WEEKLY PROGRESS REPORT 01 Ma. Vahffaru, Buruzumagu, 20-248, Male', Rep of Maldives
Project: International Terminal Baggage Sorting Area Partition & Associated works Tel: 3329467 Fax: 3329468,
Email: projects@viewbuilders.com.mv
www.viewbuilders.com.mv
8/2/2016 22:00 Partion wall - Applying putty on exterior & Interior surface 9.00 10 100.0%
As discussed no work could be carried out during daytime as we were unable to get permit from Aviation security
command
17.5 We were assured by MACL that we would be able to work minimum 2-3 hours during day shift.
Weather was generally
good
We have considered this time while planning our work schedule to finsh the project in 30 days.
17.5
REPORTED BY
(2) Fabrication, supply & installation of 12mm thick gypsum ceiling m 283.39 1,145.00 324,481.55 5.00% 16,224.08 50.00% 162,240.78 40.00% 129,792.62 95.00% 308,257.47
TOTAL COST CARRIED OVER TO GRAND SUMMARY 935,098.65 173,819.47 174,740.78 231,414.33 579,974.57
INTERIM PAYMENT CERTIFICATE - 03
Invoice No:
Date: 29th February 2016
Amount in Words: Maldivian Rufiyaa Two hundred Thirty Three Thousand One Hundred Thirty
Seven 31/100
Certified by:
Mazin Abdul Latheef
Project Manager
Approved by: