representative value for the contemplated extreme changing load;
By constantly taking a different load extreme, all load combinations can be determined that can occur with
a certain degree of certainty.
The effects of every load combination must be determined on the pipeline (forces, deformations, stresses,
strains, etc.) and it must be shown that no extreme limit state is being exceeded.
Load combinations and related load factors to be taken into account are partly material-dependent. This is
due to the fact that some of the contemplated limit states and calculation models to be applied are
material-dependent. Refer to the material-dependent section in connection to this to obtain further
elaboration of the load combinations and load factors to be taken into account.
A number of geotechnical characteristics play a role in relation to ground loads. The calculation values of
these geotechnical parameters must be determined when determining the ground load calculation value.
Next, the load should be determined via a calculation model to which a model factor (as load factor) is
applied. Refer to B.4.2 for more information.
It is not always clear from the start whether a certain geotechnical size will contribute positively or
negatively towards the contemplated limit state. Both options must be contemplated in that case.
8.2.8.2 Load Combinations and Load Factors for Serviceability Limit States
The same formulation can be utilized for the verification of the serviceability limit states for the load
combinations to be taken into account as utilized with the extreme limit states with the provision that lower
load factors are taken into account (usually q = qi = 1.0) and the number of load combinations is lower.
Material influence is also active here and we again refer to the material-dependent sections.
For every load combination, the effect of the load combination on the structure has to be tested for all
relevant mechanisms in relation to the calculation value of a corresponding strength size. The calculation
value for the strength has to be larger than or at least equal to the load effect in all those cases:
R d Sd
where
Sd is the calculation value for the load effect for the effective load combination;
The following general formula applies for determining the calculation value for the strength:
1 Xk1 Xk2
Rd = -----
M
R { ------- ,
m1
------ ,
m2
}
19
NEN 3650-1:2003
where
Refer to B.4 for the size of the factors concerning ground and refer to the material dependent sections in
this standard for material specific factors.
COMMENT 1 Often a value is taken, which may be below the limit by 5%, as typical value for strength
functions or material characteristics. An average value or a safe average value may be involved with soil.
The above is related to the nature of the mechanism and the quantity of data (see B.4).
COMMENT 2 Geometric quantities (centerline, wall thickness) can also occur in a strength function.
Usually the nominal value is used. Exceptions are geometric quantities with an important influence of the
safety such us out-of-roundness.
COMMENT 3 The uncertainties in the calculation model (of load based on load effect) are sometimes
taken into account on the strength side and sometimes on the load side. It is absolutely crucial that these
uncertainties are not forgotten.
Figure 9 specifies the quantities that are important when assessing structural safety.
Load
8.2.10.1 Outline
20
NEN 3650-1:2003
The pipeline is outlined to obtain a system of beam elements for the pipeline and spring elements for the
supports. The surrounding ground is also outlined to obtain a spring system for underground pipelines.
Loads, displacements and obstructions for the whole pipeline system must be considered as cohesive for
both static and dynamic aspects. This means that also for the sectional survey, the connection and
equilibrium conditions everywhere in the pipeline system should be sufficiently met.
It also means that points for which the following is known must be limited in relation to the contemplated
section of pipeline:
- forces or moments; or
- the connection between the displacements, on the one hand, and the forces and moments, on
the other hand.
- Tees;
- underground elbows at the end of long straight sections (thermal and pressure
expansion);
- the transition of an excavated trench to a rigid support structure aboveground or not (for
example, footings of pipeline bridges). It is advisable to include the underground and
aboveground sections in one calculation model;
- with installation connections: attention for the often occurring wall thickness differences;
- roads;
- railways;
- watercourses;
21
NEN 3650-1:2003
- which is responsible for a settlement and/or subsidence difference (for example, a section
that has been placed in a trench that connects to a thrust bored or drilled section).
Also when applying pipe sleeves, special attention should be given to subsidence
differences;
6) pipe sleeve transition of the position within a pipe sleeve to the section laid in the trench. Also the
sleeve pipe should be checked for strength.
The survey to determine the effects of the loads is directed toward the structures that play a substantial
role in relation to the operation and/or maintenance of the pipeline system as well as toward the medium
transporting pipeline.
Anchor blocks, pipe sleeves, supports and connected structures (for example, pipeline connections to
stations; see also 8.3.4) and such are involved.
Supports
The locations and design of the supports should be such that forces can be equally distributed and
passed between the supports and pipeline to ensure that high local stresses in the pipe wall are avoided.
Due to subsidence differences, a large bearing reaction may occur at the location of the support(s). The
bearing angle must be at least 60 to avoid peak stresses that have a pierced effect as a consequence.
Supports must be designed with at least the same safety level as the pipeline itself.
COMMENT In special cases, it may be advisable to limit the maximum bearing potential of the
support to avoid a too high bearing pipe reaction (for example, when subsidence occurs) and/or to make
a transversal movement possible.
Local stresses in the pipeline that are due to the supports, such as bending and movement stresses in the
wall, must be determined.
The influence of the rigidity and/or deformation capacity of the support including its foundation on the
static and dynamic behavior of the pipeline system must be investigated by taking the force transfer
relation of the foundation into consideration.
Forces, moments, forced deformations from transfers and distortions arising from the presence of
connected equipment must be included in the pipeline stress analysis.
Non-Supported Sections
Should non-supported sections (for example, clear spans) occur during the laying, burying or during the
operational phase, the stresses that arise must be determined.
The maximum admissible span must be specified in the calculations. Dynamic aspects of the clear span
must also be taken into consideration.
The actual span that is present must, in practice, be checked.
COMMENT Unchecked clear spans virtually do not occur in land pipelines; the phenomenon occurs
more often in offshore pipelines due to sand transport over the sea bottom.
22
NEN 3650-1:2003
- often occurring geotechnical values can be assumed for underneath ground level (see table C.3)
in combination with or without a limited site investigation;
- the values have to be determined based on the ground investigation and must include advise
from an expert geomechanical consultant (see also 1.3) in relation to special structures and/or
strongly changing ground conditions or where settling of some importance are expected.
Load types:
- check pipelines in groundwater in relation to being set afloat during both the implementation and
operational phase.
Construction settlements:
- should certain minimum requirements be demanded from the implementation method to limit
settling and settlement differences, they must be mentioned in the geotechnical report and must
be respected during implementation.
Load types:
- own weight including media and liquid load, respectively, for hydrostatic testing;
- wind load (only if the centerline and the height position trigger this off);
- snow and glaze in relation to cold media (< 0 C) and/or thermally insulated pipelines.
8.3.1 General
Rules are given in this paragraph that should be observed when designing and operating stations.
Gas pressure control and measurement stations must comply with NEN-EN 12186:2000 and NEN
1059:1994 and Draft NEN 1059 1059-2000. Compressor stations must comply with NEN-EN 12583:2000.
The strength-technical design of the stations falls under this standard.
23
NEN 3650-1:2003
COMMENT Parts may be present in stations (pressure equipment and pipelines with a pressure >
0.05 MPA) which fall under the Pressure Equipment Directive (PED); [34]. The PED has been
implemented in the Netherlands in the Pressure Equipment Decrees; see Appendix K. Pipelines do not
fall under the scope of application of the Decrees.
8.3.2 Requirements
General Requirements
The requirements that must be met by the station layout depend on the environment, climatological
conditions, the station type and the substance to be transported.
- the nuisance and danger for the environment are limited to a minimum;
- the station (or parts thereof) can be simply decommissioned by using a few valves;
- all parts have easy access for operation, inspection and maintenance purposes;
- the correct operation is assured for a long period under all circumstances that can occur on
location;
- there will not be any detrimental consequences of settlement and subsidence differences
between pipeline and station, corrosion or other reasons;
- unauthorized operation, vandalism and sabotage are avoided and/or hampered considerably.
Measures must be taken for arrangements in an unheated space as well as in the open air sheltered or
not sheltered by a side shelter or a few walls that will prevent disturbance of the correct operation due to
weather influences.
COMMENT These measures can be, among other measures, the following:
- providing a freeze protection cable to ensure certain parts are not frozen (for example,
controllers);
- special measures against corrosion, among others, sealing the space between flanges;
- measures against seepage, for example, via a ventilation opening towards a membrane chamber
of a regulator, safety, electronic and instrumental equipment, etc.
Distances
Stations must be positioned in such a way that hindrance and danger to the environment is avoided as
much as possible. The distances used between stations, on the one hand, and buildings, roads, railways,
high-voltage lines, etc., on the other hand, have to meet certain requirements.
When choosing the distances between stations and the underlying distances of equipment and devices in
the station, safety, maintenance and operational management must be taken into account.
COMMENT 2 NEN-1059:1994 and Draft NEN 1059:2002 include safety distances for gas pressure
control and measurement stations. The distances contained in these standards apply as minimum safety
distances for objects where people can be found; the distances in relation to roads, railways,
watercourses, other ignition sources and boundary partitions are also relevant. The size is determined by
the station being continued.
24
NEN 3650-1:2003
Fencing
A station should be surrounded by fencing, should circumstances demand this, that is installed in such a
way that access by unauthorized persons is prevented if possible and which should be provided with a
clearly visible warning and prohibition sign; see NEN 3011:1986.
To ensure that people can escape from the area immediately next to the station in case of an emergency,
there should be sufficient access points (one or more, depending on the requirements of the local
authorities) in the fencing. This also applies in the case when a station has been housed in a building.
The access points must open towards the outside and you should be able to open these from the inside
without a key. Other provisions can also be made that offer the same escape possibilities. If the size of
the station justifies it, accesses must have been measured and implemented in such a way that
accessibility for fire-fighting equipment and ambulances is safeguarded.
Electric Installation
The electric installation in stations must comply with the requirements set down in NEN 1010:2000, NEN
1041:1982 and NEN-EN-IEC 60079 for as far as these are applicable. The electric lighting must be
implemented in such a way that exits and critical places around and in the station are clearly visible
during the night and when there is fog.
Lightning
Provisions must be made against lightning where this is required based on NEN 1041:1982 (for example,
when explosion hazards are present at the installations). The provisions must comply with the
requirements contained in NEN 1024:1992.
Electrostatic Loads
Liquids can generate electrostatic loads, when flowing along the wall of a pipeline, that can ignite an
explosive mixture. Pipelines, pipe sleeves and devices that can have an electrostatic load must be
grounded or must be conductively connected.
The resistance between the pipeline and ground must amount to more than 6 ohms to offer protection
against electrostatic loads.
8.3.3 Components
General
All separate components of stations must comply with their functional requirements.
Mechanical devices (such as compressors and pumps), electrotechnical devices (generators, batteries),
components connected to pipework (pipes, ancillary equipment, flanges, bolts, gaskets, valves) are
examples of the above.
