PS report : S_ALR_87013558 Commitment value not getting update for deleted PO line item

Hi All,

We are facing issue on STD report(Report Painter) on PS module .

Report name : S_ALR_87013558 [Budget/Actual/Commitmt/Rem.Plan/Assg ]

Issue : Commitment values are not getting updated when i delete the PO line items .

Ex :

For WBS " M-455-01-01-05 " i am creating PO with 2 lines ( each 100$ ).

Once created the PO i can see the 200$ in report - commitment column. but if delete the one of my
row in PO (ex : line 1 ) , then my report should show only 100$. but my report is showing 200$.

I have gone through the following SAPnote : 1746429 - How to correct commitment
inconsistencies.but this one also not help full.

SAPnote : 1746429 Resolution

1. Please run report RKANBU01 for the incorrect projects in question, this will update any incorrect
commitments. Further details can be found in note 152571.

2. After running the reports above, please run report RKACOR04 as this will correct any problems
between the line item tables and the total record tables.

3. After running the above reports, please run transaction code CJEN for all the projects as this is very
important so that the database gets updated.

4. Finally run report CJBN which rebuilds the availability control for each project.
If anybody help me out for this case .?

Thanks

vinoth vishparaj

June 07, 2013 at 18:09 PM

0 Likes

Not what you were looking for? View more on this topic or

1 replies

Clara Lee replied

June 07, 2013 at 18:53 PM

We are experiencing the same problem, commitments are still showing on S_ALR_87013558 even
though the line items have been delete off the purchase req.

I have ran Y_RKANBU01; Y_RKACOR04; and CJEN but the report does not get updated. Have you
found a solution?

Reporting Requirements

S. No. Report Description Std SAP/

Development

T Code / Dev Ref No.

1 Structure Overview Standard SAP CN41/CN41N

2 Project Definitions Standard SAP CN42/CN42N

3 WBS Element Overview Standard SAP CN43/CN43N

4 Milestones Standard SAP CN53N

5 Plan/Actual/Variance Standard SAP S_ALR_87013532

6 Plan/Actual/Commitment/Rem.Plan/Assi

gned

Standard SAP
S_ALR_87013533

7 Plan 1/Plan 2/Actual/Commitments Standard SAP S_ALR_87013534

8 Commitment Detail Standard SAP S_ALR_87013537

9 Project Version Comparison: Actual/Plan Standard SAP S_ALR_87013538

10 Project Version Comparison: Plan Standard SAP S_ALR_87013539

11 Actual/Plan Comparison: Periods Standard SAP S_ALR_87013544

12 Period Comparison - Actual Standard SAP S_ALR_87013545

13 Commitments: Period comparison Standard SAP S_ALR_87013546

14 Period Comparison - Plan Standard SAP S_ALR_87013547

15 Comparison of 2 plan versions Standard SAP S_ALR_87013554

16 Budget/Actual/Commitment/Rem

Plan/Assigned

Standard SAP

S_ALR_87013558

17 Budget updates Standard SAP S_ALR_87013560

18 Budget Line item wise Standard SAP CJI8

19 Project Hierarchy Standard SAP S_ALR_87015124

20 Actual Costs/Revenues Standard SAP CJI3

21 Commitments Standard SAP CJI5

22 For Project Standard SAP ME5J

23 For Account Assignment Standard SAP ME5K

24 For Project Standard SAP ME2J

25 For Account Assignment Standard SAP ME2K

26 Valuated Project Stock Standard SAP MBBS

27 Plan/Actual/Variance Revenue Standard SAP S_ALR_87013564

28 Sales and Distribution Documents Standard SAP CN54N

29 Sales Document Items Standard SAP CN55N

30 Budget Status Report (Budget and

Releases)

Development ZPS_BUDG_STATUS