Sunteți pe pagina 1din 6

21, rue d'Artois, F-75008 Paris Session 2000

http://www.cigre.org 22-206 CIGR

Belgian experience on initiatives to improve


the capability of existing overhead lines
by

J. LAMSOUL J. ROGIER P. COUNESON A.VAN OVERMEERE


(Tractebel*) (Tractebel) (Tractebel) (Laborelec)

BELGIUM

1. Introduction - The benefit of technical audits The analysis of the defect allows to understand the
deterioration mechanism: the internal cause
The concern in Belgium to improve or at least to
(corrosion, wear) usually depends on a local and/or
maintain in good condition the existing overhead
variable sources (wind, ice, humidity). The cause
transmission lines has been expressed in various papers
may also be external (lightning, tree fall) (see 5).
published in recent years. This concern originates on the
one hand from the nature of the high voltage network, The risk (defined in 3) assessment in relation to
very dense, strongly meshed and relatively old, and on the condition of the defective elements allows to
the other hand from the persisting difficulty to obtain compare different intervention solutions.
the permits to build new overhead transmission lines
needed to meet the increasing demand of electricity. The decision on actions to be taken can be based
only on quantifiable criteria (see 3).
When specific old line components near the end of their
useful life and need a total or partial replacement, the The actions have to be accompanied by a
question arises whether it would be advisable to take the maintenance program appropriate to guarantee the
opportunity to proceed to a more extensive intervention new capability of the line and its components (see
on the line concerned, to avoid spreading the work in 2.4.).
time without any long-term vision. 2.2. Degradations leading to high risks
In Belgium, the decisions on integrated interventions on The audit has to detect above all the degradations that
overhead transmission lines are taken only after a may lead to high risks such as :
complete technical audit [1].
the corrosion of the conductor core if it is of steel;
2. Methodology and Process of a technical audit the corrosion of the conductors near the joints;
2.1. Methodology of a technical audit the broken strands inside the suspension clamps;
the loosening of the insulator rods and the security
One could summarise the methodology of an audit or an
clip wear;
expert assessment of an old line by the sequence :
the advanced wear or corrosion of the insulator
measure - understand - assess decide guarantee. string attachments to the towers in the case of point
contacts.
The first action corresponds to the measuring of the
the abnormal deformations and generally all
degradation of the defective elements (see 2.2.).
advanced degradations which could not be normally
eliminated by replacement or repair.

* Avenue Ariane 5-7, B-1200 BRUSSELS (BELGIUM)


2

In presence of aggravating circumstances certain risks 3. General criterium for actions required
may also be very high :
The strategy of actions to be taken is based on the
the fusion of broken strands on conductors with a absolute criterium of minimising the net present value
small cross-section due to a lightning arc or fault of the sum of the following two costs:
conditions;
the poor surface condition of the insulators in the the investment costs to improve the capability of the
presence of pollution; system (including the operation and maintenance
the cross-arm ends of an old design (for instance : costs);
attachments out of the axis resulting in cross-arm the failure risks or the product of the failure
torsion); probability and the consequences in financial terms.
the deformed or missing steel angles, in case of an
accidental loading that determines the angle; The proposed action costs must thus be at least
compensated by the reduction of the failure risks. This
the poor earthing in case of a fault.
general approach is examined more in detail by the
2.3. Process of an audit Working Group 13 "Management of existing overhead
lines" of the CIGRE Study Committee 22.
The auditing process can be outlined as follows [1] :
The practical approach applied in Belgium is described
Collection of all design data, inspection and below.
modification reports.
Scheduling a general inspection visit by a If the risk is too low, there may be no action
"reinforced" patrol detecting defects without necessary and the risk will be tolerated.
climbing the supports.
If the risk is too high, the overhead line will be put
Identifying hot points by infrared thermography.
out of service or the line dismantled.
Scheduled outage, detailed examination of towers
and their line equipment; sampling, dismantling and However, if one wants to manage the risk, one of the
replacement of complete insulator strings, including four following options with increasing investment costs
the attachments if possible; radio frequency can be justified.
inspection of conductors on suspension strings.
Drawing up a first report including a description of If the risk is identified and localised we can
the line condition. envisage:
Supply of a second report with the comparison of the
action programs proposed to the utility to increase - elimitation of recurrent causes;
the line capability. - corrective maintenance at a local scale;
- repair or possibly partial renovation (life
2.4. Capability improvement extension) of the elements of the line
equipment.
The capability of a line defined as the product of its
transit capacity and availability : If the risk is generalised but if the towers and
[capability] = [transit capacity] x [availability] foundations are still in good condition, one can
consider a renovation of the conductors as well as of
can be improved in different ways of which some are the line equipment (refurbishment or extensive
described hereunder : renovation to restore the intended design working
[transit capacity] = [current] x [voltage] life of the line component).