The total installation must, moreover, comply with the requirements related to reliability in operation,
safety and dependability. Safety in relation to the environment and hindrance of third parties must also be
at an acceptably high or low, respectively, level.
Protections
Aspects, such as the ones given below, must be given attention in relation to the above:
25
NEN 3650-1:2003
- explosion hazard (corrosion and leak detection, ventilation, hot surfaces, pressure protection);
Devices within stations are often linked to each other using internal piping. Piping for oil, gas, steam,
compressed air, water, chemicals (for example, inhibitors) as well as measurement, control, auxiliary gas
and sampling pipelines are examples. This piping and related valves, flanges, adaptors, elbows, etc.,
must be manufactured from adequate material and must be suitable for the operational pressure and
temperature of the connected devices. Pipelines in stations must be designed based on this standard as
far as it is applicable. Requirements that should be met by flanges, gaskets, bolts, nuts, valves and other
fittings are given in the material sections concerned in this standard.
Mutual influencing must be taken into account when designing the connections between the sections and
the stations (see also 8.2.7).
Special attention must be given to the following regarding connections of the aboveground components
with the underground pipelines:
- vibrations in components and aboveground sections due to machines (for example, compressor
throbbing or flow induced throbbing);
COMMENT The (welded or flanged) valve that forms the separation between the station and the
pipeline, can be positioned on a transition in foundation method (uneven subsidence). It is advisable to
investigate whether the valve (and any flanges) can withstand this.
9.1. General
The laying of the pipeline system must be performed as described and specified in the approved
specifications and approved drawings from the design phase. The methods, the organization chart and
the work procedures for the installation and delivery must also be specified in the descriptions. The
documents must be available before the installation phase is started.
The requirements and provisions for the protection of health and safety of the public, involved personnel
and the environment must be specified in a safety, health and environmental plan. The requirements
stipulated in the relevant legislation and regulations, standards and licenses and the identification of
potential risks and hazards including the corresponding measures and emergency procedures must be
described in the plan.
26
NEN 3650-1:2003
Competent supervisory personnel must supervise the implementation of the work. The persons carrying
out the work must have all required qualifications for implementing the work.
Hindrance of the owner and/or users of the involved lots and damage to goods or crops must be limited
as much as possible.
COMMENT It is advisable to identify beforehand the objects that could be influenced by the
construction of the pipeline system. Objects can affect, for example, existing roads, railways,
watercourses, footpaths, cables, pipelines and buildings.
It is advisable to name the temporary provisions and safety provisions required to protect the objects
during construction and to harmonize these with the involved owners, managers and authorities when
defining temporary provisions.
When large (implementation) installations are expected, it is recommended that marginal properties which
are influenced by the laying are subjected to a zero value investigation (determination of the situation on
the contract date).
9.2.1 General
A distinction can be made between aboveground and underground pipelines in relation to laying land
pipelines. An underground pipeline can be further subdivided into underneath ground level and crossings.
Refer to 11.5 for information regarding laying offshore pipelines. The landfalls of offshore pipelines are
viewed as land pipelines in this standard.
Laying aboveground pipelines includes the assembly and installation of pipelines that are not
continuously supported (in relation to the ground) but locally.
The pipeline is directly buried in a dry, excavated trench or the pipeline is buried and immersed in a trench
filled with water.
The laying of an underground pipeline in the underneath ground level includes assembly and installation
of a pipeline in an excavated and again filled trench. Trenchless technology can be used underneath
ground level when this is attractive financially or for other reasons.
9.2.5 Crossings
a) in an open excavation;
b) using trenchless technology (drill and thrust boring techniques and HDD);
c) by spraying;
d) by sinking;
27
NEN 3650-1:2003
Drill and thrust boring techniques are subdivided into four main groups based on accepted terminology:
COMMENT Due to required uniformity in the method used for referring to trenchless technology, the
abbreviations given above have become standard abbreviations in this sector.
Every drilling technique has its own specific application criteria and the choice of the most suitable
method depends on:
- ground conditions;
9.2.7 Landfall
The laying of a landfall can mean crossing a primary water-retaining structure (see also NEN 3651:2003).
Special (temporary or permanent) structures are required to secure the stability of the coastline during
laying or operation time.
In addition to the land pipeline aspects, the wave, current, storm surge, morphology and sand transport
phenomena play a role for the landfall.
9.2.8 Sinking
The pipeline is installed in a watercourse to be crossed when sinking. First a trench is dredged on the
bottom.
Installing a prefabricated pipeline or sag pipe can be achieved by dragging with a winch or hoisting with
cranes or hoisting sheers or driving, filling and immersing or using combinations of the aforementioned
methods.
The dredged trench must be backfilled with care after the sag pipe has been laid.
28
NEN 3650-1:2003
The approved calculations, the drawings, the specifications, the geotechnical report, the construction
descriptions, the safety, health and environmental plan and the identification of objects and facilities that
are influenced by the construction must be available before the start and licenses must be available or
you must be able to obtain them.
When a pipeline is being laid through cultivated land (arable land and meadows), a cultivation-technical
investigation (see I.1) must be performed during the design phase. The cultivation-technical requirements
and recommendations must be adhered to when the pipeline is laid.
If groundwater extraction is required during the laying, a geohydrologic investigation (see I.2) must be
performed during the design phase. This must be done in relation to the extraction of groundwater and
drainage thereof. The geohydrologic report must contain data related to the water quantity, water quality,
environmental aspects related to this, the drainage type to be applied, period, discharge of drainage water
and artificial recharge. Possible displacement of bottom contamination elsewhere should be kept in mind.
