sl.

no description nos lenghth bredth depth qty


1 EARTH WORK EXCAVATION
F1/C1 6 1.65 1.65 1.5 4.08375
F2/C2 3 1.75 1.75 1.5 4.59375

2 P.C.C CONCRETE
F1/C1 6 1.65 1.65 0.15 0.408375
F2/C2 3 1.75 1.75 0.15 0.459375

3 R.C.C SHUTTERING
F1/C1 6 1.5 1.5 0.45 2.7
F2/C2
part1 3 1.6 1.6 0.23 1.472
part2 3 0.99 1.025 0.22 0.8866

4 R.C.C CONCRETE
F1/C1 6 1.5 1.5 0.45 1.0125
F2/C2
part1 3 1.6 1.6 0.23 0.5888
part2 3 0.99 1.025 0.22 0.223245

5 Neck Columns (Shuttering)


F1/C1 6 0.23 0.3 0.9 0.954
F2/C2 3 0.23 0.3 0.9 0.954

Neck Columns (Concrete)


F1/C1 6 0.23 0.3 0.9 0.0621
F2/C2 3 0.23 0.3 0.9 0.0621

6 Refilling The Soil


F1/C1 6 1.65 1.65 1.35 3.675375
Deductions
footing1 -6 1.5 1.5 0.45 1.0125
Neck Columns -6 0.23 0.3 0.9 0.0621

Refilling The Soil


F2/C2 3 1.75 1.75 1.35 4.134375
Deductions
footing1 -3 1.6 1.6 0.45 1.152
Neck Columns -3 0.23 0.3 0.9 0.0621
total qty Remarks

24.5025
13.78125
38.28375 Cum

2.45025
1.378125
3.828375 Cum

16.2

4.416
2.6598
23.2758 Sqm

6.075

1.7664
0.669735
8.511135 Cum

5.724
2.862
8.586 Sqm

0.3726
0.1863
0.5589

22.05225

-6.075
-0.3726
15.60465 Cum

12.40313

-3.456
-0.1863
8.760825 Cum
brick work
sl.no description nos lenghth bredth depth qty total qty
1 outer walls (0.23)
Alround the building 1 51.12 0.23 3 35.2728 35.2728
Deducations
Columns -9 0.23 0.3 3 0.207 -1.863
Doors -5 1.2 0.23 2.1 0.5796 -2.898
Windows -6 1.35 0.23 1.35 0.419175 -2.51505
Ventilators -1 0.75 0.23 0.45 0.077625 -0.07763
Lintel Deducations
Doors -5 1.8 0.23 0.15 0.0621 -0.3105
Windows -6 1.95 0.23 0.15 0.067275 -0.40365
27.20498
Inner Walls (0.115)
Alround the building 1 4.115 0.115 3 1.419675 1.419675
Deducations
D1 -1 1 0.115 2.1 0.2415 -0.2415
Lintel Deduction -1 1.6 0.115 0.15 0.0276 -0.0276
1.150575

Total Qty 28.35555

Brick Work in C.M in 1:6)


Cement 1361.066 kgs Bags 27.22133
Cum 0.945185
Sand 8166.398 kgs
Cum 5.67111

Plastering
Internal Area
Room1 1 15.62 - 3 46.86 46.86
room2 1 15.16 - 3 45.48 45.48
Room3 1 17.08 - 3 51.24 51.24
Room4 1 16.62 - 3 49.86 49.86
TOILET 1 4- 3 12 12
External Toilet 1 4.23 3 12.69 12.69
External Wall 1 35 - 3.15 110.25 110.25

Dedutions
Doors 10 1.2 - 1.2 1.44 14.4
Windows 12 1.35 - 1.35 1.8225 21.87
Ventilators 2 0.75 - 0.45 0.3375 0.675
Door1 2 1- 1 1 2
367.325
1st Coat in 12 mm Thickness
4.4079 Cum
Cement 253.895 Kgs
Sand 1269.475 kgs

2nd Coat in 8mm Thickness 2.9386 Cum


Cement 282.1056 kgs
Sand 846.3168 kgs
Remarks

Cum

Cum

Cum

Sqm
brick work
sl.no description nos lenghth bredth depth qty total qty
Paint
Internal Area
Room1 1 15.62 - 3 46.86 46.86
room2 1 15.16 - 3 45.48 45.48
Room3 1 17.08 - 3 51.24 51.24
Room4 1 16.62 - 3 49.86 49.86
TOILET 1 4- 3 12 12
External Toilet 1 4.23 3 12.69 12.69
External Wall 1 35 - 3.15 110.25 110.25

Dedutions
Doors -10 1.2 - 1.2 1.44 -14.4
Windows -12 1.35 - 1.35 1.8225 -21.87
Ventilators -2 0.75 - 0.45 0.3375 -0.675
Door1 2 1- 1 1 2
293.435

69.86548 Lit

Wall Putty
Internal Area
Room1 1 15.62 - 3 46.86 46.86
room2 1 15.16 - 3 45.48 45.48
Room3 1 17.08 - 3 51.24 51.24
Room4 1 16.62 - 3 49.86 49.86
TOILET 1 4- 3 12 12
External Toilet 1 4.23 3 12.69 12.69
Doors -10 1.2 - 1.2 1.44 -14.4
Windows -6 1.35 - 1.35 1.8225 -10.935
Ventilators -1 0.75 - 0.45 0.3375 -0.3375
Door1 -2 1- 1 1 -2
190.4575

Wall Putty Thickness 3mm 0.571373 Cum


485.0953 Kgs

tiles
15.1158
14.3016
8.54
17.2508
55.2082
2ft x 2ft 297.1280595339 tiles
1ftx 1ft 594.2561190678 tiles
Remarks

Sqm

Sqm
plinth beam shutttering
pb1 10.386 Sqm
pb2 4.986 Sqm
pb3 9.786 Sqm
pb4 2.343 Sqm
total 27.501 Sqm
plinth beam concrete
pb1 1.242
pb2 0.57339
pb3 & pb4 5.3889
7.20429 Cum

10.386