The electric current can be improved (uprating) either The transit capacity can be improved by installing
by the operation of conductors at a higher temperature new conductors with a higher electrical conductivity,
or by using a conductor with a larger cross-section or a providing the towers and foundations have a
higher electrical conductivity; the voltage level by sufficient structural strength (uprating or
larger insulating distances and consequently by the improvement of the transit capacity).
replacement of cross-arms and possibly the tower top.
Generally, the installation of conductors with a
[availability] = [reliability] x [maintainability] larger cross-section requires reinforcement of towers
The specific reliability of a tower or a foundation can be and foundations (upgrading or improvement of the
improved (upgrading) by its structural strengthening; structural reliability) to cope with the higher loads.
the maintainability by safety equipment, training of line
erection personnel, etc.
3

All integrated interventions on existing overhead In the 150 kV network the initial steel earth wire has
transmission lines must be consistent with the network been modified and replaced by an earth wire with a
development plan. more substantial cross-section, generally an all
aluminium alloy conductor (AAAC), in order to
increase the short-circuit current withstand. This
4. Type of inspected network and its modification led to replacing the earth wire peak, and
particularities heightening it to compensate the greater sag of the new
earth wire.
4.1. Type of network

The technical audits in Belgium are applied only to


overhead transmission lines built 40 years ago or more.
As the 380 kV network has been developed only since
the late 1960s, the Belgian overhead network, for which
a complete audit is generally required, is essentially that
with the 70 or 150 kV voltage levels.

This particular network dates mostly back to the years


1930-1940. So it is generally over 50 years old. All the
supports concerned are towers with a bolted, riveted or
welded steel lattice, not galvanised, but with regularly
painted angles.

As the 70 and 150 kV overhead transmission lines built


after 1960 have a more modern design, the results
obtained by technical audits performed on the on Fig.1 Typical modifications on 150 and 70 kV lines
average 50 year old lines cannot be extrapolated to the
more recent lines. 5. Synthesis of the audits carried out

5.1. Maps
4.2. Particularities of the overhead network
In order to allow the verification of the regulatory
Generally speaking, all drawings related to the old lines, clearances of the line with regard to the obstacles
at least the plan views and the longitudinal profiles, are crossed, new plan views and longitudinal profiles have
rare and obsolete. If they exist they have not been been established.
updated.
Those drawings have been produced by means of aerial
Moreover, as no detailed history of those lines is photogrammetry, which considerably reduces the time
available, it is difficult to know the exact situation and and costs compared to a survey from ground level [2].
condition of the whole of their constituent elements.
They allow :
The conductors of the old 70 kV network have a small
cross-section, generally of copper; the earth wire is a more sound operation of the line concerned due to
made of bronze of a very small cross-section. One of the the fact that all the obstacles will be very well
particularities of this network is its evolution in time. defined thanks to the aerial photographs taken at a
Initially designed for a lower voltage level (50 kV), it scale of 1/7000 and to the restitution of the profile
was later adapted to 70 kV. Adaptations included the and the plan view on land registry maps;
lengthening of the cross-arms and in some cases the to detect critical points : clearances to new buildings,
transition from a double circuit to a single circuit. trees to prune and/or to cut down;
to examine the possibility of operating the line at a
The conductors of the old 150 kV network are mostly of higher temperature (increased from 40C to 60C
the aluminium conductor steel reinforced type (ACSR), and even 75C as allowed by Belgian regulations).
with a cross-section of about 200 mm. The initial earth
wire was of steel. 5.2. Conductors

5.2.1. General condition


Like the 70 kV network, the 150 kV network evolved
via one or sometimes even two intermediate voltage The investigation of the general condition and the
levels (70 and 110 kV). This situation has led to tower internal corrosion in particular of the conductors is
top modifications, sometimes in many different ways. based on the metallurgical analysis of conductor
samples taken either from the jumpers of the dead-end
strings or from the spans which recently needed repair.
4

It has been observed that the galvanised steel core of the Therefore, the solution of replacement by conductors of
jumpers deteriorates faster than that of the conductors in the same cross-section and the same nature is fully
the span, which can be explained by a lower tightening acceptable providing that after some modifications the
due to the lack of mechanical tension and consequently line may operate at a higher temperature.
by easier access of atmospheric pollutants to the steel
wires. Accordingly, the conductors may be expected to It should be borne in mind that although the lines were
be in good condition if the jumpers are. designed initially for operation at 40C, it is feasible at
little cost to operate at 75C as authorised by the present
In case of doubt about the condition of ACSR Belgian regulations. This is possible at very low cost
conductors, an investigation with the Overhead Line because the spans are generally very short (
Corrosion Detector (OHLCD) can be carried out on the 200 m). The transition from 40C to 75C allows to
spans most representative for the environment [1], [4]. increase the transit capacity by a factor 2.6.

By measuring the remaining thickness of the zinc layer 5.2.3. The 150 kV network
of the galvanised steel wires, one can detect indirectly,
by comparison with the method of Foucault currents, The ACSR conductors show generally a severe
the presence of important galvanic corrosion between galvanisation loss of the steel wires, leading to
the steel core and the aluminium layers. This process is extensive galvanic corrosion of the aluminium strands
initiated automatically if zinc is lacking, and is crucial and finally to a significant reduction in the ultimate
to the design working life of a the ACSR conductor. mechanical strength of the conductor.
The portion of the span affected by a definite rate of
degradation is registered. In this case, the conductors are replaced by compact and
more aerodynamical conductors of the type AERO-Z
As the absence of galvanisation inevitably leads to the [3] with the same external diameter. This technique
degradation in time of the conductor condition, its avoids any extensive checking and/or reinforcement of
remaining working life is no longer foreseeable. towers, while the transit capacity increases with 17 %.

5.2.2. The 70 kV network As far as the earth wire is concerned, it has been
replaced twenty years ago. Its condition is quite
Statistical analysis has shown that 70 % of the acceptable and does not need any intervention, apart
conductor ruptures occur on old overhead transmission sometimes from readjusting the sag.
lines equipped with copper or similar conductors of a
small cross-section, up to 50 mm. 5.3. Insulator strings