During the installation and thereafter, the discharge must be registered.
Before starting with the laying, licenses must be obtained and private agreements with land owners and
users must be concluded.
Arrangements must be made with third parties involved in relation to the site, the access to the site for
personnel and material and/or the use of storage areas for material, machinery and equipment.
All interested parties (private persons, authorities and other managers) in relation to the installation must
be warned and informed regarding the nature, the size and the duration of the activities before the
activities start.
Owners of existing cables and pipelines in the route must be informed regarding the activities being
contemplated. It is advisable to make a KLIC (Kabels- en Leidingen Informatie Centrum; Cable and
Pipeline Information Center) notification well in advance of the start.
COMMENT Depending on the nature and size of the activities, the decision may be taken to hold a
commencement discussion at which the involved pipeline managers and/or their representatives, license
and/or permission holders and licensing authorities are present. The contractor presents, during this
meeting, a plan of approach (working plan, planning, protective provisions, approved drawings and such).
The customer will also provide in writing the name, address, and telephone and fax number of the contact
that he has appointed for the duration of the works.
Loading and unloading, transport and storage of pipes, fittings and other material must be kept
meticulously separate to avoid damaging pipes, pipe ends, linings and other material.
Materials must be inspected to check for damage, deformations and deterioration. Materials with
unacceptable damage, deformations or deterioration must not be installed.
COMMENT Aspects that are important: pipe must be blocked to ensure that the lining is not
damaged, do not roll or drag pipe, a stable storage, sufficiently wide hoisting belts made of a soft material,
hooks must have a synthetic layer, the bottom of the pipes should not touch the ground when stored,
adequate (temporary) protection against material degradation such as corrosion or UV and O 3 effect,
completeness of inspection certificates and other cover documents. In relation to transport and storage
activities, the prevailing safety regulations (as supplied by the ARBO-wet, Working Conditions Act, and
the Wet Gevaarlijke Werktuigen, Hazardous Plant and Equipment Act) must be observed.
29
NEN 3650-1:2003
The center of the pipeline is traced. The pipeline route and the working strip as well as the special objects
within the influence sphere thereof are marked whereby the location, type, depth and characteristics of
the structure concerned are specified. The markings must be adhered to and/or detected during laying.
Before starting with the installation of the site and the building, a detailed route study must be performed.
Inspection reports must be drafted in consultation with the parties involved.
A working strip with sufficient width must be laid out for good and safe implementation of the activities and
supply of material, machines and equipment.
Aspects that must be observed during construction and, later, restoring the working strip are:
- tracing, marking and placing warning signs near aboveground high-voltage lines under which the
working strip can be found (in compliance with Chapter 10 of NPR 2760:1991);
- original function of the ground (for example, arable land, grassland, protected natural area,
industrial area) and restoration of this function after pipeline laying (see the agriculture-technical
report);
- any need to remove and separately store the topsoil (restoration of the original state, see the
agriculture-technical report);
- drainage;
- demolition of structures.
9.5.4 Activities Near High-Voltage Connections and /or Overhead Wires of Railways and
Tramways
Prior consultation must take place with the company under whose management the pipeline (or
installation) falls in relation to the safety provisions to be made when work is performed near aboveground
high-voltage cabling (also overhead wires of railways and tramways) and transmitter towers.
The safety provisions for high-voltage connections to be observed are included in chapter 10 of NPR
2760:1991.
30
NEN 3650-1:2003
9.5.5.1 General
Excavation work must be performed in such a way that damage to the cables and pipelines present in the
ground is avoided. When excavation work is performed in parallel to existing cables and pipes, excavation
must, by preference, take place within a distance of 1 m using shovels unless measures have been taken
to avoid damage. This also applies for crossing cables and pipelines. Damage to the present (deep)
drainage systems or irrigation systems must be avoided or adequately be repaired after laying. It must be
avoided that the trench can be used for water discharge when non-horizontal trenches are used.
9.5.5.2. Trenches
The pipeline must be laid, according to the working drawings, with sufficient ground cover. It is important
that excavation is not deeper than the level that is specified for the bottom of the pipeline in connection
with occurring buckling of agitated ground. The slope must be adjusted to the trench depth, the drainage
and the soil type to ensure the trench walls cannot collapse and/or subside. If required, the trench wall
must be shored up using partitions.
It is important to implement the trench bottom in such a way that the pipeline is laid as anticipated in the
calculation. It may be necessary to lay a sand layer under the pipeline. To excavate deeper than required
must be avoided in connection with occurring buckling of the agitated ground. Additional settling may
occur as a consequence in soft subsoils.
The trench wall border must match the excavation depth, drainage and soil type.
The trench must be kept free of objects that may damage the pipe or lining of the pipe. Gravel, stones
and/or other hard material near the final location for the pipeline must be removed. If this is not possible,
the pipe must be provided with a protective lining or the pipeline must be embedded in clean (sandy) soil.
Excavated ground must be stored in such a way that the original constitution of the ground profile is re-
obtained as much as possible when the trench is later backfilled.
Topsoil present must be stored separately from the underlying layers as specified in the agriculture-
technical report or in consultation with the manager of the ground. In certain cases, it may also be
necessary to excavate and store the subsoil separately. The storage must be harmonized in relation to
the local grade.
In principle, ground deposits are not planned above an existing underground pipeline. If this is necessary,
however, it must be checked, in consultation with the pipeline owner, whether this is possible and whether
special provisions must be made to protect the pipeline.
