Sunteți pe pagina 1din 7

PROJECT : STORAGE TANK DEVELOPMENT PHASE - 1, TOTAL CAP. 100.

000 MT
SUPPORTING FACILITIES & INFRASTRUCTURE
SCOPE PEKERJAAN : PACKAGE 2 - STORAGE TANK, TANK FARM & BUND WALL
LOCATION : KAWASAN PELABUHAN PELINDO 1, KUALA TANJUNG, BATUBARA, SUMUT
OWNER : PT. PRIMA TANGKI INDONESIA
CONSULTANT : PT. LYDUMA INTERMAS CONSULTANT - INDONESIA
YEAR : JANUARY 2017
Bill of Quantity
1 2 3 4 5 6 7 43 45

NO. ITEM OF WORKS UNIT TOTAL AMOUNT (Rp.)

A. PREPARATION WORKS

1 Mobilization of all personnel,plants,crane and any other required ls 1.00


equipment and materials to carry out the work and to maintain
them till job completion.
2 Provide two Insurance as follows : ls 1.00
- Conctractor's all Risks Insurance Policy
- Workman's compensation
3 Provide and maintain for the use of the contractor of works andlsclient & consultant
1.00 kind of safety helmets
and pairs of safety boots, safety glass, welding gloves, masker, full body harness of the assorted sizes as required,
scaffolding standard, safety net, fire blanket, fire extinguisher
4 To provide Medical facilities (First Aid) throughout the construction
ls period. 1.00
5 Establish and maintain during the entire period of stay at site ls 1.00
Contractors' all temporary facilities such us office,workshop,
fabrication area,store,sanitary facilities,etc.
6 Project Management, Progress Report, Work Programme ls 1.00
Prepare, maintain, modify as and when required and submit to the
Engineer for approval a detailed time schedule and progress chart as specified
7 Provide Permits that use along Construction Works ls 1.00
8 Provide Project security ls 1.00
9 To Provide Power Supply, Lighting and others, during construction ls 1.00
10 To Provide Water Supply during the construction ls 1.00
11 House Keeping during Construction and On completion of the works, ls the Contactor
1.00 shall clean up
entire site, remove and cart away all building rubbish and leave everything clean and tidy
to the Engineer's satisfaction and Authority's approval
12 Shop Drawing and as built drawing ls 1.00
13 Material Preparation ls 1.00
14 Bouwplank ls 1.00

B. TANK WORKS

B.1. EARTH WORKS

1 Excavation Works m3 6,969.92 348,495,757


2 Back Filling Works m3 6,969.92 209,097,454
3 Compacted Sand m3 305.61 9,168,201
4 Supply and Install 2" PVC Pipe Class D unit 88.00

B.2. CONCRETE WORKS

1 Cutting 450 mm Spun Pile ttk 1,404.00


2 Pile Head Works
- Concrete K-300 (include Test Cube) m3 178.64 157,200,772
- Fabrication and Install Rebar kg 22,562.73 406,129,220
- Plate 2 mm for Support m2 3,505.76 1,064,172,192

3 Lean Concrete K-100 m3 305.61 213,924,700


4 Pile Head Foundation Works
- Concrete K-300 (include Test Cube) m3 3,985.09 3,506,881,226

Prepared by : PT. Lyduma Intermas Consultant - Indonesia


- Fabrication and Install Rebar kg 434,862.18 7,827,519,224
- Form Work m2 849.89 201,229,497
5 Ring Foundation Works
- Concrete K-300 (include Test Cube) m3 225.17 198,148,613
- Fabrication and Install Rebar kg 24,744.36 445,398,482
- Form Work m2 1,340.32 317,348,528
6 Ring Sump Works
- Concrete K-300 (include Test Cube) m3 7.10 6,247,999
- Fabrication and Install Rebar kg 692.50 12,465,038
- Form Work m2 63.08 14,936,205

7 Pad of Sand Works m3 2,680.87

8 Supply and Spread Asphalt as Protective/Waterproof Bottom Tank


m3 254.32
with Specified Asphalt MACADAM
9 Filler Board. 10mm - 200 mm height m' 1,224.98

B.3. GROUNDING LOOP

1 BC Grounding Cable 50 Sq mm, include Sparing Steel Pipe 1/2"unitfor Tank 8000MT
4.00 203,200
2 BC Grounding Cable 50 Sq mm, include Sparing Steel Pipe 1/2"unitfor Tank 5000MT
8.00 406,400
3 BC Grounding Cable 50 Sq mm, include Sparing Steel Pipe 1/2"unitfor Tank 3000MT
8.00 406,400
4 BC Grounding Cable 50 Sq mm, include Sparing Steel Pipe 1/2"unitfor Tank 2000MT
2.00 101,600
5 Box Control 400 x 400 x 400 mm, with Cover, Campacted Sand unit
and lean Concrete
6.00 and Bus Bar as specified2,574,000
and drawing
6 Earth Clamp, Stick Cooper dia 1" & 2" c/w Clamp and bolt, Max.
unit2 Ohm 6.00
7 BC Grounding Cable 120 sq mm unit 6.00

B.4. STEEL WORKS FOR TANK

Fabricating, Assembling and Erecting Welded Cone Roof Tanks, with API 650 Standard for Condstruction and Designing
Carbon and Stainless Steel Standard SNI including all necessary test

1 Bottom dan Annular Plate (ASTM A 36) Harga @rp. 18000/Kg


- MS plate 20 mm x 6' x 20' kg 170,128.51 3,062,313,111
- MS plate 18 mm x 6' x 20' kg 42,007.04 756,126,694
- MS plate 16 mm x 6' x 20' kg 56,009.38 1,008,168,926
- MS plate 14 mm x 6' x 20' kg 215,636.13 3,881,450,364
- MS plate 12 mm x 6' x 20' kg 92,415.48 1,663,478,727
- MS plate 10 mm x 6' x 20' kg 7,001.17 126,021,116
- MS plate 8 mm x 6' x 20' kg 15,402.58 277,246,455
- MS Plate 12 mm, Sumpit Bottom kg 3,711.06 66,799,132
- SS 304 L Plate 10 mm x 5' x 20' sheet - 23,200,000
- SS 304 L Plate 8 mm x 5' x 20' sheet - 18,200,000
- SS 304 L Plate 12 mm, Sumpit Bottom
( 5 x 20) sheet - 28,000,000
2 Shell Tanks
- MS Plate 20 mm x 6 x 20' kg 154,025.81 2,772,464,545
- MS Plate 18 mm x 6 x 20' kg 138,623.23 2,495,218,091
- MS Plate 16 mm x 6' x 20' kg 324,854.43 5,847,379,768
- MS Plate 14 mm x 6' x 20' kg 352,859.12 6,351,464,231
- MS Plate 12 mm x 6' x 20' kg 495,683.06 8,922,294,992
- MS Plate 10 mm x 6' x 20' kg 374,562.76 6,742,129,690
- MS Plate 8 mm x 6' x 20' kg 408,868.51 7,359,633,157
- MS Plate 6 mm x 6' x 20' kg 292,999.09 5,273,983,692
- MS Plate 5 mm x 6' x 20' kg 30,630.13 551,342,381

Prepared by : PT. Lyduma Intermas Consultant - Indonesia


- SS 304 L Plate 10 mm x 5' x 20' sheet - 23,200,000
- SS 304 L Plate 8 mm x 5' x 20' sheet - 18,200,000
- SS 304 L Plate 6 mm x 5' x 20' sheet - 15,000,000
- SS 304 L Plate 5 mm x 5' x 20' sheet - 13,000,000
- Angle Ring siku 100x100x10 kg 18,835.37 339,036,701
- Channel Stiff Ring UNP 200x80x6x7.5 kg 7,260.18 130,683,232
- Channel Stiff Ring UNP 150x75x6.5 kg 17,790.90 320,236,161
- Channel Stiff Wind Girder MS Plate 8 mm thk kg 20,714.78 372,865,993
- 10mm thk MS Channel Stiff Plate, Ring kg 734.76 13,225,680
- Angle Ring SS L 100x100x10 kg -
- Channel Stiff Ring SS UNP 150x80x6x7.5 kg -
'- 10mm thk SS Channel Stiff Plate, Ring kg -

3 Roof Plate & Frame


- MS plate 5 mm x 6' x 20' kg 201,283.73 3,623,107,076
- SS 304 L Plate 5 mm x 5' x 20' sheet - 13,000,000
UNP 250.90.9 kg 51,484.80 926,726,400
UNP 150.75.6,5 kg 11,946.67 215,040,000
UNP 100.50.5 kg 60,557.28 1,090,031,040
UNP 75.40.5 kg 21,019.20 378,345,600
L 50.50.5 kg 2,939.33 52,907,904
MS Plate 16 mm 4x8 kg 4,616.63 83,099,398
MS Plate 14 mm 4x8 kg 12,231.51 220,167,166
MS Plate 12 mm 4x8 kg 1,154.16 20,774,850
MS Plate 10 mm 4x8 kg 1,786.80 32,162,380
MS Plate 8 mm 4x8 kg 16,302.68 293,448,223
SS UNP 250.90.9 kg -
SS UNP 100.50.5 kg -
SS L 50.50.5 kg -
SS 304 L Plate 16 mm 4x8 sheet - 14,000,000
SS 304 L Plate 14 mm 4x8 sheet -
SS 304 L Plate 10 mm 4x8 sheet - 8,000,000
SS 304 L Plate 8 mm 4x8 sheet - 6,000,000

4 Handrail, Cat Walk & Vertical Gutter


Pipa Hitam Medium Dia. 1,5" m' 2,086.13 87,617,567
Pipa Hitam Medium Dia. 1" m' 2,250.27 63,007,422
Pipa Galvanized Dia. 1,5", Vertical Gutter m' 2,471.57 113,692,128
Elbow LR 90, Galvanized, Vertical Gutter Pcs 264.00
Plat Support Pipe for Gutter Vertical @3000 c/c on both sides
Pcs 808.00
Expanded Metal, Cat Walk m2 762.32
Plate 18 mm, Plate Support kg 2,650.79 47,714,184
L 50.50.5, Plate Support kg 3,288.60 59,194,800
Plate 6 mm for Kick Plate kg 13,148.97 236,681,469

5 Level Indicator, Incl. Numbering of Level


Sling, 65x12mm thk Pulley, Pulley Cover, S.S Float, etc Set
and all accessories
22.00 complete

6 Drain Pipe
CS Pipe Seamless dia. 3" sch. 40, Class 150 m' 208.00 125,000
Elbow LR 90 dia. 3" CS. Sch. 40 Pcs 22.00
UNP 100.50.5 Kg 1,045.20 18,813,600
Plate 10 mm Kg 535.76 9,643,725
U-Bolt w/ 2 nuts dia. 8mm Unit 130.00
Compensating Plate Welded Pcs 22.00
Stub End c/w Slip On Flange Class 150, dia. 3" Pcs 22.00
SS Pipe Seamless dia. 3" sch. 10 m' -
SS Elbow LR 90 dia. 3" SS 304 L Sch. 10 Pcs -
SS UNP 100.50.5 Kg -
SS 304 L Plate 10 mm Kg -
U-Bolt w/ 2 nuts dia. 8mm Unit -
Compensating Plate Welded Pcs -