Short-circuit currents or mechanical overloads (wind) The examinations of both 70 and 150 kV insulator
can cause a rupture if the conductor with a small cross- strings reveal extended wear of certain elements,
section has been previously damaged. This weak point especially on U-bolts and on eyes providing the
has mostly arisen from a direct electrical arc on the attachment of suspension strings to towers.
conductor. Another possible cause of rupture is the
exaggerated heating of the conductor during short- Also, the line equipment is strongly corroded (arcing
circuits in corroded places in the clamps or near the ring, ball and socket joints, bolts, etc.).
clamps.
As in the majority of cases the conductors have to be
The solutions recommended to remedy those defects replaced, it would be logical in the context of the
are: strength coordination to also replace the insulator
strings and modify them. For instance :
installation of arcing devices, if absent;
protection of the conductor in a clamp by an armor- attachment of the strings to the tower cross-arms
rod; with hinges in order to avoid point contact;
transition from an A insulator set to a single
suspension insulator set (to increase the insulating installation of a suspension clamp with a triple
distance to the conductor); articulation designed for conductors protected with
armor-rods, to decrease bending moments in the
replacement of the existing conductors.
conductor;
However, the low cross-section and the nature of the
conductors make it very expensive to replace them. For installation of toughened glass insulators instead of
instance, replacing them by all aluminium alloy porcelain.
conductors (AAAC) with a larger cross-section can
make it necessary to reinforce the towers.
5

5.4. Towers Therefore it is recommended to heighten the chimneys


concerned to avoid frequent and costly maintenance.
The towers have been painted regularly, so that their Other chimneys simply need clearing the covering soil
condition with regard to angle steel corrosion is to the level corresponding to the surrounding terrain.
satisfactory.
However, the advanced deteriorated condition of the
Some profiles are bent, twisted or buckled and have to greater part of the top of the chimneys rising above the
be replaced. A few cases, relatively rare, present very soil necessitates their repair. This is the more
extensive corrosion needing the complete replacement indispensable that their degradation is going to continue
of angles; namely the concrete-stub interface area is due their exposure to weather conditions.
generally the most critical one.
6. Practical experiences in increasing the line
As said previously, certain lines have undergone some capacity
modifications during changes made to their voltage
level. Certain of theses adaptations were implemented 6.1. Synthesis of uprating analysis
correctly and need only a few small interventions.
However, some were made in an incongruous way and Taking into account the conclusions the audits generally
necessitated serious interventions or even full lead to, i.e. the replacement of conductors, and hence
replacement of the tower top as this option is the most significant investment costs, it may be advisable to
reliable and even the least expensive. conduct additional evaluations to identify the difference
in cost for at the same time increasing substantially the
5.5. Foundations transit capacity of the line concerned (uprating).

The observed degradations on the old foundations are If the outside diameter of the new conductors is larger
essentially due to poor in-situ execution of the concrete: than that of the existing conductors and that as a
incomplete mixing of the concrete, gravel pockets and consequence the loading on supports is increased, the
presence of cavities in the concrete due to insufficient Belgian Regulations on Electrical Installations impose
vibration during concrete placing, and due to low to verify the structural strength of the supports,
cement dosage. This situation has led to an initial poor including the foundations of the line concerned
mechanical resistance. (upgrading).

On some foundations we can observe the erosion in This check up has to be performed consistent with the
time of the sand and the fine granules in the concrete. stipulations of the current regulations, i.e. a normal
The cement that must bind them chemically has maximum wind velocity of 126 km/h and an exceptional
gradually disappeared by the chemical attack of sulfates maximum wind velocity of 178 km/h (double dynamic
and chlorides from the soil and/or the organic attack of pressure of the former).
the possibly unwashed sands used in the concrete. In
certain circumstances the formation of expansive salts The second hypothesis is of course very severe for the
and the alkali reactions cause expansion of the concrete existing lines and particularly for the steel lattice towers
which may result in internal cracking and explosion. At of the 70 kV lines.
present, only appropriate cements are used so as to
avoid degradations that were not yet known at the time. However, we notice that the impact of the second
hypothesis on towers and foundations is somewhat
One can also notice fortunately that the general mitigated when using compact conductors of the
condition of the backfilled concrete is better than the AERO-Z type [3] for which the corresponding
condition of the visible concrete. Probably the water in aerodynamical coefficient is reduced with a factor 0.83
the concrete evaporated quicker in the upper part for a diameter smaller than 27.65 mm and a factor 0.62
exposed to the air during the concrete curing, while the for a diameter between 28 and 30.65 mm.
lower backfilled part is situated in a more moist
environment less exposed to the weather. At present the 6.2. The 70 kV network
upper part of the foundations is always protected
(watering, curing compound) during the curing process. The checks required by the regulations lead to
considerable reinforcements of supports and even more
The upper level of certain chimneys is often not enough so as the distances between the towers footings are
raised, and sometimes buried with regard to the soil. As very small.
a result the stubs may get overgrown by vegetation,
which may cause a preliminary corrosion of the stubs As a result the majority of supports necessitate doubling
due to their being permanently exposed to humidity. of the main legs from the lower cross-arms to the level
of the foundations. In this case it seems more
economical to replace the existing towers by new towers
with a similar outline but using a higher steel quality.
6