If explosives are to be used, it must be provided for in the design of the pipeline. Special regulations apply
and an explosion plan must be drafted.
COMMENT The use of explosives for laying a pipeline will virtually never occur in the Netherlands
with its relatively soft granular and peaty ground structure. It may even be impossible due to the buildings
present. Special attention must also be given to any occurrence of liquefaction of sandy soils that are
sensitive to this phenomenon.
31
NEN 3650-1:2003
9.5.6.1 General
A distinction can be made between laying an axially rigid and an articulated pipeline in a dry trench or in a
wet trench.
The pipeline is lowered between the pipe elements in the trench after mounting the string and finishing
the connections. The trench must be dry at this moment and must remain dry until the trench is backfilled.
The pipeline must be laid in a dry bed.
COMMENT 1 The laid pipeline can be set afloat should there be water in the trench.
The string must be lowered using hoisting equipment. The hoisting resources to be used such as hoisting
belts and slings must be covered to ensure that the pipe and lining are not damaged.
It is important that as little as possible stress is allowed to build up in the pipeline both during composition
and when lowering the pipeline. The admissible curvature of the pipeline and the slight rigidity of the
elbows should be taken into account. The lowering must also be done without shocks to avoid buckling
and wrinkling of the pipeline or other permanent deformations. After lowering the pipeline, the position
should be corrected if required. The pipeline must thereafter be measured off. The use of resources not
anticipated in the design to keep the pipeline in its place is not permitted.
Articulated Pipeline
Pile elements that are connected with a bell-and-spigot joint form an articulated pipeline which is not
axially rigid. Articulated pipelines are, in general, built up in the trench. The trench must be dry during
laying up to backfilling.
A rubber ring provides the sealing of the pipe connection for the internal pressure. You can check the
correct assembly of the rubber ring during laying. This often leads to the decision to backfill the trench
immediately after laying the pipe elements. Buoyancy forces on the empty pipe in the return groundwater
must be taken into account. The trench backfill also prevents the articulated pipeline from becoming
deformed through initial thrust during the hydrostatic test.
The available length by which it can be extended must be divided among the implementation phase and
the final phase with connections that are not resistant to tension. Any direction corrections and the
method for backfilling must be geared towards the available length by which it can be extended. During
installation, the joint displacement that is available for the installation, whether internal or external, must
be monitored.
COMMENT 2 It is advisable to include the jointing openings of every connection when articulated
pipelines to which access can be gained are involved. The opening is measured at 3:00, 6:00, 9:00 ad
12:00 oclock. The angle of rotation of the joint and the axial width of the joint can be determined from the
measurements as well as the three-dimensional position of the pipeline. Requirements can be included in
the design regarding the admissible rotation and width.
COMMENT 3 It has been observed based on joint measurements that some pipe elements undergo a
slight axial movement when pipelines are immediately backfilled after laying in soft Holocene ground. The
impression exists that the elements only lay still after the groundwater level is stable.
32
NEN 3650-1:2003
A wet installation is appropriate when the area has relatively many watercourses or when the grade is so
bad that many provisions are required to be able to achieve a dry trench and/or when this is impossible.
The trench is oversized in order to make a channel through which a section can be driven in or buried
and, subsequently, sunk.
The laying method can be applied for both rigid and articulated pipelines. The connections in the
articulated pipeline must, in that case, be resistant to tension.
In general, it applies that the location of the pipeline must be measured off in the open trench during
laying. Preferably in coordinates (Rijksdriehoekscordinatensysteem!; national triangulation coordinate
system). The measuring work must be updated accurately in digital or analog form. The measurement
data are the basis for the as-built drawing of the pipeline.
9.5.7.1 General
The backfill work and site finishing must take place based on the agriculture-technical report and the
safety regulations to be observed. The backfill of the ground in layers must take place after lowering the
pipeline.
If installed wet, backfill must take place, by preference, in the water when the flow is directed downwards
to ensure good compaction. The water has to also be driven forwards when backfilling to avoid water
closing off in the trench to be backfilled.
In peaty areas, lightweight material is applied under the groundwater level (peat and wood fiber pellets)
and Flugsand (i.e. volcanic tuff sand) or another lightweight granular material on top to limit settling.
The excavated material must be added with care in the correct sequence and should be free of stones
and such to restore as much as possible the original profile. The trench must be filled with soil free of
coarse and hard components up to a height of 0.3 m above the top of the pipeline to protect the pipeline
and lining. This first backfill layer must have such a quality and must be provided in such a way that the
pipeline is given an even and sturdy support on all sides and over the whole length. Backfilling must occur
in such a way that the ground mechanical departure points, used in the design, are achieved.
A slight surplus height on top of the trench must be implemented, if necessary, with a view to
consolidating the ground.
This must be done in such a way at road locations that the traffic will not be greatly disrupted or is
otherwise warned using temporary traffic measures in consultation with the road manager.
Softening
If the coefficient of soil reaction is too large to make safe positioning of the pipeline demonstrable,
increasing the freedom of movement of the pipeline may be considered by applying lightweight
compressible synthetics. Its application may only occur where no additional risk can occur for water
management projects.
The synthetics must be made for the type of structure being considered for application.
33
NEN 3650-1:2003
The compressive and tensile strengths may not be exceeded in the course of time.
COMMENT For now only cell rubber (foam rubber made of butyl rubber with 100% closed cells) is
deemed suitable for this aim.