Prepared by : PT. Lyduma Intermas Consultant - Indonesia


Stub End c/w Slip On Flange Class 150, dia. 3" Pcs -

7 Discharge Pipe
CS Pipe Seamless dia. 8" sch. 40 Class 150 m' 208.00 500,000
Elbow dia. 8" LR 90 CS. Sch. 40 Pcs 22.00
UNP 100.50.5 Kg 2,961.40 53,305,200
Plate 10 mm Kg 306.15 5,510,700
U-Bolt w/ 2 nuts dia. 12mm Unit 130.00
Compensating Plate Welded Pcs 22.00
Stub End c/w Slip On Flange Class 150, dia. 8" Pcs 22.00
SS 304 L Pipe Seamless dia. 8" sch. 10 m' -
Elbow dia. 8" LR 90 SS. 304 Sch. 10 Pcs -
SS UNP 100.50.5 Kg -
SS 304 L Plate 10 mm Kg -
U-Bolt w/ 2 nuts dia. 12mm Unit -
Compensating Plate Welded Pcs -
Stub End c/w Slip On Flange Class 150, dia. 8" Pcs -

8 Heating Coil
CS Pipe Seamless dia. 2" sch. 40, Class 150 m' 6,872.00 68,000
Pipe Shoe 1/2-dia. 2" Sch. 40, Class 150 Unit 4,016.00
L 65.65.6, Support Kg 30,938.85 556,899,300
U-Bolt w/ 2 nuts dia. 8mm Set 4,016.00
Compensating Plate Welded Pcs 184.00
Stub End c/w Slip On Flange Class 150, dia. 2" Pcs 184.00
SS Pipe Seamless dia. 2" sch. 10 m' -
Pipe Shoe 1/2-dia. 2" SS Sch. 10 Unit -
SS L 65.65.6, Support Kg -
U-Bolt w/ 2 nuts dia. 8mm Set -
Compensating Plate Welded Pcs -
Stub End c/w Slip On Flange Class 150, dia. 2" Pcs -

9 Sounding Pipe
Standard Cap Screw, Incl. 9 MS Rod Unit 22.00
CS Pipe Seamless dia. 4" sch. 40, Class 150 m' 638.00 178,000
L 75.75.6 Kg 3,309.97 59,579,388
U-Bolt & nuts dia. 8mm unit 66.00
Plate 8 mm kg 221.06 3,979,008
Plate 6 mm kg 302.16 5,438,807
Standard Cap Screw, Incl. 9 MS Rod Unit -
SS Pipe Seamless dia. 4" sch. 10 m' -
SS L 75.75.6 Kg -
U-Bolt & nuts dia. 8mm unit -
SS Plate 8 mm kg -
SS Plate 6 mm kg -

10 Product Inlet Pipe


CS Pipe Seamless dia. 8" sch. 40, Class 150, Perforated Hole
m' dia. 20
1,232.00
mm
L 75.75.6 kg 6,347.88 114,261,840
Plate 18 mm kg 420.73 7,573,086
Plate 10 mm kg 1,934.24 34,816,320
Plate 8 mm Kg 442.11 7,958,016
U-Bolt & nuts dia. 16mm Set 616.00
Stub End c/w Slip On Flange Class 150, dia. 8" Pcs 44.00
SS Pipe Seamless dia. 8" sch. 10, Perforated Hole dia. 20m'
mm -
SS L 75.75.6 kg -
SS Plate 18 mm kg -
SS Plate 10 mm kg -
SS Plate 8 mm Kg -
U-Bolt & nuts dia. 16mm Set -
Stub End c/w Slip On Flange Class 150, dia. 8" Pcs -

11 Top Cover and Vent

Prepared by : PT. Lyduma Intermas Consultant - Indonesia


CS. Wire Mesh Cover w/ 6mm SQ. Hole Welded to 6mm Unit
thk MS Flange
22.00
CS Pipe Seamless dia. 12" sch. 40, Class 150 m' 66.00
Elbow dia. 12" LR 90 CS. Sch. 40 Pcs 44.00
SS. Wire Mesh Cover w/ 6mm SQ. Hole Welded to 6mm Unit
thk MS Flange -
SS Pipe Seamless dia. 12" sch. 10 m' -
Elbow dia. 12" LR 90 SS. Sch. 10 Pcs -