Also, the foundations that are the monoblock type need 7. Conclusion
to be reinforced, be it to a lesser extent, providing the
monolithic character of the foundation can be A better knowledge of the actual capability or the real
maintained. This assumes that the concrete does not capacity and availability of the overhead transmission
deteriorate, which may not always be the case. line obtained by on the one side the standard
methodology of a technical audit and on the other side
In the hypothesis that the foundations present a good the historical data based on performance statistics and
quality, it is estimated that the cost difference, inspection reports, allows us to take the appropriate
characterised by a multiplication factor with regard to decisions to adapt their performance. The examples
the basic solution that is let us repeat the supplied in the present report prove this assertion.
replacement of the conductors by conductors of the
same outside diameter, is situated between: Acknowledgment :

2.3 and 3.2 in the case of tower reinforcement; We thank for their contribution the authors of the
2.0 and 2.2 in the case of tower replacement. different audit reports : J.L. Berlemont, B. Brijs, A.
Bruneau, E. Celens, B. De Waele, D. Franois, A. Gille,
If the foundations are of poor quality, thus implying Y. Le Roy, N. Michalakis, R. Sverzutti and E. Vilret.
intervention on every foundation, these factors become
respectively 4.7 and 4.3. References

6.3. The 150 kV network [1] Delre X., Rogier J., Van Overmeere A. :
Inspection policy of existing overhead lines and
For the 150 kV network the situation is generally assessment methodology based on practical experience.
simpler and easier to manage. Report CIGRE 22-302; Paris, 1994.

This is essentially due to the fact that the towers have [2] Rogier J., Goossens L., Mazoin M., Robberechts
another outline than that of the 70 kV lines, allowing W., De Clerck E., Jadot A. : Visualization of overhead
simpler reinforcements: either replacement of angles line project. Report CIGRE 22-209, Paris, 1996.
using provisional angles, or doubling of angles, or
addition of a secondary bracing to reduce the [3] Couneson P., Lamsoul J., Delplanque D., Capelle
slenderness ratio of members that have to be T., Havaux M., Gury D., Delre X. : Improvement of
strengthened. Furthermore, the pad and chimney existing high voltage overhead lines performance by
foundations for each foot have a concrete of higher using fully locked conductors and ground wires. Report
quality and allow easier reinforcement. CIGRE 22-209, Paris, 1998.

The problem generally encountered on foundations is [4] Rogier J., Goossens L., Lilien J.L., Wolfs M., Van
uplift stability. Overmeere A., Lugentz L. : Experience with occasional
and permanent measurements on Belgian overhead
From the point of view of costs, the difference with lines. Report CIGRE 22-104, Paris, 1998.
respect to the basic solution (replacement of the existing
conductors by conductors of the same outside diameter)
is the following:

for an increasing of the transit capacity by 45 %, the


basic price is multiplied by a factor 1.45 to 1.7;
for an increasing of the transit capacity by 80 %, the
basic price has to be multiplied by a factor 1.65 to
1.90.

Generally speaking, we can conclude that for the


150 kV network, the multiplication factor for the costs
is obviously equal to the multiplication factor of the
transit capacity of the line.

S-ar putea să vă placă și