Hardening
Use can be made of an injection method for soil with a chemical product that is suitable for the purpose to
ensure that the crush pressure of the pipeline is diverted sideways and/or the bottom pressure is spread.
An adverse side effect is that the coefficient of soil reaction also increases.
Sand and gravel-containing sand can be considered for application: clay and peat soils are not suitable
for injection.
Fixed layers (sand) must be present under the ground to be treated. Mild layers (clay and peat) will lead
to subsidence.
Before switching to chemical injection, a ground investigation must be performed to obtain insight into the
particle distribution of the ground and the composition of the layers to be injected.
In order to avoid increasing the volume mass of the ground too much, the volumetric mass of the
chemical injection liquid must not be much heavier than the volumetric mass of water (approx. 1050
kg/m3).
The best result is obtained in ground that has not been agitated in connection with the regular distribution
of the injection agents whereby the top injection level must lay at least 0.75 m below grade.
COMMENT If there is less cover, it can be considered possible that the chemicals will not arrive at the
required location due to the formation of leakage paths. Injecting in a backfill can lead to less adequate
results due to irregular packing density (leakage paths) and contamination.
The effect of the injection on the state of the ground must be checked using cone penetration tests and
sample boring. The petrified sand mass can also be excavated for inspection.
Compaction
The following applies in order to be able to deem the backfill as compacted when the trench backfill next
to the pipeline has to be compacted (see also D.3.5 for the other requirements) for more sideway support
pressure.
The backfill soil is sand that is placed carefully in the dry trench and is compacted mechanically in layers
at a maximum of 30 cm. This is continued up to a minimum of 0.15 m above the crest before the trench is
backfilled with other soil and compacted if required. The percentage of the maximum proctor density is
larger than or equal to 94%. This must be proven with manual cone penetration tests. The backfill will be
deemed not compacted within the framework of this standard if the percentage is lower.
The use of the grade (for example, as surface that has been hardened or has plants and shrubs) has to
meet requirements in relation to the finish of the (top) of the trench.
34
NEN 3650-1:2003
Below Paving
The compaction below the paving can be checked measuring cone resistance (cone surface of 100 mm2
and vertex angle of 60 degrees).
The resistance must increase by a minimum of 0.2 MPa and/or it must amount to at least 4 MPa per
10 mm penetration depth.
The cone resistance must amount to 4 MPa and 6 MPa at a depth of 0.6 m.
Paving
Paving that has been taken up must be laid in its original state.
Quality and color must agree as far as possible with the building materials present regarding the
dimensions related to building materials to be supplied.
Paving brick and concrete pavior roadway paving must be strewn with sand or crusher sand and
compacted (using a vibrating machine). Pavior paving must be washed in.
The longitudinal and cross-sectional profile of the paving must agree with the original altitude with
sufficient surplus height to set off the remaining consolidation after the compaction of the trench backfill.
Unstabilized Foundation
Unstabilized foundations that have been taken up must be reinstalled and must be supplemented with
equivalent building materials up to the original layer thickness unless otherwise agreed.
Ground, except topsoil, that is processed in backfills in plant and shrub sections or below grass at a depth
of less than 0.8 m must have a cone value of no more than 1.5 MPa after compaction. This does not
apply to water-retaining structures or verges.
Excessive compacting or structure decay must not occur when compacting soil in plant and shrub
sections or below grass.
In consultation, it will be determined which plants and shrubs (trees, shrubs, plants and turfs) may be
removed for the activities and which and how they must be put back once the activities have finished.
Plants and shrubs that has been removed must be stored professionally on a temporary basis to prevent
them from dying.
Removed plants and shrub material that does not strike once it has been returned must be replaced with
new similar material in a favorable season after consultation.
Damage to the plants and shrubs that are to be kept must be made good.
COMMENT Root growth (for example, in asphaltic lining or bell-and-spigot joints) can occur with
certain plants and shrubs. Root growth can be discouraged by applying a root sheet or by laying the top
of the pipeline 0.50 m below groundwater.
35
NEN 3650-1:2003
Soil deficits can occur with certain soil types after backfilling the trench. These deficits must be
supplemented with soil that meets requirements that agree with the purpose of the ground (prior soil
analysis).
Any soil surpluses (after the surplus height has been installed) or soil that cannot be used for backfilling
must be removed after approval from the ground owner. This must never be the top layer or the topsoil,
respectively.
COMMENT Soil deficits occur especially in peaty areas as a consequence of oxidation and
irreversible contraction. Surpluses can occur (aside from the surplus created by the pipeline volume) in
ice cap preloaded areas as a consequence of overconsolidation.
When you expect that warning tape may clearly prevent damages to the pipeline, such tape must be
installed. The correct location is on top of the pipeline half-way between the top of the pipeline and the
grade. This tape must be in a bright and eye-catching color (for example, yellow).
As soon as possible after backfilling has finished, the site must be cleaned. All material, extra plants and
equipment and leftover material must be taken away. The working strip must be restored to its original
state. When cultivated land is involved, attention must be paid to the final cultivation of the work strip
used based on the agriculture-technical report.
All involved parties, including the users, owners and licensing authorities, must perform a final inspection
of the site.
9.5.8 Proximity and Crossing of Underground Structures (Including Existing Cables and
Pipelines)
The method used for crossing and excavating must be determined in consultation and agreement with the
user or owner of the underground structure. Special measures may be necessary to avoid structural
damage. If necessary, shovels must be used for excavating.
Special provisions apply to pipelines near aboveground high-voltage lines (see also 9.5.4).