12 Mixer Agitator
Mixer Agitator LSS-400, ex. Lightnin Mixer Unit 36.00
Mixer Agitator LSS-220, ex. Lightnin Mixer Unit 2.00

13 Temperature Indicator
Temperature Gauge ex. Wika Unit 22.00

12 Spiral Staircase
Chequered Plate 4.5 mm Thk Kg 27,912.50 502,425,000
UNP 100.50.5 Kg 1,500.80 27,014,400
L 75.75.6 Kg 769.44 13,849,920
L 60.60.6 Kg 1,244.43 22,399,776
Plate 6 mm Kg 1,002.29 18,041,184
Round Bar 19mm Kg 3,547.55 63,855,911
Pipa Hitam Medium Dia. 1,5" m' 400.00 16,800,000

13 Nozzle Orientation
Roof Area (Complete with compensating plate welded and all accessories)
- Radar Nozzle 4", ANSI 150 B16.5 Set -
- Level Indicator Nozzle (Manual) 2", ANSI 150 B16.5 Set 22.00
- Nitrogen Inlet 2", ANSI 150 B16.5 Set -
- Line Sensing for BV 1", ANSI 150 B16.5 Set -
- Pressure Indicator (PI) 1/2", ANSI 150 B16.5 Set -
- Breather Valve / Ventilation 12", ANSI 150 B16.5 Set -
- Product Inlet 10", ANSI 150 B16.5 Set -
- Product Inlet 8", ANSI 150 B16.5 Set 44.00
- Manhole dia. 600 mm, Complete with all Accessories Set 22.00
- Transfer Line / Circulation Line / Return Line 6", ANSI 150
Set B16.5 -
- Steam/Condensate Nozzle 2" ANSI 150 B16.5 Set -
- Transfer Line / Circulation Line / Return Line 10", ANSISet
150 B16.5 -
- Spare 6", ANSI 150 B16.5 Set 22.00
Shell Area (Complete with compensating plate welded and all accessories)
- Temp. Indicator, ANSI 150 B16.5 Set 22.00
- Manhole dia. 800 mm, ANSI 150 B16.5, complete with All Set
Accessories22.00
- Agitator 8", ANSI 150 B16.5 Set 64.00
- Temp. Element w/ Condom, ANSI 150 B16.5 Set 22.00
- Steam/Condensate Nozzle 2" ANSI 150 B16.5 Set 184.00

14 Test Works
a. Vaccum Test for joints of bottom plate 100 % unit 22.00
b. Hydro Test for Plat Shell (Pengadaan Pompa, Genset, air dan
unit Chemical22.00
ditanggung oleh Kontraktor)
c. Dye Penetran for Nozzle, Ventilasi dan Manhole 100 % unit 22.00
d. Dye Penetran for T-Joint Shell 10% unit 22.00
e. Vaccum Test for Roof plate 10 % unit 22.00
f. Callibration Test By Metrologi (Pemerintah) unit 22.00
15 Testing for Heating Coil
a. Dye Penetran for Heating coil 100 % unit 22.00
b. Hydro Test unit 22.00

B.5. PAINTING WORKS


Sandblasting and Painting resistant to temperature 200 C
1 - External Coating, Sandblasting to SA 2 (SSPC SP 10 m2 45,707.55
2 - Sandblasting to SA 2 (SSPC SP 10 near white metal m2 79,947.13

Prepared by : PT. Lyduma Intermas Consultant - Indonesia


C. STAIR SND CONNECTING BRIDGE WORKS

C.1. CONNECTING BRIDGE

1 UNP 200.80.7,5 kg 2,190.70 39,432,528


2 L 50.50.5 kg 416.18 7,491,204
3 Plate 12 mm kg 2,314.49 41,660,892
4 Plate 8 mm kg 344.21 6,195,722
5 Bolt & Nuts M18x50 mm set 84.00
6 Expanded Metal m2 44.40 1,054,000
7 Pipa Hitam Medium Dia. 1,5" m' 132.00 5,544,000
8 Pipa Hitam Medium Dia. 1" m' 353.00 9,884,000
9 Plate 6 mm, for Kick Plate kg 627.37 11,292,696