9.6.1 General
The way in which pipelines cross roads, railways, watercourse, dikes and embankments depends on the
local circumstances and must be determined in consultation with and with the permission of the relevant
licensing authorities. If pipe sleeves are to be used or sheetpile wall structures will be applied, it will be
specified in the design.
The design must specify provisions such as sheetpile walls, pipe sleeves and implementation methods.
These must also be depicted in drawings and descriptions for implementation.
The crossing (see 6.5) must comply with NEN 3651:2003 in relation to important water management
projects. Crossings in relation to any related safety areas can be implemented separately from those
36
NEN 3650-1:2003
beneath ground level. Additional attention must be given, in this case, to the connection, especially the
tie-in (outside the safety area), the blocking of the pipe and the backfilling of the trench on site.
The following requirements must be met by the structure of the pipe sleeves (also see 8.1.7):
- the media transportation pipe must be provided with sufficiently suitable spacers (thinsulators)
at adequate distances. This must especially be taken into account (concentration of spacers) at
the ends of the pipe sleeves where there is a transition in laying method (implementation settling
difference). It is advisable to jack up and block the pipeline before backfilling the trench or the pit
to ensure the spacers in the top of the pipe sleeve make contact and the implementation settling
(partial) can occur without straining the pipe sleeve;
- there must not be any internal projections in the pipe sleeve. The pipe sleeve ends must not have
any sharp edges.
Refer to 9.7 of NEN 3650-2-2003 in relation to pipelines that must be provided with cathodic protection
and are in a pipe sleeve.
9.6.3 Trenchless
In certain cases (for example, a road that cannot be closed) and in other cases (most economic or safest
solution) a crossing may be implemented without a trench.
Meticulous implementation must take place at the transition of a thrust bored or drilled crossing to the field
reach to limit the postsubsidence difference of the pipeline. A good compaction of the backfill of the
pressure pit and collection pit is required; especially for a crossing with a thrust bored or drilled pipe
sleeve. This requirement is less stringent for two cases:
- if the crossed road embankment is heavily susceptible to subsidence (for example, a ramp to a
bridge or viaduct);
- if the pits are provided with a groundwater retaining floor (made of underwater cement) and the
sheetpile wall boards are not removed (burnt down above the floor).
If no groundwater extraction should take place, the bottom of the building pit can be closed off with
(underwater) concrete. The building pit and concrete slab must be dimensioned in such a way that
cracking is prevented.
The closing off must be done in such a manner that there is no communication between phreatic water
and pressure water.
The foundations of the concrete floor that stays behind in the works can be laid on a sand layer with
bearing capacity or the pit can be filled above the floor with lightweight material (for example, peat or
wood fiber pellets under the groundwater level and expanded clay pellets, polyurethane foam, foam
cement or Flugsand above the groundwater level) to limit the additional (implementation) subsidence to
limit the particle tension under the concrete floor to the original level. It may be necessary to tuck in the
pipeline using soft material to prevent hard line support; for example, peat pellets whereby the spaces
are filled with bentonite powder.
37
NEN 3650-1:2003
COMMENT The peat pellets with bentonite powder will lead to contamination if under the phreatic
surface; there are three functions to prevent oxidation: 1) light, 2) closed (after swelling) and 3) soft
material.
The vibratory extraction of sheetpile walls leads, in all cases, to greater subsidence of the soil and a
larger subsidence difference, respectively, for the pipeline (see C.4.7.4). Burning of the walls above the
concrete floor will prevent this.
Also, there should be no communication between the phreatic water and the pressure water once the
sheetpile walls have been extracted. There should be a sealing soil layer underneath (not agitated) or
above (agitated) the concrete floor.
The installation of the station units must be carried out with care and skill and in compliance with the
design. Attention should be given to the following among others:
- incoming and outgoing pipelines must be installed and supported in such a way that no
inadmissible tension can occur in the equipment. Attention must especially be given to possible
subsidence differences between the pipeline foundation and the station and especially when piles
are supporting the station.
9.8.1 General
After completion of the pipeline construction or a part thereof, it must be cleaned and tested, and, if
necessary, calibrated and dried.
9.8.2 Cleaning
Before starting the hydrostatic test (see 9.9), the pipeline must be cleaned using a suitable brush (pig)
until all the dirt has been removed.
The pipeline must be provided with a seal before and after the test to prevent dirt, animals and such from
entering the pipeline.
Once the pipeline hydrostatic test has been approved, the pipeline must be cleaned and emptied using
pigs. The discharge of the water that is used for the hydrostatic test must not be a nuisance.
The calibration, checking for any out-of-roundness, root penetration and dents must take place by
sending a pig provided with a thin metal disc, for example, made of aluminum, with a thickness of 3 mm to
5 mm through the pipeline. The centerline of the metal (aluminum) disk must be at least 90% or 95% of
the nominal internal pipeline centerline.
Calibration is not necessary in relation to pipeline sections that can be adequately inspected visually (for
example, because of the large centerline) or through another method.
38
NEN 3650-1:2003
9.8.4 Drying
Once the pipeline has been cleaned and emptied, it can be dried, if necessary, using, for example air up
to a dew point as specified in the pipeline design requirements.
If the pipeline will not be put to use immediately after delivery, it is advisable to protect the pipeline.
9.9 Tests
9.9.1 General
Transport pipelines must be tested for strength and density before delivery. The test must be performed
with water. In exceptional cases other media may be used. This must be specified in the design. The
water must be suitable (not too dirty, not too aggressive) for the application.