C.2. BUNDWALL/PIPE RACK BRIDGE WORKS

1 Pondasi Concrete K-250 m3 0.09 72,576


2 Plate 10 mm kg 271.30 4,883,328
3 Anchor bar dia. 10 mm kg 35.51 639,187
4 UNP 150.75.6,5 kg 3,886.40 69,955,200
5 Chequered Plate 4.5 mm Thk kg 2,247.34 40,452,030
6 Pipa Hitam Medium Dia. 1,5" m' 337.00 14,154,000
7 Pipa Hitam Medium Dia. 1" m' 437.00 12,236,000

C.3. PAINTING WORKS


Cleaning w/ wirebrush and Painting resistant to temperature 200 C
1 - External Coating, Wirebrush, Painting Total thickness m2 595.36

D. TANK FARM AREA

D.1. PIPE RACK FOUNDATION WORKS

1 Excavation Works m3 168.73 8,436,525


2 Back filling Works m3 168.73 5,061,915
3 Compacted Sand m3 13.05 391,526
4 Lean Concrete m3 13.05 567,713
5 Pile Cap
Concrete K-300 m3 32.99 29,028,780
Fabrication and Install Rebar kg 2,854.72 51,384,969
Form Work m2 87.21 20,648,712
6 Beam 300 x 500 mm
Concrete K-300 m3 68.46 60,244,800
Fabrication and Install Rebar kg 7,945.11 143,011,904
Form Work m2 456.40 108,061,828
7 Pedestal
Concrete K-300 m3 1.87 1,647,360
Fabrication and Install Rebar kg 1,130.78 20,354,080
Form Work m2 31.20 7,387,224
Anchor Bolt unit 208.00 4,160,000

D.2. SLAB TANK FARM & BUNDWALL

1 Stripping, Cutting, Filling and Compacting Tank farm area to reached


m2 design
2,584.00
Level
2 Compacted Sand m3 129.20 3,876,000
3 Lean Concrete m3 129.20 5,620,200
4 Tank Farm Slab, 100 mm thk
Concrete K-300 m3 258.40 227,392,000
Wiremesh M6-150 m2 2,713.20
5 Kolom 150 x 150 mm
Concrete K-300 m3 2.97 2,613,600
Fabrication and Install Rebar kg 3,421.78 61,592,079
Form Work m2 79.20 18,752,184
6 Beam 150x150 mm

Prepared by : PT. Lyduma Intermas Consultant - Indonesia


Concrete K-300 m3 8.89 7,821,000
Fabrication and Install Rebar kg 1,458.64 26,255,538
Form Work m2 118.50 28,057,245
7 110 mm thick Cement and Sand Brickwall Works in Cement Mortar
m2 (1:4) and
217.20
cement Reinder for Surface finished
8 15 mm Thick Plaster for Brickwall in Cement Mortar (1:4) m2 434.40
9 Finishing Topping Bundwall m' 395.00
10 Construct 20 cm width of Drainage inside Tank Farm area m' 1,873.40

D.3. FAT TRAP TANK FARM AREA

1 Excavation Works m3 27.95 1,397,550


2 Back filling Works m3 27.95 838,530
3 Compacted Sand m3 0.77 22,995
4 Lean Concrete m3 0.77 33,343
5 Construct Slab & Wall Fat Trap
Concrete K-300 m3 10.21 8,983,040
Fabrication and Install Rebar kg 2,017.92 36,322,612
Form Work m2 107.36 25,419,627
Water Stop m' 23.20 1,600,800

6 Supply, Fabrication and Install Folding Gate, c/w all accessories


unit 1.00

83,724,104,375

Prepared by : PT. Lyduma Intermas Consultant - Indonesia

S-ar putea să vă placă și