A strength test is sufficient for tests of pipe sleeves that have to withstand the design pressure of the
media transportation pipeline (see also 8.1.7). A density test is not necessary.
The pipeline must be filled in such a way that inclusions of air that influence test results are avoided. The
filling of the pipeline is usually performed with rubber balls or foam plastic brushes.
The trench is usually backfilled to prevent large temperature differences during the test. If the ground
temperature at the pipeline is below 2 C, in general, antifreeze has to be added to the water.
COMMENT 1 Additions such as antifreeze can be a problem in relation to obtaining permission for
discharging.
COMMENT 2 Time should be taken for leveling the temperature and stabilizing for the resolution of
small inclusions of air pockets.
Regardless of the material type, a test plan must be drafted before the test takes place. As a minimum the
following should be described in the plan:
- the calibrated measuring equipment including inaccuracies of, among other elements, pressure
gages, thermometers, recording manometers and discharge meters;
9.9.3 Completion
A report is drafted for the test in which at least the following data is included:
39
NEN 3650-1:2003
- pipeline builder;
- the value for the pressure during the strength test and the duration thereof;
- the value for the pressure during the density test and the duration thereof;
- the results;
The safety of personnel carrying out the tests, the environment and the installation must be safeguarded
during testing. Although explosions do not occur when testing using liquid, the propulsion of a section or
spraying away of the test liquid during failure may constitute a hazard to people.
A test procedure including the safety measures (ARBO-technical) to be taken must be drafted.
If it is unavoidable that the test is to be performed during a period in which the pipeline and the pumped in
water are liable to temperature fluctuations, the necessary measures must be taken against an
inadmissible pressure increase or decrease.
9.10 Delivery
9.10.1 Documents
Quality records that contain all documents (as built construction drawings, geomechanical reports,
design calculations, welding and pipe book, etc.) with the location and description of the pipeline must be
put together by the end of the works. These files are transferred to the owner of the pipeline system and
is a part of the management system (refer to Chapter 16).
Preparation for commissioning (precommissioning) must occur before bringing up to pressure for the
commissioning of the pipeline system. During precommissioning, the correct operation of all parts and of
the system as a whole must be demonstrated. The provisions and control sections required for a safe
transportation of hazardous substances must be configured and adjusted during that phase. The system
must undergo a test with a (harmless) medium to demonstrate correct operation. It is advisable to draft a
plan with all sequential activities that must be performed including hold and witness points before
precommissioning.
The pipeline system must be transferred to the manager after precommissioning along with inspection
certificates, quality administration, as-built drawings and maintenance and control manuals.
40
NEN 3650-1:2003
The system may only be commissioned if completely laid, tested and cleaned and connected to upstream
and downstream flowing installations if applicable. The management system must be in place and must
be operational at that moment.
Effective inspection (by or in the name of the pipeline owner) is essential to check and verify that the
specified materials have been applied and that the structural works are performed according to this
standard, the specifications and the drawings during the laying of a pipeline system or parts thereof.
- agriculture-technical activities;
- groundwork; especially the separation of different layers, setting out trench dimensions;
- groundwater extraction;
- quality and dimensions of pipes and other material included related inspection documents;
- material transport, storage and management; especially in relation to pipe and lining damage;
- laying the pipeline including admission into the trench and setting out dimensions for the laying
and measuring off for revised drawing as well as sufficient clearance in relation to other structures
(sheetpile walls, pipelines from third parties, etc.);
- trench backfilling including compaction, surplus height; install lowering and/or settling containers if
necessary;
- testing;
With inspection is meant the verification of the deliveries of materials and structures. The pipeline
elements must be inspected and it should be checked whether the requirements of the standards and
specifications through tests and inspection documents have been met. These inspections involve both the
(parent) material and the assembly and the proper operation of accessories and structures.
Certain parts of the pipeline system fall under the Machine Directive (for example, valve or actuator
combinations). Refer to Appendix J for information in relation to verification points based on this directive.
9.12 Safety
9.12.1 General
All activities related to the construction of the pipeline systems must be installed in compliance with the
prevailing legislation and regulations regarding the safety and working conditions. The regulations that are
applicable to this area must be available at the works.
41
NEN 3650-1:2003
Personnel involved in the construction of pipelines must be trained regarding the legislation and
regulations for safety and working conditions applicable to the site. Executive personnel and supervisors
must ensure that the prevailing regulations are complied with.
The construction, environmental and safety plan must have been drafted before the activities begin. As a
minimum, the following should be included in the construction, environmental and safety plan:
- environmental regulations;
- the manner in which contamination of the environment is avoided and managed, respectively;
- the manner in which mishaps are concluded and accidents are dealt with.
Personnel involved in the performance of the activities must be informed regarding the content of the
safety plan and must act accordingly.
The accessibility of houses, public buildings and such should be safeguarded for (disabled) pedestrians.
The degree of accessibility can be further determined in consultation with the involved parties.
Local motorized traffic to houses, shops, companies, buildings, farms, etc., must be maintained as much
as possible in consultation with the involved parties.
If due to limited accessibility, emergency services cannot arrive sufficiently near objects or the supply of
shops and companies must be arranged in a different way than normally, it is necessary that interested
parties and the municipality are consulted beforehand.
For activities on or near the properties and installations of third parties, prior consultation must occur
regarding any specific precautionary safety measures. These measures must also be included in the
safety plan.
If contamination, however, occurs, the size and duration must be limited to the minimum. Contamination
must be cleaned up in consultation with the competent authorities.
42